Charging probe structure, charging tube and tube feeding device

By using guides in the loading probe structure to form a cone or table structure, the problem of loading tubes stuck in different rock layers in mine mining is solved, and the charging efficiency is improved.

CN222012916UActive Publication Date: 2024-11-15BEIJING BGRIMM YIBO TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420875701.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-25
Publication Date
2024-11-15
Estimated Expiration
2034-04-25

AI Technical Summary

Technical Problem

During mine mining, due to the differences in physical properties of different rock formations during deep hole loading, misaligned holes or gravel accumulation are prone to occur, resulting in holes or plugging of the loading pipe, affecting the loading efficiency.

Method used

Design a charging probe structure, and by setting guides at both ends of the connecting tube, a cone or table structure is formed, which is used to guide and reduce the chance of gravel entering the charging tube, ensuring that the charging tube is smoothly sent into the gun hole , and adjust the channels during the charge to avoid jamming and plugging of the pipe.

Benefits of technology

It effectively avoids the phenomenon of jamming and plugging of the charging tube in the blast hole, improves the charging efficiency, ensures that the explosive can enter the blast hole smoothly, and improves the overall charging efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222012916U_ABST
    Figure CN222012916U_ABST
Patent Text Reader

Abstract

The utility model discloses a charging probe structure, a charging pipe and a pipe conveying device, the charging probe structure is applied to the charging pipe, the charging pipe comprises a charging pipe body, and the charging probe structure comprises a connecting pipe and a probe assembly. A first opening and a second opening are formed in the two ends of the connecting pipe in the first direction correspondingly, and the connecting pipe is used for being connected with the charging pipe body through the second opening. The probe assembly comprises a plurality of guiding pieces, each guiding piece is provided with a first end and a second end, the first ends and the second ends are arranged at intervals in the first direction, the multiple first ends are arranged at intervals along the edge of the first opening, and each first end is rotationally connected with the edge of the first opening, so that the multiple second ends are close to or far away from one another in the second direction; wherein the second direction is perpendicular to the first direction. According to the charging probe structure, the charging efficiency of charging the blast hole can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of mine mining, and in particular to a charge probe structure, a charge pipe and a pipe delivery device. Background Art

[0002] Deep hole charging is usually used for blasting in mining. Since the ore body is covered by the rock body, which is composed of different rock layers, the rock physical properties of different rock layers are very different, which leads to the problem of misaligned holes or accumulation of gravel at the connection between different rock layers. When using powdered explosives for blasting, rubber tubes are usually used as charging tubes, and then the rubber tubes are directly sent into the blastholes. In the process of sending them to the bottom of the blasthole, it is very easy for the charging tube to get stuck at the position of the misaligned hole in the blasthole, and the charging tube cannot be sent to the bottom of the blasthole. In addition, gravel is easy to enter the rubber tube at the place where gravel is accumulated, resulting in blockage of the rubber tube and inability to charge normally, further affecting the charging efficiency. Utility Model Content

[0003] In view of this, the purpose of the present application is to overcome the deficiencies in the prior art and to provide a charging probe structure that can improve the charging efficiency of charging into a blast hole.

[0004] The present application also provides a medicine-filled tube.

[0005] The present application also provides a pipe delivery device.

[0006] To achieve the above objectives, the technical solutions adopted in this application are as follows:

[0007] The charge probe structure according to the first aspect of the present application is applied to a charge tube, wherein the charge tube includes a charge tube body, and the charge probe structure includes:

[0008] A connecting tube, wherein the connecting tube is provided with a first opening and a second opening at both ends along the first direction, and the connecting tube is used to be connected to the charge tube body through the second opening;

[0009] A probe assembly, wherein the probe assembly includes a plurality of guide members, each of the guide members having a first end and a second end, the first end and the second end being spaced apart along the first direction, the plurality of first ends being spaced apart along the edge of the first opening, and each of the first ends being rotatably connected to the edge of the first opening so that the plurality of second ends are moved closer to or farther from each other along the second direction;

[0010] The second direction is perpendicular to the first direction.

[0011] The charge probe structure of the present application has the following advantages:

[0012] In the above-mentioned charge probe structure, the probe assembly and the charge tube body can be connected to the two ends of the connecting tube along the first direction respectively to realize the connection between the probe assembly and the charge tube body. In this process, since the first end of each guide member is rotatably connected to the edge of the first opening of the connecting tube, each guide member can be rotatably connected to the connecting tube, so that the second end of each guide member can rotate around the second direction relative to the first end, and further the multiple second ends can approach or move away from each other along the second direction. When the multiple second ends approach each other along the second direction, the second end of each guide member can be closer to the central axis of the connecting tube relative to the first end, so that the multiple guide members can rotate around the second direction. It is provided to form a cone structure or a platform structure. In this way, when the charge tube is fed into the blast hole, the probe assembly forming the cone structure or the platform structure can play a guiding role at the staggered hole position to avoid the hole jamming phenomenon, so as to improve the charging efficiency. At the same time, the probe assembly forming the cone structure or the platform structure can reduce the probability of gravel entering the charge tube, thereby reducing the phenomenon of charge tube blockage, and further improve the charging efficiency. When the charge tube enters the bottom of the blast hole, the multiple second ends can be moved away from each other along the second direction, so that the explosive in the charge tube can be transferred from the charge tube to the blast hole to realize the charging of the blast hole. In this way, the charging efficiency of charging into the blast hole can be improved by the above-mentioned charge probe structure.

[0013] According to the charging probe structure of the first aspect embodiment of the present application, each of the guide members has a first side surface and a second side surface, the first side surface and the second side surface are spaced apart along the second direction, the first end and the second end are respectively arranged at the two ends of the first side surface along the first direction, and the first end and the second end are respectively arranged at the two ends of the second side surface, and in any two adjacent guide members, the first side surface of one of the guide members and the second side surface of the other guide member are close to or separated from each other along the second direction.

[0014] According to the charging probe structure of the first aspect of the present application, when any adjacent first side surface is in close contact with the second side surface, the angles between the first side surface and the second side surface and the second direction are both α, satisfying: 45°≤α≤60°.

[0015] According to the drug charging probe structure of the first aspect embodiment of the present application, a plurality of guide members are arranged to define a drug delivery channel, the drug delivery channel is provided with an inlet and an outlet, the inlet and the outlet are arranged at intervals along the first direction, and the inlet is connected to the first opening, a plurality of first ends are arranged to define the edge of the inlet, and a plurality of second ends are arranged to define the edge of the outlet.

[0016] According to the charging probe structure of the first embodiment of the present application, the diameter of the inlet is D1 The diameter of the outlet is D 2 , satisfied: D 2 ≥0;

[0017] Among them, when D 2 =0, D 1 >D 2 , when D 2 >0, D 1 ≥D 2 .

[0018] According to the charge probe structure of the first aspect embodiment of the present application, the charge probe structure also includes a plurality of support members, each of the support members having a third end and a fourth end, the third end of any one of the support members being connected to the connecting tube, the fourth end of any one of the support members being connected to one of the guide members, and each of the support members having a traction force to bring the fourth end close to the third end.

[0019] According to the charging probe structure of the first aspect of the present application, each of the first ends is hinged to the edge of the first opening, and each of the supporting members can be a spring, a gas spring, a pneumatic rod or a hydraulic rod.

[0020] The charge tube according to the second aspect of the present application includes:

[0021] Charge tube body;

[0022] As described above, the connecting tube of the charge probe structure is connected to one end of the charge tube body.

[0023] The charge tube of the present application has the following advantages:

[0024] In the above-mentioned charge tube, since the above-mentioned charge probe structure can reduce the probability of the charge tube getting stuck and blocked in the blast hole, the charge efficiency can be improved when charging into the blast hole through the above-mentioned charge tube.

[0025] According to the charging tube of the second aspect embodiment of the present application, the connecting tube includes a tube body and a limiting portion, the limiting portion is arranged on the inner wall of the tube body, and the limiting portion protrudes from the inner wall of the tube body along the tube diameter of the tube body, the first opening and the second opening are respectively arranged at the two ends of the tube body along the first direction, the charging tube main body is passed through the second opening in the tube body, and is against the limiting portion.

[0026] The pipe delivery device according to the third aspect of the present application includes: the drug-loading tube as described above.

[0027] The pipe delivery device of the present application has the following advantages:

[0028] In the above-mentioned pipe delivery device, since the above-mentioned charging pipe has a higher charging efficiency, the above-mentioned pipe delivery device can have a higher pipe delivery efficiency, thereby further improving the charging efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0030] Figure 1 The structure of the charge tube of the embodiment of the present application is shown in FIG. Figure 1 ;

[0031] Figure 2 The structure of the charge tube of the embodiment of the present application is shown in FIG. Figure 2 ;

[0032] Figure 3 The front view of the charge probe structure of the embodiment 1 and the embodiment 2 of the present application is shown. Figure 1 ;

[0033] Figure 4 The front view of the charge probe structure of Example 1 of the present application is shown. Figure 2 ;

[0034] Figure 5 A schematic top view of the charge probe structure of Example 1 of the present application is shown;

[0035] Figure 6 The front view of the charge probe structure of Example 2 of the present application is shown. Figure 2 ;

[0036] Figure 7 A schematic top view of the charge probe structure of Example 2 of the present application is shown.

[0037] Description of main component symbols:

[0038] 10-Charge probe structure;

[0039] 100 - connecting pipe; 110 - first opening; 120 - second opening; 130 - pipe body; 140 - limiting part;

[0040] 200-probe assembly; 210-guide member; 211-first end; 212-second end; 213-first side; 214-second side; 220-drug delivery channel; 221-inlet; 222-outlet;

[0041] 300-support member; 310-third end; 320-fourth end;

[0042] 20-Charge tube body. DETAILED DESCRIPTION

[0043] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0044] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0045] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0046] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0047] In the present application, unless otherwise clearly specified and limited, a first feature being “above” or “below” a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being “above”, “above”, and “above” a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being “below”, “below”, and “below” a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0048] Reference Figure 1 , Figure 2 as well as Figure 3 As shown, the charge probe structure 10 involved in the embodiment of the present application is applied to a charge tube. The charge tube includes a charge tube body 20 . The charge probe structure 10 includes: a connecting tube 100 and a probe assembly 200 .

[0049] Specifically, the connecting tube 100 is provided with a first opening 110 and a second opening 120 at both ends along the first direction, and the connecting tube 100 is used to be connected to the charge tube body 20 through the second opening 120; the probe assembly 200 includes a plurality of guide members 210, each of which has a first end 211 and a second end 212, the first end 211 and the second end 212 are arranged at intervals along the first direction, and the plurality of first ends 211 are arranged at intervals along the edge of the first opening 110, and each first end 211 is rotatably connected to the edge of the first opening 110, so that the plurality of second ends 212 are close to or away from each other along the second direction; wherein the second direction is perpendicular to the first direction.

[0050] It should be noted that the first direction is Figure 3 The direction indicated by x, the second direction is Figure 3 The direction that y points to.

[0051] It should be noted that when the charge tube is fed into the blast hole, the charge probe structure 10 is located in front of the charge tube body 20 along the moving direction of the charge tube.

[0052] In the above-mentioned charge probe structure 10, the probe assembly 200 and the charge tube body 20 can be connected to the two ends of the connecting tube 100 along the first direction respectively, so as to realize the connection between the probe assembly 200 and the charge tube body 20. In this process, since the first end 211 of each guide member 210 is rotatably connected to the edge of the first opening 110 of the connecting tube 100, each guide member 210 can be rotatably connected to the connecting tube 100, so that the second end 212 of each guide member 210 can rotate around the second direction relative to the first end 211, and further, the plurality of second ends 212 can approach or move away from each other along the second direction. When the plurality of second ends 212 approach each other along the second direction, the second end 212 of each guide member 210 can be closer to the first end 211. The central axis of the proximal connecting tube 100 is close to the proximal connecting tube 100, so that a plurality of guide members 210 are arranged around to form a cone structure or a platform structure. In this way, when the charge tube is fed into the blast hole, the probe assembly 200 forming the cone structure or the platform structure can play a guiding role at the staggered hole position to avoid the hole jamming phenomenon, so as to improve the charging efficiency. At the same time, the probe assembly 200 forming the cone structure or the platform structure can reduce the probability of gravel entering the charge tube, thereby reducing the phenomenon of charge tube blockage, and further improve the charging efficiency. When the charge tube enters the bottom of the blast hole, the plurality of second ends 212 can be moved away from each other along the second direction, so that the explosive in the charge tube can be transferred from the charge tube into the blast hole to realize the charging of the blast hole. In this way, the charging efficiency of charging into the blast hole can be improved by the above-mentioned charge probe structure 10.

[0053] Reference Figure 5 as well as Figure 7 As shown, each guide member 210 has a first side surface 213 and a second side surface 214, the first side surface 213 and the second side surface 214 are spaced apart along the second direction, the first end 211 and the second end 212 are respectively arranged at the two ends of the first side surface 213 along the first direction, and the first end 211 and the second end 212 are respectively arranged at the two ends of the second side surface 214, and in any two adjacent guide members 210, the first side surface 213 of one guide member 210 and the second side surface 214 of the other guide member 210 are close to or separated from each other along the second direction.

[0054] It can be understood that when the multiple second ends 212 are close to each other, in any two adjacent guide members 210, the first side 213 of one of the guide members 210 and the second side 214 of the other guide member 210 can be close to each other along the second direction. In this way, the multiple guide members 210 can be arranged to form a cone structure or a platform structure. In this way, when the charging tube is sent into the blast hole, the probe assembly 200 forming the cone structure or the platform structure can play a guiding role at the staggered hole position to avoid the hole jam phenomenon, so as to improve the charging efficiency. At the same time, the probe assembly 200 forming the cone structure or the platform structure can reduce the probability of gravel entering the charging tube, thereby reducing the phenomenon of charging tube blockage and further improving the charging efficiency.

[0055] Example 1

[0056] Specifically, refer to Figure 4 as well as Figure 5 As shown, in Example 1, when any adjacent first side 213 and second side 214 are close to each other, multiple guide members 210 are arranged to form a conical structure, each guide member 210 is a part of the conical structure, and each first side 213 and second side 214 are parallel to the center line of the conical structure.

[0057] More specifically, in Example 1, the probe assembly 200 includes four guide members 210, and the second ends 212 of the four guide members 210 are symmetrically arranged on the edge of the first opening 110 in pairs. When any adjacent first side surface 213 and second side surface 214 are close to each other, the four guide members 210 are arranged to form a conical structure, each guide member 210 is a part of the conical structure, and each first side surface 213 and second side surface 214 are parallel to the generatrix of the conical structure.

[0058] Example 2

[0059] Further, refer to Figure 6 as well as Figure 7 As shown, in Example 2, when any adjacent first side 213 and second side 214 are close to each other, a plurality of guide members 210 are arranged to form a pyramid structure, each guide member 210 is a part of the pyramid structure, and each first side 213 and second side 214 are parallel to the edges of the pyramid structure.

[0060] More specifically, in Example 2, the probe assembly 200 includes four guide members 210, and the second ends 212 of the four guide members 210 are symmetrically arranged on the edge of the first opening 110 in pairs. When any adjacent first side surface 213 and second side surface 214 are close to each other, the four guide members 210 are arranged to form a pyramid structure, each guide member 210 is a part of the pyramid structure, and each first side surface 213 and second side surface 214 are parallel to the edges of the pyramid structure.

[0061] Reference Figure 3 As shown, based on Example 1 and Example 2, when any adjacent first side surface 213 and second side surface 214 are in close contact, the angles between the first side surface 213 and the second side surface 214 and the second direction are both α, satisfying: 45°≤α≤60°.

[0062] Specifically, in the above embodiments, α may be 45°, 50°, 55°, 60°, etc.

[0063] It can be understood that when any adjacent first side surface 213 and second side surface 214 are in close contact, if the angle α between the first side surface 213 and the second side surface 214 and the second direction is less than 45°, the taper of the cone or the platform will be too large, and the distance between the second end 212 of the guide member 210 and the connecting pipe 100 in the second direction will be too small, which will affect the guiding performance of the guide member 210. When the charge tube encounters a staggered hole in the blast hole, the probability of the hole being stuck will increase. If the angle α between the first side surface 213 and the second side surface 214 and the second direction is greater than 60°, the second end 212 of each guide member 210 will be too small. The distance between the first end 212 and the first end 211 is too large, which causes the size of the guide member 210 to be too large. When the charge tube is sent to the bottom of the blasthole, the charge tube body 20 will be too far away from the bottom of the blasthole, so that the charge tube body 20 cannot reach the bottom of the blasthole, affecting the explosive filling of the blasthole section near the bottom of the blasthole. When the angle α between the first side surface 213 and the second side surface 214 and the second direction satisfies: 45°≤α≤60°, it can reduce the influence on the explosive filling of the blasthole section at the bottom of the blasthole, and improve the guiding performance of the guide member 210, thereby reducing the probability of the charge tube getting stuck in the blasthole.

[0064] It should be noted that, when the taper of the cone or the table is larger, the height of the cone or the table is smaller.

[0065] Reference Figure 4 as well as Figure 6 As shown, a plurality of guide members 210 are arranged to define a drug delivery channel 220, and the drug delivery channel 220 is provided with an inlet 221 and an outlet 222, and the inlet 221 is connected to the first opening 110, a plurality of first ends 211 are arranged to define the edge of the inlet 221, and a plurality of second ends 212 are arranged to define the edge of the outlet 222.

[0066] It can be understood that the explosive in the charge tube can enter the blast hole through the charge tube body 20, the connecting tube 100 and the charge delivery channel 220 of the probe assembly 200 in sequence. In this process, since the inlet 221 is connected to the first opening 110, the explosive in the connecting tube 100 can enter the charge delivery channel 220 through the inlet 221. Since the plurality of first ends 211 are arranged to define the edge of the inlet 221, and the plurality of second ends 212 are arranged to define the edge of the outlet 222, when the plurality of second ends 21 When the plurality of second ends 212 are close to each other and closely attached to each other along the second direction, the outlet 222 can be closed, that is, the explosive can enter the medicine delivery channel 220 through the inlet 221, and cannot enter the blast hole through the outlet 222. At this time, the charge tube is in a tube delivery state in the blast hole. When the plurality of second ends 212 are away from each other along the second direction, the outlet 222 can be opened, that is, the explosive can enter the medicine delivery channel 220 through the inlet 221, and can enter the blast hole through the outlet 222. At this time, the charge tube is in a medicine delivery state in the blast hole.

[0067] Continue to refer to Figure 4 as well as Figure 6 As shown, the diameter of the inlet 221 is D 1 , the diameter of the outlet 222 is D 2 , satisfied: D 2 ≥0;

[0068] Among them, when D 2 =0, D 1 >D 2 , when D 2 >0, D 1 ≥D 2 .

[0069] Understandably, when D 2 = 0, at this time, the charge tube is in the feeding state in the blast hole, that is, the plurality of second ends 212 are close to each other and closely attached along the second direction, which can reduce the probability of blockage of the charge tube. 1 >D 2 , multiple guide members 210 can be arranged to form a cone structure or a table structure, so that the probe assembly 200 can guide the delivery of the charge tube and reduce the probability of the charge tube being stuck in the blast hole; when D 2 >0, at this time, the charge tube is in the charge delivery state in the blast hole, that is, the plurality of second ends 212 are away from each other along the second direction. 1 ≥D 2In the process that the multiple second ends 212 move away from each other along the second direction, each guide member 210 can continue to maintain an angle setting with respect to the first direction, that is, the probe assembly 200 can continue to play a guiding role in the process that the multiple second ends 212 move away from each other along the second direction, thereby further reducing the probability of the charge tube getting stuck in the borehole.

[0070] Reference Figure 3 , Figure 4 as well as Figure 6 As shown, the charge probe structure 10 also includes a plurality of support members 300, each support member 300 has a third end 310 and a fourth end 320, the third end 310 of any support member 300 is connected to the connecting tube 100, the fourth end 320 of any support member 300 is connected to a guide member 210, and each support member 300 has a traction force to bring the fourth end 320 close to the third end 310.

[0071] It can be understood that, since the third end 310 of any support member 300 is connected to the connecting pipe 100, the fourth end 320 of any support member 300 is connected to a guide member 210, and each support member 300 has a traction force to make the fourth end 320 close to the third end 310, therefore, the guide member 210 can be close to the connecting pipe 100, that is, the multiple second ends 212 can be close to each other along the second direction. In this way, under the action of the support member 300, the multiple second ends 212 are continuously in a state of being close to each other, so that the multiple guide members 210 can form a cone structure or a table structure, and the outlet 222 can be closed, so that the delivery process of the charge tube can proceed smoothly. When the charge tube needs to deliver medicine in the blast hole, the explosive in the probe assembly 200 can provide extrusion to each guide member 210, so that the multiple second ends 212 are away from each other along the second direction, so that the outlet 222 can be opened, thereby realizing the medicine delivery function.

[0072] Continue to refer to Figure 3 , Figure 4 as well as Figure 6 As shown, each first end 211 is hinged to the edge of the first opening 110 , and each support member 300 can be a spring, a gas spring, a gas pressure rod or a hydraulic rod.

[0073] It can be understood that when the support member 300 is a spring, a gas spring, a pneumatic rod or a hydraulic rod, the support member 300 can have a traction force so that the support member 300 can pull the guide member 210 close to the connecting tube 100, that is, it can make the multiple second ends 212 approach each other along the second direction. In this way, under the action of the support member 300, the multiple second ends 212 are continuously in a state of being close to each other, so that the multiple guide members 210 can form a cone structure or a platform structure, and the outlet 222 can be closed, so that the delivery process of the charge tube can proceed smoothly.

[0074] Reference Figure 1 as well as Figure 2 As shown, the charge tube involved in the embodiment of the present application includes: a charge tube body 20 and a charge probe structure 10.

[0075] Specifically, the connecting pipe 100 of the charge probe structure 10 is connected to one end of the charge tube body 20 .

[0076] More specifically, in the above-mentioned embodiment, the charge tube body 20 is a rubber tube, and the connecting tube 100 is a metal tube.

[0077] In the above-mentioned charge tube, since the above-mentioned charge probe structure 10 can reduce the probability of the charge tube getting stuck and blocked in the blast hole, the charge efficiency can be improved when charging into the blast hole through the above-mentioned charge tube.

[0078] Reference Figure 3 , Figure 4 as well as Figure 6 As shown, the connecting tube 100 includes a tube body 130 and a limiting portion 140. The limiting portion 140 is arranged on the inner wall of the tube body 130, and the limiting portion 140 protrudes from the inner wall of the tube body 130 along the tube diameter of the tube body 130. The first opening 110 and the second opening 120 are respectively provided at both ends of the tube body 130 along the first direction. The charge tube main body 20 is passed through the tube body 130 at the second opening 120 and abuts against the limiting portion 140.

[0079] Specifically, the charge tube body 20 is connected to the inner wall of the tube body 130 through threads, or the charge tube body 20 is connected to the inner wall of the tube body 130 through a threaded quick-connect joint.

[0080] It can be understood that when the charge tube body 20 is inserted into the tube body 130 through the second opening 120, the charge tube body 20 can be connected to the connecting tube 100, thereby realizing the connection between the charge tube body 20 and the above-mentioned charge probe structure 10. When the charge tube body 20 is inserted into the tube body 130 through the second opening 120, since the charge tube body 20 abuts against the limiting portion 140, the limiting portion 140 can prevent the charge tube body 20 from penetrating into the probe assembly 200, thereby avoiding damaging the internal structure of the probe assembly 200.

[0081] The pipe delivery device involved in the embodiment of the present application includes: the above-mentioned charge-loading tube.

[0082] In the above-mentioned pipe delivery device, since the above-mentioned charging pipe has a higher charging efficiency, the above-mentioned pipe delivery device can have a higher pipe delivery efficiency, thereby further improving the charging efficiency.

[0083] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0084] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in this field can change, modify, replace and modify the above embodiments within the scope of the present application.

Claims

1. A charge probe structure, characterized in that: Applied to a charge tube, the charge tube comprises a charge tube body, and the charge probe structure comprises: A connecting tube, wherein the connecting tube is provided with a first opening and a second opening at both ends along the first direction, and the connecting tube is used to be connected to the charge tube body through the second opening; A probe assembly, wherein the probe assembly includes a plurality of guide members, each of the guide members having a first end and a second end, the first end and the second end being spaced apart along the first direction, the plurality of first ends being spaced apart along the edge of the first opening, and each of the first ends being rotatably connected to the edge of the first opening so that the plurality of second ends are moved closer to or farther from each other along the second direction; The second direction is perpendicular to the first direction.

2. The charge probe structure according to claim 1, characterized in that: Each of the guide members has a first side surface and a second side surface, the first side surface and the second side surface are spaced apart along the second direction, the first end and the second end are respectively arranged at the two ends of the first side surface along the first direction, and the first end and the second end are respectively arranged at the two ends of the second side surface, and in any two adjacent guide members, the first side surface of one of the guide members and the second side surface of the other guide member are close to or separated from each other along the second direction.

3. The charge probe structure according to claim 2, characterized in that: When any adjacent first side surface is in close contact with the second side surface, the angles formed between the first side surface and the second side surface and the second direction are both α, satisfying: 45°≤α≤60°.

4. The charge probe structure according to claim 1, characterized in that: A plurality of the guide members are arranged to define a drug delivery channel, the drug delivery channel is provided with an inlet and an outlet, the inlet and the outlet are arranged at intervals along the first direction, and the inlet is connected to the first opening, a plurality of the first ends are arranged to define the edge of the inlet, and a plurality of the second ends are arranged to define the edge of the outlet.

5. The charge probe structure according to claim 4, characterized in that: The diameter of the inlet is D1, and the diameter of the outlet is D2, satisfying: D2 ≥ 0; Among them, when D2=0, D1>D2, and when D2>0, D1≥D2.

6. The charge probe structure according to claim 1, characterized in that: The charging probe structure also includes a plurality of support members, each of which has a third end and a fourth end, the third end of any one of the support members is connected to the connecting tube, the fourth end of any one of the support members is connected to one of the guide members, and each of the support members has a traction force to bring the fourth end close to the third end.

7. The charge probe structure according to claim 6, characterized in that: Each of the first ends is hinged to the edge of the first opening, and each of the support members can be a spring, a gas spring, a gas pressure rod or a hydraulic rod.

8. A powder-filled tube, characterized in that: include: Charge tube body; According to any one of claims 1 to 7, the connecting tube of the charge probe structure is connected to one end of the charge tube.

9. The powder-filled tube according to claim 8, characterized in that: The connecting tube includes a tube body and a limiting portion, wherein the limiting portion is arranged on the inner wall of the tube body and protrudes from the inner wall of the tube body along the tube diameter of the tube body, the first opening and the second opening are respectively arranged at two ends of the tube body along the first direction, and the main body of the charge tube is passed through the second opening in the tube body and abuts against the limiting portion.

10. A pipe delivery device, characterized in that: include: A charge tube as claimed in any one of claims 8 to 9.