By introducing lifting components and threaded rods into the fire-fighting pipeline fixture, the problems of damage to the outer wall of the pipeline and low installation efficiency during the fixing process are solved, and stable clamping and efficient installation of pipes of different diameters are achieved.
Patent Information
- Application Number
- CN202420473816.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-12
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-03-12
AI Technical Summary
The existing fire-fighting pipe fixing frame may cause damage to the outer wall of the pipe during the fixing process and have low installation efficiency.
A fire-fighting pipe fixing frame including a support plate, a vertical plate, a mounting plate, a first clamping assembly and a lifting assembly are designed. Through the coordination of the lifting assembly and the threaded rod, the clamping and fixing of pipes of different diameters is realized, and the pipes of different diameters are achieved through a spring. The telescopic rod avoids direct stress on the outer wall of the pipe, increasing the buffering effect while providing adjustment of the position of the clamping assembly to accommodate pipe offset.
It effectively avoids damage to the outer wall of the pipe, improves the fixing efficiency and stability, and is suitable for pipe installation of different diameters and locations.
Smart Images

Figure CN222018852U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of fire protection engineering, and in particular to a fire protection pipe fixing frame. Background Art
[0002] At present, when installing fire-fighting pipes in buildings, the fire-fighting pipes are usually fixed to the wall through pipe brackets. The pipe brackets serve as the supporting structure of the fire-fighting pipes to increase the stability of the fire-fighting pipes. Generally, the pipe brackets include support rods and fasteners. The support rods are used to fix the fasteners to the wall, and the fasteners are used to clamp and fix the fire-fighting pipes.
[0003] In the publication number CN218152746U, a fire pipe fixing bracket is disclosed. A fire pipe fixing bracket includes a mounting plate, a fixing plate and a clamping frame for fixing the fire pipe. The top of the fixing plate is rotatably mounted with four quick-release connecting rods distributed in a rectangular array. The bottom of the mounting plate is fixedly connected with four groups of docking parts, and each group of docking parts includes two connecting plates. A sleeve is fixedly mounted between the two connecting plates. In the utility model, when disassembling the fixing bracket, the fire pipe is firstly released from the fixation, and then the fixing plate is lifted upward so that the top of each quick-release connecting rod pushes up the baffle plate. At this time, the reset spring is compressed until the undercut moves out of the limit groove, and then each quick-release connecting rod is rotated 90 degrees so that the undercut is vertically aligned with the through hole. Finally, the fixing plate and the quick-release connecting rod are moved downward so that the quick-release connecting rod is released from the fixation with the connecting plate. No auxiliary tools are required during the disassembly and assembly process, and the operation is simple and fast, so as to inspect or maintain the fixing bracket.
[0004] In the process of clamping and fixing the fire-fighting pipe in the above scheme, the clamping frame is controlled by the threaded rod to clamp and fix the pipe. When it contacts the outer surface of the pipe, the outer surface of the pipe may be damaged due to direct force. In order to improve the protection of the pipe surface, we propose a new type of fire-fighting pipe fixing frame. Therefore, those skilled in the art provide a fire-fighting pipe fixing frame to solve the problems raised in the above background technology. Utility Model Content
[0005] In order to solve the problems raised in the above background technology, the present application provides a fire protection pipe fixing bracket.
[0006] The fire protection pipe fixing frame provided in this application adopts the following technical solution:
[0007] A fire-fighting pipe fixing frame comprises a support plate, both sides of the top of the support plate are fixedly connected to vertical plates, the top of the support plate is slidably connected to two mounting plates, the opposite sides of the two mounting plates are provided with a first clamping assembly, one side of the mounting plate is rotatably connected to a first threaded rod, the first threaded rod passes through the vertical plate and is threadedly connected to the vertical plate, and the extending end is fixedly connected to a first knob, the first clamping assembly comprises a fixing plate, one side of the fixing plate is fixedly connected to the clamping plate via a telescopic rod, the clamping plate and the fixing plate are elastically connected via a spring, and further comprises
[0008] Two lifting assemblies are used to respectively drive the two first clamping assemblies to lift.
[0009] By adopting the above technical scheme, when fixing the pipeline, firstly, the pipeline is placed in the middle of the two first clamping assemblies, on the top of the support plate, and the lifting assembly can be used to drive the first clamping assembly to lift and lower, so that the center of the pipeline and the center of the first clamping assembly are in the same horizontal plane, so that pipelines of different diameters can be clamped and fixed, and then the two first threaded rods are respectively rotated to drive the mounting plate to move, thereby respectively driving the two first clamping assemblies to approach each other, so that the clamping plate approaches the pipeline to clamp the pipeline, at this time, the first threaded rod is continued to be rotated to drive the mounting plate to move, and the outer wall of the pipeline of the clamping plate is prevented from being directly stressed by the elastic force of the spring, thereby increasing the buffering effect of the pipeline fixing process, avoiding damage to the outer wall of the pipeline, and then protecting the pipeline, and by respectively setting two first threaded rods to drive the two first clamping assemblies to move, when the position of the pipeline is offset, the pipeline can be fixed by adjusting the position of the two first clamping assemblies, which facilitates the installation and fixation of the fire-fighting pipeline and improves the installation efficiency of the fire-fighting pipeline.
[0010] Preferably, a protective plate is detachably connected between the two vertical plates, a long hole is opened on the protective plate, a slider is slidably connected inside the long hole, a second threaded rod is threadedly connected to the slider, a second clamping assembly is arranged at the bottom of the second threaded rod, and a second knob is fixedly connected to the top of the second threaded rod.
[0011] By adopting the above technical solution, by setting a protective plate that is detachably connected to the vertical plate, it is convenient to install or disassemble the pipeline for maintenance, thereby improving the convenience of the device. By setting the second clamping assembly, the pipeline can be fixed from the top of the pipeline. When the position of the pipeline and the second clamping assembly is offset, the position of the second clamping assembly can be adjusted by setting the long hole, the slider and the second threaded rod, thereby facilitating the installation and fixation of the fire-fighting pipeline and improving the installation efficiency of the fire-fighting pipeline.
[0012] Preferably, the lifting assembly includes a groove opened on one side of the mounting plate, a third threaded rod is rotatably connected inside the groove, a nut seat is threadedly connected to the third threaded rod and is slidably connected to the groove, one end of the third threaded rod passes through the mounting plate, and the extended end is fixedly connected to the third knob.
[0013] By adopting the above technical solution, the lifting component can drive the clamping component to rise and fall, so that the center of the clamping plate is always in the same horizontal plane with the center of the pipe, so that the clamping plate can clamp pipes of different diameters, ensuring the fixing effect of the pipe.
[0014] Preferably, the first clamping assembly and the second clamping assembly have the same structure, and the fixing plate in the first clamping assembly is fixedly connected to the nut seat, and the fixing plate in the second clamping assembly is rotatably connected to the second threaded rod.
[0015] By adopting the above technical solution, the first clamping assembly can clamp the two sides of the pipeline, and the second clamping assembly can clamp the top of the pipeline. By clamping and fixing the pipeline in different directions, the fixing effect of the pipeline is improved.
[0016] Preferably, a protective pad is fixedly connected to the inner side of the clamping plate.
[0017] By adopting the above technical solution, the protective pad can further prevent the outer wall of the pipeline from being directly subjected to force, thereby increasing the buffering effect on the pipeline fixing process, and can increase the friction between the pipeline and the clamping plate, thereby improving the stability of the pipeline fixing.
[0018] Preferably, the protective plate is arranged in a U shape, and threaded holes are provided on both sides of the protective plate, limiting holes are provided on the two vertical plates, and one side of the vertical plate is provided with a bolt that passes through the limiting hole and is threadedly connected to the threaded hole.
[0019] By adopting the above technical solution, by setting bolts, limiting holes and threaded holes, it is easy to install and disassemble the protective plate, and the protective plate can play a protective effect on the pipeline.
[0020] In summary, this application includes the following beneficial technical effects:
[0021] 1. When fixing a pipe, the fire-fighting pipe fixing rack first places the pipe between the two first clamping assemblies and on the top of the support plate. The first clamping assembly can be driven to be lifted and lowered by the provided lifting assembly, so that the center of the pipe and the center of the first clamping assembly are in the same horizontal plane, so that pipes of different diameters can be clamped and fixed. Then, the two first threaded rods are respectively rotated to drive the mounting plate to move, thereby driving the two first clamping assemblies closer to each other, so that the clamping plate is close to the pipe to clamp the pipe. At this time, the first threaded rod is continued to be rotated to drive the mounting plate and the fixing plate to move. At this time, the spring and the telescopic rod are contracted, and the elastic force of the spring is used to prevent the outer wall of the pipe from being directly stressed, thereby increasing the buffering effect on the process of fixing the pipe and avoiding damage to the outer wall of the pipe.
[0022] 2. The fire-fighting pipe fixing frame is provided with two first threaded rods to respectively drive the two first clamping assemblies to move. When the position of the pipe is offset, the pipe can be fixed by adjusting the positions of the two first clamping assemblies, thereby facilitating the installation and fixation of the fire-fighting pipe and improving the installation efficiency of the fire-fighting pipe.
[0023] 3. The fire-fighting pipe fixing frame can clamp and fix the pipe from the top of the pipe by means of the second clamping assembly, and can further improve the fixing effect of the pipe by clamping and fixing the pipe in different directions. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a schematic diagram of the overall structure of a fire protection pipe fixing frame in an embodiment of the present application;
[0025] Figure 2 It is a fire protection pipe fixing frame in the embodiment of the present application. Figure 1 The enlarged part of part A;
[0026] Figure 3 It is a fire protection pipe fixing frame in the embodiment of the present application. Figure 1 The enlarged part of part B.
[0027] Explanation of the accompanying drawings: 1. Support plate; 2. Vertical plate; 3. Mounting plate; 4. First clamping assembly; 5. First threaded rod; 6. First knob; 41. Fixed plate; 42. Telescopic rod; 43. Clamping plate; 44. Spring; 7. Lifting assembly; 45. Protection pad; 8. Protective plate; 9. Long hole; 10. Slider; 11. Second threaded rod; 12. Second clamping assembly; 13. Second knob; 14. Threaded hole; 15. Limiting hole; 16. Bolt; 71. Groove; 72. Third threaded rod; 73. Nut seat; 74. Third knob. DETAILED DESCRIPTION
[0028] The following is combined with Figure 1-3This application is described in further detail.
[0029] The present application embodiment discloses a fire protection pipe fixing bracket. Figure 1-3 A fire protection pipe fixing frame includes a support plate 1, both sides of the top of the support plate 1 are fixedly connected to a vertical plate 2, the top of the support plate 1 is slidably connected to two mounting plates 3, the opposite sides of the two mounting plates 3 are provided with a first clamping assembly 4, one side of the mounting plate 3 is rotatably connected to a first threaded rod 5, the first threaded rod 5 passes through the vertical plate 2 and is threadedly connected to the vertical plate 2, and the extending end is fixedly connected to a first knob 6, the first clamping assembly 4 includes a fixing plate 41, one side of the fixing plate 41 is fixedly connected to a clamping plate 43 through a telescopic rod 42, and the clamping plate 43 is elastically connected to the fixing plate 41 through a spring 44, and also includes
[0030] Two lifting assemblies 7 are used to respectively drive the two first clamping assemblies 4 to lift.
[0031] In the above embodiment, when fixing the pipeline, the pipeline is first placed in the middle of the two first clamping assemblies 4, on the top of the support plate 1, and then the two first knobs 6 are rotated respectively to drive the two first threaded rods 5 to rotate respectively, so that the two mounting plates 3 move closer to each other, thereby driving the two fixing plates 41 and the clamping plate 43 closer to each other respectively, so that the clamping plate 43 is close to the pipeline to clamp the pipeline. At this time, the first threaded rod 5 continues to be rotated to drive the mounting plate 3 and the fixing plate 41 to move. At this time, the spring 44 and the telescopic rod 42 are contracted, and the elastic force of the spring 44 is used to prevent the outer wall of the pipeline from being directly stressed, thereby increasing the buffering effect on the process of fixing the pipeline and avoiding damage to the outer wall of the pipeline.
[0032] Furthermore, the lifting assembly 7 includes a groove 71 opened on one side of the mounting plate 3, and the interior of the groove 71 is rotatably connected to a third threaded rod 72, and the third threaded rod 72 is threadedly connected to a nut seat 73 that is slidably connected to the groove 71. One end of the third threaded rod 72 passes through the mounting plate 3, and the extended end is fixedly connected to a third knob 74.
[0033] On the basis of the above embodiment, the third threaded rod 72 can be driven to rotate by rotating the third knob 74, so that the nut seat 73 moves inside the groove 71, thereby driving the first clamping assembly 4 to rise and fall, so that the center of the pipe and the center of the first clamping assembly 4 are in the same horizontal plane, so that pipes of different diameters can be clamped and fixed.
[0034] Furthermore, a protective plate 8 is detachably connected between the two vertical plates 2, a long hole 9 is opened on the protective plate 8, a slider 10 is slidably connected inside the long hole 9, a second threaded rod 11 is threadedly connected to the slider 10, a second clamping assembly 12 is arranged at the bottom of the second threaded rod 11, and a second knob 13 is fixedly connected to the top of the second threaded rod 11.
[0035] The first clamping assembly 4 and the second clamping assembly 12 have the same structure, and the fixing plate 41 in the first clamping assembly 4 is fixedly connected to the nut seat 73 , and the fixing plate 41 in the second clamping assembly 12 is rotatably connected to the second threaded rod 11 .
[0036] On the basis of the above embodiment, at the same time, the protective plate 8 is installed, and then the second threaded rod 11 is driven to rotate by rotating the second knob 13, so that the second threaded rod 11 drives the second clamping assembly 12 to descend, so that the clamping plate 43 inside the second assembly contacts the top of the pipe, and then the second threaded rod 11 continues to be rotated to shrink the spring 44 and the telescopic rod 42, thereby increasing the buffering effect on the process of fixing the pipe, and clamping and fixing the pipe through the top of the pipe further improves the fixing effect of the pipe.
[0037] Furthermore, a protection pad 45 is fixedly connected to the inner side of the clamping plate 43 .
[0038] On the basis of the above embodiment, the protective pad 45 is provided to further prevent the outer wall of the pipeline from being directly stressed, thereby increasing the buffering effect on the process of fixing the pipeline, and increasing the friction between the pipeline and the clamping plate 43, thereby improving the stability of the pipeline fixation.
[0039] Furthermore, the protective plate 8 is configured to be U-shaped, and threaded holes 14 are provided on both sides of the protective plate 8, limiting holes 15 are provided on the two vertical plates 2, and a bolt 16 is provided on one side of the vertical plate 2 that penetrates the limiting hole 15 and is threadedly connected to the threaded hole 14.
[0040] On the basis of the above embodiment, by providing bolts 16, limiting holes 15 and threaded holes 14, it is convenient to install, disassemble and overhaul the protective plate 8, thereby improving the convenience of the device, and the protective plate 8 can protect the pipeline.
[0041] The implementation principle of a fire-fighting pipe fixing frame in an embodiment of the present application is as follows: when fixing the pipe, first place the pipe in the middle of the two first clamping assemblies 4, on the top of the support plate 1, and the first clamping assembly 4 can be driven to lift and lower by the provided lifting assembly 7, so that the center of the pipe and the center of the first clamping assembly 4 are in the same horizontal plane, so that pipes of different diameters can be clamped and fixed, and then the two first threaded rods 5 are respectively rotated to drive the mounting plate 3 to move, thereby driving the two first clamping assemblies 4 to approach each other, so that the clamping plate 43 is close to the pipe to clamp the pipe, and at this time, continue to rotate the first threaded rod 5 to drive the mounting plate 3 to move, and the elastic force of the spring 44 is used to prevent the outer wall of the pipe from being directly stressed, thereby increasing the buffering effect on the process of fixing the pipe and avoiding damage to the outer wall of the pipe.
[0042] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A fire protection pipe fixing frame, comprising a support plate (1), Features: Both sides of the top of the support plate (1) are fixedly connected to the vertical plates (2), the top of the support plate (1) is slidably connected to two mounting plates (3), the opposite sides of the two mounting plates (3) are each provided with a first clamping assembly (4), one side of the mounting plate (3) is rotatably connected to a first threaded rod (5), the first threaded rod (5) passes through the vertical plate (2) and is threadedly connected to the vertical plate (2), and the extending end is fixedly connected to a first knob (6), the first clamping assembly (4) comprises a fixing plate (41), one side of the fixing plate (41) is fixedly connected to a clamping plate (43) via a telescopic rod (42), the clamping plate (43) is elastically connected to the fixing plate (41) via a spring (44), and further comprises Two lifting assemblies (7), the two lifting assemblies (7) are used to respectively drive the two first clamping assemblies (4) to lift and lower.
2. A fire protection pipe fixing bracket according to claim 1, Features: A protective plate (8) is detachably connected between the two vertical plates (2), a long hole (9) is provided on the protective plate (8), a slider (10) is slidably connected inside the long hole (9), a second threaded rod (11) is threadedly connected to the slider (10), a second clamping assembly (12) is provided at the bottom of the second threaded rod (11), and a second knob (13) is fixedly connected to the top of the second threaded rod (11).
3. A fire protection pipe fixing bracket according to claim 1, Features: The lifting assembly (7) comprises a groove (71) formed on one side of the mounting plate (3); a third threaded rod (72) is rotatably connected to the interior of the groove (71); a nut seat (73) is threadedly connected to the third threaded rod (72) and is slidably connected to the groove (71); one end of the third threaded rod (72) passes through the mounting plate (3), and a third knob (74) is fixedly connected to the extended end.
4. A fire protection pipe fixing bracket according to claim 1, Features: The first clamping assembly (4) and the second clamping assembly (12) have the same structure, and the fixing plate (41) in the first clamping assembly (4) is fixedly connected to the nut seat (73), and the fixing plate (41) in the second clamping assembly (12) is rotatably connected to the second threaded rod (11).
5. A fire protection pipe fixing bracket according to claim 1, Features: A protection pad (45) is fixedly connected to the inner side of the clamping plate (43).
6. A fire protection pipe fixing bracket according to claim 2, Features: The protective plate (8) is arranged in a U shape, and threaded holes (14) are provided on both sides of the protective plate (8), and limiting holes (15) are provided on the two vertical plates (2). A bolt (16) penetrating the limiting hole (15) and threadedly connected to the threaded hole (14) is provided on one side of the vertical plate (2).