Production water control system of flotation process concentrate foam tank
By designing an automated variable frequency water supply system and high-definition infrared monitoring in the ore dressing plant, the problems of inconvenience of manual control and high power consumption are solved, and the water stability and energy-saving water supply for concentrate foam tanks are achieved.
Patent Information
- Application Number
- CN202420541478.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-20
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-03-20
AI Technical Summary
In the prior art, the water control for the production of concentrate foam tanks in the flotation process of the ore dressing plant relies on manual observation and high-head pumping, resulting in inconvenient operation and high power consumption.
A production water control system including a main variable frequency water supply system, a backup variable frequency water supply system and a high-level pool was designed, and automated control was achieved using variable frequency water supply pumps and high-definition infrared cameras to ensure stability and energy saving of water supply.
Automatic control is realized, reducing operational difficulty and power consumption, and improving the reliability and energy-saving effect of the water supply system.
Smart Images

Figure CN222025161U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of industrial production water control, in particular to a production water control system for a flotation process concentrate foam tank. Background Art
[0002] For a long time, the production water of the froth tank of the flotation process of the ore dressing plant has been controlled in a relatively traditional way. It is mainly controlled by manually operating the manual valve on site according to the flow of the concentrate in the froth tank. The water source is taken from the high-level water tank of the ore dressing plant (the high-level water tank is the production water source of the entire ore dressing plant. The water in the pool flows to various water use points of the ore dressing by gravity, so it is set at a place higher than all water use points of the ore dressing plant. Most of its water storage comes from the reusable production water of the ore dressing plant, and the reusable production water is pumped into the pool by a water pump). There are two defects in this water supply method: 1. The water use of the concentrate foam tank depends entirely on manual on-site observation and control, and the operation convenience is extremely poor; 2. The reusable production water is directly transported to the high-level water tank by a pump. Due to the very high head, the consumption of electricity is relatively large. Utility Model Content
[0003] The utility model aims to solve the defects in the prior art and provides a production water control system for a flotation process concentrate foam tank.
[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:
[0005] A production water control system for a flotation process concentrate foam tank comprises a concentrate thickener overflow tank, a high-level water tank, and a concentrate foam tank. A main variable frequency water supply system and a backup variable frequency water supply system are arranged between the concentrate thickener overflow tank and the concentrate foam tank, and a second backup water supply system is arranged between the high-level water tank and the concentrate foam tank.
[0006] Furthermore, the main variable frequency water supply system includes a first water supply pipe connected between the concentrate thickener overflow pool and the concentrate foam tank, and the first water supply pipe is provided with a first variable frequency water supply slurry pump and a first hand-electric integrated electric valve.
[0007] Furthermore, the standby variable frequency water supply system includes a second water supply pipe connected between the concentrate thickener overflow pool and the concentrate foam tank, and the second water supply pipe is provided with a second variable frequency water supply slurry pump and a second hand-electric integrated electric valve.
[0008] Furthermore, the second backup water supply system includes a third water supply pipe connected between the high-level water tank and the concentrate foam tank, and a high-level water tank outlet electric regulating valve arranged on the third water supply pipe.
[0009] Furthermore, the first variable frequency water supply slurry pump and the second variable frequency water supply slurry pump are both connected to a water seal water hand-electric integrated electric valve.
[0010] Furthermore, the first water supply pipe and the second water supply pipe are provided with a pressure transmitter and an electromagnetic flow meter.
[0011] Furthermore, an ultrasonic level meter is provided on the overflow pool of the concentrate thickener.
[0012] Furthermore, a high-definition infrared camera is provided on one side of the concentrate foam tank.
[0013] The beneficial effects of the utility model are as follows: in the control system, two variable frequency water supply slurry pumps are arranged in an overflow water pool of a concentrate thickener, one for use and one for standby, and the variable frequency water supply slurry pump adopts variable frequency control to transfer the water in the pool to the concentrate foam tank, which is directly used as its production water; compared with the traditional method of directly pumping the production water that can be reused by the ore dressing plant to the high-level water pool by the industrial frequency pump, and the water in the high-level water pool flows by gravity to supply water to the concentrate foam tank, the energy-saving effect is very obvious because the conveying head is greatly reduced and the water pump adopts variable frequency control;
[0014] The concentrate foam tank is supplied with water by a water pump when there is sufficient water in the overflow pool. When both water pumps fail or the liquid level in the overflow pool is lower than the lower limit setting value, water is supplied by the high-level water tank through an electric regulating valve. The control system has two major functions: "manual" and "automatic". The "manual" function is used for maintenance and single-machine debugging, and the electric control valves and variable frequency water pumps of the control system can be operated separately. Selecting "automatic" has the following functions: A. When the water level in the overflow pool is between the upper and lower limit setting values, water is supplied to the concentrate foam tank through one set of variable frequency water pumps and related electric switch valves. When the water supply fails (mainly judged and controlled by the frequency converter, pressure transmitter, electromagnetic flowmeter, and PLC), the system automatically switches to another set of variable frequency water pumps and related electric switch valves. B. When the water level in the overflow pool is lower than the lower limit of the setting value or there are problems with both sets of variable frequency water supply systems, the system automatically switches to the high-level water tank pipeline and supplies water to the concentrate foam tank through an electric regulating valve. C. The water volume of the variable frequency water supply and the high-level water tank water supply can be set through the operator station in the central control room. The output speed of the frequency converter or the opening of the electric regulating valve can be controlled by PID regulation to ensure that the water supply meets the production requirements. D. The water supply of each variable frequency water supply system and the electric regulating valve of the high-level water tank is interlocked. Only one water supply can be provided at any time to avoid the water supply flow direction not meeting the use requirements. E. Install a high-definition video surveillance camera at a suitable location in the froth tank of the flotation process concentrate. The operator can see the water use in the froth tank in real time through the video workstation in the ore dressing control room, and can increase or decrease the water supply accordingly.
[0015] The system adopts remote automatic control to replace traditional manual control. Compared with the traditional concentrate foam tank water supply control, this control system has obvious advantages in terms of operational convenience and control reliability, and also has a significant effect in energy saving and consumption reduction. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is the structural diagram of the system;
[0017] Figure 2 This is a schematic diagram of the control principle of this system. DETAILED DESCRIPTION
[0018] Reference Figure 1 , Figure 2 A production water control system for a flotation process concentrate foam tank, comprising a concentrate thickener overflow pool 1, a high-level water tank 2, and a concentrate foam tank 3. A main variable frequency water supply system and a backup variable frequency water supply system are provided between the concentrate thickener overflow pool 1 and the concentrate foam tank 3, and a second backup water supply system is provided between the high-level water tank 2 and the concentrate foam tank 3.
[0019] The main variable frequency water supply system comprises a first water supply pipe 4 connected between the concentrate thickener overflow pool 1 and the concentrate foam tank 3 , on which a first variable frequency water supply slurry pump 5 and a first hand-electric integrated electric valve 6 are provided.
[0020] Furthermore, the standby variable frequency water supply system includes a second water supply pipe 7 connected between the concentrate thickener overflow pool 1 and the concentrate foam tank 3, and the second water supply pipe 7 is provided with a second variable frequency water supply slurry pump 8 and a second hand-electric integrated electric valve 9.
[0021] The second backup water supply system comprises a third water supply pipe 10 connected between the high-level water tank 2 and the concentrate foam tank 3 , and a high-level water tank outlet electric regulating valve 11 arranged on the third water supply pipe 10 .
[0022] Furthermore, the first variable frequency water supply slurry pump 5 and the second variable frequency water supply slurry pump 8 are both connected to a water seal water hand-electric integrated electric valve 12, the first water supply pipe 4 and the second water supply pipe 7 are provided with a pressure transmitter 13 and an electromagnetic flowmeter 14, the concentrate thickener overflow pool 1 is provided with an ultrasonic level meter 15, and a high-definition infrared camera 16 is provided on one side of the concentrate foam tank 3.
[0023] The overflow water of the concentrate thickener is an important component of reusable production water, which overflows to the corresponding overflow pool through the thickener. In the traditional way, a water pump is installed at the bottom of the overflow pool, and the water pump transports water to the high-level water pool under the condition of power frequency operation. In this control system, a concentrate thickener overflow pool 1 is equipped with two variable frequency water supply slurry pumps, one for use and one for backup. The variable frequency water supply slurry pump adopts variable frequency control to transfer the water in the pool to the concentrate foam tank 3, which is directly used as its production water; compared with the high-level water pool, due to the significant reduction in the delivery head and the use of variable frequency control of the water pump, the energy-saving effect is very obvious.
[0024] The concentrate foam tank 3 is supplied with water by the variable frequency water supply slurry pump when there is sufficient water in the overflow pool. When the water supply of the two variable frequency water supply slurry pumps fails or the liquid level in the overflow pool is lower than the lower limit setting value, water is supplied by the high-level water pool through the electric regulating valve. The control system has two major functions: "manual" and "automatic". The "manual" function is used for maintenance and single-machine debugging, and the electronically controlled valves and variable frequency water pumps of the control system can be operated separately. Selecting "automatic" has the following functions: when the water level in the overflow pool 1 of the concentrate thickener is between the upper and lower limit setting values, water is supplied to the concentrate foam tank through one of the variable frequency water supply slurry pumps and the related electric switch valves. When the water supply fails (mainly judged and controlled by the frequency converter, pressure transmitter, electromagnetic flowmeter, and PLC), the system automatically switches to another set of variable frequency water supply slurry pumps and related electric switch valves;
[0025] When the water level in overflow pool 1 is lower than the lower limit of the set value or there are problems with both frequency conversion water supply systems, the system automatically switches to the high-level pool pipeline and supplies water to the concentrate foam tank through the electric regulating valve;
[0026] The water volume of variable frequency water supply and high-level water tank water supply can be set through the operator station in the central control room. The inverter output speed or electric regulating valve opening can be controlled by PID adjustment to make the water supply meet production requirements.
[0027] The water supply of each variable frequency water supply system and the high-level water tank electric regulating valve are interlocked and restricted. Only one water supply can be provided at any time to avoid the water supply flow direction not meeting the use requirements.
[0028] A high-definition video surveillance camera 16 is installed at a suitable position of the froth tank 3 of the flotation process concentrate. The operator can view the water usage in the froth tank in real time through the video workstation in the ore dressing control room, and can increase or decrease the water supply accordingly.
[0029] Compared with the traditional concentrate foam tank water supply control, this control system has obvious advantages in terms of operational convenience and control reliability, and also has a significant effect in energy saving and consumption reduction.
[0030] It should be understood that the above description of the preferred embodiment is relatively detailed and cannot be regarded as limiting the scope of patent protection of the utility model. Under the enlightenment of the utility model, ordinary technicians in this field can also make substitutions or modifications without departing from the scope of protection of the claims of the utility model, which all fall within the scope of protection of the utility model. The scope of protection requested for the utility model shall be based on the attached claims.
Claims
1. A production water control system for a flotation process concentrate foam tank, comprising a concentrate thickener overflow tank, a high-level water tank, and a concentrate foam tank, characterized in that: A main variable frequency water supply system and a backup variable frequency water supply system are provided between the concentrate thickener overflow water tank and the concentrate foam tank, and a second backup water supply system is provided between the high-level water tank and the concentrate foam tank.
2. A production water control system for a flotation process concentrate foam tank according to claim 1, characterized in that: The main variable frequency water supply system comprises a first water supply pipe connected between the concentrate thickener overflow pool and the concentrate foam tank, and the first water supply pipe is provided with a first variable frequency water supply slurry pump and a first hand-electric integrated electric valve.
3. A production water control system for a flotation process concentrate foam tank according to claim 2, characterized in that: The standby variable frequency water supply system comprises a second water supply pipe connected between the concentrate thickener overflow pool and the concentrate foam tank, and the second water supply pipe is provided with a second variable frequency water supply slurry pump and a second hand-electric integrated electric valve.
4. A production water control system for a flotation process concentrate foam tank according to claim 1, characterized in that: The second backup water supply system comprises a third water supply pipe connected between the high-level water tank and the concentrate foam tank, and a high-level water tank outlet electric regulating valve arranged on the third water supply pipe.
5. The production water control system of the flotation process concentrate foam tank according to claim 3, characterized in that: The first variable frequency water supply slurry pump and the second variable frequency water supply slurry pump are both connected to a water seal water hand-electric integrated electric valve.
6. A production water control system for a flotation process concentrate foam tank according to claim 3, characterized in that: The first water supply pipe and the second water supply pipe are provided with a pressure transmitter and an electromagnetic flow meter.
7. A production water control system for a flotation process concentrate foam tank according to claim 3, characterized in that: An ultrasonic level meter is provided on the overflow pool of the concentrate thickener.
8. The production water control system of the flotation process concentrate foam tank according to claim 3, characterized in that: A high-definition infrared camera is provided on one side of the concentrate foam tank.