Double-drum water quenching furnace
By adopting a double-roller design and water pump system in the water quenching furnace, uniform spraying of water and rotating of the roller are achieved, solving the problems of low efficiency and uneven efficiency of traditional water quenching furnaces, and significantly improving the quenching effect of metals.
Patent Information
- Application Number
- CN202420682432.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional single drum water quenching furnaces have problems of low water quenching efficiency and unevenness.
Design a double-roller water quenching furnace. By setting two drums inside the furnace body, the water pump, water tank, pumping pipe, drainage pipe and nozzle system can achieve uniform spraying of water, and drive the drum to rotate through the drive assembly to ensure that the metal is rolling. Uniform quenching during the process.
Improves water quenching efficiency and uniformity, and enhances the hardness and wear resistance of metals.
Smart Images

Figure CN222043293U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of water quenching furnaces, and in particular to a double-drum water quenching furnace. Background Art
[0002] In the metal processing process, quenching is a commonly used heat treatment process to improve the hardness and wear resistance of metal materials. The working principle of the water quenching furnace is based on the quenching technology in metal heat treatment. Under high temperature, the internal structure of the metal will change to form unstable structures such as austenite. Through rapid cooling, the atomic arrangement inside the metal can be changed, thereby obtaining higher hardness, strength and wear resistance.
[0003] With respect to the above-mentioned related technologies, the inventors believe that the water quenching equipment in the traditional technology usually adopts a single drum design, which has the problems of low water quenching efficiency and uneven water quenching, and has defects. Therefore, a double-drum water quenching furnace is proposed to solve the above problems.
[0004] The above information disclosed in the background technology is only used to increase the understanding of the background technology of the present application, and therefore, it may include information that does not constitute the prior art known to ordinary technicians in the field. Utility Model Content
[0005] In order to solve the problems that the quenching equipment in the traditional technology usually adopts a single drum design, and has low water quenching efficiency, uneven water quenching and the like, the present application provides a double drum water quenching furnace.
[0006] The double-drum water quenching furnace provided in this application adopts the following technical solution:
[0007] A double-drum water quenching furnace comprises a furnace body and a driving assembly, wherein two drums are arranged inside the furnace body, and both ends of the drums are fixedly connected with transverse pipes, and the transverse pipes are rotatably connected with the left and right side walls of the furnace body respectively, a water tank is installed on the front side wall of the furnace body, and a water pump is installed on the right side wall of the furnace body, and a water pump is connected to the water suction port of the water pump and provided with a water suction pipe, and the end of the water suction pipe away from the water pump extends to the inside of the water tank, and the water discharge port of the water pump is connected with a drainage pipe, and the outer wall of the drainage pipe is connected with two water inlet pipes, and the water inlet pipe is away from the drainage pipe. One end extends to the interior of the horizontal pipe and is connected to a water storage pipe. The interior of the water storage pipe is connected to a plurality of nozzles at equal intervals. A certain amount of water is stored in the water tank. By starting the water pump, the water source in the water tank can be extracted through the pumping pipe. The extracted water will enter the interior of the water storage pipe through the drain pipe and two water inlet pipes. The water is discharged through the nozzle, and finally the water quenching process of the metal to be water-quenched is realized. The drum is rotating all the time, so the metal in the roller is rolling all the time, so that the metal in the drum can be evenly water quenched, which improves the water quenching effect.
[0008] Preferably, one end of the transverse tube away from the roller extends to the outside of the furnace body and is fixedly connected to a first roller, and the rotation of the first roller drives the transverse tube to rotate.
[0009] Preferably, the driving assembly includes a driving motor fixedly connected to one of the side walls of the furnace body, and the output end of the driving motor is fixedly connected to the second roller through a coupling, the two first rollers and the second rollers are in contact with each other, and the second roller drives the two first rollers to rotate through transmission action, and the rotation of the two first rollers will drive the cross tube and the roller connected to the cross tube to rotate, thereby realizing the rotation of the roller.
[0010] Preferably, a slot is provided on the outer wall of the drum, a cover is hingedly provided inside the slot, a door is hingedly provided on the front side of the furnace body, and the metal to be water-quenched can be added into or taken out of the drum by opening the door and then the cover.
[0011] In summary, this application includes the following beneficial technical effects:
[0012] The metal to be water quenched is placed in the drum. The water in the water tank can be sucked into the water storage pipe through the action of the water pump, water tank, water suction pipe, drainage pipe and two water inlet pipes. The water is discharged through the nozzle, and finally the water quenching of the metal to be water quenched is realized. Under the action of the driving component, the two drums are rotating all the time. Therefore, the metal in the rollers is rolling all the time, so that the metal in the drum can be uniformly water quenched, thereby improving the water quenching effect. Compared with the prior art, the water quenching furnace proposed in the present application is provided with double drums, which has the effects of high water quenching efficiency and uniform water quenching, thereby improving the water quenching efficiency of the metal. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the main structure of the embodiment of the application;
[0014] Figure 2 It is a schematic diagram of the overall structure of the embodiment of the application;
[0015] Figure 3 It is a schematic cross-sectional structure diagram of an embodiment of the application;
[0016] Figure 4 It is a schematic diagram of a partial cross-sectional structure of an embodiment of the application;
[0017] Figure 5 yes Figure 1 A schematic diagram of the structure enlargement in the middle;
[0018] Figure 6 yes Figure 2 A magnified schematic diagram of the structure at B in the middle;
[0019] Figure 7 yes Figure 4Enlarged schematic diagram of the structure at point C in the middle.
[0020] Explanation of the accompanying drawings: 1. furnace body; 2. drum; 3. horizontal pipe; 4. water tank; 5. water pump; 6. water suction pipe; 7. water inlet pipe; 8. water storage pipe; 9. nozzle; 10. first roller; 11. driving motor; 12. second roller; 13. notch; 14. cover; 15. box door; 16. drain pipe. DETAILED DESCRIPTION
[0021] The following is combined with Figure 1-7 This application is described in further detail.
[0022] The present application embodiment discloses a double drum water quenching furnace, referring to Figure 1 , Figure 2 , Figure 4 , Figure 6 and Figure 7 , including a furnace body 1 and a driving assembly, two rollers 2 are arranged inside the furnace body 1, both ends of the rollers 2 are fixedly connected with a transverse pipe 3, the transverse pipe 3 is rotatably connected with the left and right side walls of the furnace body 1 respectively, a water tank 4 is installed on the front side wall of the furnace body 1, a water pump 5 is installed on the right side wall of the furnace body 1, a water pump 6 is connected to the water pump 5, and the end of the water pump 6 away from the water pump 5 extends to the inside of the water tank 4, the water pump 5 is connected to the drain outlet with a drain pipe 16, and the outer wall of the drain pipe 16 is connected with two water inlet pipes 7, and the end of the water inlet pipe 7 away from the drain pipe 16 extends to the inside of the transverse pipe 3. A water storage pipe 8 is provided inside and connected thereto, and a plurality of nozzles 9 are provided inside the water storage pipe 8 at equal intervals. A certain amount of water is stored inside the water tank 4. By starting the water pump 5, the water source in the water tank 4 can be extracted through the water extraction pipe 6. The extracted water will enter the water storage pipe 8 through the drain pipe 16 and the two water inlet pipes 7. The water is discharged through the nozzle 9, and finally the water quenching process of the metal to be water-quenched is realized. The drum 2 is rotating all the time, so the metal in the drum 2 is rolling all the time, so that the uniform water quenching of the metal in the drum 2 can be achieved, thereby improving the water quenching effect.
[0023] Reference Figure 4 and Figure 5 One end of the transverse tube 3 away from the drum 2 extends to the outside of the furnace body 1 and is fixedly connected to the first roller 10. The rotation of the first roller 10 will drive the transverse tube 3 to rotate.
[0024] Reference Figure 1 and Figure 5The driving assembly includes a driving motor 11 fixedly connected to one of the side walls of the furnace body 1. The output end of the driving motor 11 is fixedly connected to the second roller 12 through a coupling. The two first rollers 10 and the second rollers 12 are in contact with each other. The driving motor 11 is started, and the driving motor 11 drives the second roller 12 to rotate. The second roller 12 drives the two first rollers 10 to rotate through transmission. The rotation of the two first rollers 10 will drive the cross tube 3 and the roller 2 connected to the cross tube 3 to rotate, thereby realizing the rotation of the roller 2.
[0025] Reference Figure 3 A slot 13 is provided on the outer wall of the drum 2, a cover 14 is hingedly provided inside the slot 13, a door 15 is hingedly provided on the front side of the furnace body 1, and the metal to be quenched can be added into or taken out of the drum 2 by opening the door 15 and then opening the cover 14.
[0026] The implementation principle of a double-drum water quenching furnace in the embodiment of the present application is as follows: open the box door 15, then open the cover 14, and add or take out the metal to be water quenched into or from the inside of the drum 2, then close the cover 14 and the box door 15, a certain amount of water is stored in the water tank 4, and by starting the water pump 5, the water source in the water tank 4 can be extracted through the pumping pipe 6, and the extracted water will enter the inside of the water storage pipe 8 through the drain pipe 16 and the two water inlet pipes 7, and the water will be discharged through the nozzle 9, and finally the water quenching processing of the metal to be water quenched is realized, and the driving motor 11 is started, and the driving motor 11 drives the second roller 12 to rotate, and the second roller 12 drives the two first rollers 10 to rotate through the transmission action, and the rotation of the two first rollers 10 will drive the cross tube 3 and the drum 2 connected to the cross tube 3 to rotate, thereby realizing the rotation of the drum 2, and the drum 2 is rotating all the time, so the metal in the roller 2 is rolling all the time, so that the uniform water quenching of the metal in the drum 2 can be achieved, and the water quenching effect is improved.
[0027] Finally, a few points should be explained: First, in the description of this application, it should be noted that, unless otherwise specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, which may refer to mechanical connection or electrical connection, or internal communication between two components, or direct connection. "upper", "lower", "left", "right", etc. are only used to indicate relative positional relationships. When the absolute position of the object being described changes, the relative positional relationship may change;
[0028] Secondly: In the drawings of the embodiments disclosed in the present utility model, only the structures related to the embodiments disclosed in the present utility model are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present utility model can be combined with each other;
[0029] Finally: The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present utility model should be included in the protection scope of the present utility model.
[0030] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A double drum water quenching furnace, comprising a furnace body (1) and a drive assembly, characterized in that: Two rollers (2) are arranged inside the furnace body (1), and both ends of the rollers (2) are fixedly connected with a transverse tube (3), and the transverse tube (3) is rotatably connected with the left and right side walls of the furnace body (1). A water tank (4) is installed on the front side wall of the furnace body (1), and a water pump (5) is installed on the right side wall of the furnace body (1). The water suction port of the water pump (5) is connected with a water suction pipe (6), and the end of the water suction pipe (6) away from the water pump (5) extends to the inside of the water tank (4). The water discharge port of the water pump (5) is connected with a drainage pipe (16), and the outer wall of the drainage pipe (16) is connected with two water inlet pipes (7), and the end of the water inlet pipe (7) away from the drainage pipe (16) extends to the inside of the transverse tube (3) and is connected with a water storage pipe (8), and the inside of the water storage pipe (8) is connected with a plurality of nozzles (9) at equal intervals.
2. A double drum water quenching furnace according to claim 1, characterized in that: One end of the transverse tube (3) away from the roller (2) extends to the outside of the furnace body (1) and is fixedly connected to the first roller (10).
3. A double drum water quenching furnace according to claim 2, characterized in that: The driving assembly comprises a driving motor (11) fixedly connected to one of the side walls of the furnace body (1), the output end of the driving motor (11) being fixedly connected to a second roller (12) via a coupling, and the first roller (10) and the second roller (12) are in contact with each other.
4. The double-drum water quenching furnace according to claim 1, characterized in that: The outer wall of the drum (2) is provided with a notch (13), and a cover (14) is hinged inside the notch (13).
5. The double-drum water quenching furnace according to claim 1, characterized in that: A door (15) is hingedly connected to the front side of the furnace body (1).