Fabricated roof system

By designing a prefabricated roof system and using the combined structure of unit plates and roof frames, the problems of poor connection stability and glue pollution in the roof system of small temporary buildings are solved, rapid disassembly and assembly and stability improvement are achieved, and construction costs are reduced.

CN222120755UActive Publication Date: 2024-12-06ZHEJIANG ZHONGNAN PHOTOVOLTAIC CURTAIN WALL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420730435.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-10
Publication Date
2024-12-06
Estimated Expiration
2034-04-10

AI Technical Summary

Technical Problem

The existing small temporary building roof system has poor connection stability, low disassembly and assembly efficiency, and there are glue pollution problems, resulting in cumbersome construction and delayed progress.

Method used

A prefabricated roofing system is designed, using a combined structure of unit plates and roof frames. Through technologies such as sealing connection, adjustment bolts and insulation layers, rapid disassembly and assembly and sealing are achieved, and the glueing process is avoided.

Benefits of technology

It improves construction convenience and stability of the roof system, reduces glue pollution, realizes rapid dismantling and reuse, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120755U_ABST
    Figure CN222120755U_ABST
Patent Text Reader

Abstract

The utility model provides an assembly type roof system which comprises a roof frame and a unit plate connected to the roof frame, the end portion of an aluminum plate of the unit plate is provided with a connecting portion extending into the roof frame, and the connecting portion is connected with the roof frame in a sealed mode. First frames connected through end sealing plates are arranged at the ridge and the roof of the roof frame, supporting structures fixed to the main body steel structure are arranged on the first frames, connecting intervals are formed between the adjacent first frames, and the end sealing plates are provided with inner pressing plates and outer pressing plates on the indoor sides and the outdoor sides of the first frames correspondingly. The inner pressing plate and the outer pressing plate jointly cover the first frames on the adjacent sides, and the inner pressing plate is provided with an adjusting bolt which penetrates through the connecting interval to be connected with the outer pressing plate. All curtain wall plates are unitized and can be directly assembled on site, the construction period problem is solved, and the design time and the machining and manufacturing time are saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of curtain walls, in particular to an assembled roofing system. Background Art

[0002] Small temporary buildings such as project departments of construction projects are currently mainly prefabricated houses or container-type temporary buildings. Although they can be reused, their appearance and shape are limited. In addition, the structure and connection method of the roof of the above-mentioned small temporary buildings are relatively simple, so the stability of the connection is not good, resulting in low efficiency of disassembly and reassembly during construction. In addition, the roof will be contaminated by glue due to glue application. If the roof system is to be disassembled, the glued parts must be cut, and glue must be applied again when reassembling, which is cumbersome and delays the construction progress. Utility Model Content

[0003] The purpose of the utility model is to provide a prefabricated roof system with a convenient and repeated disassembly and assembly function, which can effectively improve the convenience of construction.

[0004] To this end, the utility model adopts the following technical solutions:

[0005] A prefabricated roofing system comprises a roof frame and a unit plate connected to the roof frame, wherein the end of the aluminum plate of the unit plate is provided with a connecting portion extending into the roof frame, and the connecting portion is sealed and connected to the roof frame; the roof frame is provided with a first frame connected by an end sealing plate at the ridge and the roof, the first frame is provided with a supporting structure fixed to a main steel structure, and a connecting gap is provided between adjacent first frames, the end sealing plate is provided with an inner pressure plate and an outer pressure plate on the indoor side and the outdoor side of the first frame respectively, the inner pressure plate and the outer pressure plate simultaneously cover the first frames on the adjacent sides, and the inner pressure plate is provided with an adjusting bolt connected to the outer pressure plate through the connecting gap; the roof frame is provided with a second frame and a third frame connected in a spliced ​​manner at the joint of the upper and lower unit plates of the roof, and the roof frame is provided with a fourth frame at the end of the unit plate at the eaves.

[0006] Furthermore: the outer part of the outer pressure plate is covered with a roof buckle cover, and the first roof buckle cover and the second roof buckle cover are respectively arranged on the outer pressure plate at the roof and the ridge.

[0007] Furthermore: an aluminum plate is arranged at the joint position of the roof cover, and a building sealant is evenly applied to the inner periphery.

[0008] Furthermore: the inner pressure plate is externally covered with an inner buckle cover.

[0009] Furthermore, the unit plates are layered in sequence from top to bottom, with an upper aluminum plate and a lower aluminum plate, and an insulation layer is arranged between the upper aluminum plate and the lower aluminum plate.

[0010] Furthermore: an inner buckle portion connected to the second frame is provided in the upper unit panel, an installation gap is provided between the inner buckle portion and the end of the upper unit panel, and a first square tube is connected to the side end surface of the second frame; the end of the lower unit panel and its third frame extend into the inner buckle portion of the upper unit panel, and the installation portion of the second frame extends out of the upper unit panel and is embeddedly connected with the third frame.

[0011] Furthermore: sealing aluminum plates are provided at the ends of the unit panels at the upper layer and at the ends of the unit panels at the eaves.

[0012] Furthermore: a sealing tape is provided on the inner wall of the connecting portion of the unit plate and is in contact with the outer surface of the roof frame.

[0013] Furthermore: a second square tube is arranged inside the roof frame.

[0014] Furthermore: reinforcing ribs are arranged inside the roof frame.

[0015] Compared with the prior art, the utility model has the following beneficial effects:

[0016] The utility model unitizes all the roof panels so that they can be assembled directly on site, thus solving the construction period problem and saving design time and processing time. Moreover, all the unit panels are waterproofed and drained through pressure plates and cover plates on the roof, ridge and joints. On this basis, the roof system levels the adjacent unit panels through upper and lower pressure plates, and can also be compressed and sealed to ensure the airtightness of the interior of the building. Moreover, the roof system is spliced ​​with bolts, and the roof system does not require glue, so there is no glue pollution, and there is no need to cut the glue or re-glue because of disassembly. In this way, while ensuring the stability of the roof, it can be quickly disassembled and rebuilt in a different location within the service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the connection between the unit plates of the utility model;

[0018] Figure 2 For this utility model Figure 1 Schematic diagram of AA direction in;

[0019] Figure 3 It is a schematic diagram of the connection between the unit panels at the ridge of the utility model;

[0020] Figure 4 It is a schematic diagram of the connection between the upper and lower unit plates of the utility model;

[0021] Figure 5 It is a schematic diagram of the connection between the unit panels at the eaves of the utility model;

[0022] Figure 6 It is a schematic diagram of the roof frame of the utility model;

[0023] Figure 7 For this utility model Figure 6 Cross-section at the middle BB;

[0024] Figure 8 For this utility model Figure 6 Sectional view at CC;

[0025] Fig. 9 For this utility model Figure 6 Cross-sectional view at DD in the middle.

[0026] The markings in the attached drawings are: 1-unit plate; 11-upper aluminum plate; 12-insulation layer; 13-lower aluminum plate; 14-sealing aluminum plate; 2-end sealing plate; 21-outer pressure plate; 211-first roof buckle cover; 212-second roof buckle cover; 22-adjusting bolt; 23-inner pressure plate; 231-inner buckle cover; 3-support structure; 31-steel square tube; 32-connecting plate; 33-steel pedestal; 4-main steel structure; 5-sealing tape; 6-roof frame; 601-second square tube; 602-reinforcement rib; 61-first frame; 62-second frame; 63-third frame; 64-fourth frame; 65-first square tube; 7-roof outer closing. DETAILED DESCRIPTION

[0027] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.

[0028] like Figure 1-9As shown, an assembled roof system includes a roof frame 6 and a unit plate 1 connected to the roof frame 6, the aluminum plate end of the unit plate 1 is provided with a connecting portion extending into the roof frame 6, and the connecting portion is sealed and connected to the roof frame 6; the roof frame 6 is provided with a first frame 61 connected by an end sealing plate 2 at its ridge and roof, the first frame 61 is provided with a supporting structure 3 fixed to the main steel structure 4, and there is a connecting gap between adjacent first frames 61, the end sealing plate 2 is provided with an inner pressure plate 23 and an outer pressure plate 21 on the indoor side and the outdoor side of the first frame 61, respectively, the inner pressure plate 23 and the outer pressure plate 21 simultaneously cover the first frame 61 on the adjacent side, and the inner pressure plate 23 is provided with a support structure 3 that passes through the connecting gap and connects with the outer pressure plate The adjusting bolt 22 connected to 21 can apply pressure to the inner pressure plate 23 and the outer pressure plate 21 at both ends of the adjusting bolt 22 at the same time when it is continuously tightened, so as to level the adjacent unit panels 1, and at the same time make the inner pressure plate 23 and the outer pressure plate 21 fit each other and press and seal the outer surface of the unit panel 1; the roof frame 6 is provided with a second frame 62 and a third frame 63 connected in a spliced ​​manner at the joints of the upper and lower unit panels 1 of the roof, and the roof frame 6 is provided with a fourth frame 64 at the end of the unit panel 1 at the eaves, so that the periphery of the unit panels 1 in each area is enclosed by the roof frame 6, and the roof frame 6 provides a connection basis for adjacent unit panels 1, so that the disassembly and assembly of the overall roof system can be completed by connecting the frames.

[0029] like Figure 1 and 3 As shown, the outer side of the outer pressure plate 21 is covered with a roof buckle cover. It should be noted that a first roof buckle cover 211 and a second roof buckle cover 212 are respectively provided on the outer pressure plate 21 at the roof and the ridge.

[0030] Among them, an aluminum veneer is set at the joint position of the roof buckle cover, and the inner periphery is evenly coated with building sealant. The thickness of the aluminum veneer is 2mm.

[0031] like Figure 1 and 3 As shown, the inner pressure plate 23 is covered with an inner buckle cover 231 on the outside, and this buckle cover can be removed if there is a suspended ceiling inside the building.

[0032] In this embodiment, the unit plate 1 is layered from top to bottom with an upper aluminum plate 11 and a lower aluminum plate 13, the inner walls of the upper aluminum plate 11 and the lower aluminum plate 13 are respectively attached to the outer surfaces of both sides of the frame, and an insulation layer 12 is arranged between the upper aluminum plate 11 and the lower aluminum plate 13 to improve the energy saving effect, and the insulation cotton and the aluminum plate are fixed with rock wool nails during assembly. Among them, the thickness of the upper aluminum plate 11 is 3mm, the thickness of the lower aluminum plate 13 is 2mm, which can be used as an insulation aluminum plate, and the insulation layer 12 is 100mm thick insulation cotton.

[0033] like Figure 4As shown, an inner buckle portion connected to the second frame 62 is provided in the upper unit panel 1, and the inner buckle portion is concave so that the thickness of the insulation layer 12 in this area is reduced, and an installation gap is provided between the inner buckle portion and the end of the upper unit panel 1, and a first square tube 65 is connected to the side end surface of the second frame 62, and the first square tube 65 is arranged in the area where the thickness of the insulation layer 12 is reduced, so as to increase the strength of the inner buckle portion of the upper unit panel 1; the end of the lower unit panel 1 and its third frame 63 extend into the inner buckle portion of the upper unit panel 1, and the installation portion of the second frame 62 extends out of the upper unit panel 1 and is embedded in the third frame 63, so that the second frame 62 and the third frame 63 are connected to each other.

[0034] like Figure 5 As shown, the fourth frame 64 in the unit panel 1 at the eaves is spaced apart from the end of the unit panel 1, and the fourth frame 64 is connected to the outer opening 7 of the roof at its installation portion extending outdoors, and the outer opening 7 of the roof also has a water collection function and can be used as a gutter.

[0035] like Figure 4-5 As shown, in this embodiment, the ends of the upper unit panels 1 and the ends of the unit panels 1 at the eaves are provided with sealing aluminum plates 14 to guide rainwater on the roof. The thickness of the sealing aluminum plates 14 is 2 mm.

[0036] like Figure 1 and 3 As shown in FIG. 5 , a sealing tape 5 is provided on the inner wall of the connecting portion of the unit panel 1 and is in contact with the outer surface of the roof frame 6 .

[0037] like Figure 6-9 As shown, the roof frame 6 of this embodiment is provided with a second square tube 601 made of aluminum alloy inside, and the end of the second square tube 601 can be connected to the folded edge of the roof frame 6 through an aluminum angle code, as shown in FIG. Figure 8 .

[0038] Moreover, the angles at the folded edges of the roof frame 6 can also be connected by aluminum corner brackets, as shown in the figure. Fig. 9 .

[0039] Among them, when the side length of the roof frame 6 is greater than 600mm, the reinforcing rib 602 needs to be fixed. The reinforcing rib 602 is made of aluminum alloy profile, and the spacing between the reinforcing rib 602 and the second square tube 601 is not greater than 300mm; the reinforcing rib 602 is fixed with aluminum welding nails, but during processing, it should be ensured that the outer surface of the aluminum plate does not deform or fade, and the fixation should be firm. Aluminum planting nails must be used when welding aluminum plates; the welding voltage of aluminum planting nails should be above 90V, and they should be welded perpendicular to the aluminum plate, with an allowable deviation of ±1°

[0040] The arrangement of the reinforcing rib 602 and the connection method with the aluminum plate are shown as follows: Figure 7Note that the starting position of the reinforcement rib 602 should be away from the aluminum plate to avoid the aluminum corner. The reinforcement rib 602 is arranged perpendicular to the long side. When both sides are greater than 200mm, the ribs are arranged in two directions (the short side direction is the main reinforcement rib arrangement).

[0041] like Figure 1 , 3 As shown in Figure 5, in this embodiment, the supporting structure 3 includes a steel square tube 31 directly or indirectly arranged on the main steel structure 4, and the steel square tube 31 is bolted to a connecting plate 32 on the side in the opposite direction, and the first frame 61 is connected through the connecting plate 32 to fix the adjacent first frame 61 together by bolts at the same time; the main steel structure 4 can also be provided with a steel pedestal 33 for connecting with the steel square tube 31, and the steel pedestal 33 is mainly formed by splicing a first steel plate and a second steel plate, the first steel plate is used to connect with the main steel structure 4, and the second steel plate forms a connecting platform on its top for supporting the steel square tube 31.

[0042] Therefore, based on the above content, the roof system of this embodiment and the main steel structure 4 of the building to which it is connected are preferably connected and fixed with bolts to avoid the situation where a large amount of welding is required during the on-site assembly of traditional temporary buildings, thereby reducing the requirements for construction and avoiding the need to cut and re-weld when the on-site welding position and the connection position designed according to the specific site are wrong.

[0043] At the same time, all panels of the roof system can be disassembled and rebuilt in a different location within the service life. Except for embedded parts, local screws, bolts and other small hardware, almost all materials can be reused. According to the design service life of 25 years, the temporary building is used for 3-5 years at a time, and can be reused 5-8 times. Although the one-time investment is slightly higher than that of ordinary temporary buildings, it can be recycled for a long time, and the overall cost is greatly reduced.

[0044] The above embodiment is only a preferred technical solution of the present invention. Those skilled in the art should understand that the technical solutions or parameters in the embodiments can be modified or replaced without departing from the principle and essence of the present invention, and all should be included in the protection scope of the present invention.

Claims

1. An assembled roofing system, characterized in that: It comprises a roof frame (6) and a unit plate (1) connected to the roof frame (6), wherein the aluminum plate end of the unit plate (1) is provided with a connection portion extending into the roof frame (6), and the connection portion is sealed to the roof frame (6); the roof frame (6) is provided with a first frame (61) connected by an end sealing plate (2) at its ridge and roof, the first frame (61) is provided with a support structure (3) fixed to a main steel structure (4), and there is a connection gap between adjacent first frames (61); the end sealing plate (2) is provided with an inner pressure plate (23) and an outer pressure plate (21) on the indoor side and the outdoor side of the first frame (61), respectively, the inner pressure plate (23) and the outer pressure plate (21) simultaneously cover the first frames (61) on the adjacent sides, and the inner pressure plate (23) is provided with an adjustment bolt (22) passing through the connection gap and connected to the outer pressure plate (21); The roof frame (6) is provided with a second frame (62) and a third frame (63) connected in a spliced ​​manner at the joint of the upper and lower unit panels (1) of the roof, and the roof frame (6) is provided with a fourth frame (64) at the end of the unit panel (1) at the eaves.

2. The assembled roofing system according to claim 1, characterized in that: The outer portion of the outer pressure plate (21) is covered with a roof buckle cover, and a first roof buckle cover (211) and a second roof buckle cover (212) are respectively provided on the outer pressure plate (21) at the roof and the ridge.

3. The assembled roofing system according to claim 2, characterized in that: Aluminum veneers are arranged at the joint positions of the roof cover, and building sealant is evenly applied to the inner periphery.

4. The assembled roofing system according to claim 1, characterized in that: The inner pressure plate (23) is externally covered with an inner buckle cover (231).

5. The assembled roofing system according to claim 1, characterized in that: The unit plate (1) is layered in sequence from top to bottom, with an upper aluminum plate (11) and a lower aluminum plate (13), and a heat-insulating layer (12) is arranged between the upper aluminum plate (11) and the lower aluminum plate (13).

6. The assembled roofing system according to claim 1, characterized in that: An inner buckle portion connected to a second frame (62) is provided in the upper unit plate (1), and a mounting gap is provided between the inner buckle portion and the end of the upper unit plate (1), and a first square tube (65) is connected to the side end surface of the second frame (62); The end of the lower unit plate (1) and its third frame (63) extend into the inner buckle portion of the upper unit plate (1), and the mounting portion of the second frame (62) extends out of the upper unit plate (1) and is embeddedly connected with the third frame (63).

7. The assembled roofing system according to claim 1, characterized in that: The ends of the unit panels (1) at the upper layer and the ends of the unit panels (1) at the eaves are provided with sealing aluminum plates (14).

8. The assembled roofing system according to claim 1, characterized in that: The inner wall of the connecting portion of the unit plate (1) is provided with a sealing tape (5) which fits the outer surface of the roof frame (6).

9. The assembled roofing system according to claim 1, characterized in that: A second square tube (601) is arranged inside the roof frame (6).

10. The assembled roofing system according to claim 1, characterized in that: Reinforcing ribs (602) are arranged inside the roof frame (6).