Fabricated construction site supervision device and system based on BIM

By designing adjustable brackets and automatic cleaning devices in BIM-based construction supervision devices, the increase in labor and dust impact caused by the separate setting of cameras and dust instruments in the prior art is solved, and convenient installation, stable supervision and high efficiency are achieved Cleaning effect.

CN222128156UActive Publication Date: 2024-12-06JIANGSU JIANKE PROJECT MANAGEMENT
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323486160.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-20
Publication Date
2024-12-06
Estimated Expiration
2033-12-20

AI Technical Summary

Technical Problem

When installing and disassembling the existing BIM-based construction supervision device, the supervision camera and the dust instrument are separately installed, which increases the labor volume and is not convenient to clean the dust on the camera, reducing the practicality of the supervision device.

Method used

A supervision device including a bracket, screw, casing, fixing plate, dust meter, alarm lamp and cleaning device is designed. The camera height is adjusted through the screw and casing, and the camera is rotated under the motor drive for easy angle adjustment and dust cleaning. , automatically clean the dust on the camera with a sponge brush and slider assembly.

Benefits of technology

It improves the convenience of installation, disassembly and moving of the regulatory device, reduces the amount of labor, enhances the supervision efficiency and cleaning effect, and improves the practicality and stability of the regulatory device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222128156U_ABST
    Figure CN222128156U_ABST
Patent Text Reader

Abstract

The utility model discloses a BIM-based fabricated construction site supervision device and system, and relates to the technical field of construction supervision, the BIM-based fabricated construction site supervision device comprises a support, the arc surface of the support is slidably connected with a sleeve, screw rods slidably penetrate through the arc surfaces of the support and the sleeve, one end of each screw rod is in threaded connection with a nut, and the other end of each screw rod is in threaded connection with a bolt. The lower surface of the support is fixedly connected with a bottom plate, the upper surface of the sleeve is fixedly connected with a fixing plate, the surface of the fixing plate is fixedly connected with a dust meter and an alarm lamp, the surface of the fixing plate is provided with a cleaning device, the cleaning device comprises a fixing frame, and the fixing frame is fixedly connected with the fixing plate. The supervision effect of the supervision device on the construction site is improved, the problem that the workload of constructors is increased due to the fact that the camera and the dust meter need to be mounted and dismounted separately is reduced, dust attached to the camera on the construction site can be cleaned conveniently, and the practicability of the supervision device is further improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction supervision, and in particular to an assembled construction site supervision device and system based on BIM. Background Art

[0002] Prefabricated buildings refer to buildings that transfer a large amount of on-site work in traditional construction methods to factories, where building components and accessories (such as floor slabs, wall panels, stairs, balconies, etc.) are processed and manufactured in factories, transported to construction sites, and assembled and installed on site through reliable connection methods. Prefabricated buildings mainly include prefabricated concrete structures, steel structures, modern wooden structures, etc., and are representatives of modern industrialized production methods because they use standardized design, factory production, assembly construction, information management, and intelligent applications.

[0003] Prior art such as the utility model with publication number CN210128921U discloses a BIM-based construction supervision device, including a workbench, a display screen is provided on one side of the top of the workbench, a controller is provided on the other side of the top of the workbench, a fixed plate is provided on one side of the workbench, a first support column is fixed on the top of the fixed plate, and an alarm light is fixed on the other side of the top of the fixed plate. The utility model can check the noise, environmental PM10 and PM2.5 indicators of the construction site in real time through the dust meter provided, so as to avoid the construction affecting the normal life of nearby residents, and through the first and second sleeves provided, the second sleeve is stretched downward to a suitable height, fixed by a screw, and then the angle of the support rod is adjusted based on the fixed frame, so as to carry the construction detection device well, reduce the difficulty of transportation operation of on-site operators, and make the use effect of the BIM-based construction supervision device better.

[0004] The above-mentioned and existing related technologies often have the following defects: when the existing monitoring device is in use, the noise, environmental PM10 and PM2.5 indicators of the construction site are viewed in real time through the dust meter, while the monitoring camera is manually installed at other locations on the construction site. This method of setting the monitoring camera and the dust meter separately increases the labor workload during installation and disassembly of the monitoring device, and is inconvenient to clean the dust from the construction site attached to the monitoring camera, reducing the practicality of the monitoring device.

[0005] To this end, we propose a BIM-based prefabricated construction site supervision device and system. Utility Model Content

[0006] The purpose of the utility model is to provide a BIM-based assembled construction site monitoring device and system to solve the problems raised in the above-mentioned background technology.

[0007] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an assembled construction site supervision device and system based on BIM, comprising a bracket, a sleeve is slidably connected to the arc surface of the bracket, a screw is slidably penetrated through the arc surfaces of the bracket and the sleeve, a nut is threadedly connected to one end of the screw, a bottom plate is fixedly connected to the lower surface of the bracket, a fixed plate is fixedly connected to the upper surface of the sleeve, a dust meter and an alarm light are fixedly connected to the surface of the fixed plate, a cleaning device is provided on the surface of the fixed plate, the cleaning device comprises a fixed frame, the fixed frame is fixedly connected to the fixed plate, a motor is fixedly connected to the inner wall of the fixed frame, a support platform is fixedly connected to the surface of the fixed plate, a support plate is rotatably connected to the surface of the support plate, a camera is fixedly connected to the surface of the support plate, the support plate is fixedly connected to the output end of the motor, a square plate is fixedly connected to the surface of the support platform, a sliding rod is slidably connected to the surface of the square plate, one end of the sliding rod is fixedly connected to a card plate, a sponge brush is fixedly connected to the inner wall of the card plate, and the cross-section of the sponge brush is trapezoidal.

[0008] The effects achieved by the above components are: when the monitoring device is in use, the staff can select a suitable position on the construction site, place the bracket, and use screws and sleeves to adjust and fix the height of the camera. At this time, the noise, environmental PM10 and PM2.5 indicators of the construction site can be viewed in real time through the dust meter, and the camera can monitor the construction workers on the construction site. By setting the camera and the dust meter together, the convenience of installation, disassembly and movement of the monitoring device is effectively improved, and the workload of the staff is reduced. At this time, the motor in the fixed frame is started, and the motor can drive the camera on the support plate to rotate on the support table. When the motor is stopped, the camera will stop rotating, thereby fixing the camera's supervision angle. When the camera rotates, the card plate will gradually contact the camera, and when squeezed by the corners of the camera, it will drive the slide bar to move in the square plate, and drive the sponge brush gradually away from the camera. When the corners of the camera lose contact with the card plate, the sponge brush will contact the camera. At this time, the sponge brush can clean the dust on the camera, reducing the dust on the construction site attached to the camera, resulting in reduced clarity and affecting the supervision effect.

[0009] Preferably, a spring is fixedly connected to a surface of the sliding rod and the square plate that is close to each other.

[0010] The effect achieved by the above components is: when the sliding rod moves, it will drive the spring to stretch. When the card plate is out of contact with the corner of the camera, the sliding rod will drive the cleaning brush on the card plate to stick to the camera under the action of the spring tension, thereby improving the tightness between the sponge brush and the camera, making it easier for the sponge brush to clean the camera.

[0011] Preferably, a plurality of balls are rotatably connected to the surface of the square plate, a plurality of rolling grooves are formed on the arc surface of the slide rod, the balls are spherical structures, and the sizes of the balls and the rolling grooves on the arc surface of the slide rod are adapted.

[0012] The effect achieved by the above components is that the arrangement of the balls and the rolling grooves can effectively reduce the friction between the slide bar and the square plate, thereby reducing the jamming between the slide bar and the square plate.

[0013] Preferably, a fixing device is provided on the surface of the bottom plate, and the fixing device includes an insertion rod. A circular hole is opened on the surface of the bottom plate, and the insertion rod is connected to the bottom plate through and through. One end of the insertion rod is fixedly connected to a top cover, and the size of the top cover is larger than the size of the circular hole on the surface of the bottom plate.

[0014] The effect achieved by the above components is: after the bracket is placed at a suitable position on the construction site, the insertion rod can be pushed through the round hole on the bottom plate and inserted into the ground, which can preliminarily improve the stability of the bracket.

[0015] Preferably, the surface of the top cover is slidably connected to a support rod, one end of the support rod is fixedly connected to a round block, the arc surface of the round block is fixedly connected to a plurality of round rods, and the arc surface of the round rod is rotatably connected to a fixing rod.

[0016] The effect achieved by the above components is: pushing the support rod to move downward, at this time the round block will drive the fixing rod to move under the action of the support rod, at this time the bottom of the fixing rod will contact the insertion rod, and after being blocked by the insertion rod, it will tilt upward. When the fixing rod tilts upward, the resistance of the insertion rod when inserting into the ground can be reduced. When the insertion rod is inserted into the ground, the support rod can be pulled upward, the top of the fixing rod will contact the insertion rod and gradually rotate downward. At this time, stop pulling the support rod, and the fixing rod will remain in a horizontal position under the blockage of the insertion rod. At this time, the fixing rod can effectively increase the friction between the insertion rod and the ground, further improve the stability of the bracket, and thereby reduce the problem of shaking and tipping of the supervision device when it is hit by the outside world. When the supervision device needs to be moved or disassembled, the limit rod can be pulled out, and the support rod can continue to be pulled upward. The fixing rod will gradually tilt downward under the blockage of the insertion rod, and the insertion rod can be easily pulled out.

[0017] Preferably, a support block is fixedly connected to the surface of the top cover, a limit rod is slidably connected to the surface of the support block, three insertion holes are opened on the arc surface of the support rod, and the limit rod is snap-fitted with the insertion holes on the arc surface of the support rod.

[0018] The effect achieved by the above components is: pushing the limit rod to be inserted into the support rod can effectively improve the stability of the support rod and reduce the sliding of the support rod.

[0019] A system of an assembled construction site supervision device based on BIM includes a main control module, a monitoring module, a face recognition module and a display module. The monitoring module and the face recognition module are both arranged in a camera. The input end of the main control module is electrically connected to the output end of the monitoring module, the input end of the main control module is electrically connected to the output end of the face recognition, and the output end of the main control module is electrically connected to the input end of the display module.

[0020] The effect achieved by the above components is: when the camera is working, the construction site and construction workers are supervised through the monitoring module and the face recognition module. When problems occur at the construction site, the signals sent by the monitoring module and the face recognition module can be received through the main control module and viewed through the display module, which makes it easy to understand the problems occurring at the construction site.

[0021] Compared with the prior art, the beneficial effects of the utility model are:

[0022] The utility model improves the supervision effect of the supervision device on the construction site by arranging a cleaning device, reduces the need to separately install and disassemble the camera and the dust meter, which leads to an increase in the workload of construction workers, facilitates the cleaning of dust on the construction site attached to the camera, and further improves the practicability of the supervision device.

[0023] The utility model improves the stability of the monitoring device by arranging the fixing device, reduces the shaking and tipping of the monitoring device, and further improves the use effect of the monitoring device. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0025] Figure 2 It is a structural schematic diagram of the cleaning device in the utility model;

[0026] Figure 3 It is a cross-sectional structural diagram of the support plate in the utility model;

[0027] Figure 4 This is a schematic diagram of the split structure of the sponge brush in the utility model;

[0028] Figure 5 It is a cross-sectional structural schematic diagram of the fixing device in the utility model;

[0029] Figure 6 For the utility model Figure 5 Schematic diagram of the local structure;

[0030] Figure 7 It is a flow chart of the utility model.

[0031] In the figure: 1. bracket; 2. sleeve; 3. screw; 4. bottom plate; 5. fixing plate; 6. cleaning device; 601. fixing frame; 602. motor; 603. support platform; 604. support plate; 605. camera; 606. square plate; 607. slide bar; 608. card plate; 609. sponge brush; 610. spring; 611. ball; 612. rolling groove; 7. fixing device; 71. plug rod; 72. top cover; 73. support rod; 74. round block; 75. round rod; 76. fixing rod; 77. limit rod; 8. dust monitor; 9. alarm light. DETAILED DESCRIPTION

[0032] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0033] See also Figure 1-7 The utility model provides a technical solution: an assembled construction site monitoring device and system based on BIM, including a bracket 1, a sleeve 2 is slidably connected to the arc surface of the bracket 1, a screw 3 is slidably penetrated through the arc surfaces of the bracket 1 and the sleeve 2, a nut is threadedly connected to one end of the screw 3, a bottom plate 4 is fixedly connected to the lower surface of the bracket 1, a fixing plate 5 is fixedly connected to the upper surface of the sleeve 2, a dust monitor 8 and an alarm light 9 are fixedly connected to the surface of the fixing plate 5, a cleaning device 6 is provided on the surface of the fixing plate 5, and a fixing device 7 is provided on the surface of the bottom plate 4.

[0034] The specific arrangement and function of the cleaning device 6 and the fixing device 7 will be described in detail below.

[0035] like Figure 2 and Figure 3 as well as Figure 4As shown, the cleaning device 6 includes a fixed frame 601, which is fixedly connected to the fixed plate 5, the inner wall of the fixed frame 601 is fixedly connected to a motor 602, the surface of the fixed plate 5 is fixedly connected to a support platform 603, the surface of the support platform 603 is rotatably connected to a support plate 604, the surface of the support plate 604 is fixedly connected to a camera 605, the support plate 604 is fixedly connected to the output end of the motor 602, the surface of the support platform 603 is fixedly connected to a square plate 606, the surface of the square plate 606 is slidably connected to a slide rod 607, one end of the slide rod 607 is fixedly connected to a card plate 608, the inner wall of the card plate 608 is fixedly connected to a sponge brush 609, and the cross-section of the sponge brush 609 is trapezoidal. When the monitoring device is in use, the staff can select a suitable position at the construction site, place the bracket 1, and adjust and fix the height of the camera 605 with the help of the screw 3 and the sleeve 2. At this time, the noise, environmental PM10 and PM2.5 indicators of the construction site can be viewed in real time through the dust monitor 8, and the camera 605 can monitor the construction workers at the construction site. By setting the camera 605 and the dust monitor 8 together, the convenience of installing, disassembling and moving the monitoring device is effectively improved, and the labor of the staff is reduced. At this time, the motor 602 in the fixed frame 601 is started, and the motor 602 can drive the camera 605 on the support plate 604 to rotate on the support platform 603, so as to facilitate the monitoring angle of the camera 605. The camera 605 can be adjusted to improve the supervision efficiency of the construction sites of different ranges. When the motor 602 is stopped, the camera 605 will stop rotating, thereby fixing the supervision angle of the camera 605. When the camera 605 rotates, the card plate 608 will gradually contact the camera 605, and when squeezed by the corners of the camera 605, it will drive the slide bar 607 to move in the square plate 606, and drive the sponge brush 609 to gradually move away from the camera 605. When the corners of the camera 605 are out of contact with the card plate 608, the sponge brush 609 will contact the camera 605. At this time, the sponge brush 609 can clean the dust on the camera 605, reducing the dust on the construction site attached to the camera 605, resulting in reduced clarity and affecting the supervision effect. The side of the slide bar 607 and the square plate 606 close to each other is fixedly connected with a spring 610. When the slide bar 607 moves, the spring 610 will be extended. When the card plate 608 is out of contact with the corner of the camera 605, the slide bar 607 will drive the cleaning brush on the card plate 608 to abut against the camera 605 under the tension of the spring 610, thereby improving the tightness between the sponge brush 609 and the camera 605, making it easier for the sponge brush 609 to clean the camera 605. A plurality of balls 611 are rotatably connected to the surface of the square plate 606, and a plurality of rolling grooves 612 are provided on the arc surface of the slide bar 607. The balls 611 are spherical structures, and the sizes of the balls 611 and the rolling grooves 612 on the arc surface of the slide bar 607 are adapted.The arrangement of the ball bearings 611 and the rolling grooves 612 can effectively reduce the friction between the slide bar 607 and the square plate 606 , thereby reducing the possibility of jamming between the slide bar 607 and the square plate 606 .

[0036] like Figure 1 and Figure 5 as well as Figure 6 As shown, the fixing device 7 includes an insertion rod 71, a circular hole is provided on the surface of the bottom plate 4, the insertion rod 71 is connected to the bottom plate 4 through the insertion rod 71, one end of the insertion rod 71 is fixedly connected to a top cover 72, and the size of the top cover 72 is larger than the size of the circular hole on the surface of the bottom plate 4. After the bracket 1 is placed at a suitable position on the construction site, the insertion rod 71 can be pushed to pass through the circular hole on the bottom plate 4 and inserted into the ground, which can preliminarily improve the stability of the bracket 1. The surface of the top cover 72 is slidably connected to a support rod 73, one end of the support rod 73 is fixedly connected to a round block 74, the arc surface of the round block 74 is fixedly connected to a plurality of round rods 75, and the arc surface of the round rod 75 is rotatably connected to a fixing rod 76. When the locking cam 73 is in the unlocked position, the locking cam 73 is in the unlocked position, and the locking cam 73 is in the unlocked position, so that the locking cam 73 can be unlocked easily. The surface of the top cover 72 is fixedly connected with a support block, the surface of the support block is slidably connected with a limit rod 77, the arc surface of the support rod 73 is provided with three insertion holes, and the limit rod 77 is engaged with the insertion holes of the arc surface of the support rod 73. Pushing the limit rod 77 to insert into the support rod 73 can effectively improve the stability of the support rod 73 and reduce the possibility of the support rod 73 sliding.

[0037] like Figure 7As shown, a system of a BIM-based assembled construction site monitoring device includes a main control module, a monitoring module, a face recognition module and a display module. The monitoring module and the face recognition module are both arranged in a camera 605. The input end of the main control module is electrically connected to the output end of the monitoring module, the input end of the main control module is electrically connected to the output end of the face recognition, and the output end of the main control module is electrically connected to the input end of the display module. When the camera 605 is working, the construction site and construction personnel are monitored through the monitoring module and the face recognition module. When problems occur at the construction site, the signals sent by the monitoring module and the face recognition module can be received by the main control module, and viewed through the display module, so as to facilitate understanding of the problems occurring at the construction site.

[0038] Working principle: When the monitoring device is in use, the staff can select a suitable position on the construction site, place the bracket 1, and use the screw 3 and the sleeve 2 to adjust and fix the height of the camera 605. At this time, the noise, environmental PM10 and PM2.5 indicators of the construction site can be viewed in real time through the dust monitor 8, and the camera 605 can monitor the construction workers on the construction site. By setting the camera 605 and the dust monitor 8 together, the convenience of installing, disassembling and moving the monitoring device is effectively improved, and the workload of the staff is reduced. At this time, the motor in the fixed frame 601 is started. 602, the motor 602 can drive the camera 605 on the support plate 604 to rotate on the support platform 603, so as to facilitate the adjustment of the monitoring angle of the camera 605, and improve the monitoring efficiency of the camera 605 on construction sites of different ranges. When the motor 602 is stopped, the camera 605 will stop rotating, so as to fix the monitoring angle of the camera 605. When the camera 605 rotates, the card plate 608 will gradually contact with the camera 605, and when squeezed by the corner of the camera 605, it will drive the slide bar 607 to move in the square plate 606, and drive the sponge brush 609 to gradually move away. Camera 605, when the corner of camera 605 is out of contact with card plate 608, sponge brush 609 will contact with camera 605, at this time, sponge brush 609 can clean the dust on camera 605, reducing the dust on camera 605 attached to the construction site, resulting in reduced clarity and affecting the supervision effect. When the slide bar 607 moves, it will drive the spring 610 to stretch. When the card plate 608 is out of contact with the corner of camera 605, the slide bar 607 will drive the cleaning brush on the card plate 608 to stick to the camera 605 under the action of the pulling force of the spring 610, thereby improving the contact between the sponge brush 609 and the camera 605. The tightness between the cameras 605 makes it convenient for the sponge brush 609 to clean the cameras 605. The setting of the ball 611 and the rolling groove 612 can effectively reduce the friction between the slide bar 607 and the square plate 606, and reduce the jamming between the slide bar 607 and the square plate 606. By setting up the cleaning device 6, the supervision effect of the supervision device on the construction site is improved, and the need to separately install and disassemble the camera 605 and the dust meter 8, which leads to an increase in the workload of the construction workers, is reduced. It is convenient to clean the dust on the construction site attached to the camera 605, and the practicability of the supervision device is further improved.

[0039] After the bracket 1 is placed at a suitable position on the construction site, the support rod 73 is first pushed to move downward. At this time, the round block 74 will drive the fixing rod 76 to move under the action of the support rod 73. At this time, the bottom of the fixing rod 76 contacts the insertion rod 71 and, after being blocked by the insertion rod 71, tilts upward. At this time, the insertion rod 71 can be pushed through the round hole on the bottom plate 4 and inserted into the ground, which can preliminarily improve the stability of the bracket 1. When the fixing rod 76 tilts upward, the resistance of the insertion rod 71 when it is inserted into the ground can be reduced. At this time, the insertion rod 71 is inserted into the ground, and the support rod 73 can be pulled upward. The top of the fixing rod 76 contacts the insertion rod 71 and gradually rotates downward. At this time, stop pulling the support rod 73, and the fixing rod 76 will remain in a horizontal position under the blockage of the insertion rod 71. The fixing rod 76 can effectively increase the friction between the insertion rod 71 and the ground, further improve the stability of the bracket 1, thereby reducing the problem of shaking and tipping of the monitoring device when it is hit by the outside world. At this time, pushing the limit rod 77 to be inserted into the support rod 73 can effectively improve the stability of the support rod 73 and reduce the sliding of the support rod 73. When the monitoring device needs to be moved or disassembled, the limit rod 77 can be pulled out. At this time, the support rod 73 continues to be pulled upward. The fixing rod 76 will gradually tilt downward under the obstruction of the insertion rod 71, and the insertion rod 71 can be easily pulled out at this time. By setting the fixing device 7, the stability of the monitoring device is improved, the shaking and tipping of the monitoring device are reduced, and the use effect of the monitoring device is further improved.

[0040] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0041] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A BIM-based assembled construction site monitoring device, comprising a bracket (1), the arc surface of the bracket (1) being slidably connected to a sleeve (2), the arc surfaces of the bracket (1) and the sleeve (2) both being slidably penetrated by a screw (3), one end of the screw (3) being threadedly connected to a nut, the lower surface of the bracket (1) being fixedly connected to a bottom plate (4), the upper surface of the sleeve (2) being fixedly connected to a fixing plate (5), the surface of the fixing plate (5) being fixedly connected to a dust monitor (8) and an alarm light (9), the surface of the fixing plate (5) being provided with a cleaning device (6), characterized in that: The cleaning device (6) comprises a fixing frame (601), wherein the fixing frame (601) is fixedly connected to a fixing plate (5), a motor (602) is fixedly connected to the inner wall of the fixing frame (601), a support platform (603) is fixedly connected to the surface of the fixing plate (5), a support plate (604) is rotatably connected to the surface of the support platform (603), a camera (605) is fixedly connected to the surface of the support plate (604), the support plate (604) is fixedly connected to the output end of the motor (602), a square plate (606) is fixedly connected to the surface of the square plate (606), a sliding rod (607) is slidably connected to the surface of the square plate (606), one end of the sliding rod (607) is fixedly connected to a clamping plate (608), a sponge brush (609) is fixedly connected to the inner wall of the clamping plate (608), and the cross section of the sponge brush (609) is trapezoidal.

2. According to the BIM-based assembled construction site monitoring device of claim 1, it is characterized by: A spring (610) is fixedly connected to a surface of the sliding rod (607) and the square plate (606) that is close to each other.

3. The BIM-based assembled construction site monitoring device according to claim 2, characterized in that: A plurality of balls (611) are rotatably connected to the surface of the square plate (606), a plurality of rolling grooves (612) are provided on the arc surface of the slide bar (607), the balls (611) are spherical structures, and the sizes of the balls (611) and the rolling grooves (612) on the arc surface of the slide bar (607) are adapted.

4. The BIM-based assembled construction site monitoring device according to claim 1, characterized in that: A fixing device (7) is provided on the surface of the bottom plate (4), the fixing device (7) comprising an insertion rod (71), a circular hole is provided on the surface of the bottom plate (4), the insertion rod (71) is connected to the bottom plate (4) through and through, one end of the insertion rod (71) is fixedly connected to a top cover (72), the size of the top cover (72) being larger than the size of the circular hole on the surface of the bottom plate (4).

5. The BIM-based assembled construction site monitoring device according to claim 4 is characterized in that: The surface of the top cover (72) is slidably connected to a support rod (73), one end of the support rod (73) is fixedly connected to a round block (74), the arc surface of the round block (74) is fixedly connected to a plurality of round rods (75), and the arc surface of the round rod (75) is rotatably connected to a fixing rod (76).

6. The BIM-based assembled construction site monitoring device according to claim 5 is characterized by: A support block is fixedly connected to the surface of the top cover (72), a limit rod (77) is slidably connected to the surface of the support block, three insertion holes are formed on the arc surface of the support rod (73), and the limit rod (77) is snap-fitted with the insertion holes on the arc surface of the support rod (73).

7. A system of a BIM-based assembled construction site supervision device, the system adopts a BIM-based assembled construction site supervision device according to any one of claims 1 to 6, characterized in that: It comprises a main control module, a monitoring module, a face recognition module and a display module, wherein the monitoring module and the face recognition module are both arranged in a camera (605), the input end of the main control module is electrically connected to the output end of the monitoring module, the input end of the main control module is electrically connected to the output end of the face recognition module, and the output end of the main control module is electrically connected to the input end of the display module.