Dumbbell-shaped reinforced concrete column

By designing the avoidance section and bearing part of dumbbell-shaped reinforced concrete columns, the problems of vulnerability and insufficient strength of traditional columns are solved, greater space utilization and structural strength improvement are achieved, and service life is extended.

CN222207342UInactive Publication Date: 2024-12-20INSPECTION & CERTIFICATION CO LTD MCC +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420775330.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-15
Publication Date
2024-12-20
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional rectangular reinforced concrete columns are easily damaged by collision in industrial factories, resulting in concrete corners falling off and steel bars rusting, poor structural strength and durability, and too large cross-sectional area cannot meet the operating needs of new cranes.

Method used

A dumbbell-shaped reinforced concrete column is designed to reduce cross-sectional area and increase structural strength by setting up a barrier section and a load-bearing part in the column, and ensure the stability of force transmission through welding connections and transition sections to avoid equipment collision and damage.

Benefits of technology

It effectively reduces the collision between the equipment and reinforced concrete columns, increases the structural strength and durability of the columns, meets the operation needs of larger equipment, and extends the service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222207342U_ABST
    Figure CN222207342U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of concrete column transformation, and discloses a dumbbell-shaped reinforced concrete column. The dumbbell-shaped reinforced concrete column comprises a bottom column body, a top column body and a receding section, the receding section comprises a receding column body, the two corresponding sides of the receding column body are each provided with a force bearing part, and the two force bearing parts are located on the inner sides of reinforcing steel bars on the two corresponding side faces of the bottom column body and the top column body. According to the dumbbell-shaped reinforced concrete column, the avoiding section is formed at the preset position, so that the sectional area of the avoiding section is reduced, a larger space is provided for a site, the requirement of operation of large-size equipment on the site is met, collision between the equipment and the reinforced concrete column is reduced, and meanwhile, the service life of the reinforced concrete column is prolonged. The force bearing part can improve the structural strength of the position, easy to scrape and collide, of the reinforced concrete column, the force bearing part is scraped and collided by equipment even if misoperation occurs, the phenomenon that the reinforced concrete column is damaged is avoided, and the durability of the reinforced concrete column is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of existing concrete column reconstruction, in particular to a dumbbell-shaped reinforced concrete column. Background Art

[0002] Reinforced concrete columns are columns made of reinforced concrete. They are the most basic load-bearing components in various engineering structures such as houses, bridges, and hydraulic structures. They are often used as floor pillars, bridge piers, foundation columns, towers, and truss compression rods.

[0003] Traditional reinforced concrete columns are rectangular column structures. In industrial plants, there are many forklifts coming and going, and during operation, the corners of reinforced concrete columns are often damaged. As a result, the concrete corners fall off, and the steel bars (main force-bearing bars) on the sides leak out, causing the steel bars to rust, affecting the structural strength and service life of the concrete columns, and the durability is poor. In addition, because the operating crane is often replaced and the width of the newly replaced crane increases, the cross-sectional area of ​​the traditional reinforced concrete column is larger and cannot meet the operating requirements of the new crane. It can be seen that the traditional concrete column cannot meet the structural strength requirements, has poor durability, and its own cross-section is large, which cannot meet the site requirements for the operation of larger equipment. Utility Model Content

[0004] In order to solve the above technical problem or at least partially solve the above technical problem, the utility model provides a dumbbell-shaped reinforced concrete column.

[0005] The utility model provides a dumbbell-shaped reinforced concrete column, comprising a bottom column, a top column and an avoidance section, wherein the avoidance section comprises an avoidance column for connecting the top column and the bottom column, corresponding two sides of the avoidance column are respectively provided with load-bearing parts, the top and bottom of the load-bearing parts are respectively connected to the steel bars on the top column and the steel bars on the bottom column, wherein the two load-bearing parts are located on the inner sides of the steel bars on the corresponding two side surfaces of the bottom column and the top column.

[0006] Optionally, the load-bearing part includes two first steel plates and one second steel plate arranged on the side of the avoidance column, one of the first steel plates is used to connect with the steel bars on the top column, the other first steel plate is used to connect with the steel bars on the bottom column, both ends of the second steel plate are respectively connected to the two first steel plates, and the second steel plate is located on the side of the first steel plate facing the avoidance column.

[0007] Optionally, the thickness of the first steel plate is greater than the thickness of the second steel plate.

[0008] Optionally, a transition section is provided at the connection between the first steel plate and the second steel plate.

[0009] Optionally, the avoidance section further includes two connecting parts, and the two connecting parts are respectively used to connect corresponding sides of the two load-bearing parts.

[0010] Optionally, the connecting portion includes two side plates arranged on the side surfaces of the avoidance column, and a plurality of connecting plates for connecting the two side plates, and the two side plates are respectively connected to the two load-bearing portions.

[0011] Optionally, the side panels extend in a vertical direction, and the gusset panels extend in a horizontal direction.

[0012] Optionally, a plurality of the fixing plates are arranged at intervals along the vertical direction.

[0013] Optionally, the top of the side panel extends upward from the load-bearing part, and the top extending end of the side panel is connected to the top column, and the bottom of the side panel extends downward from the load-bearing part, and the bottom extending end of the side panel is connected to the bottom column.

[0014] Optionally, the sizes of the two panels at the edges are larger than the sizes of the remaining panels.

[0015] Compared with the prior art, the technical solution provided by the present invention has the following advantages:

[0016] The dumbbell-shaped reinforced concrete column provided by the utility model is provided with an avoidance section at a preset position to reduce the cross-sectional area at the avoidance section, thereby providing a larger space for the site, meeting the site requirements for the operation of larger-sized equipment, and reducing the collision between the equipment and the reinforced concrete column. At the same time, the load-bearing part can increase the structural strength of the reinforced concrete column at the position where it is easy to be scratched, and even if an operating error occurs, it is the equipment that scratches the load-bearing part, thereby avoiding the phenomenon of damaging the reinforced concrete column and increasing the durability of the reinforced concrete column. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The accompanying drawings herein are incorporated in and constitute a part of the specification, illustrate embodiments consistent with the present utility model, and together with the description, are used to explain the principles of the present utility model.

[0018] In order to more clearly illustrate the implementation mode of the utility model or the technical solution in the prior art, the drawings required for use in the implementation mode or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0019] Figure 1 It is a side view of the dumbbell-shaped reinforced concrete column described in the embodiment of the utility model;

[0020] Figure 2 This is a front view of the dumbbell-shaped reinforced concrete column described in the embodiment of the utility model;

[0021] Figure 3 It is a cross-sectional view of the first steel plate position of the dumbbell-shaped reinforced concrete column described in the embodiment of the utility model;

[0022] Figure 4 This is a cross-sectional view of the dumbbell-shaped reinforced concrete column at the position of the second steel plate described in the embodiment of the utility model.

[0023] Description of Reference Numerals

[0024] 1. Bottom column; 2. Top column; 3. Avoidance section; 31. Avoidance column; 32. Load-bearing part; 321. First steel plate; 322. Second steel plate; 323. Transition section; 33. Connection part; 331. Side plate; 332. Adhesive plate; 4. Rebar. DETAILED DESCRIPTION

[0025] In order to more clearly understand the above-mentioned purpose, features and advantages of the utility model, the scheme of the utility model will be further described below. It should be noted that the embodiments of the utility model and the features in the embodiments can be combined with each other without conflict.

[0026] The following description sets forth many specific details to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein; obviously, the implementation methods in the specification are only part of the implementation methods of the present invention, rather than all of the implementation methods.

[0027] Combination Figures 1 to 4 As shown, the dumbbell-shaped reinforced concrete column provided by the embodiment of the utility model includes a bottom column 1, a top column 2 and an avoidance section 3. Specifically, the top column 2, the avoidance section 3 and the bottom column 1 are arranged in sequence from top to bottom. The avoidance section 3 includes an avoidance column 31 for connecting the top column 2 and the bottom column 1, wherein the avoidance column 31 is integrally formed with the top column 2 and the bottom column 1 to increase the structural strength. The side of the avoidance column 31 is a planar structure, which is convenient for the installation of subsequent structures.

[0028] The corresponding two sides of the avoidance column 31 are respectively provided with a load-bearing part 32, and the top and bottom of the load-bearing part 32 are respectively connected to the steel bars 4 on the top column 2 and the steel bars 4 on the bottom column 1, so that the force at the top can be transmitted to the load-bearing part 32 through the top column 2, and then transmitted to the bottom column 1, ensuring the stable transmission of the force, so that the dumbbell-shaped reinforced concrete column can provide sufficient supporting force. Among them, the two load-bearing parts 32 are located on the inner side of the steel bars 4 on the two corresponding sides of the bottom column 1 and the top column 2. This design method makes the cross-sectional area of ​​the avoidance section 3 smaller, and the top column 2, the avoidance section 3 and the bottom column 1 can form a dumbbell shape, providing a larger space for the use of the equipment. It can be understood that the load-bearing part 32 of the present application is supported by a hard material, such as stainless steel, to ensure its own structural strength and force transmission effect.

[0029] The dumbbell-shaped reinforced concrete column provided by the utility model is provided with an avoidance section 3 at a preset position to reduce the cross-sectional area at the position of the avoidance section 3, provide a larger space for the site, meet the site requirements for the operation of larger-sized equipment, and reduce the collision between the equipment and the reinforced concrete column 4. At the same time, the load-bearing part 32 can increase the structural strength of the reinforced concrete column 4 at the position that is easy to scratch. Even if an operating error occurs, it is the equipment that scratches the load-bearing part 32, avoiding the phenomenon of damaging the reinforced concrete column 4, thereby increasing the durability of the reinforced concrete column 4.

[0030] In some embodiments, in combination Figure 1 and Figure 2 As shown, the load-bearing part 32 includes two first steel plates 321 and a second steel plate 322 arranged on the side of the avoidance column 31, wherein one of the first steel plates 321 is used to connect with the steel bars 4 on the top column 2, and the other first steel plate 321 is used to connect with the steel bars 4 on the bottom column 1, and both ends of the second steel plate 322 are respectively connected to the two first steel plates 321, and the second steel plate 322 is located on the side of the first steel plate 321 facing the avoidance column 31.

[0031] Specifically, the first steel plate 321 is connected to the steel bars 4 on the top column 2 and the steel bars 4 on the bottom column 1 by welding, and the two first steel plates 321 are also connected to the two ends of the second steel plate 322 by welding to increase the firmness of the connection. The second steel plate 322 is located on the inner side of the first steel plate 321, so that the distance between the side of the second steel plate 322 and the side of the bottom column 1 and the top column 2 is large enough, further providing a clearance space for the movement of the equipment.

[0032] In some embodiments, in combination Figures 1 to 4 As shown, the thickness of the first steel plate 321 is greater than the thickness of the second steel plate 322 .

[0033] like Figure 4 As shown, the first steel plate 321 with a larger thickness has sufficient structural strength to ensure the welding effect of the first steel plate 321 and the steel bars 4 on the top column 2 and the steel bars 4 on the bottom column 1, and at the same time, can effectively transmit the force from the steel bars 4 on the top column 2. Figure 4 As shown, the thickness of the second steel plate 322 is relatively small, but it can ensure its own structural strength and force transmission effect. In addition, the second steel plate 322 reduces its own structural thickness, can reduce the space occupied in the horizontal direction, and further provide avoidance space for the movement of the equipment.

[0034] In some embodiments, Figure 1 As shown, a transition section 323 is provided at the connection between the first steel plate 321 and the second steel plate 322 .

[0035] With this design, the force on the first steel plate 321 at the top can be stably transmitted to the second steel plate 322 through the transition section 323, and the force received by the second steel plate 322 can be stably transmitted to the first steel plate 321 at the bottom through the transition section 323, thereby ensuring the stability of force transmission.

[0036] The cross section of the transition section 323 may be a right triangle, and the right angle of the transition section 323 is welded at the connection between the first steel plate 321 and the second steel plate 322 to ensure stable transmission and combination of forces. Figures 1 to 4 As shown, the avoidance section 3 further includes two connecting portions 33 , and the two connecting portions 33 are respectively used to connect corresponding sides of the two load-bearing portions 32 .

[0037] In this design, the two connecting parts 33 are used to connect the two load-bearing parts 32 into a whole. The two load-bearing parts 32 and the two connecting parts 33 are wrapped around the avoidance column 31 to ensure the stability of force transmission and increase the load-bearing effect of the load-bearing part 32.

[0038] In some embodiments, when the load-bearing portion 32 is designed with two first steel plates 321 and one second steel plate 322, the connecting portion 33 connects the relatively arranged first steel plates 321 and second steel plates 322 of the two load-bearing portions 32 to ensure the connection effect.

[0039] In some embodiments, the connection portion 33 includes two side plates 331 disposed on the side of the avoidance column 31 , and a plurality of gusset plates 332 for connecting the two side plates 331 , and the two side plates 331 are respectively connected to the two load-bearing portions 32 .

[0040] Specifically, both side plates 331 extend in the vertical direction, and one side of the side plate 331 is welded to the load-bearing part 32, specifically, the first steel plate 321 and the second steel plate 322 of the load-bearing part 32. A plurality of gusset plates 332 are provided, and the plurality of gusset plates 332 extend in the horizontal direction, and the plurality of gusset plates 332 are spaced apart in the vertical direction, so as to ensure the connection effect of the two relatively arranged side plates 331, and further ensure the connection effect of the two load-bearing parts 32.

[0041] In some embodiments, in combination Figure 1 and Figure 2 As shown, the top of the side plate 331 extends upward from the load-bearing portion 32, and the top extended end of the side plate 331 is connected to the top column 2, and the bottom of the side plate 331 extends downward from the load-bearing portion 32, and the bottom extended end of the side plate 331 is connected to the bottom column 1.

[0042] Under this design, the side panel 331 can also be connected to the top column 2 and the bottom column 1. At this time, the top column 2 and the bottom column 1 form an integral structure through the connecting part 33 of the side panel 331 and the load-bearing part 32, ensuring the load-bearing effect of the entire reinforced concrete column 4.

[0043] In some embodiments, continue to refer to Figure 1 and Figure 2 , the sizes of the two panels 332 at the edges are larger than the sizes of the other panels 332 .

[0044] Since the top and bottom surfaces of the side panel 331 also need to be connected to the top column 2 and the bottom column 1 , the top and bottom surfaces of the side panel 331 can be reinforced by a larger-sized fixing plate 332 to ensure the connection effect between the side panel 331 and the top column 2 and the bottom column 1 .

[0045] The utility model also provides a method for transforming a reinforced concrete column, comprising the following steps:

[0046] Step S1, the concrete and the stressed steel bars 4 on the corresponding two sides of the target position of the steel bar 4 concrete column are removed to form a top column 2 located above the target position and a bottom column 1 located below the target position, and an avoidance column 31 is formed at the target position. Specifically, the side of the avoidance column 31 is a planar structure or a nearly planar structure, which is convenient for the installation of subsequent components.

[0047] Step S2, connecting the steel bars 4 on the top column 2 and the steel bars 4 on the bottom column 1 through the load-bearing part 32, and making the two load-bearing parts 32 located inside the steel bars 4 on the two corresponding side surfaces of the bottom column 1 and the top column 2. The load-bearing part 32 here includes all the technical features of the load-bearing part 32 described above.

[0048] In some embodiments, the load-bearing portion 32 includes two first steel plates 321 and a second steel plate 322. During installation, the two first steel plates 321 are welded to the steel bars 4 on the bottom column 1 and the top column 2, respectively, and then the two ends of the second steel plate 322 are welded to the inner sides of the two ends of the first steel plate 321, and a transition section 323 is welded at the connection between the first steel plate 321 and the second steel plate 322, thereby completing the installation of the load-bearing portion 32.

[0049] Under this design, the force is transmitted through the top column 2 in sequence to the first steel plate 321 at the top, the transition section 323 at the top, the second steel plate 322, the transition section 323 at the bottom, and the first steel plate 321 at the bottom and then transmitted to the bottom column 1, ensuring the stability of force transmission.

[0050] In other embodiments, the utility model provides a method for transforming a reinforced concrete column, comprising the following steps:

[0051] Step S1, the concrete and the stressed steel bars 4 on the corresponding two sides of the target position of the steel bar 4 concrete column are removed to form a top column 2 located above the target position and a bottom column 1 located below the target position, and an avoidance column 31 is formed at the target position. Specifically, the side of the avoidance column 31 is a planar structure or a nearly planar structure, which is convenient for the installation of subsequent components.

[0052] Step S2, connecting the steel bars 4 on the top column 2 and the steel bars 4 on the bottom column 1 through the load-bearing part 32, and making the two load-bearing parts 32 located inside the steel bars 4 on the two corresponding side surfaces of the bottom column 1 and the top column 2. The load-bearing part 32 here includes all the technical features of the load-bearing part 32 described above.

[0053] In some embodiments, the load-bearing portion 32 includes two first steel plates 321 and a second steel plate 322. During installation, the two first steel plates 321 are welded to the steel bars 4 on the bottom column 1 and the top column 2, respectively, and then the two ends of the second steel plate 322 are welded to the inner sides of the two ends of the first steel plate 321, and a transition section 323 is welded at the connection between the first steel plate 321 and the second steel plate 322, thereby completing the installation of the load-bearing portion 32.

[0054] Under this design, the force is transmitted through the top column 2 in sequence to the first steel plate 321 at the top, the transition section 323 at the top, the second steel plate 322, the transition section 323 at the bottom, and the first steel plate 321 at the bottom and then transmitted to the bottom column 1, ensuring the stability of force transmission.

[0055] Step S3, connecting the corresponding side surfaces of the two load-bearing parts 32 through the connecting part 33. The connecting part 33 here includes all the technical features of the connecting part 33 mentioned above.

[0056] In some embodiments, the connection part 33 includes two side plates 331 and a plurality of gusset plates 332. When in use, the two side plates 331 are respectively welded to the corresponding first steel plate 321 and the second steel plate 322, and the two connected side plates 331 are then welded to the plurality of gusset plates 332 to complete the connection of the connection part 33. The top of the side plate 331 is connected to the top column 2, and the bottom of the side plate 331 is connected to the bottom column 1. The connection method can be screw connection, or connecting ribs are inserted through the top column 2 and the bottom column 1, and the side plate 331 is welded to the protruding end of the connecting rib, and the connecting rib is carried on the existing steel bar 4.

[0057] In this design, the two connecting parts 33 and the two load-bearing parts 32 are connected as a whole to ensure the load-bearing and force-transmitting effects.

[0058] Step S4, after the load-bearing part 32 and the connecting part 33 are installed, structural adhesive is poured into the gap between the load-bearing part 32 and the avoidance column 31 to ensure structural strength.

[0059] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0060] The above description is only a specific embodiment of the present invention, so that those skilled in the art can understand or implement the present invention. Various modifications to these embodiments will be obvious to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments described herein, but should conform to the widest scope consistent with the principles and novel features of the present invention.

Claims

1. A dumbbell-shaped reinforced concrete column, characterized in that: The invention comprises a bottom column (1), a top column (2) and an avoidance section (3), wherein the avoidance section (3) comprises an avoidance column (31) for connecting the top column (2) and the bottom column (1), and the avoidance column (31) is provided with load-bearing parts (32) on two corresponding sides, and the top and bottom of the load-bearing parts (32) are respectively connected to the steel bars (4) on the top column (2) and the steel bars (4) on the bottom column (1), wherein the two load-bearing parts (32) are located on the inner sides of the steel bars (4) on the two corresponding side surfaces of the bottom column (1) and the top column (2).

2. The dumbbell-shaped reinforced concrete column according to claim 1, characterized in that: The load-bearing portion (32) comprises two first steel plates (321) and a second steel plate (322) arranged on the side of the avoidance column (31), wherein one of the first steel plates (321) is used to connect to the steel bars (4) on the top column (2), and the other first steel plate (321) is used to connect to the steel bars (4) on the bottom column (1), and the two ends of the second steel plate (322) are respectively connected to the two first steel plates (321), and the second steel plate (322) is located on the side of the first steel plate (321) facing the avoidance column (31).

3. The dumbbell-shaped reinforced concrete column according to claim 2, characterized in that: The thickness of the first steel plate (321) is greater than the thickness of the second steel plate (322).

4. The dumbbell-shaped reinforced concrete column according to claim 2, characterized in that: A transition section (323) is provided at the connection between the first steel plate (321) and the second steel plate (322).

5. The dumbbell-shaped reinforced concrete column according to any one of claims 1 to 4, characterized in that: The avoidance section (3) further comprises two connecting parts (33), and the two connecting parts (33) are respectively used to connect corresponding sides of the two load-bearing parts (32).

6. The dumbbell-shaped reinforced concrete column according to claim 5, characterized in that: The connecting portion (33) comprises two side plates (331) arranged on the side of the avoidance column (31), and a plurality of gusset plates (332) used for connecting the two side plates (331), and the two side plates (331) are respectively connected to the two load-bearing portions (32).

7. The dumbbell-shaped reinforced concrete column according to claim 6, characterized in that: The side plate (331) extends in a vertical direction, and the gusset plate (332) extends in a horizontal direction.

8. The dumbbell-shaped reinforced concrete column according to claim 6, characterized in that: A plurality of the fixing plates (332) are arranged at intervals along the vertical direction.

9. The dumbbell-shaped reinforced concrete column according to claim 6, characterized in that: The top of the side plate (331) extends upward from the load-bearing portion (32), and the top protruding end of the side plate (331) is connected to the top column (2); the bottom of the side plate (331) extends downward from the load-bearing portion (32), and the bottom protruding end of the side plate (331) is connected to the bottom column (1).

10. The dumbbell-shaped reinforced concrete column according to claim 6, characterized in that: The sizes of the two fixing plates (332) at the edges are larger than the sizes of the other fixing plates (332).

Citation Information

Cited By

  • Dumbbell-shaped reinforced concrete column and transformation method of reinforced concrete column

    CN118327336A