Water delivery structure for high-frequency breaking hammer, high-frequency breaking hammer and tunneling equipment

By designing a spray system combining internal and external waterways on high-frequency breaker hammers, the dust drifting problem is solved, and the precise spraying and slowing drifting effect is achieved at the source of dust generation, which improves the dust protection effect.

CN222253950UActive Publication Date: 2024-12-27HUNAN BLUE OCEAN INTELLIGENT EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421034436.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-13
Publication Date
2024-12-27
Estimated Expiration
2034-05-13

AI Technical Summary

Technical Problem

During high-frequency breaker operation, dust is prone to drift, and the existing spraying system cannot effectively spray the moment and source of dust, resulting in poor dust protection effect.

Method used

A water transport structure combining the inner water channel and the outer water channel is designed. The outer water channel is located outside the vibration output part, and the inner water channel is arranged in the vibration output part. Large-scale spraying and precise spraying are achieved through the first, second and third nozzles. Ensure that the source of dust generation is sprayed in time.

Benefits of technology

Effectively slows down dust drift, improves dust protection effect, and ensures timely spraying and cleaning of dust at the moment of occurrence.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222253950U_ABST
    Figure CN222253950U_ABST
Patent Text Reader

Abstract

The embodiment of the utility model provides a water conveying structure for a high-frequency breaking hammer, the high-frequency breaking hammer and tunneling equipment, and relates to the field of engineering machinery. The water conveying structure for the high-frequency breaking hammer comprises an outer water channel used for conveying water to a first spray head and an inner water channel used for conveying water to a second spray head. Wherein the outer water channel is located in an outer water pipe on the outer side of a vibration output part of the high-frequency breaking hammer, and the inner water channel is formed in the vibration output part. According to the water conveying structure for the high-frequency breaking hammer, outer water conveying spraying can be achieved through the outer water channel, inner water conveying spraying can be achieved through the inner water channel, on one hand, large-range spraying is achieved, on the other hand, accurate spraying can be conducted on a generation source at the moment when dust is generated, and then dust drifting is slowed down. The high-frequency breaking hammer and the tunneling equipment comprise the water conveying structure for the high-frequency breaking hammer, and all the functions of the water conveying structure for the high-frequency breaking hammer are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of engineering machinery, and in particular to a water delivery structure for a high-frequency breaker, a high-frequency breaker and excavation equipment. Background Art

[0002] During the operation of the high-frequency breaker, a large amount of dust will be generated when the bucket teeth come into contact with the broken rocks, which will have a negative impact on the health of the workers and the ecological environment.

[0003] Existing dust protection usually arranges a spray pipe on the outside of the high-frequency breaker, but for safety reasons, there is usually a certain distance between the end of the spray pipe and the bucket tooth, so that it is impossible to spray at the moment when the dust is generated and at the source of the dust, causing the dust to easily float. Utility Model Content

[0004] The utility model provides a water delivery structure for a high-frequency breaker, a high-frequency breaker and excavation equipment, which can achieve precise spraying of the source of dust at the moment of dust generation by arranging an inner waterway in coordination with an outer waterway, thereby slowing down the dispersion of dust.

[0005] The embodiments of the present invention can be implemented as follows:

[0006] The embodiment of the utility model provides a water delivery structure for a high-frequency breaker, which comprises:

[0007] an outer water channel for conveying water to the first sprinkler and an inner water channel for conveying water to the second sprinkler;

[0008] Wherein, the external water channel is located in an external water pipe outside the vibration output part of the high-frequency breaker, and the internal water channel is opened in the vibration output part.

[0009] Optionally, the vibration output part includes a connected drill rod and a bucket tooth seat, and the internal water channel includes a front water channel and a rear water channel that are connected, the front water channel is opened in the drill rod, and the rear water channel is opened in the bucket tooth seat.

[0010] Optionally, a first groove is formed on the outer side of the drill rod, and the first groove and the outer water pipe are combined to form the front water channel.

[0011] Optionally, a reserved hole is formed between the drill rod and the bucket tooth seat, and the reserved hole is connected between the front water channel and the rear water channel.

[0012] Optionally, the water supply structure for the high-frequency breaker also includes a third nozzle, which is arranged at the vibration output part, the third nozzle is spaced apart from the first nozzle, and the inlet of the third nozzle is connected to the outlet of the first nozzle.

[0013] Optionally, the second nozzle is arranged at the vibration output part and is spaced apart from the output end of the inner water channel.

[0014] Optionally, the vibration output portion is provided with a second groove, and the output end of the inner water channel is provided on the groove wall of the second groove.

[0015] Optionally, the second nozzle is accommodated in the second groove.

[0016] An embodiment of the utility model further provides a high-frequency breaker hammer, including a water delivery structure for the high-frequency breaker hammer.

[0017] An embodiment of the utility model further provides a tunneling device, comprising a high-frequency breaker hammer.

[0018] The beneficial effects of the water delivery structure for high-frequency breaker, high-frequency breaker and excavation equipment of the embodiment of the utility model include, for example:

[0019] The water supply structure for the high-frequency breaker includes an external water channel for supplying water to the first nozzle and an internal water channel for supplying water to the second nozzle; wherein the external water channel is located in an external water pipe outside the vibration output part of the high-frequency breaker, and the internal water channel is opened in the vibration output part. The water supply structure for the high-frequency breaker can realize external water supply spraying through the external water channel and internal water supply spraying through the internal water channel, which can realize large-scale spraying on the one hand, and can accurately spray the source of dust at the moment of dust generation on the other hand, thereby slowing down the dust dispersion.

[0020] The high-frequency breaker comprises a water delivery structure for the high-frequency breaker, which has all the functions of the water delivery structure for the high-frequency breaker.

[0021] The excavation equipment includes a high-frequency breaker hammer, which has all the functions of a high-frequency breaker hammer. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 This is a schematic structural diagram of a water delivery structure for a high-frequency breaker provided in an embodiment of the utility model;

[0024] Figure 2 It is a cross-sectional schematic diagram of a water delivery structure for a high-frequency breaker provided in an embodiment of the utility model.

[0025] Icons: 100-water delivery structure for high-frequency breaker; 110-external water channel; 120-internal water channel; 121-front water channel; 122-rear water channel; 130-first nozzle; 140-second nozzle; 150-third nozzle; 180-external water pipe; 190-vibration output part; 191-drill rod; 192-bucket tooth seat; 193-first groove; 194-reserved hole; 195-second groove. DETAILED DESCRIPTION

[0026] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.

[0027] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0029] In the description of the present utility model, it should be noted that if the terms "upper", "lower", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the utility model product is usually placed when used. It is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present utility model.

[0030] In addition, the terms “first”, “second”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.

[0031] The terms "comprises," "comprising," or any other variation thereof are intended to encompass non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article, or apparatus that includes the element.

[0032] Unless otherwise clearly specified and limited, the terms "disposed", "connected" and the like should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this utility model can be understood according to specific circumstances.

[0033] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.

[0034] Please refer to Figure 1 and Figure 2 The water delivery structure 100 for a high-frequency breaker, the high-frequency breaker and the excavation equipment provided in the embodiments of the utility model can solve the above-mentioned problems, which will be described in detail below.

[0035] The water supply structure 100 for the high-frequency breaker includes an external water channel 110 for supplying water to a first nozzle 130 and an internal water channel 120 for supplying water to a second nozzle 140; wherein the external water channel 110 is located in an external water pipe 180 outside a vibration output part 190 of the high-frequency breaker, and the internal water channel 120 is opened in the vibration output part 190.

[0036] The water supply structure 100 for the high-frequency breaker can realize external water spraying through the external water channel 110 and internal water spraying through the internal water channel 120. On the one hand, it can realize large-scale spraying, and on the other hand, it can accurately spray the source of dust at the moment of dust generation, thereby slowing down the dispersion of dust.

[0037] Specifically, the vibration output part 190 includes a connected drill rod 191 and a bucket tooth seat 192 , and the internal water channel 120 includes a front water channel 121 and a rear water channel 122 that are connected. The front water channel 121 is opened in the drill rod 191 , and the rear water channel 122 is opened in the bucket tooth seat 192 .

[0038] refer to Figure 1 and Figure 2In order to reduce the processing difficulty and reduce the negative impact on the strength of the drill rod 191, a first groove 193 may be provided on the top surface of the drill rod 191. The first groove 193 is used to enclose the outer water pipe 180 to form the front water channel 121.

[0039] It should be noted that the outer water pipe 180 is usually welded to the top surface of the drill rod 191, thereby sealing the top side of the first groove 193 to prevent the diving knife from leaking during the water delivery process.

[0040] In this embodiment, because the drill rod 191 and the bucket tooth seat 192 usually need to be fixed to ensure that there is no relative movement between the two, the specific fixing method can be welding, clamping, etc. In addition, because the front water channel 121 and the rear water channel 122 are not completely aligned, in order to ensure that the spray water flows stably between the two, a reserved hole 194 can be formed between the drill rod 191 and the bucket tooth seat 192, and the reserved hole 194 is connected between the front water channel 121 and the rear water channel 122.

[0041] refer to Figure 1 and Figure 2 In order to prevent the opening of the front water channel 121 from having a significant negative impact on the self-strength and internal stress distribution of the vibration output part 190, the front water channel 121 can be opened at the top of the drill rod 191.

[0042] It should be noted that the top of the drill rod 191 refers to the position of the drill rod 191 away from the ground in the vertical direction in the working state. At the same time, the front water channel 121 can be located in the middle position of the vibration output part 190 in the horizontal direction to prevent the physical structures on the upper and lower sides of the front water channel 121 from being unevenly stressed.

[0043] Similarly, in order to prevent the opening of the rear water channel 122 from having a significant negative impact on the strength and internal stress distribution of the bucket tooth seat 192, the rear water channel 122 can be opened at the top of the bucket tooth.

[0044] It should be noted that the top of the tooth seat 192 refers to the position of the tooth seat 192 away from the ground in the vertical direction when the tooth seat 192 is in the working state. At the same time, the rear water channel 122 can be located in the middle position of the tooth seat 192 in the horizontal direction to prevent the physical structures on both sides of the rear water channel 122 from being unevenly stressed.

[0045] Of course, in other embodiments of the utility model, on the premise of ensuring that the strength of the drill rod 191 and the bucket tooth seat 192 and the internal stress distribution meet the requirements of the excavation operation, the front water channel 121 can be opened in the middle or bottom of the drill rod 191, and the rear water channel 122 can be opened in the middle or bottom of the bucket tooth seat 192. There is no limitation on the specific opening positions of the front water channel 121 and the rear water channel 122.

[0046] In this embodiment, the front water channel 121 and the rear water channel 122 are both straight lines, which are easy to process. In other embodiments of the utility model, without affecting the water delivery effect, the front water channel 121 and the rear water channel 122 can also be in the form of a broken line or a curve, and there is no limitation on their specific extension shapes.

[0047] refer to Figure 1 and Figure 2 The water delivery structure 100 for the high-frequency breaker also includes a third nozzle 150 , which is disposed at the vibration output portion 190 , the third nozzle 150 is spaced apart from the first nozzle 130 , and an inlet of the third nozzle 150 is connected to an outlet of the first nozzle 130 .

[0048] It should be noted that the first nozzle 130 is arranged on the top side of the drill rod 191. By arranging the third nozzle 150, the first nozzle can be shielded and protected to prevent the first nozzle from being blocked by mud during the operation. In addition, because the third nozzle 150 is spaced apart from the first nozzle 130, during the crushing operation, rock debris is more likely to block the third nozzle 150. The third nozzle 150 can be directly unblocked using a tool so that the rock debris is discharged from the gap between the first nozzle 130 and the third nozzle 150.

[0049] Specifically, the first nozzle 130 and the third nozzle 150 are both inverted trumpet-shaped structures, and their inner diameters gradually decrease from the inlet to the outlet. Their inner walls can be inclined straight lines or arc-shaped; of course, the inner walls of the two can also be stepped to ensure that their inner diameters at the inlets are larger.

[0050] At the same time, the second nozzle 140 is arranged on the vibration output part 190 and is spaced apart from the output end of the inner waterway 120. It should be noted that the second nozzle 140 is arranged on the bucket tooth seat 192 and is spaced apart from the output end of the rear waterway 122. The second nozzle 140 can shield and protect the output end of the rear waterway 122 to prevent mud from clogging the rear waterway 122 during operation.

[0051] Specifically, the second nozzle 140 can be an inverted trumpet-shaped structure, whose inner diameter gradually decreases from the inlet to the outlet, and its inner wall can be an inclined straight line or an arc-shaped; of course, the inner wall of the second nozzle 140 can also be stepped to ensure that its inner diameter at the inlet is larger.

[0052] The water supply structure 100 for the high-frequency breaker can be used to pressurize the outflowing spray water by providing the first nozzle 130, the second nozzle 140 and the third nozzle 150, which can help prevent blockage on the one hand and improve the dust removal effect on the other hand.

[0053] refer to Figure 1 and Figure 2 In order to ensure that there is a safe distance between the output end of the rear water channel 122 and the source of dust generation, and to avoid clogging the output end of the rear water channel 122 at the moment of dust generation, the bucket tooth seat 192 can be provided with a second groove 195, and the output end of the rear water channel 122 can be opened on the groove wall of the second groove 195.

[0054] Similarly, in order to improve the protection effect and prevent the second nozzle 140 from colliding during the crushing operation, the second nozzle 140 can also be accommodated in the second groove 195.

[0055] In the present embodiment, the number of the second grooves 195 is two, and the two second grooves 195 are respectively formed on both sides of the top of the bucket tooth seat 192; of course, in other embodiments of the present invention, the number of the second grooves 195 can also be one, three, five, etc., and their setting positions can be at the bottom, the middle or the edge of the left and right parts of the bucket tooth seat 192. There is no limitation on the specific number and setting positions of the second grooves 195.

[0056] The embodiment of the utility model also provides a high-frequency breaker, including a hydraulic motor, an excitation box, a radiator and a water supply structure 100 for the high-frequency breaker, wherein the hydraulic motor is used to provide a power source to drive the eccentric gear in the excitation box to rotate and generate centrifugal force, so as to drive the vibration output part 190 to perform a crushing operation under the action of the centrifugal force. The radiator is arranged on the side of the excitation box to dissipate heat and cool the excitation box to avoid overheating of the excitation box. The radiator can specifically be a cooling fan or a water cooling box. In order to improve the utilization rate of cooling water, the water cooling box can be connected to the internal water supply pipeline and the external water supply pipeline, and then the cooling water can be used for spraying and dust removal.

[0057] An embodiment of the utility model also provides a tunneling equipment, including a high-frequency breaker, a walking carrier and a driving source. The walking carrier is used to drive the high-frequency breaker to move, so as to perform crushing operations at different positions, and the driving source is used to provide a power source to the walking carrier and the high-frequency breaker.

[0058] Specifically, the excavation equipment can be a tunneling machine and a rock drill, etc., which mainly performs crushing operations by contacting the soil layer or rock with a high-frequency breaker. The excavation equipment includes a high-frequency breaker, which has all the functions of a high-frequency breaker.

[0059] In summary, the water delivery structure 100 for a high-frequency breaker, the high-frequency breaker, and the excavation equipment provided by the embodiments of the present utility model have at least the following advantages:

[0060] (1) On the one hand, it can realize large-scale spraying of bucket teeth, and on the other hand, it can accurately spray the source of dust at the moment of dust generation, thereby slowing down the dispersion of dust;

[0061] (2) By limiting the location of the front water channel 121 and the rear water channel 122, the negative impact of the opening of the water channel on the strength and internal stress distribution of the drill rod 191 and the bucket tooth seat 192 can be reduced.

[0062] The above is only a specific implementation of the utility model, but the protection scope of the utility model is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the utility model should be included in the protection scope of the utility model. Therefore, the protection scope of the utility model should be based on the protection scope of the claims.

Claims

1. A water delivery structure for a high-frequency breaker, characterized in that: include: An external water channel (110) for conveying water to a first nozzle (130) and an internal water channel (120) for conveying water to a second nozzle (140); The external water channel (110) is located in an external water pipe (180) outside a vibration output part (190) of the high-frequency breaker, and the internal water channel (120) is opened in the vibration output part (190).

2. The water delivery structure for a high-frequency breaker according to claim 1, characterized in that: The vibration output part (190) comprises a connected drill rod (191) and a bucket tooth seat (192); the internal water channel (120) comprises a front water channel (121) and a rear water channel (122) which are connected; the front water channel (121) is opened in the drill rod (191), and the rear water channel (122) is opened in the bucket tooth seat (192).

3. The water delivery structure for a high-frequency breaker according to claim 2, characterized in that: A first groove (193) is provided on the outer side of the drill rod (191), and the first groove (193) and the outer water pipe (180) are combined to form the front water channel (121).

4. The water delivery structure for a high-frequency breaker according to claim 2, characterized in that: A reserved hole (194) is formed between the drill rod (191) and the bucket tooth seat (192), and the reserved hole (194) is connected between the front water channel (121) and the rear water channel (122).

5. The water delivery structure for a high-frequency breaker according to any one of claims 1 to 4, characterized in that: The water supply structure for the high-frequency breaker also includes a third nozzle (150), which is arranged on the vibration output part (190), the third nozzle (150) is spaced apart from the first nozzle (130), and the inlet of the third nozzle (150) is connected to the outlet of the first nozzle (130).

6. The water delivery structure for a high-frequency breaker according to any one of claims 1 to 4, characterized in that: The second nozzle (140) is disposed on the vibration output portion (190) and is spaced apart from the output end of the inner water channel (120).

7. The water delivery structure for a high-frequency breaker according to any one of claims 1 to 4, characterized in that: The vibration output portion (190) is provided with a second groove (195), and the output end of the inner water channel (120) is provided on the groove wall of the second groove (195).

8. The water delivery structure for a high-frequency breaker according to claim 7, characterized in that: The second nozzle (140) is accommodated in the second groove (195).

9. A high frequency breaker, characterized in that: The water supply structure for a high-frequency breaker comprises the water supply structure for a high-frequency breaker according to any one of claims 1 to 8.

10. A tunneling device, characterized in that: Including the high-frequency breaker hammer as described in claim 9.