Arrangement structure of riverside water intake pumping station
By setting the water intake head in a suitable position in the river and the foundation pit of the pump room on the river bank, the water intake port structure and the main structure of the pump room are separated and arranged, the high investment in the engineering caused by the water level change of the riverside water intake pump station is solved. Problem, achieving lower pump room design height and better adaptability.
Patent Information
- Application Number
- CN202421079552.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-17
- Publication Date
- 2024-12-31
- Estimated Expiration
- 2034-05-17
AI Technical Summary
Due to the large water level of the river water intake pump station, the pump room has a higher height, the project investment is greater, and the adaptability is poor.
The water intake head is set at a suitable location in the river, the foundation pit of the pump room is set on the river bank side, the main pump room is set in the foundation pit of the pump room, the water diversion steel pipe connects the water intake head and the water inlet end of the pump room, separate the water intake structure and the pump The main structure of the house.
The impact of the river water level change on the pump room structure is reduced, the design height of the main pump room is reduced, the project investment is effectively reduced, and the adaptability to the large river water level change is improved.
Smart Images

Figure CN222275648U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water conservancy and hydropower engineering, in particular to an arrangement structure of a riverside water intake pump station. Background Art
[0002] At present, riverside water intake pump stations generally build pump houses on the shore, and the water intake structure is integrated with the main structure of the pump house. For pump stations with large fluctuations in river water levels and large water intake scales, the adaptability of the overall layout structure is poor. Due to the large fluctuations in river water levels, the height of the pump house is generally high, resulting in large project investments. Utility Model Content
[0003] The technical problem to be solved by the utility model is: to provide a layout structure of a riverside water intake pump station in view of the above-mentioned existing problems.
[0004] The technical solution adopted by the utility model is: a layout structure of a riverside water intake pump station, characterized in that it includes:
[0005] The water intake head foundation pit is set at a suitable position in the river;
[0006] A water intake head is arranged in the water intake head foundation pit, and the water intake head takes water through the water inlet hole;
[0007] The pump house foundation pit is located on the river bank side, and the pump house foundation pit is a certain distance away from the river bank;
[0008] The main pump room is located in the pump room foundation pit;
[0009] A water diversion steel pipe has a first end connected to the water intake head and a second end connected to the water inlet end of the main pump room.
[0010] Through the above-mentioned technical means, the water intake head is arranged at a suitable position in the river, and the water intake head can take high-quality water from a suitable position in the river. The main pump room is arranged at a certain distance from the river bank, which can reduce the impact of the river water level fluctuation on the pump room structure, thereby reducing the design height of the main pump room and further reducing the project investment.
[0011] In some embodiments, the water outlet of the main pump room is connected to a water outlet structure.
[0012] In some embodiments, the water outlet structure includes a water outlet tunnel, a water outlet tower foundation pit and a water outlet tower. The water outlet tower is installed in the water outlet tower foundation pit, and the water outlet end of the main pump room is connected to the water outlet tower via the water outlet tunnel.
[0013] In some embodiments, the water diversion steel pipe includes a immersed tube and a top pipe, and the water outlet of the water intake head is connected to the water inlet of the main pump room through the immersed tube and the top pipe in sequence.
[0014] In some embodiments, a maintenance valve well is provided in the middle of the jacking pipe, and the maintenance valve well can also serve as a working well and a receiving well of the jacking pipe during construction.
[0015] In some embodiments, a water inlet well is provided between the top pipe and the water inlet end of the main pump room.
[0016] The beneficial effects of the utility model are:
[0017] 1. By arranging the water intake head at a suitable position in the river, the water intake structure can obtain a better quality water source from the river, and the main pump room is arranged on the shore, and the main pump room is located at a certain distance from the riverside, so as to reduce the impact of the river water level fluctuation on the pump room structure, and the design height of the main pump room can also be reduced accordingly, thereby effectively reducing the project investment. Compared with the scheme of arranging the water intake structure and the main structure of the pump room as a whole, this application can have better adaptability in the face of large fluctuations in the river water level by separating the water intake structure from the main structure of the pump room. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the planar structure of this application.
[0019] Figure 2 It is a schematic diagram of the cross-sectional structure of this application.
[0020] Description of reference numerals:
[0021] 1. Water intake head; 2. Immersed pipe; 3. Jacking pipe; 4. Maintenance valve well; 5. Water inlet well; 6. Main pump room; 7. Water outlet tunnel; 8. Water outlet tower; 9. Water intake head foundation pit; 10. Pump room foundation pit; 11. Water outlet tower foundation pit; 12. Original ground line.
[0022] This specification includes references to "one embodiment" or "an embodiment." The appearance of the phrase "in one embodiment" or "in an embodiment" does not necessarily refer to the same embodiment. The particular features, structures or characteristics may be combined in any suitable manner consistent with the present disclosure.
[0023] The term "comprising" is open ended. As used in the appended claims, the term does not exclude additional structures or steps. DETAILED DESCRIPTION
[0024] In order to enable those skilled in the art to better understand the technical solution of the present utility model, the technical solution of the present utility model is further described below in conjunction with specific embodiments.
[0025] Combination Figure 1 to Figure 2As shown, this embodiment is a layout structure of a riverside water intake pump station, which is mainly used in large-scale riverside water intake pump stations. A layout structure of a riverside water intake pump station includes a water intake head foundation pit 9, a water intake head 1, a pump house foundation pit 10, a main pump house 6 and a water diversion steel pipe. The water intake head foundation pit 9 is set at a suitable position in the river, and the water intake head 1 is set in the water intake head foundation pit 9. The water intake head 1 draws water from the river through the water inlet hole. The position of the water intake head foundation pit 9 can be flexibly arranged to ensure that the water intake head 1 can obtain high-quality water from a suitable position in the river. The pump house foundation pit 10 is set on the river bank side, and the position of the pump house foundation pit 10 is a certain distance away from the river bank. The pump house foundation pit 10 is lower than the original ground line 12, and a main pump house 6 is arranged in the pump house foundation pit 10. At the same time, the position of the pump house foundation pit 10 needs to consider avoiding the impact of the river water level fluctuation on the main pump house 6 as much as possible. The first end of the water diversion steel pipe is connected to the water intake head 1, and the second end of the water diversion steel pipe is connected to the water inlet end of the main pump room 6. The water outlet end of the main pump room 6 is connected to the water outlet structure.
[0026] Compared with the solution of arranging the water intake structure and the main structure of the pump house together as an integral whole, the present application arranges the water intake structure separately from the main structure of the pump house. On the one hand, the water intake structure can obtain high-quality water at a suitable position in the river. On the other hand, the main structure of the pump house is far away from the river bank, reducing the impact of the river water level fluctuation on the main structure of the pump house, thereby eliminating the need to build a higher pump house building and reducing project investment.
[0027] In some embodiments, the water outlet structure includes a water outlet tunnel 7, a water outlet tower foundation pit 11 and a water outlet tower 8. The water outlet tower 8 is installed in the water outlet tower foundation pit 11. One end of the water outlet tunnel 7 is connected to the water outlet end of the main pump room 6, and the other end of the water outlet tunnel 7 is connected to the water outlet tower 8.
[0028] In some embodiments, the water diversion steel pipe includes a submerged pipe 2 and a jacking pipe 3, and the water outlet of the water intake head 1 is connected to the water inlet of the main pump room 6 through the submerged pipe 2 and the jacking pipe 3 in sequence. A maintenance valve well 4 is provided in the middle of the jacking pipe 3, and the maintenance valve well 4 can also serve as a working well and a receiving well of the jacking pipe 3 during construction. A water inlet well 5 is provided between the jacking pipe 3 and the water inlet of the main pump room 6. The water inlet well 5 can serve as a forebay of the water pump suction pipe of the main pump room 6, so that the river water sediment flowing into the water body through the jacking pipe 3 can be fully precipitated, thereby reducing the abrasive damage of the sediment to the water pump unit in the main pump room 6.
[0029] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.
Claims
1. A layout structure of a riverside water intake pump station, characterized in that: include: The water intake head foundation pit (9) is set at a suitable position in the river; A water intake head (1) is arranged in the water intake head foundation pit (9), and the water intake head (1) takes water through the water inlet hole; A pump house foundation pit (10) is arranged on the river bank side, and the pump house foundation pit (10) is a certain distance away from the river bank; A main pump room (6) is arranged in the pump room foundation pit (10); A water diversion steel pipe has a first end connected to the water intake head (1) and a second end connected to the water inlet end of the main pump room (6).
2. The arrangement structure of a riverside water intake pump station according to claim 1 is characterized in that: The water outlet end of the main pump room (6) is connected to a water outlet structure.
3. The arrangement structure of a riverside water intake pump station according to claim 2 is characterized in that: The water outlet structure comprises a water outlet tunnel (7), a water outlet tower foundation pit (11) and a water outlet tower (8); the water outlet tower (8) is arranged in the water outlet tower foundation pit (11); and the water outlet end of the main pump room (6) is connected to the water outlet tower (8) via the water outlet tunnel (7).
4. The arrangement structure of a riverside water intake pump station according to claim 1 is characterized in that: The water diversion steel pipe comprises a submerged pipe (2) and a top pipe (3), and the water outlet end of the water intake head (1) is connected to the water inlet end of the main pump room (6) via the submerged pipe (2) and the top pipe (3) in sequence.
5. The arrangement structure of a riverside water intake pump station according to claim 4 is characterized in that: A maintenance valve well (4) is provided in the middle of the jacking pipe (3), and the maintenance valve well (4) can also serve as a working well and a receiving well of the jacking pipe (3) during construction.
6. The arrangement structure of a riverside water intake pump station according to claim 4, characterized in that: A water inlet well (5) is provided between the top pipe (3) and the water inlet end of the main pump room (6).