One-time pre-embedded hardcover positioning device applying floor penetrating sleeve
By using a single-time pre-embedded positioning device through the floor casing with steel plate outer frame and infrared calibration device in construction, the problem of prefabricating and removing foam boards or wooden boxes in the prior art has been solved, and efficient and accurate Casing installation reduces construction costs and leakage risks.
Patent Information
- Application Number
- CN202420789256.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-17
- Publication Date
- 2025-01-03
- Estimated Expiration
- 2034-04-17
AI Technical Summary
In multi-story building construction, the prior art requires prefabricating and later removal of foam boards or wooden boxes before concrete pouring, which increases labor costs and leakage risks, and the pipeline installation cycle is long, resulting in high costs.
A single-time pre-embedded and fine-fit positioning device for the casing through the floor, including steel plate frame, calibration ruler, infrared calibration device and fixing fixing, and the precise positioning and fixing of the casing is achieved through infrared calibration and level bubbles, avoiding prefabrication and removal. process.
It realizes the installation of casing at one time before pouring, improves construction efficiency, reduces costs, and ensures the accuracy and flexibility of the embedded casing. It is suitable for casing pre-embedding in various specifications and locations.
Smart Images

Figure CN222295752U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a one-time pre-buried fine installation positioning device using a floor slab sleeve. Background Art
[0002] In the current traditional construction process of pre-buried multi-story buildings, foam boards, plastic boxes or nailed wooden boxes are mainly buried at the vertical pipe position before concrete pouring, and the pre-buried foam boards, plastic boxes or wooden boxes are removed before the pipeline is installed later to facilitate the installation of casing hanging formwork. This process is very costly: prefabrication of foam boards or wooden boxes of appropriate sizes in advance, as well as later removal, roughening of holes, and casing hanging formwork all require increased labor costs; the secondary utilization rate of foam boards and wooden boxes is almost zero, and the process material flooding cost is close to 100%; the secondary hanging formwork of the floor increases the risk of leakage and the cost of handling leakage; ④ The pipeline installation cycle is greatly increased, which indirectly causes an increase in labor costs. Utility Model Content
[0003] The utility model aims to address the deficiencies in the prior art and provides a one-time pre-embedded fine-finished positioning device for penetrating floor slab casings, comprising a steel plate outer frame, two calibration rulers are arranged on the midpoint line of the inner opposite sides of the steel plate outer frame, the calibration rulers are provided with scales, an infrared calibration device is arranged on the coincidence point of the two calibration rulers, fixing clamps are installed in four directions of the coincidence point on the two calibration rulers, clamp fixing bolts located on the calibration rulers are installed on the side of the four fixing clamps away from the infrared calibration device, and 5mm thick galvanized steel plates are connected in the vertical direction of the four fixing clamps, and the 5mm thick galvanized steel plates are close to the outer wall of the pre-embedded casing of the next floor.
[0004] Preferably, the fixing fixture is bent into an arc shape on one side close to the infrared calibration device and is made of a 2 mm thick galvanized steel plate.
[0005] Preferably, two level bubbles are fixedly arranged on the steel plate outer frame.
[0006] Preferably, two short angle steels with holes are welded on the side of the embedded sleeve to be positioned on the upper floor, the sleeve is positioned according to the drilling position of the template, and the short angle steel on the sleeve is fixed to the template with screws.
[0007] Compared with the prior art, the beneficial effects of the utility model are as follows: the method can install the floor sleeve in place at one time before pouring, without the need for prefabrication and embedding, removal of foam or wooden boxes, and without the need for roughening holes and hanging molds, which greatly improves construction efficiency and greatly reduces construction costs, ensures that the accuracy of the embedded sleeve meets the requirements of pipeline installation, and can be flexibly applied to embedded sleeves of various specifications and different positions for repeated use. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0009] Figure 1 It is a schematic diagram of the structure of the utility model;
[0010] Figure 2 for Figure 1 A cross-sectional view of
[0011] Figure 3 It is a schematic diagram of the use of the utility model.
[0012] In the figure: 1. Steel plate frame, 2. Level bubble, 3. Fixing fixture, 4. Fixing bolts of fixture, 6. Infrared calibration device; 7. Calibration ruler, 8. 5mm thick galvanized steel plate, 9. Embedded casing; 10. Embedded casing to be positioned, 11. Template of the previous floor, 12. Light beam, 13. Concrete slab of the next floor. DETAILED DESCRIPTION
[0013] The technical solution of the utility model is described in detail below with reference to the accompanying drawings, but the protection scope of the utility model is not limited to the embodiments.
[0014] Reference Figure 1 and Figure 2 The utility model discloses a one-time pre-embedded fine-fitting positioning device for penetrating floor slab casing, comprising a steel plate outer frame 1, on which two level bubbles 2 are fixedly arranged, two calibration rulers 7 are arranged on the midpoint connection line of the inner opposite sides of the steel plate outer frame 1, the calibration ruler 7 is provided with scales, an infrared calibration device 6 is arranged on the coincidence point of the two calibration rulers 7, and fixing clamps 3 are installed on the four directions of the coincidence point of the two calibration rulers 7, the fixing clamps 3 are bent into an arc shape on the side close to the infrared calibration device 6, and are made of 2mm thick galvanized steel plate, and the four fixing clamps 3 are installed with clamp fixing bolts 4 located on the calibration ruler 7 on the side away from the infrared calibration device 6, and the four fixing clamps 3 are connected with 5mm thick galvanized steel plates 8 in the vertical direction, and the 5mm thick galvanized steel plates 8 are close to the outer wall of the pre-embedded casing 9 of the next floor.
[0015] In the utility model, the fixing fixture 3 on the four calibration scales 7 is slid to make the 5mm thick galvanized steel plate 8 connected to the fixture close to the outer wall of the casing, and the readings of the corresponding positions of the fixtures on the four scales are fine-tuned to be the same; secondly, the two level bubbles 2 of the level ruler are observed and fine-tuned until the two bubbles are both centered, indicating that the entire positioning and calibration device is in a horizontal state; tighten the fixture fixing bolts 4 to make the 5mm thick galvanized steel plate 8 reliably fixed on the pre-buried casing 9 of the next floor to be positioned and measured; open the infrared calibration device 6 in the center of the calibration scale 7, find the infrared light spot on the template 11 of the previous floor, and drill a hole at the light spot to locate the center of the pre-buried casing 10 of the previous floor; weld two short angle steels with eyes on the side of the casing in advance, locate the casing according to the drilling position of the template, and fix the short angle steel on the casing to the template with screws to prevent the casing from shifting. At this point, the method for one-time pre-embedded positioning of pre-embedded casing through the floor slab has completed the construction of a complete set of process flows.
[0016] The utility model first fixes itself on the embedded sleeve 9 extending out of the concrete floor slab 13 of the next floor, and the light beam 12 emitted by the infrared calibration device 6 hits the template of the previous floor. The hole drilled at the light spot is the center of the embedded sleeve 10 to be positioned on the previous floor. The sleeve penetrating the floor slab is installed in place at one time before pouring, and there is no need for prefabrication and embedding, removal of foam or wooden boxes, and no need to roughen the hole or hang the mold, which greatly improves the construction efficiency and greatly reduces the construction cost. It ensures that the accuracy of the embedded sleeve meets the pipeline installation, and can be flexibly applied to the embedded sleeves of various specifications and different positions for repeated use.
[0017] As above, although the utility model has been shown and described with reference to specific preferred embodiments, it should not be interpreted as limiting the utility model itself. Various changes can be made to it in form and detail without departing from the spirit and scope of the utility model defined in the attached claims.
Claims
1. A one-time pre-buried fine-fitting positioning device using a floor sleeve, characterized in that: It includes a steel plate outer frame, and two calibration rulers are set on the midpoint line of the inner opposite sides of the steel plate outer frame, and the calibration rulers are provided with scales. An infrared calibration device is set at the overlapping point of the two calibration rulers, and fixing clamps are installed in four directions of the overlapping point of the two calibration rulers. The clamp fixing bolts located on the calibration rulers are installed on the side of the four fixing clamps away from the infrared calibration device, and 5mm thick galvanized steel plates are connected in the vertical direction of the four fixing clamps, and the 5mm thick galvanized steel plates are close to the outer wall of the embedded casing on the next floor.
2. According to claim 1, a one-time pre-buried fine-fitting positioning device using a floor sleeve is characterized by: The fixing fixture is bent into an arc shape on one side close to the infrared calibration device and is made of a 2mm thick galvanized steel plate.
3. According to claim 2, a one-time pre-buried fine-fitting positioning device using a floor sleeve is characterized by: Two level bubbles are fixedly arranged on the steel plate outer frame.
4. The one-time pre-buried fine-fitting positioning device using a floor sleeve according to claim 3 is characterized in that: Weld two short angle steels with holes on the side of the embedded casing that needs to be positioned on the upper floor, position the casing according to the drilling position of the template, and fix the short angle steel on the casing to the template with screws.