Pipeline mounting and fixing device

By designing a fixed device including the base, the supporting rod, the positioning of the positioning, the holding seat, and the clip holding block, the problem of the stability of the fixed fixed devices in the existing technology and the fixing of multiple sets of pipelines in the existing technology The fixed effect of high stability and flexibility is achieved.

CN222392149UActive Publication Date: 2025-01-24JINAN HEATING POWER ENG CO
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421005670.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-10
Publication Date
2025-01-24
Estimated Expiration
2034-05-10

AI Technical Summary

Technical Problem

The existing pipeline fixing devices have low stability and are easy to shake. When fixing multiple sets of pipelines, multiple sets of fixing devices need to be installed, resulting in construction troubles.

Method used

A pipeline installation and fixing device is designed, including a base, a support rod, a positioning pin, a clamping seat, a first clamping block and a second clamping block. The pipe height is adjusted through the combination of the casing and the lifting rod, and the clamping The snap connection of the holding block secures the pipe.

Benefits of technology

This device is fixed and stable, which can effectively resist vibration and external collisions. At the same time, multiple groups of pipelines can be fixed at the same time without installing multiple fixed devices to improve construction efficiency and flexibility.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222392149U_ABST
    Figure CN222392149U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipeline installation fixing device which structurally comprises a base, a supporting rod, a positioning pin, a clamping seat, a first clamping block and a second clamping block, the positioning pin is arranged on one side of the clamping seat and connected with the supporting rod in an inserted mode, the first clamping block is connected with the other side of the clamping seat in a buckled mode, and the second clamping block is connected with the supporting rod in a buckled mode. One side of the second clamping block is movably connected with the first clamping block in an inserted mode, and the other side of the second clamping block is connected with the clamping base in a matched mode. In the mounting and fixing construction process of the air conditioner pipeline, a base is fixed through a positioning bolt, then the length of a lifting rod and a sleeve is adjusted by pulling the lifting rod, then a second positioning pin is inserted into a through hole in the surface of the sleeve and the lifting rod, and then one end of the second positioning pin is in threaded connection and fixed through a connecting block; and then the air conditioner pipeline is placed in an arc-shaped groove in one side of the clamping base, so that the first clamping block and the second clamping block can be connected with the clamping base in a clamped mode, and the air conditioner pipeline can be fixed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline installation, in particular to a pipeline installation fixing device. Background Art

[0002] When the air-conditioning duct is being fixed, a fixing device is usually required to fix it on the top of the building. After searching, the Chinese patent authorization number CN218088729U discloses a fixing device for installing central air-conditioning duct. Although the device drives the winding roller to rotate by rotating the worm, thereby adjusting the height of the duct, aligning the pipe sections, and facilitating welding, it can also play the role of lifting the duct, and then tighten the stud two to make the rubber top holding block against the side plate one to fix the rotating plate to prevent the rotating plate from rotating spontaneously. However, the height adjustment of the device is controlled by adjusting the length of the sling. However, fixing the duct by the sling will cause the duct to be easily swung by the sling due to external force, thereby reducing stability. At the same time, the device can only fix a single duct. When multiple groups of ducts need to be fixed, multiple groups of fixing devices need to be installed, which makes the installation during the construction process more troublesome. Utility Model Content

[0003] The utility model aims to provide a pipeline installation and fixing device, which solves the problems in the background technology that the existing pipeline fixing devices have low stability, are easy to shake when subjected to external forces, and need to install multiple sets of fixing devices when fixing multiple sets of pipelines.

[0004] The technical solution adopted by the utility model to solve its technical problems is: a pipeline installation and fixing device, whose structure includes a base, a support rod, a positioning pin, a clamping seat, a first clamping block and a second clamping block, a positioning pin is provided on one side of the clamping seat, the positioning pin is plugged into the support rod, the first clamping block is buckled with the other side of the clamping seat, one side of the second clamping block is movably plugged into the first clamping block, and the other side of the second clamping block is cooperatively connected with the clamping seat.

[0005] Furthermore, the support rod includes a sleeve and a lifting rod, one end of the sleeve is connected to the base, and the other end of the sleeve is sleeved on the lifting rod, and the side walls of the sleeve and the lifting rod are respectively provided with sockets that cooperate with the positioning pin.

[0006] Furthermore, a first locating pin and a second locating pin are provided on one side of the clamping seat, the free end of the second locating pin is threadedly matched with a connecting block, and a slot for buckling with the first clamping block or the second clamping block is provided on the other side of the clamping seat.

[0007] Furthermore, a buckle cooperating with a clamping seat is provided on one side of the first clamping block, and an inserting block plug-fitting with the second clamping block is provided on the other side of the first clamping block.

[0008] Furthermore, a buckle cooperating with the clamping seat is provided on one side of the second clamping block, and a sliding groove cooperating with the first clamping block is provided on the other side of the second clamping block.

[0009] Furthermore, positioning bolts are respectively provided on both sides of the base.

[0010] Furthermore, a semicircular groove is provided on one side of the clamping seat, the first clamping block and the second clamping block.

[0011] Beneficial effects of the utility model:

[0012] During the installation and fixing process of the air conditioning duct, the base is fixed by positioning bolts, and then the length of the lifting rod and the sleeve is adjusted by pulling the lifting rod, and then the second positioning pin is inserted into the through hole on the surface of the sleeve and the lifting rod, and then one end of the second positioning pin is threadedly connected and fixed by the connecting block, and then the air conditioning duct is placed in the arc groove on one side of the clamping seat, so that the first clamping block and the second clamping block can be connected with the clamping seat, so that the air conditioning duct can be fixed. The multiple holes and grooves distributed from top to bottom through the sleeve and the telescopic tube are conducive to adjusting the height of the pipeline installation up and down, and the device is firmly fixed and is not easy to shake due to vibration and external collision, which greatly improves the stability of the device.

[0013] When fixing the pipeline, one side of the first clamping block is slidably inserted into the groove on one side of the second clamping block, so that the first clamping block and the second clamping block can be connected to each other, which is conducive to the two pipelines being installed and fixed side by side, thereby helping to improve the flexibility of the use of the device, and at the same time, multiple groups of pipelines can be fixed without installing multiple fixing devices, which solves the problem that the existing pipeline fixing devices have low stability and are easy to shake when subjected to external forces, and multiple groups of fixing devices need to be installed when fixing multiple groups of pipelines. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0015] Figure 2 This is a schematic diagram of the lifting rod structure of the utility model;

[0016] Figure 3 This is a schematic diagram of the structure of the clamping seat of the utility model;

[0017] Figure 4 This is a schematic diagram of the structure of the first clamping block of the utility model;

[0018] Figure 5 This is a schematic diagram of the structure of the second clamping block of the utility model.

[0019] In the figure:

[0020] 1. Base; 2. Positioning bolt; 3. Sleeve; 4. Lifting rod; 5. First positioning pin; 6. Second positioning pin; 7. Connecting block; 8. Clamping seat; 9. Second clamping block; 10. First clamping block; 11. Buckle. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] like Figure 1-5 As shown: a pipe installation and fixing device, including a base 1, a support rod, a positioning pin, a clamping seat 8, a first clamping block 10 and a second clamping block 9, a positioning pin is provided on one side of the clamping seat 8, the positioning pin is plugged with the support rod, the first clamping block 10 is buckled with the other side of the clamping seat 8, one side of the second clamping block 9 is movably plugged with the first clamping block 10, and the other side of the second clamping block 9 is connected with the clamping seat 8. If only one pipe needs to be fixed, only the support seat 8 and the first clamping block 10 can be used to form a clamping hole, and if two pipes need to be fixed in the same row, two clamping seats 8, a first clamping block 10 and a second clamping block 9 are used.

[0023] The support rod comprises a sleeve 3 and a lifting rod 4, one end of the sleeve 3 is connected to the base 1, and the other end of the sleeve 3 is sleeved with the lifting rod 4, and the side walls of the sleeve 3 and the lifting rod 4 are respectively provided with a socket matched with a positioning pin. The overall height of the support rod can be adjusted by telescopic lifting rod to meet the positioning of pipelines of different heights.

[0024] like Figure 1As shown, a pipeline installation and fixing device comprises a base 1, a sleeve 3, a first locating pin 5, a second clamping block 9 and a first clamping block 10. Circular through holes are opened at both ends of the base 1, and positioning bolts 2 are inserted inside the circular through holes. A sleeve 3 is welded at the bottom of the base 1, and a lifting rod 4 is inserted inside the sleeve 3. The first locating pin 5 is inserted inside the sleeve 3. One end of the first locating pin 5 is welded to one side of a clamping seat 8. The clamping seat 8 is respectively connected to the second clamping block 9 and the first clamping block 10. The first clamping block 10 and the second clamping block 9 are respectively spliced ​​with the corresponding clamping seats 8 to form a circular through hole. The interior of the sleeve 3 is a hollow structure, and the inner wall of the sleeve 3 is in sliding contact with the outer wall of the lifting rod 4. A plurality of through holes are opened on the surfaces of the sleeve 3 and the lifting rod 4, and the through holes on the surfaces of the sleeve 3 and the lifting rod 4 are arranged at equal intervals from top to bottom. The inner diameters of the through holes on the surfaces of the sleeve 3 and the lifting rod 4 are consistent. A second locating pin 6 is provided above the first locating pin 5. The other end of the positioning pin 6 is welded to the clamping seat 8, and the surface of the other end of the second positioning pin 6 is a threaded structure. The second positioning pin 6 is threadedly connected to the connecting block 7 through an external threaded structure. When the device is in use, the base 1 is fixed by the positioning bolt 2, and then the length of the lifting rod 4 and the sleeve 3 is adjusted by pulling the lifting rod 4, and then the second positioning pin 6 is inserted into the through hole on the surface of the sleeve 3 and the lifting rod 4, so that one end of the second positioning pin 6 is threadedly connected and fixed through the connecting block 7, and then the air-conditioning pipe is placed in the arc-shaped groove on one side of the clamping seat 8, so that the second clamping block 9 and the first clamping block 10 can be snap-connected with the clamping seat 8, so that the air-conditioning pipe can be fixed, and the multiple holes and grooves distributed from top to bottom through the sleeve 3 and the telescopic tube are conducive to adjusting the height of the pipe installation up and down, and the device is firmly fixed and is not easy to shake due to vibration and external collision, which greatly improves the stability of the device.

[0025] One side of the first clamping block 10 is provided with a buckle 11 that cooperates with the clamping seat, and the other side of the first clamping block is provided with an insert block that plugs and cooperates with the second clamping block. One side of the second clamping block 9 is provided with a buckle 11 that cooperates with the clamping seat or the first clamping block, and the other side of the second clamping block is provided with a slide groove that plugs and cooperates with the first clamping block. The connection between the first clamping block and the second clamping block is achieved through the plug-in cooperation between the insert block and the slide groove.

[0026] like Figure 4 , Figure 5As shown, the second clamping block 9 and the first clamping block 10 are both provided with buckles 11 on the top and bottom, and the buckles 11 of the second clamping block 9 and the first clamping block 10 are snap-connected with the top and bottom of the base 1, a protrusion is provided on one side of the first clamping block 10, and the cross-section of the protrusion on one side of the first clamping block 10 is a T-shaped structure, and the protrusion on one side of the first clamping block 10 is slidably connected with the groove on one side of the second clamping block 9, and by placing the air-conditioning pipe in the arc-shaped groove on one side of the clamping seat 8, the second clamping block 9 and the first clamping block 10 can be snap-connected with the clamping seat 8, so that the air-conditioning pipe can be quickly fixed, thereby avoiding the use of bolts for fixing, greatly improving convenience, and by sliding one side of the second clamping block 9 into the groove on one side of the first clamping block 10, it is beneficial to connect the second clamping block 9 and the first clamping block 10 to each other, which is beneficial to enable the two pipes to be installed and fixed side by side, which is beneficial to improve the flexibility of the use of the device, and at the same time, multiple groups of pipes can be fixed without installing multiple fixing devices.

[0027] How it works

[0028] When the air-conditioning pipe is installed and fixed, the base 1 is fixed by the positioning bolt 2, and then the length of the lifting rod 4 and the sleeve 3 is adjusted by pulling the lifting rod 4, and then the second positioning pin 6 is inserted into the through hole on the surface of the sleeve 3 and the lifting rod 4, so that one end of the second positioning pin 6 is threadedly connected and fixed by the connecting block 7, and then the air-conditioning pipe is placed in the arc-shaped groove on one side of the clamping seat 8, so that the first clamping block 10 and the second clamping block 9 can be respectively engaged and connected with the corresponding clamping seat 8, so that the air-conditioning pipe can be fixed, and the multiple holes and grooves distributed from top to bottom through the sleeve 3 and the telescopic tube are conducive to adjusting the height of the pipe installation up and down, and the device is firmly fixed and is not easy to shake due to vibration and external collision, which greatly improves the stability of the device, and by sliding one side of the second clamping block 9 into the groove on one side of the first clamping block 10, it is conducive to connecting the first clamping block and the second clamping block to each other, which is conducive to installing and fixing the two pipes side by side.

[0029] The above description is only used to illustrate some principles of the utility model. This specification is not intended to limit the utility model to the specific structure and application scope shown and described. Therefore, all corresponding modifications and equivalents that may be used belong to the patent scope applied for the utility model.

[0030] Except for the technical features described in the specification, the other technical features are known to those skilled in the art.

Claims

1. A pipeline installation and fixing device, characterized in that: It includes a base, a support rod, a positioning pin, a clamping seat, a first clamping block and a second clamping block. A positioning pin is provided on one side of the clamping seat, the positioning pin is plugged into the support rod, the first clamping block is buckled with the other side of the clamping seat, one side of the second clamping block is movably plugged into the first clamping block, and the other side of the second clamping block is cooperatively connected with the clamping seat.

2. A pipeline installation and fixing device according to claim 1, characterized in that: The support rod comprises a sleeve and a lifting rod, one end of the sleeve is connected to the base, the other end of the sleeve is sleeved on the lifting rod, and the side walls of the sleeve and the lifting rod are respectively provided with sockets that cooperate with the positioning pin.

3. A pipeline installation and fixing device according to claim 1, characterized in that: A first locating pin and a second locating pin are provided on one side of the clamping seat, the free end of the second locating pin is threadedly matched with a connecting block, and a clamping groove for buckling with the first clamping block or the second clamping block is provided on the other side of the clamping seat.

4. A pipeline installation and fixing device according to claim 1, characterized in that: A buckle matched with the clamping seat is provided on one side of the first clamping block, and an inserting block matched with the second clamping block is provided on the other side of the first clamping block.

5. A pipeline installation and fixing device according to claim 1, characterized in that: A buckle matched with the clamping seat is provided on one side of the second clamping block, and a sliding groove plug-matched with the first clamping block is provided on the other side of the second clamping block.

6. A pipeline installation and fixing device according to claim 1, characterized in that: Positioning bolts are respectively arranged on both sides of the base.

7. A pipeline installation and fixing device according to claim 1, characterized in that: A semicircular groove is provided on one side of the clamping seat, the first clamping block and the second clamping block.

Citation Information

Patent Citations

  • Fixing device for installing central air conditioner pipeline

    CN218088729U