Device for measuring drifting loss of cooling tower
By designing a cooling tower drip loss measurement device that is easy to operate and carry, the existing device has solved the problems of cumbersome structure, complex operation and large volume, and a safer and more convenient measurement process is achieved.
Patent Information
- Application Number
- CN202420223122.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-30
- Publication Date
- 2025-02-07
- Estimated Expiration
- 2034-01-30
AI Technical Summary
The existing cooling tower drip loss measurement device has cumbersome structure, many operating steps, safety hazards, and the device is large in size, making it inconvenient to carry and use.
A measuring device consisting of two articulated main frames is designed, and the absorbent filter paper is placed through the area between the main frames, the lifting hand handle and retractable rod are used for easy operation and carrying, and the absorbent filter paper is fixed by metal wire to Ensure breathability and prevent falling.
The convenience and safety of measuring the drop loss of cooling towers is achieved, reducing operating steps, reducing safety risks, and making the device lighter and easier to carry and store.
Smart Images

Figure CN222438912U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cooling tower tools, in particular to a cooling tower drip loss measuring device. Background Art
[0002] In modern large-scale thermal power station projects, natural ventilation cooling towers or mechanical ventilation cooling towers use water as the circulating coolant, and discharge the heat absorbed from the return water of the condenser circulating water system into the atmosphere to achieve the purpose of lowering the water temperature.
[0003] During the normal operation of the cooling tower, drip loss will occur. The drip loss water volume generally refers to the amount of water carried away by the air in the form of water droplets at the water outlet of the cooling tower duct, and also includes the loss part of the water droplets falling on the filler and splashing outside the cooling tower. When the drip loss rate is high, the cooling tower replenishes a lot of water, and some of the cooled water droplets are carried away, which will cause the loss and decrease of the effective heat exchange rate. Therefore, strictly controlling the drip loss rate of the cooling tower is an important means of saving water. To achieve this goal, the drip loss rate of the cooling tower must be accurately measured first. Only by accurately measuring this value can the improvement of the cooling tower structure be effectively guided, and then more energy-saving cooling tower products can be developed.
[0004] The prior art discloses a patent CN207730292U, which includes a collection part and a measuring part, a flow channel is set between the collection part and the measuring part, the collection part includes a shell, a duct is set in the shell, the duct has an air inlet section connected to the air inlet, and also has an air outlet section connected to the air outlet, and a confluence section is between the air inlet section and the air outlet section, and the confluence section is connected to the flow channel. Compared with the traditional collection test method, this device omits the laboratory weighing link and reduces manpower consumption; this device has the advantages of simple structure, low cost, and high test result accuracy.
[0005] As the existing devices including the above patents are used, the shortcomings of the technology are gradually exposed, which are mainly manifested in the following aspects:
[0006] First, the existing measuring device has a complicated structure, many operating steps, and requires operators to climb high to operate, which poses a safety hazard.
[0007] Second, the existing measuring devices are relatively large in size, especially when not in use, they occupy a large space and are not convenient to carry.
[0008] In summary, the prior art obviously has inconveniences and defects in practical use, so it is necessary to improve it. Utility Model Content
[0009] In view of the defects in the prior art, the utility model provides a cooling tower drip loss measuring device to solve the problems that the measuring device in the traditional technology has a cumbersome structure, many operating steps, and requires operators to climb up to operate, which poses a safety hazard; and the existing measuring device has a large structure and volume, especially when not in use, it occupies a large space and is not convenient to carry and use.
[0010] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0011] A cooling tower drip loss measuring device comprises two hinged main frames, the two main frames are opened and closed, and the area between the two main frames is used to place moisture-absorbing filter paper. A locking structure is provided when the two main frames are closed, and the lower end of one of the main frames is connected to a lifting hand handle.
[0012] As an optimized solution, each of the main frames is connected with a plurality of metal wires which are perpendicular to each other in the longitudinal and transverse directions, and the moisture-absorbing filter paper is fixed through the area between the metal wires on the two main frames.
[0013] As an optimized solution, the hinged ends of the two main frames are hingedly connected by two hinges arranged in parallel.
[0014] As an optimized solution, the locking structure includes a latch vertically slidably connected to one of the side walls of the main frame, and a plug-in sleeve located below the latch is fixedly connected to the side wall of the other main frame.
[0015] As an optimized solution, a mounting groove is provided on the inner wall of the main frame, and the moisture-absorbing filter paper is arranged in the area between the mounting grooves on the two main frames.
[0016] As an optimized solution, a connection hole is provided on the installation groove corresponding to the metal wire, and the end of the metal wire is fixedly connected to the connection hole.
[0017] As an optimized solution, the lifting handle includes a connecting rod, the upper end of the connecting rod is connected to one of the main frames, the lower end of the connecting rod is slidably inserted into the hand-held tube, and an extension length scale line is provided between the outer wall of the connecting rod and the outer wall of the hand-held tube.
[0018] As an optimized solution, a plurality of clamping plates are arranged on the end wall where the hand-held tube and the connecting rod are mounted together, and a thread is provided on the outer wall of the plurality of clamping plates together with the outer wall of the hand-held tube, and the plurality of clamping plates are threadedly connected to a clamping sleeve by utilizing the thread.
[0019] As an optimized solution, a clamping sheet is provided on the inner wall of the clamping plate, and the thickness of the clamping sheet is arranged to increase toward the connecting rod.
[0020] As an optimized solution, a threaded sleeve is fixedly connected to the lower end of one of the main frames, and the upper end of the connecting rod is threadedly connected to the threaded sleeve.
[0021] Compared with the prior art, the beneficial effects of the utility model are:
[0022] When measuring the drip loss of the cooling tower, open the lifting handle to an appropriate length, divide the equal-area rings according to the different objects to be tested to determine the measuring point position, and use the extended length scale line to realize intuitive viewing of the height and mark it; tighten the connecting rod and the threaded sleeve, pull out the pin, open the hinge, and the main frame is divided into two left and right leaves. Use the space in the installation slot to load the moisture-absorbing filter paper that has been weighed in advance. Use the metal wire to ensure air permeability and prevent the moisture-absorbing filter paper from falling; After the assembled measuring device stays at the corresponding measuring point of the wind duct outlet for a period of time, quickly remove the moisture-absorbing filter paper in the measuring device and put it into a sealed bag, repeat the above test process at different measuring points to complete the test of the drip loss of the entire tower;
[0023] After removing the lifting handle at the tail, it can be stored separately from the main frame, making the device light and portable;
[0024] A threaded sleeve is welded at the rear of the main frame and connected to the connecting rod through threads, which is convenient for disassembly and installation. The lifting handle is a carbon fiber retractable rod, which is lightweight and portable, and has a fully extended length of 5m. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the specific implementation of the utility model or the technical solution in the prior art, the following is a brief introduction to the drawings required for the specific implementation or the prior art description. In all the drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, each element or part is not necessarily drawn according to the actual scale.
[0026] Figure 1 It is a structural schematic diagram of the utility model in a closed state;
[0027] Figure 2 This is a schematic diagram of the structure of the utility model in an open state;
[0028] Figure 3 for Figure 1 A magnified schematic diagram of part A;
[0029] Figure 4 It is a structural schematic diagram of the installation slot of the utility model.
[0030] In the figure: 1-main frame, 2-metal wire, 3-hinge, 4-latch, 5-insertion sleeve, 6-threaded sleeve, 7-connecting rod, 8-hand-held tube; 9-clamping plate; 10-clamping sleeve; 11-clamping sheet; 12-installation slot; 13-connecting hole; 14-hygroscopic filter paper. DETAILED DESCRIPTION
[0031] The following embodiments of the technical solution of the utility model are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the utility model, and are therefore only used as examples, and cannot be used to limit the protection scope of the utility model.
[0032] like Figures 1 to 4 As shown, the cooling tower drip loss measuring device includes two hinged main frames 1, the two main frames 1 are opened and closed, and the area between the two main frames 1 is used to place moisture-absorbing filter paper 14, and a locking structure is provided when the two main frames 1 are closed, and the lower end of one of the main frames 1 is connected to a lifting hand handle.
[0033] A plurality of metal wires 2 perpendicular to each other in the longitudinal and transverse directions are connected to each main frame 1 , and the moisture-absorbing filter paper 14 is fixed through the area between the metal wires 2 on the two main frames 1 .
[0034] The hinged ends of the two main frames 1 are hingedly connected via two hinges 3 arranged in parallel.
[0035] The locking structure includes a latch pin 4 vertically slidably connected to the side wall of one of the main frames 1 , and an insert sleeve 5 located below the latch pin 4 is fixedly connected to the side wall of the other main frame 1 .
[0036] The inner wall of the main frame 1 is surrounded by a mounting groove 12 , and the moisture-absorbing filter paper 14 is arranged in the area between the mounting grooves 12 on the two main frames 1 .
[0037] A connecting hole 13 is formed on the mounting groove 12 corresponding to the metal wire 2 , and an end of the metal wire 2 is fixedly connected to the connecting hole 13 .
[0038] The lifting handle includes a connecting rod 7, the upper end of which is connected to one of the main frames 1, and the lower end of which is slidably inserted into a hand-held tube 8. A protruding length scale line is provided between the outer wall of the connecting rod 7 and the outer wall of the hand-held tube 8.
[0039] A plurality of clamping plates 9 are arranged around the end wall where the hand-held tube 8 and the connecting rod 7 are fitted together. The outer walls of the plurality of clamping plates 9 and the outer wall of the hand-held tube 8 are provided with a section of thread. The plurality of clamping plates 9 are threadedly connected with a clamping sleeve 10 by thread.
[0040] A clamping piece 11 is provided on the inner wall of the clamping plate 9 , and the thickness of the clamping piece 11 is arranged to increase gradually toward the connecting rod 7 .
[0041] A threaded sleeve 6 is fixedly connected to the lower end of one of the main frames 1 , and the upper end of the connecting rod 7 is threadedly connected in the threaded sleeve 6 .
[0042] The working principle of this device is:
[0043] When measuring the drip loss of the cooling tower, open and raise the hand-held handle to a suitable length, and after determining the measuring point position according to the different reasonable divisions of equal-area rings of the tested object, use the extended length scale line to realize intuitive viewing of the height and make marks; tighten the connecting rod 7 and the threaded sleeve 6, pull out the latch 4, open the hinge 3, and the main frame 1 is divided into two left and right leaves. The space of the mounting groove 12 is used to load the moisture-absorbing filter paper 14 that has been weighed in advance, and the metal wire 2 is used to ensure air permeability while preventing the moisture-absorbing filter paper 14 from falling; after the assembled measuring device is left at the corresponding measuring point of the air duct outlet for a period of time, the moisture-absorbing filter paper 14 in the measuring device is quickly removed and put into a sealed bag, and the above test process is repeated at different measuring points to complete the test of the drip loss of the entire tower;
[0044] After the lifting handle at the tail is removed, it can be stored separately from the main frame 1, making the device light and portable;
[0045] A threaded sleeve 6 is welded at the rear of the main frame 1 and is connected to the connecting rod 7 by threads, which is convenient for disassembly and installation. The lifting handle is a carbon fiber telescopic rod, which is light and portable and has a fully expanded length of 5m.
[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model, and they should all be included in the scope of the claims and specification of the utility model.
Claims
1. Cooling tower drip loss measuring device, characterized by: The invention comprises two main frames (1) which are hingedly arranged, the two main frames (1) are arranged to be opened and closed, and the area between the two main frames (1) is used to place moisture-absorbing filter paper (14), and a locking structure is provided when the two main frames (1) are closed, wherein the lower end of one of the main frames (1) is connected to a lifting handle.
2. The cooling tower drip loss measuring device according to claim 1, characterized in that: Each of the main frames (1) is connected to a plurality of metal wires (2) which are perpendicular to each other in the longitudinal and transverse directions, and the moisture-absorbing filter paper (14) is fixed through the area between the metal wires (2) on the two main frames (1).
3. The cooling tower drip loss measuring device according to claim 1, characterized in that: The hinged ends of the two main frames (1) are hingedly connected via two hinges (3) arranged in parallel.
4. The cooling tower drip loss measuring device according to claim 1, characterized in that: The locking structure comprises a latch (4) vertically slidably connected to a side wall of one of the main frames (1); and a plug-in sleeve (5) located below the latch (4) is fixedly connected to a side wall of the other main frame (1).
5. The cooling tower drip loss measuring device according to claim 2, characterized in that: The inner wall of the main frame (1) is provided with a mounting groove (12), and the moisture absorbing filter paper (14) is arranged in the area between the mounting grooves (12) on the two main frames (1).
6. The cooling tower drip loss measuring device according to claim 5, characterized in that: A connection hole (13) is provided on the installation groove (12) corresponding to the metal wire (2), and the end of the metal wire (2) is fixedly connected to the connection hole (13).
7. The cooling tower drip loss measuring device according to claim 1, characterized in that: The lifting handle comprises a connecting rod (7), the upper end of the connecting rod (7) is connected to one of the main frames (1), the lower end of the connecting rod (7) is slidably inserted into a hand-held tube (8), and a protruding length scale line is provided between the outer wall of the connecting rod (7) and the outer wall of the hand-held tube (8).
8. The cooling tower drip loss measuring device according to claim 7, characterized in that: A plurality of clamping plates (9) are arranged on the end wall of the hand-held tube (8) and the connecting rod (7), and a thread is provided on the outer wall of the plurality of clamping plates (9) together with the outer wall of the hand-held tube (8), and the plurality of clamping plates (9) are threadedly connected with a clamping sleeve (10) by means of the thread.
9. The cooling tower drip loss measuring device according to claim 8, characterized in that: A clamping sheet (11) is provided on the inner wall of the clamping plate (9), and the thickness of the clamping sheet (11) is arranged to increase gradually toward the connecting rod (7).
10. The cooling tower drip loss measuring device according to claim 7, characterized in that: A threaded sleeve (6) is fixedly connected to the lower end of one of the main frames (1), and the upper end of the connecting rod (7) is threadedly connected to the threaded sleeve (6).
Citation Information
Patent Citations
Power plant's cooling tower drips with wafing collects measuring device
CN207730292U