Building electromechanical pipeline mounting and connecting device
By designing a construction electromechanical pipeline installation and connection device with worm and turbine transmission, the problem that existing devices cannot adjust the connection angle is solved, and stable connection and convenient maintenance of electromechanical pipelines of different angles are achieved.
Patent Information
- Application Number
- CN202420553017.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2025-02-28
- Estimated Expiration
- 2034-03-21
AI Technical Summary
The existing construction electromechanical pipeline installation connection device cannot adjust the connection angle of the electromechanical pipeline, resulting in the inability to connect the construction electromechanical pipelines of different levels, resulting in improper connection and looseness.
A construction electromechanical pipeline installation and connection device including a support frame, an adjustment mechanism and a connecting box is designed. Through the transmission of the worm and the turbine, the swing angle of the connecting box is adjusted to meet the electromechanical pipeline installation needs of different angles.
The adjustment effect of the laying angle of the connection device is improved, the installation adaptability of electromechanical pipelines of different angles is enhanced, and the stable connection and maintenance convenience of electromechanical pipelines are ensured.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building electromechanical pipeline installation, in particular to a building electromechanical pipeline installation connection device. Background Art
[0002] Prefabricated buildings use factory assembly lines to prefabricate building components in an industrialized manner and assemble them at the residential installation site. The layout of the electromechanical pipelines in prefabricated buildings needs to be reserved and embedded in advance. Designers accurately locate equipment pipelines during the design phase and generate a BIM model together with civil engineering components to provide to the prefabricated component factory. Different electromechanical pipelines in prefabricated buildings need to be installed and connected using connecting devices.
[0003] For example, application number: CN214044907U discloses an assembled building electromechanical pipeline installation and connection device, in which two wires to be connected pass through two hinged connection boxes respectively, and are buckled, fixed and connected in the connection boxes. The connection device adjusts the angle through the two hinged connection boxes to adapt to the installation of corners with different angles. However, the assembled building electromechanical pipeline installation and connection device can only be used for installation of corners with different angles on the same horizontal plane. The use angle of the building electromechanical pipeline connection box is relatively fixed, and the convenience of adjusting the overall angle of the connection device is low, so when connecting and installing electromechanical pipelines with different laying angles, the electromechanical pipelines will not be connected in place and will become loose.
[0004] Therefore, it is hoped that a building mechanical and electrical pipeline installation and connection device can solve the problems existing in the prior art. Utility Model Content
[0005] 1. Technical issues to be resolved
[0006] In view of the above-mentioned shortcomings and deficiencies of the prior art, the utility model provides a building mechanical and electrical pipeline installation and connection device, which solves the technical problem that the building mechanical and electrical pipeline installation and connection device cannot adjust the connection angle of the mechanical and electrical pipeline, and thus cannot connect building mechanical and electrical pipelines on different horizontal planes.
[0007] (II) Technical solution
[0008] In order to achieve the above-mentioned purpose, the utility model adopts a building electromechanical pipeline installation connection device, the connection device includes: a support frame, an adjustment mechanism and a connection box, the front and rear sides of the connection box are equipped with protective covers for opening or closing the connection device to inspect the electromechanical pipelines, the interior of the connection box is equipped with a wire clamping assembly for fixing the electromechanical pipelines, two wire inlets are symmetrically arranged on the left side of the connection box, a turbine is installed below the wire inlet, a support frame is installed below the connection box, an adjustment mechanism is installed inside the support frame, the adjustment mechanism includes a worm, the worm is transmission-connected to the turbine, and is used to adjust the swing angle of the connection box with the turbine shaft of the turbine as the axis.
[0009] The utility model is used for the installation and connection of mechanical and electrical pipelines in buildings, and meets the needs of mechanical and electrical pipeline installation scenes at different angles by adjusting the swing angle of the installation and connection device of the mechanical and electrical pipelines in buildings.
[0010] Preferably, the adjustment mechanism further includes an adjustment knob, which is disposed on the outer side of the support frame and fixedly mounted on one end of the worm, for adjusting the rotation of the worm and driving the turbine shaft of the turbine to rotate.
[0011] Preferably, the two support plates of the support frame are fixedly mounted below the left and right outer edges of the connection box, the adjustment mechanism is mounted on the support plates, and the support bottom plate of the support frame is arranged below the connection box at a preset distance.
[0012] Preferably, the wire clamping assembly includes: a first clamping ring, a second clamping ring, a threaded slider, a threaded rod, a slide groove and a positioning knob. The first clamping ring is fixedly installed inside the connecting box through a fixing rod. The second clamping ring is semicircular. Threaded sliders are respectively installed at the upper and lower ends of the second clamping ring. The threaded slider is slidably connected to the threaded rod. Positioning knobs are respectively installed at the left and right ends of the threaded rod for controlling the rotation of the threaded rod and moving the threaded slider. Slide grooves are respectively provided at the upper and lower ends of the inner side of the connecting box. The threaded slider slides in the slide groove for fixing the electromechanical pipelines.
[0013] Preferably, the first clamping ring includes two semicircular clamping grooves arranged in opposite directions, and the upper and lower ends of the first clamping ring are fixedly installed inside the connection box through fixing rods respectively, and a through hole is opened in the fixing rod for the threaded rod to pass through.
[0014] Preferably, the protective cover is installed on the front and rear sides of the connection box through hinges.
[0015] Preferably, a connecting piece is installed below the protective cover, and a connecting groove is provided in the connecting piece.
[0016] Preferably, T-shaped bolts are respectively installed on the front and rear sides of the connection box, and the T-shaped bolts are detachably connected to the connection piece.
[0017] Preferably, the longitudinal section width of the head of the T-bolt is smaller than the width of the connecting groove.
[0018] (III) Beneficial effects
[0019] The utility model discloses a building electromechanical pipeline installation connection device which uses the transmission cooperation of a worm and a turbine to meet the installation requirements of electromechanical pipelines at different angles and improves the adjustment effect of the laying angle of the connection device. In addition, the utility model discloses a building electromechanical pipeline installation connection device which improves the convenience of internal pipeline inspection and the stability of pipeline installation by arranging a protective cover and a wire clamping assembly. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 The utility model is a structural schematic diagram of a construction electromechanical pipeline installation and connection device.
[0021] Figure 2 The utility model is a structural schematic diagram of a building electromechanical pipeline installation and connection device with a protective cover opened.
[0022] Figure 3 The utility model is a structural schematic diagram of the connection between the connecting piece and the T-shaped bolt.
[0023] Figure 4 It is a schematic diagram of the internal structure of the connection box of the utility model.
[0024] [Description of Reference Numerals]
[0025] 1: Support frame;
[0026] 11: Connection box;
[0027] 12: Cable inlet;
[0028] 2: Adjustment mechanism;
[0029] 211: Worm;
[0030] 212: Adjustment knob;
[0031] 213: Turbine;
[0032] 3: Protective cover;
[0033] 31: connecting piece;
[0034] 32: T-bolt;
[0035] 33: connection slot;
[0036] 4: Wire clamp assembly;
[0037] 41: first clasp;
[0038] 42: second clasp;
[0039] 43: threaded slider;
[0040] 44: threaded rod;
[0041] 45: chute;
[0042] 46: Positioning knob. DETAILED DESCRIPTION
[0043] In order to better explain the present invention and facilitate understanding, the present invention is described in detail below in conjunction with the accompanying drawings through specific embodiments. Figure 1 The orientation is used as a reference.
[0044] The building mechanical and electrical pipeline installation and connection device proposed in the embodiment of the present invention solves the technical problem that building mechanical and electrical pipelines at different horizontal planes cannot be connected. The embodiment of the present invention meets the installation requirements of mechanical and electrical pipelines at different angles, improves the adjustment effect of the laying angle of the connection device, and the embodiment of the present invention has a simple and reasonable structure and is easy to operate, thereby improving the installation efficiency of prefabricated and assembled buildings.
[0045] In order to better understand the above technical solution, exemplary embodiments of the present invention will be described in more detail with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a clearer and more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.
[0046] Embodiment 1:
[0047] like Figure 1-3 As shown, the building electromechanical pipeline installation connection device includes: a support frame 1, an adjustment mechanism 2 and a connection box 11, and protective covers 3 are installed on the front and rear sides of the connection box 11 for opening or closing the connection device to inspect the electromechanical pipelines. A wire clamping assembly 4 is installed inside the connection box 11 for fixing the electromechanical pipelines. Two wire inlets 12 are symmetrically arranged on the left side of the connection box 11, and a turbine 213 is installed below the wire inlet 12. A support frame 1 is installed below the connection box 11.
[0048] The two support plates of the support frame 1 are fixedly mounted below the left and right outer edges of the connection box 11 , the adjustment mechanism 2 is mounted on the support plates, and the support bottom plate of the support frame 1 is arranged below the connection box 11 at a preset distance.
[0049] The adjusting mechanism 2 includes a worm 211 and an adjusting knob 212. The adjusting knob 212 is arranged on the outside of the support frame 1 and is fixedly installed on one end of the worm 211 for adjusting the rotation of the worm 211. The worm 211 is transmission-connected to the turbine 213. When the two electromechanical pipelines to be connected are not in the same horizontal plane, the adjusting knob 212 is rotated, and the worm 211 rotates and drives the worm 211 to rotate, thereby adjusting the swing angle of the connection box 11 with the turbine shaft of the turbine 213 as the axis, which is used to adjust the positions of the two inlets 12 so that the two electromechanical pipelines pass through the inlet 12 and enter the interior of the connection box 11 for fixed connection.
[0050] The protective cover 3 is installed on the front and rear sides of the connection box 11 through hinges. A connecting piece 31 is installed below the protective cover 3. A connecting groove 33 is provided in the connecting piece 31. T-bolts 32 are installed on the front and rear sides of the connection box 11 respectively. The T-bolts 32 are detachably matched with the connecting piece 31. When the electromechanical pipeline needs to be effectively repaired, the T-bolts 32 are rotated so that the head of the T-bolts 32 is parallel to the connecting groove 33, and the protective cover 3 is opened through the hinges. When the electromechanical pipeline is repaired, the protective cover 3 is closed through the hinges, and the T-bolts 32 are passed through the connecting groove 33. The head of the T-bolts 32 is rotated so that an angle greater than 30° is formed between the T-bolts 32 and the connecting groove 33. In addition, the longitudinal section width of the head of the T-bolt 32 is smaller than the width of the connecting groove 33.
[0051] Embodiment 2:
[0052] like Figure 4 As shown, the wire clamping assembly 4 includes: a first clamping ring 41, a second clamping ring 42, a threaded slider 43, a threaded rod 44, a slide groove 45 and a positioning knob 46. The first clamping ring 41 is fixedly installed inside the connecting box 11 through a fixing rod. The second clamping ring 42 is semicircular. The upper and lower ends of the second clamping ring 42 are respectively installed with threaded sliders 43. The threaded slider 43 is slidably connected to the threaded rod 44. Positioning knobs 46 are respectively installed on the left and right ends of the threaded rod 44 for controlling the rotation of the threaded rod 44 and moving the threaded slider 43. The upper and lower ends of the inner side of the connecting box 11 are respectively provided with slide grooves 45. The threaded slider 43 slides in the slide groove 45 to fix the electromechanical pipelines.
[0053] The first clamping ring 41 includes two semicircular clamping grooves arranged in opposite directions. The upper and lower ends of the first clamping ring 41 are fixedly installed inside the connection box 11 through fixing rods respectively. A through hole is opened in the fixing rod for the threaded rod 44 to pass through.
[0054] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0055] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0056] In the present invention, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.
[0057] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.
[0058] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may alter, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A building electromechanical pipeline installation and connection device, characterized in that: The connection device comprises: a support frame (1), an adjustment mechanism (2) and a connection box (11); protective covers (3) are installed on the front and rear sides of the connection box (11) for opening or closing the connection device to inspect the electromechanical pipeline; a wire clamping assembly (4) is installed inside the connection box (11) for fixing the electromechanical pipeline; two wire inlets (12) are symmetrically arranged on the left side of the connection box (11); a turbine (213) is installed below the wire inlets (12); a support frame (1) is installed below the connection box (11); an adjustment mechanism (2) is installed inside the support frame (1); the adjustment mechanism (2) comprises a worm (211); the worm (211) is transmission-connected to the turbine (213) and is used to adjust the angle at which the connection box (11) swings around the turbine shaft of the turbine (213) as the axis.
2. The building electromechanical pipeline installation and connection device according to claim 1, characterized in that: The adjustment mechanism (2) further comprises an adjustment knob (212), which is arranged on the outside of the support frame (1) and fixedly mounted on one end of the worm (211) and is used to adjust the rotation of the worm (211) and drive the turbine shaft of the turbine (213) to rotate.
3. The building electromechanical pipeline installation and connection device according to claim 2, characterized in that: The two support plates of the support frame (1) are fixedly mounted below the left and right outer edges of the connection box (11), the adjustment mechanism (2) is mounted on the support plates, and the support bottom plate of the support frame (1) is arranged below the connection box (11) at a preset distance.
4. The building electromechanical pipeline installation and connection device according to claim 3 is characterized in that: The wire clamping assembly (4) comprises: a first clamping ring (41), a second clamping ring (42), a threaded slider (43), a threaded rod (44), a slide groove (45) and a positioning knob (46); the first clamping ring (41) is fixedly mounted inside the connection box (11) through a fixing rod; the second clamping ring (42) is semicircular; the upper and lower ends of the second clamping ring (42) are respectively mounted with threaded sliders (43); the threaded slider (43) is slidably connected to the threaded rod (44); positioning knobs (46) are respectively mounted on the left and right ends of the threaded rod (44) for controlling the rotation of the threaded rod (44) and moving the threaded slider (43); the upper and lower ends of the inner side of the connection box (11) are respectively provided with slide grooves (45); the threaded slider (43) slides in the slide grooves (45) for fixing the electromechanical pipelines.
5. The building electromechanical pipeline installation and connection device according to claim 4 is characterized in that: The first clamping ring (41) comprises two semicircular clamping grooves arranged in opposite directions. The upper and lower ends of the first clamping ring (41) are respectively fixedly mounted inside the connection box (11) via fixing rods. A through hole is provided in the fixing rod for the threaded rod (44) to pass through.
6. The building electromechanical pipeline installation and connection device according to claim 5, characterized in that: The protective cover (3) is installed on the front and rear sides of the connection box (11) through hinges.
7. The building mechanical and electrical pipeline installation and connection device according to claim 6, characterized in that: A connecting piece (31) is installed below the protective cover (3), and a connecting groove (33) is provided in the connecting piece (31).
8. The building electromechanical pipeline installation and connection device according to claim 7, characterized in that: T-shaped bolts (32) are respectively installed on the front and rear sides of the connection box (11), and the T-shaped bolts (32) are detachably connected to the connection piece (31).
9. The building mechanical and electrical pipeline installation and connection device according to claim 8, characterized in that: The width of the longitudinal section of the head of the T-shaped bolt (32) is smaller than the width of the connecting groove (33).
Citation Information
Patent Citations
Assembly type building electromechanical pipeline mounting and connecting device
CN214044907U