Urban road slope protection design structure
By designing the main drainage ditch, auxiliary drainage ditch and planting area in the urban road slope protection structure, and setting branch drainage ditch and a detachable second shoulder stop, the problem of low drainage efficiency in the slope protection structure in the prior art is solved, achieving more efficient drainage and longer service life.
Patent Information
- Application Number
- CN202420245692.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-01
- Publication Date
- 2025-03-04
- Estimated Expiration
- 2034-02-01
AI Technical Summary
The drainage efficiency of existing urban road slope protection structures is low, and when precipitation is large, it is easy to be washed by rainwater, which affects its service life.
A design structure for urban road slope protection including main drainage ditch, auxiliary drainage ditch and planting area is designed, and the drainage efficiency of the slope is improved by setting branch drainage ditch and a detachable second shoulder stop.
It effectively improves the drainage efficiency of the slope, reduces the drainage pressure of the main drainage ditches, prevents rainwater from eroding, and extends the service life of the slope protection structure.
Smart Images

Figure CN222557651U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of slope protection, and more specifically, particularly to a design structure for urban road slope protection. Background Art
[0002] Road slopes are an important part of urban infrastructure and an important factor affecting the safety of traffic operations. Landslides caused by slope instability cause huge losses to property and people's lives. Weather factors and human activities will have a significant impact on the stability of road slope structures, and the urban road slope protection design directly affects the safety and service life of urban roads. Therefore, strengthening slope protection design is an issue that should be considered in urban road design.
[0003] The utility model patent with the prior art announcement number CN220184049U discloses a municipal road slope protection structure, including a slope protection baffle and a planting area, a planting area is formed in the middle of the slope protection baffle, and fixed angle steel plates are arranged at the six top corners of the slope protection baffle. Two adjacent fixed angle steel plates are connected by external connecting ribs, and a connecting matching steel plate is arranged in the middle of the external connecting ribs by welding, and a connecting fixing hole is processed on the connecting matching steel plate, and an installation fixing hole is processed on the fixed angle steel plate. The overall structural strength is high and the safety performance is good. The disadvantage is that the drainage efficiency of the slope protection structure is low. When the precipitation is large, the slope protection baffle and the planting area will be washed by a large amount of rainwater, which will affect the service life. Utility Model Content
[0004] The utility model aims to overcome the problem of low drainage efficiency of the existing slope protection structure and to provide a city road slope protection design structure which can solve the above problem.
[0005] A design structure for urban road slope protection comprises a main drainage ditch and an auxiliary drainage ditch which are alternately spaced and longitudinally arranged on the slope surface, a planting area is arranged between the main drainage ditch and the auxiliary drainage ditch, a first shoulder block is arranged at the top of the planting area and at the top of the slope, a second shoulder block is detachably arranged at the top of the auxiliary drainage ditch and at the top of the slope, and a drainage channel is arranged transversely at the bottom of the slope.
[0006] Furthermore, the planting area includes a planting frame fixed on the slope surface and a plurality of branch ditches obliquely arranged between the main drainage ditch and the auxiliary drainage ditch, plants are planted in the planting frame, both ends of the branch ditches are connected with the main drainage ditch and the auxiliary drainage ditch, and one end of the branch ditch close to the auxiliary drainage ditch is lower than the other end.
[0007] Furthermore, the planting frame includes a continuous or independently arranged outer frame, and the outer frame is provided with a water leakage hole.
[0008] Furthermore, the planting frame also includes a fixing frame fixed inside the outer frame, and the fixing frame is fixed to the slope surface through anchor rods.
[0009] Furthermore, the fixing frame includes a fixing sleeve and a connecting rod fixed outside the fixing sleeve, the connecting rod is fixedly connected one by one to the edge of the outer frame surrounded by the outer side of the fixing sleeve, and the anchor rod passes through the fixing sleeve.
[0010] Furthermore, ground nails are provided at the bottom of the outer frame, and the outer frame is fixed to the slope through the ground nails.
[0011] Furthermore, the slope corresponding to the bottom of the planting frame is composed of an original soil layer, a geotextile layer, a transition layer and a planting soil layer from bottom to top. The upper surface of the original soil layer has a wavy structure, and the geotextile layer is laid on the original soil layer in a wavy structure.
[0012] Furthermore, the corresponding slopes below the main drainage ditch, the auxiliary drainage ditch and the branch ditch are, from bottom to top, the original soil layer, the geotextile layer, the transition layer and the concrete layer.
[0013] Furthermore, the planting frame has a parallelogram structure.
[0014] Compared with the prior art, the beneficial effects of the utility model are:
[0015] The urban road slope protection design structure in the utility model is provided with a main drainage ditch, an auxiliary drainage ditch and a planting area on the slope surface. When the rainfall is small, the rainwater on the top of the slope flows into the drainage channel through the main drainage ditch. When the rainfall is large, the second shoulder block is removed, and the rainwater on the top of the slope flows into the drainage channel through the main drainage ditch and the auxiliary drainage ditch, thereby effectively improving the drainage efficiency of the slope.
[0016] By setting up branch ditches, when the rainfall is heavy, if there is no time to remove the second shoulder block, the rainwater in the main drainage ditch can be diverted to the auxiliary drainage ditch through the branch ditches, and then flow into the drainage channel, thereby reducing the drainage pressure of the main drainage ditch.
[0017] By arranging the water leakage holes on the planting frame, it is convenient for rainwater to enter the planting frame to water the plants, and it is convenient for rainwater to flow out of the planting frame to prevent the plants from being soaked. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0019] Figure 1It is a schematic diagram of the overall structure of the urban road slope protection design structure in the embodiment of the utility model.
[0020] Figure 2 It is a structural schematic diagram of a planting frame in an embodiment of the utility model.
[0021] Figure 3 It is a structural schematic diagram of the planting frame in the embodiment of the utility model from another perspective.
[0022] Figure 4 yes Figure 1 Enlarged view of point A in the middle.
[0023] Figure 5 It is a cross-sectional view of the urban road slope protection design structure in the embodiment of the utility model.
[0024] In the figure: 1. main drainage ditch; 2. auxiliary drainage ditch; 3. first shoulder block; 4. second shoulder block; 5. drainage channel; 6. planting frame; 7. branch ditch; 8. outer frame; 9. leakage hole; 10. fixing sleeve; 11. connecting rod; 12. anchor rod; 13. ground nail; 14. original soil layer; 15. geotextile layer; 16. transition layer; 17. planting soil layer; 18. block. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] like Figure 1 As shown, the urban road slope protection design structure in this embodiment includes a main drainage ditch 1 and an auxiliary drainage ditch 2 which are alternately spaced and longitudinally arranged on the slope surface, a planting area is arranged between the main drainage ditch 1 and the auxiliary drainage ditch 2, a first shoulder block 3 is arranged at the top of the planting area and at the top of the slope, a second shoulder block 4 is detachably arranged at the top of the auxiliary drainage ditch 2 and at the top of the slope, and a drainage channel 5 is arranged horizontally at the bottom of the slope.
[0027] By setting the main drainage ditch 1, the auxiliary drainage ditch 2 and the planting area on the slope surface, when the rainfall is small, the rainwater on the top of the slope flows into the drainage channel 5 through the main drainage ditch 1. When the rainfall is heavy, the second shoulder block 4 is removed, and the rainwater on the top of the slope flows into the drainage channel 5 through the main drainage ditch 1 and the auxiliary drainage ditch 2, thereby effectively improving the drainage efficiency of the slope.
[0028] In this embodiment, the planting area includes a planting frame 6 fixed on the slope surface and a plurality of branch ditches 7 obliquely arranged between the main drainage ditch 1 and the auxiliary drainage ditch 2. Plants are planted in the planting frame 6. Both ends of the branch ditches 7 are connected with the main drainage ditch 1 and the auxiliary drainage ditch 2, and one end of the branch ditch 7 close to the auxiliary drainage ditch 2 is lower than the other end, so that rainwater in the main drainage ditch 1 is diverted to the auxiliary drainage ditch 2 through the branch ditch 7, thereby reducing the drainage pressure of the main drainage ditch 1.
[0029] By setting up the branch ditch 7, when the rainfall is heavy, if there is no time to remove the second shoulder block 4, the rainwater in the main drainage ditch 1 can be diverted to the auxiliary drainage ditch 2 through the branch ditch 7, and then flow into the drainage channel 5, thereby reducing the drainage pressure of the main drainage ditch 1.
[0030] In the present utility model, if Figure 2 , Figure 3 As shown, the planting frame 6 includes an outer frame 8 that is continuously or independently arranged, and the outer frame 8 is provided with a drainage hole 9. Specifically, in the present embodiment, the planting frame 6 between adjacent main drainage ditches 1 and auxiliary drainage ditches 2 includes two rows of continuously arranged outer frames 8, and the planting frame 6 between two adjacent branch ditches 7 is in a parallelogram structure. A ground nail 13 is fixed to the bottom of the outer frame 8, and an anti-slip barb (not shown in the figure) is arranged on the outer side of the lower end of the ground nail 13. The ground nail 13 is inserted into the slope body, thereby fixing the planting frame 6 on the slope surface. By providing a drainage hole 9 on the planting frame 6, rainwater can enter or be discharged from the planting frame 6 through the drainage hole 9. On the one hand, when the rainfall is small, it is convenient for rainwater to enter the planting frame 6 to irrigate the plants, and the rainwater is effectively utilized; on the other hand, when the rainfall is large, it is convenient for rainwater to flow out of the planting frame 6 to prevent the plants from being soaked by rainwater, which affects the growth of the plants.
[0031] In this embodiment, a fixing frame is fixed inside the outer frame 8, and the fixing frame includes a fixing sleeve 10 and a connecting rod 11 fixed to the outside of the fixing sleeve 10. The connecting rod 11 is fixedly connected one by one with the edge of the outer frame 8 surrounded by the outside of the fixing sleeve 10. Preferably, the connecting rod 11 is fixed to the middle of the outer frame 8, so that the lower surface of the connecting rod 11 is suspended in the air, which is convenient for rainwater to pass through, and the lower surface of the fixing sleeve 10 abuts against the slope surface. An anchor rod 12 is inserted into the fixing sleeve 10, and the fixing frame is fixedly connected to the slope surface through the anchor rod 12. Preferably, an anti-slip barb (not shown in the figure) is provided on the outer side of the lower end of the anchor rod 12. By providing a fixing frame and an anchor rod 12, the stability and safety performance of the planting frame 6 can be effectively improved.
[0032] In practical applications, when the planting frames 6 at the top and bottom of the slope surface are not complete, the outer frame 8 can be spliced with the first shoulder block 3 or the bottom of the slope.
[0033] In this embodiment, if Figure 4As shown, a clamping block 18 is fixedly provided on both sides of the second shoulder stopper 4 near the first shoulder stopper 3, and the clamping block 18 extends to the upper and lower end surfaces of the second shoulder stopper 4 and is flush with the upper and lower end surfaces of the second shoulder stopper 4. A clamping slot is provided on the side of the first shoulder stopper 3 adjacent to the second shoulder stopper 4 near the second shoulder stopper 4, and the upper end of the clamping slot passes through the upper end of the first shoulder stopper 3, the height of the clamping slot is the same as the height of the clamping block 18, and the shape and size of the cross section of the clamping slot are adapted to the shape and size of the cross section of the clamping block 18. Specifically, the shape of the cross section of the clamping slot and the shape of the cross section of the clamping block 18 are both T-shaped structures. The second shoulder stopper 4 can be installed and removed by moving it up and down. When the second shoulder stopper 4 is in the installed state, the second shoulder stopper 4 is flush with the upper surface of the first shoulder stopper 3.
[0034] By setting a removable second shoulder block 4, when the precipitation is small, the second shoulder block 4 can block rainwater from flowing into the auxiliary drainage ditch 2 from the top of the slope, so that as much rainwater as possible flows into the main drainage ditch 1, and is diverted to the branch ditch 7 through the main drainage ditch 1. The rainwater in the main drainage ditch 1 and the branch ditch 7 enters the planting frame 6 through the leakage hole 9 as much as possible to water the plants. When the precipitation is large, the second shoulder block 4 is removed, and the rainwater on the top of the slope is directly discharged through the main drainage ditch 1 and the auxiliary drainage ditch 2, which speeds up the drainage efficiency, prevents rainwater from scouring the entire slope surface, and avoids affecting the service life of the urban road slope protection design structure.
[0035] In this embodiment, if Figure 5 As shown, the corresponding slope below the planting frame 6 is, from bottom to top, the original soil layer 14, the geotextile layer 15, the transition layer 16 and the planting soil layer 17. The upper surface of the original soil layer 14 is a wavy structure, and the geotextile layer 15 is laid on the original soil layer 14 in a wavy structure. The corresponding slopes below the main drainage ditch 1, the auxiliary drainage ditch 2 and the branch ditch 7 are, from bottom to top, the original soil layer 14, the geotextile layer 15, the transition layer 16 and the concrete layer (not shown in the figure). The bottoms of the ground nails 13 and the anchor rods 12 are inserted into the transition layer 16 above the geotextile layer 15. Specifically, the transition layer 16 can be a sandy protective layer or a gravel layer. The geotextile layer 15 adopts a waterproof geotextile to effectively prevent rainwater from seeping into the slope and causing landslides. The wavy structure of the upper surface of the original soil layer 14 can improve the stability between the geotextile layer 15 and the original soil layer 14 and prevent the waterproof geotextile from shifting.
[0036] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A design structure for urban road slope protection, characterized in that: include: Main drainage ditches (1) and auxiliary drainage ditches (2) are alternately spaced and longitudinally arranged on the slope surface; A planting area arranged between the main drainage ditch (1) and the auxiliary drainage ditch (2); A first shoulder block (3) arranged at the top of the planting area and located at the top of the slope; A second shoulder stopper (4) detachably arranged on the top of the auxiliary drainage ditch (2) and located at the top of the slope; as well as A drainage channel (5) arranged transversely at the bottom of the slope; The planting area comprises a planting frame (6) fixed on the slope surface and a plurality of branch ditches (7) obliquely arranged between the main drainage ditch (1) and the auxiliary drainage ditch (2); plants are planted in the planting frame (6); both ends of the branch ditches (7) are connected to the main drainage ditch (1) and the auxiliary drainage ditch (2); and one end of the branch ditches (7) close to the auxiliary drainage ditch (2) is lower than the other end; The planting frame (6) comprises a continuously or independently arranged outer frame (8) and a fixing frame fixed inside the outer frame (8); the outer frame (8) is provided with a water leakage hole (9); the fixing frame is fixed to the slope surface via an anchor rod (12); the fixing frame comprises a fixing sleeve (10) and a connecting rod (11) fixed outside the fixing sleeve (10); the connecting rod (11) is fixedly connected one by one to the edge of the outer frame (8) surrounded by the outer side of the fixing sleeve (10); and the anchor rod (12) passes through the fixing sleeve (10).
2. The urban road slope protection design structure according to claim 1 is characterized in that: A ground nail (13) is provided at the bottom of the outer frame (8), and the outer frame (8) is fixed to the slope via the ground nail (13).
3. The urban road slope protection design structure according to any one of claims 1-2 is characterized in that: The side slope corresponding to the bottom of the planting frame (6) comprises, from bottom to top, an original soil layer (14), a geotextile layer (15), a transition layer (16) and a planting soil layer (17); the upper surface of the original soil layer (14) is in a wavy structure, and the geotextile layer (15) is laid on the original soil layer (14) in a wavy structure.
4. The urban road slope protection design structure according to any one of claims 1-2 is characterized in that: The corresponding side slopes below the main drainage ditch (1), the auxiliary drainage ditch (2) and the branch ditch (7) are, from bottom to top, an original soil layer (14), a geotextile layer (15), a transition layer (16) and a concrete layer.
5. The urban road slope protection design structure according to claim 1 is characterized in that: The planting frame (6) is in a parallelogram structure.
Citation Information
Patent Citations
Municipal road slope protection structure
CN220184049U