Anti-blocking dechlorinator system
By designing an anti-blocking dechlorinator system in petrochemical production, and using the combination of multiple pipelines and pressure sensors, the problem of ash and colloid blockage in the dechlorination tank is solved, extending the service life of the dechlorination agent, reducing costs, and ensuring the continuous operation of the device.
Patent Information
- Application Number
- CN202420908039.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-29
- Publication Date
- 2025-03-14
- Estimated Expiration
- 2034-04-29
AI Technical Summary
During the petrochemical production process, the raw materials contain chloride, which causes the ash and colloid in the dechlorination tank to be easily blocked, causing pressure to rise, affecting operational safety, resulting in scrapping of dechlorination agents and increasing economic losses.
An anti-blocking dechlorinator system was designed. By setting up multiple pipelines and pressure sensors, it ensures that when the upstream pipeline is blocked, the lower layer of dechlorination agent can still be used effectively, avoiding the scrapping of the entire tank of dechlorination agent.
It extends the service life of the dechlorination agent, reduces the cost of dechlorination, ensures the continuous operation of the device, and reduces equipment usage costs, labor costs and solid waste treatment costs.
Smart Images

Figure CN222613263U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of petrochemical industry, in particular to an anti-clogging dechlorinator system. Background Art
[0002] In the production process of petrochemical products, chlorides are contained in the raw materials themselves, and chlorides are also introduced during the processing and production process. However, excessive chlorides will bring some negative effects, such as corrosion to reforming unit equipment, pipeline blockage, and even catalyst poisoning to workers. Therefore, the removal of chlorides is of great significance to ensure the normal production of enterprises.
[0003] The desulfurization process of chloride mainly uses a dechlorinating agent to react in a dechlorination tank. The main use of dechlorinating agents for dechlorination is that the active components of the dechlorinating agent will undergo an acid-base neutralization reaction with HCl to generate stable metal chlorides which are then fixed, thereby achieving the purpose of removing HCl.
[0004] However, in the prior art, the upstream raw materials contain a large amount of ash and colloid during the reaction of the dechlorination tank, which is easy to block the gaps between the catalysts at the top during operation, causing pressure to rise, affecting operation safety, and thus causing the entire tank of dechlorination agent to be scrapped, resulting in economic losses. This in turn increases the company's equipment usage fees, labor costs, solid waste treatment fees, etc. Utility Model Content
[0005] In view of the above-mentioned defects, the utility model provides a blockage-resistant dechlorinator system which can timely avoid the blockage section when blockage occurs, thereby ensuring continuous operation of the device and reducing losses and risks, thereby achieving good effect and low risk, long dechlorination agent service life and low dechlorination cost.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a blockage-proof dechlorinator system, comprising a dechlorinator feed main pipeline, a dechlorinator side feed main pipeline, and a discharge pipeline, wherein the dechlorinator feed main pipeline is connected to the feed end at the top of the dechlorinator, the dechlorinator feed end is provided with a dechlorinator feed main pipeline through valve, the dechlorinator feed main pipeline is also connected to the dechlorinator side feed main pipeline, and the upper, middle, and tail portions of the dechlorinator side feed main pipeline are sequentially connected to the upper side of the dechlorinator. The feed pipe, the feed pipe in the middle of the dechlorination tank, and the feed pipe at the bottom of the dechlorination tank are connected to the upper, middle and lower parts of the dechlorination tank respectively. Valves are provided on the outer sides of the connection points between the feed pipe in the upper side of the dechlorination tank, the feed pipe in the middle of the dechlorination tank, and the feed pipe at the bottom of the dechlorination tank and the dechlorination tank. The bottom discharge end of the dechlorination tank is connected to the discharge pipeline, and a discharge pipe through valve is provided at the bottom discharge end of the dechlorination tank.
[0007] As a further improvement of the utility model, the dechlorination tank feed main pipeline through valve and the discharge pipeline through valve are both solenoid valves.
[0008] As a further improvement of the utility model, the dechlorination tank is filled with a reformed oil liquid phase dechlorination agent.
[0009] As a further improvement of the utility model, a pressure sensor is installed on the pipe wall of the dechlorination tank feed main pipe.
[0010] As a further improvement of the present invention, a pressure sensor is installed on the pipe wall of the discharge pipeline.
[0011] As a further improvement of the utility model, pressure sensors are provided at the connection points between the upper feed pipe of the dechlorination tank, the middle feed pipe of the dechlorination tank, the lower feed pipe of the dechlorination tank and the dechlorination tank.
[0012] Beneficial effects of the utility model:
[0013] 1. By setting up multiple pipelines, it is ensured that when the upper part of the pipeline is blocked, the dechlorinating agent in the lower layer of the pipeline can still be used effectively, and the chlorine capacity of the dechlorinating agent in the dechlorinating tank is fully utilized, thereby ensuring that the service life of the dechlorinating agent is extended as much as possible.
[0014] 2. Different pipelines and valves on the pipelines are relatively independent and can be opened individually or together at will. Users can use them flexibly according to their needs, avoiding the current situation of blockage of the dechlorinator at the line inlet and insufficient use of the dechlorinator. It can effectively improve the dechlorination effect and dechlorination efficiency, reduce the cost of catalyst use, labor costs, solid waste treatment costs, etc., and ensure maximum corporate benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the structure of the utility model anti-clogging dechlorinator system;
[0016] Figure 2 This is a working principle diagram of the utility model under normal conditions;
[0017] Figure 3 This is a working principle diagram of the utility model in the top blocking state;
[0018] Figure 4 This is a working principle diagram of the utility model in the upper blocking state;
[0019] Figure 5 This is a working principle diagram of the utility model in the middle blocking state;
[0020] In the figure: 1-dechlorination tank feed main pipeline, 10-dechlorination tank feed main pipeline through valve; 2-dechlorination tank side feed main pipeline; 3-dechlorination tank upper side feed pipeline, 30-upper through valve; 4-dechlorination tank middle side feed pipeline, 40-middle through valve; 5-dechlorination tank lower side feed pipeline, 50-lower through valve; 6-dechlorination tank; 7-discharge pipeline, 70-discharge pipeline through valve. DETAILED DESCRIPTION
[0021] In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model is further described in detail below in conjunction with the accompanying drawings. It should be understood that the specific examples described herein are only used to explain the utility model and are not used to limit the utility model. The directional terms mentioned in the following embodiments, such as: up, down, left, right, front or back, etc., are only referenced to the directions of the accompanying drawings. Therefore, the directional terms used are used to illustrate and are not used to limit the utility model. In addition, in all embodiments, the same figure numbers represent the same elements.
[0022] like Figures 1 to 5 The anti-clogging dechlorinator system shown in the figure comprises a dechlorinating tank feed main pipeline 1 and a dechlorinating tank side feed main pipeline 2. One end of the dechlorinating tank feed main pipeline 1 is connected to the material supply end, and the other end of the dechlorinating tank feed main pipeline 1 is connected to the feed end at the top of the dechlorinating tank 6. A pressure sensor is provided on the pipeline wall at the connection between the dechlorinating tank feed main pipeline 1 and the feed end, and the pressure sensor can detect the pressure drop of the dechlorinating tank feed main pipeline 1. The feed end of the dechlorinating tank 6 is provided with a dechlorinating tank feed main pipeline through valve 10. The dechlorinating tank 6 is filled with a dechlorinating agent, and the dechlorinating agent is mainly a reforming oil liquid phase dechlorinating agent, which is generally a molecular sieve and a calcium zinc type. The discharge end of the dechlorinating tank 6 is connected to one end of the discharge pipeline 7, and a pressure sensor is provided on the pipeline wall at the connection between the discharge pipeline 7 and the discharge end. The discharge end at the bottom of the dechlorinating tank 6 is provided with a discharge pipeline through valve 70, and the other end of the discharge pipeline 7 is connected to the discharge collection place.
[0023] As a further illustration of this example, the dechlorination tank feed main pipeline through valve 10 and the discharge pipeline through valve 70 are both solenoid valves.
[0024] The dechlorination tank feed main pipeline 1 is also connected to the dechlorination tank side feed main pipeline 2. The upper part of the dechlorination tank side feed main pipeline 2 is connected to the dechlorination tank 6 through the dechlorination tank upper side feed pipeline 3. The dechlorination tank upper side feed pipeline 3 is connected to the upper part of the inner side of the dechlorination tank 6. The upper side feed of the dechlorination tank 6 is provided with an upper through valve 30.
[0025] The middle part of the dechlorination tank side feed main pipeline 2 is connected to the dechlorination tank 6 through the dechlorination tank middle side feed pipeline 4, and the dechlorination tank middle side feed pipeline 4 is connected to the middle part of the inner side of the dechlorination tank 6. The middle side feed of the dechlorination tank 6 is provided with a middle through valve 40.
[0026] The tail of the dechlorination tank side feed main pipeline 2 is connected to the dechlorination tank 6 through the dechlorination tank lower side feed pipeline 5, and the dechlorination tank middle side feed pipeline 5 is connected to the lower part of the inner side of the dechlorination tank 6. The lower side feed of the dechlorination tank 6 is provided with a lower through valve 50.
[0027] As a further illustration of this example, the upper through valve 30 , the middle through valve 40 , and the lower through valve 50 are all solenoid valves.
[0028] Pressure sensors are arranged on the pipe walls of the upper feed pipe 3 of the dechlorination tank, the middle feed pipe 4 of the dechlorination tank, the lower feed pipe 5 of the dechlorination tank and the connection points with the dechlorination tank 6.
[0029] As a further illustration of this example, after the colloid is blocked, the pressure drop will increase, and the pressure sensor is used to detect whether it is blocked by the pressure drop. The blockage position is generally blocked from top to bottom, and the pressure drop will gradually increase.
[0030] The working principle and use process of this utility model:
[0031] 1. In normal working state: the upper through valve 30, the middle through valve 40 and the lower through valve 50 are all in the closed state, the main pipeline through valve 10 and the discharge pipeline through valve 70 are in the open state, and the undechlorinated material enters the top feed end of the dechlorination tank 6 from the material supply end through the dechlorination tank feed main pipeline 1. After the undechlorinated material reacts with the dechlorination agent in the dechlorination tank 6 for dechlorination, it is discharged from the discharge end at the bottom of the dechlorination tank 6 through the discharge pipeline 7 to the discharge collection point.
[0032] 2. When the pressure drop of the pressure sensor at the dechlorination tank feed main pipeline 1 increases and the top pipeline of the dechlorination tank 6 is blocked: the main pipeline through valve 10, the middle through valve 40, and the lower through valve 50 are all in a closed state, and the upper through valve 30 and the discharge pipeline through valve 70 are in an open state. The undechlorinated material first enters the dechlorination tank side feed main pipeline 2 from the material supply end through the dechlorination tank feed main pipeline 1, and then directly enters the upper part of the dechlorination tank 6 from the upper side feed pipeline 3 of the dechlorination tank. After the undechlorinated material undergoes dechlorination reaction with the dechlorination agent in the dechlorination tank 6, it is discharged from the discharge end at the bottom of the dechlorination tank 6 through the discharge pipeline 7 to the discharge collection point.
[0033] 3. When the pressure drop of the pressure sensor at the upper feed pipe 3 of the dechlorination tank increases and the upper pipeline of the dechlorination tank 6 is blocked: the main pipeline through valve 10, the upper through valve 30, and the lower through valve 50 are all in a closed state, and the middle through valve 40 and the discharge pipeline through valve 70 are in an open state. The undechlorinated material first enters the dechlorination tank side feed main pipe 2 from the material supply end through the dechlorination tank feed main pipe 1, and then directly enters the middle part of the dechlorination tank 6 from the dechlorination tank middle side feed pipe 4. After the undechlorinated material undergoes dechlorination reaction with the dechlorinating agent in the dechlorination tank 6, it is discharged from the discharge end at the bottom of the dechlorination tank 6 through the discharge pipeline 7 to the discharge collection point.
[0034] 4. When the pressure drop of the pressure sensor at the upper feed pipe 4 of the dechlorination tank increases and the middle pipeline of the dechlorination tank 6 is blocked: the main pipeline through valve 10, the upper through valve 30, and the middle through valve 40 are all in a closed state, and the lower through valve 50 and the discharge pipe through valve 70 are in an open state. The undechlorinated material first enters the dechlorination tank side feed main pipe 2 from the material supply end through the dechlorination tank feed main pipe 1, and then directly enters the lower part of the dechlorination tank 6 from the lower feed pipe 5 of the dechlorination tank. After the undechlorinated material undergoes dechlorination reaction with the dechlorination agent in the dechlorination tank 6, it is discharged from the discharge end at the bottom of the dechlorination tank 6 through the discharge pipeline 7 to the discharge collection point.
[0035] After the switch, the blocked part is not processed temporarily, and after the dechlorination reaction of the dechlorinating agent is complete, the dechlorinating agent in the dechlorinating tank 6 is uniformly unloaded.
[0036] The above are only preferred implementations of the utility model. The protection scope of the utility model is not limited to the above implementation measures. All technical solutions under the idea of the utility model belong to the protection scope of the utility model. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the utility model should also be regarded as the protection scope of the utility model.
Claims
1. An anti-clogging dechlorinator system, characterized in that: The invention comprises a dechlorination tank feed main pipeline (1), a dechlorination tank side feed main pipeline (2), and a discharge pipeline (7), wherein the dechlorination tank feed main pipeline (1) is connected to the feed end at the top of the dechlorination tank (6), and the feed end of the dechlorination tank (6) is provided with a dechlorination tank feed main pipeline through valve (10), and the dechlorination tank feed main pipeline (1) is also connected to the dechlorination tank side feed main pipeline (2), and the upper part, middle part, and tail part of the dechlorination tank side feed main pipeline (2) are connected to the dechlorination tank upper side feed pipeline (3), the dechlorination tank middle side feed pipeline (4), and the dechlorination tank The lower feed pipe (5) is connected to the upper, middle and lower parts of the dechlorination tank (6) respectively. The upper feed pipe (3), middle feed pipe (4) and lower feed pipe (5) of the dechlorination tank are connected to the upper, middle and lower parts of the dechlorination tank (6). Valves are provided on the outer sides of the connection points between the upper feed pipe (3), middle feed pipe (4) and lower feed pipe (5) of the dechlorination tank and the dechlorination tank (6). The bottom discharge end of the dechlorination tank (6) is connected to the discharge pipeline (7). The bottom discharge end of the dechlorination tank (6) is provided with a discharge pipe through valve (70).
2. The anti-clogging dechlorinator system according to claim 1, characterized in that: The dechlorination tank feed main pipeline through valve (10) and the discharge pipeline through valve (70) are both solenoid valves.
3. The anti-clogging dechlorinator system according to claim 1, characterized in that: The dechlorination tank (6) is filled with a reformed oil liquid phase dechlorination agent.
4. The anti-clogging dechlorinator system according to claim 1, characterized in that: A pressure sensor is installed on the pipe wall of the dechlorination tank feed main pipe (1).
5. The anti-clogging dechlorinator system according to claim 1, characterized in that: A pressure sensor is installed on the pipe wall of the discharge pipe (7).
6. The anti-clogging dechlorinator system according to claim 1, characterized in that: Pressure sensors are provided at the connection points between the upper feed pipe (3) of the dechlorination tank, the middle feed pipe (4) of the dechlorination tank, the lower feed pipe (5) of the dechlorination tank and the dechlorination tank (6).