Novel disassembly-free membrane shell structure for concrete pouring molding

By adopting a new membrane-free shell structure, using components such as U-shaped membrane shell and built-in steel mesh, problems such as time-consuming and insufficient structural connectivity in the traditional mold support process are solved, and the effects of stable structure, simple operation and cost-saving are achieved.

CN222614833UActive Publication Date: 2025-03-14LIANGGU NEW WALL MATERIALS (SHANGHAI) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420117545.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-17
Publication Date
2025-03-14
Estimated Expiration
2034-01-17

AI Technical Summary

Technical Problem

During the casting of traditional structural columns and structural beams, there are problems such as time-consuming, labor-intensive, insufficient structural connectivity, waste of materials and increased costs.

Method used

A new type of film-free shell structure for concrete casting molding is adopted, including two U-shaped film shells with the same length, width and height. The inner cavity is equipped with steel mesh, galvanized flat steel mesh, anchor tie-up parts and bolt sleeves, and is poured with high-strength concrete.

Benefits of technology

It achieves a stable and reliable structure, easy operation and no need to dismantle molds, improves structural connectivity, and saves construction period and construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222614833U_ABST
    Figure CN222614833U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of buildings, and provides a novel disassembly-free membrane shell structure for concrete pouring molding, which comprises a disassembly-free membrane shell, the whole disassembly-free membrane shell is formed by combining two U-shaped membrane shells with the same length, width and height, a reinforcing mesh, a galvanized flat steel mesh, an anchoring tie piece and a bolt sleeve are arranged in an inner cavity of the U-shaped membrane shell, and high-strength concrete is poured in the inner cavity of the U-shaped membrane shell; wherein a plurality of anchoring convex blocks are uniformly arranged on the inner side shell wall of the U-shaped membrane shell. According to the novel disassembly-free membrane shell structure for concrete pouring forming, through optimization design and construction procedures, the structural stability and the construction efficiency are improved, meanwhile, material use is optimized, the construction period and the construction cost can be saved without formwork disassembly, and an innovative solution with wide application prospects is provided for the building industry.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction, in particular to a novel non-disassembly membrane shell structure for concrete casting. Background Art

[0002] In the traditional formwork pouring process of structural columns and beams, wooden or metal formwork is often used for formwork, and these formworks are removed after the concrete solidifies. This method has some disadvantages:

[0003] Time-consuming and labor-intensive: Traditional formwork requires additional installation and removal steps, which increases the time and labor costs of the project. Manual formwork removal is not only time-consuming and labor-intensive, but may also damage the formwork, increasing the cost of maintenance and replacement of the formwork.

[0004] Insufficient structural connectivity: Traditional formwork may leave marks or gaps after removal, which may lead to insufficient connectivity in the concrete structure. This may lead to structural weaknesses and damage, and require additional reinforcement and repair work during use.

[0005] Material waste and increased costs: Traditional formwork may be damaged after removal and cannot be reused, resulting in material waste. In addition, the production and maintenance of these formworks themselves also require certain costs.

[0006] Therefore, this invention proposes a novel membrane shell structure for concrete casting without disassembly to solve the above problems. Utility Model Content

[0007] In order to overcome the defects of the prior art, the utility model aims to provide a novel non-disassembly membrane shell structure for concrete casting.

[0008] To achieve the above object, the technical solution of the utility model is implemented as follows: a novel non-disassembly membrane shell structure for concrete casting, comprising a non-disassembly membrane shell, wherein the non-disassembly membrane shell is composed of two U-shaped membrane shells with the same length, width and height, and a steel mesh, a galvanized flat steel mesh, an anchoring tie and a bolt sleeve are arranged inside the inner cavity of the U-shaped membrane shell, and high-strength concrete is poured in the inner cavity of the U-shaped membrane shell;

[0009] A plurality of anchoring protrusions are evenly arranged on the inner shell wall of the U-shaped membrane shell;

[0010] The steel mesh is U-shaped and integrated, and is laid in a designated U-shaped membrane shell mold, and the galvanized flat steel mesh is laid inside the steel mesh;

[0011] The galvanized flat steel mesh and the steel mesh are bound and fixed by steel wire.

[0012] Preferably, a plurality of the anchoring anchors and the bolt sleeves are equidistantly installed at designated positions of the steel mesh, and an outer end of the anchoring anchor passes through the interior of the U-shaped membrane shell.

[0013] The beneficial effects of the utility model are embodied in:

[0014] Stable and reliable structure: The structure is composed of two identical U-shaped membrane shells, with steel mesh, galvanized flat steel mesh, anchoring parts and bolt sleeves set inside, and the internal cavity is poured with high-strength concrete. This design ensures that the formed non-disassembly membrane shell has good firmness and stability after the concrete solidifies, enhances the connection stability of the structure, and reduces the displacement and looseness between components.

[0015] Easy to operate and no need to remove the formwork: There is no need to remove the formwork, it has good stability and is easy to install. It can be directly used for the casting and forming of house structural columns and structural beams, and it can be integrated with the cast-in-place concrete, saving construction time and construction costs.

[0016] Improve structural connectivity: The added anchoring protrusions and the design of the anchoring tie pieces make the non-dismantling membrane shell and the poured concrete structure form a tighter connection, ensuring that after the concrete solidifies, the non-dismantling membrane shell and the internal concrete form a whole. This structure further improves the stability and bearing capacity of the overall structure.

[0017] In general, this new type of membrane shell structure for concrete casting and molding improves structural stability and construction efficiency by optimizing the design and construction process, while optimizing material usage. The absence of mold removal can save construction time and construction costs, providing an innovative solution with broad application prospects for the construction industry. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In the attached picture:

[0019] Figure 1 It is a schematic diagram of the structure of the utility model in a combined use state;

[0020] Figure 2 It is a structural schematic diagram of a horizontal section of the utility model;

[0021] Description of reference numerals:

[0022] 1. Non-disassembly membrane shell; 11. Steel mesh; 12. Galvanized flat steel mesh; 13. Anchoring tie bars; 14. High-strength concrete; 15. Bolt sleeve; 16. U-shaped membrane shell; 17. Anchoring protrusion. DETAILED DESCRIPTION

[0023] The utility model will be further described in detail below in conjunction with the accompanying drawings and embodiments. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments. In the absence of conflict, the embodiments in this application and the features in the embodiments can be combined with each other. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] It should be noted that if the utility model embodiments involve directional indications (such as up, down, left, right, front, back...), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0025] In addition, "multiple" means more than two. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the fact that ordinary technicians in the field can implement it. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such combination of technical solutions does not exist and is not within the scope of protection required by the utility model.

[0026] Please refer to the instruction manual Figure 1-Figure 2 The utility model provides a novel non-disassembly membrane shell structure for concrete casting, including a non-disassembly membrane shell 1, the non-disassembly membrane shell 1 as a whole is composed of two U-shaped membrane shells 16 with the same length, width and height, the inner cavity of the U-shaped membrane shell 16 is provided with a steel mesh 111, a galvanized flat steel mesh 12, an anchoring member 13 and a bolt sleeve 15, and the inner cavity of the U-shaped membrane shell 16 is poured with high-strength concrete 14;

[0027] A plurality of anchoring protrusions 17 are evenly arranged on the inner shell wall of the U-shaped membrane shell 16;

[0028] Among them, the design of the anchoring protrusion 17 can be firmly anchored inside the non-disassembly membrane housing 1 after the concrete is solidified after being subsequently poured inside the non-disassembly membrane housing 1, and cooperate with the penetrating anchoring tie piece 13 to form a whole with the internally poured concrete structure to the greatest extent, thereby increasing the connection stability;

[0029] The overall cross-section of the anchoring protrusion 17 is set to an isosceles trapezoid, which can ensure the anchoring performance while increasing the angle between its side and the surface of the U-shaped membrane shell 17, ensuring that the entire anchoring protrusion 17 can be completely covered after concrete pouring to avoid hollowing.

[0030] The steel mesh 111 is U-shaped and integrated, and is laid in a designated U-shaped membrane shell mold, and the galvanized flat steel mesh 12 is laid on the inner side of the steel mesh 111 .

[0031] The galvanized flat steel mesh 12 and the steel mesh 111 are bound and fixed by steel wire.

[0032] A plurality of the anchoring members 13 and the bolt sleeves 15 are equidistantly installed at designated positions of the steel mesh 11 , and an outer end of the anchoring member 13 passes through the interior of the U-shaped membrane shell 16 .

[0033] Specific operation process:

[0034] Two U-shaped membrane shells 6 with the same length, width and height are buckled and fixed with a special clamp to form a non-disassembly membrane shell 7 for concrete molding required in the house construction process.

[0035] The steel mesh 11 is laid in the designated U-shaped membrane shell mold 16, and the galvanized flat steel mesh 2 is laid on the inner side of the steel mesh 11 and then tied and fixed to the steel mesh 11. Then, a number of anchoring parts 3 and bolt sleeves 15 are equidistantly installed at designated positions of the steel mesh 11. After the installation is completed, high-strength concrete 4 is poured throughout the entire U-shaped membrane shell mold 16, and then mechanically compacted to form a half-disassembly-free membrane shell 1, and then the two formed half-disassembly-free membrane shells 1 are buckled together and locked and fixed with a special clamp, thereby forming a complete non-disassembly membrane shell 7 formed by concrete required in the house construction process.

[0036] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

[0037] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

[0038] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A novel non-disassembly membrane shell structure for concrete casting, comprising a non-disassembly membrane shell (1), characterized in that: The non-disassembly membrane shell (1) is composed of two U-shaped membrane shells (16) of the same length, width and height. A steel mesh (11), a galvanized flat steel mesh (12), an anchoring member (13) and a bolt sleeve (15) are arranged inside the inner cavity of the U-shaped membrane shell (16). High-strength concrete (14) is poured inside the inner cavity of the U-shaped membrane shell (16); A plurality of anchoring protrusions (17) are evenly arranged on the inner shell wall of the U-shaped membrane shell (16); The steel mesh (11) is U-shaped and integrated, and is laid in a designated U-shaped membrane shell mold, and the galvanized flat steel mesh (12) is laid on the inner side of the steel mesh (11); The galvanized flat steel mesh (12) and the steel mesh (11) are bound and fixed by steel wire.

2. A novel non-disassembly membrane shell structure for concrete casting according to claim 1, characterized in that: A plurality of the anchoring anchors (13) and the bolt sleeves (15) are equidistantly installed at designated positions of the steel mesh (11), and an outer end of the anchoring anchor (13) passes through the interior of the U-shaped membrane shell (16).