Bridge single-column pier reinforcing device
By designing a bridge single-column pier reinforcement device including box girders and steel cover beams, the problems of aging rubber bearings and loose connections of steel cover beams in bridge single-column piers are solved, and the stability and load-bearing capacity of the bridge are significantly improved.
Patent Information
- Application Number
- CN202420856150.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-23
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2034-04-23
AI Technical Summary
The aging, cracking, and air removal of rubber bearings of single-column piers of bridges, as well as the loosening and cracking of the connection between the steel cover beams and the bridge piers, resulting in insufficient bridge stability and load-bearing capacity.
A bridge single-column pier reinforcement device is designed, including a box beam and a steel cover beam. The lower side of the box beam is provided with a steel cover beam. The steel cover beam is connected to the outer surface of the bridge column piers. Through the tenon-and-bonding structure of the first beam slab frame and the second beam slab frame and the base plate, a stable structural state is formed.
It effectively improves the overall stability and bearing capacity of the bridge, avoids the problem of aging of rubber bearings, and uses the complementary structure of steel cover beams and box beams to share the load of the bridge, improving the safety of the bridge and traffic flow tolerance.
Smart Images

Figure CN222632068U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of bridges, and more specifically to a single-column pier reinforcement device for bridges. Background Art
[0002] A single-column pier bridge refers to a bridge supported by a single row of piers. This type of structure is widely used in the construction of bridges, subway stations, high-rise buildings, etc. It has the advantages of small footprint, small visual interference, strong spatial adaptability, beautiful bridge shape, smaller span, and greater economy. However, single-column pier bridges also have some potential problems, such as weak torsional resistance at the pier top and insufficient lateral anti-overturning capacity. In some extreme cases, such as multiple heavily loaded large trucks driving on the same lane on the same side of the bridge at the same time, the bridge may be in danger of overturning. In order to improve the performance of single-column pier bridges, people usually take a series of reinforcement measures.
[0003] In order to improve the performance of single-column pier bridges, the existing technology is to install steel cap beams and rubber bearings on the top of the piers to improve their stability. However, single-column piers of bridges still have certain safety hazards. On the one hand, with the passage of time, the rubber bearings will age, crack, become hollow, etc., resulting in a decrease in the bearing capacity of the bearings, which in turn affects the stability of the entire bridge. On the other hand, if overloaded vehicles or special load conditions act on the bridge, the connection between the steel cap beam and the pier will become loose or cracked, resulting in the steel cap beam being unable to effectively play its reinforcement role. Utility Model Content
[0004] The purpose of the utility model is to provide a bridge single-column pier reinforcement device to solve the problems of aging, cracking, and hollowing of rubber bearings, as well as the shortcomings of loosening and cracking of the connection between the steel cap beam and the pier, which is easy to use.
[0005] In order to achieve the above-mentioned purpose, the technical solution provided by the utility model is:
[0006] The utility model discloses a bridge single-column pier reinforcement device, comprising a bridge column pier and a box beam arranged at the top end of the bridge column pier, a steel cap beam is arranged at the lower side of the box beam, the steel cap beam is sleeved on the outer surface of the bridge column pier, the steel cap beam comprises a first beam frame and a second beam frame which are relatively arranged on both sides of the bridge column pier, a base plate is arranged below the first beam frame and the second beam frame, the base plate is sleeved on the outer surface of the bridge column pier, a first mortise and tenon is arranged at the top end of the first beam frame, a second mortise and tenon is arranged at the top end of the second beam frame, and the first mortise and tenon and the second mortise and tenon cooperate to form a mortise structure for supporting the box beam.
[0007] Preferably, the first beam frame includes a first semicircular plate sleeved on the outside of the bridge column pier and a first wing plate installed on both side ends of the first semicircular plate, the surface of the first semicircular plate is arranged with first punched grooves, the first semicircular plate is fixedly connected to the bridge column pier through a connecting piece passing through the first punched groove, a track plate is fixedly installed on the inner surface of the first wing plate, and a first mortise and tenon joint is arranged on the upper surface of the first wing plate, and the first mortise and tenon joint is staggered with the track plate.
[0008] Preferably, the second beam frame includes a second semicircular plate opposite to the first semicircular plate and second wing plates installed on both side ends of the second semicircular plate, a second punching groove is provided on the surface of the second semicircular plate, the second semicircular plate is fixedly connected to the bridge pier by a connecting piece passing through the second punching groove, a rail groove is provided on the inner surface of the second wing plate, a second mortise and tenon is installed on the upper surface of the second wing plate, the second mortise and tenon are staggered with the rail groove, and the second mortise and tenon are in contact with the side surface of the first mortise, the rail groove and the rail plate cooperate to form the positioning of the first beam frame and the second beam frame.
[0009] Preferably, a docking slot is provided at the side end of the first wing plate, and a hook truss is provided at the side end of the second wing plate. The hook truss cooperates with the docking slot to form a clamping connection between the first beam frame and the second beam frame.
[0010] Preferably, a casting area is provided between the first semicircular plate and the bridge column pier and between the second semicircular plate and the bridge column pier, respectively, and the casting area is used for pouring concrete.
[0011] Preferably, a central bottom column is installed in the center of the lower surface of the box girder, and the box girder is fixedly connected to the upper top surface of the bridge pier through the central bottom column. Support grooves are provided on both sides of the central bottom column, and the support grooves are opened on the lower surface of the box girder, and the first mortise and tenon joints and the second mortise and tenon joints are connected to the support grooves.
[0012] Preferably, the base plate includes a matching plate that is sleeved on the surface of the bridge pier and a connecting rod installed on the upper surface of the matching plate. A matching steel ring is provided on the lower surface of the matching plate. The matching steel ring is sleeved on the surface of the bridge pier. A third punching groove is provided on the surface of the matching steel ring. The third punching groove is fixedly connected to the side surface of the bridge pier by anchor bolts.
[0013] Preferably, the lower surfaces of the first beam frame and the second beam frame are respectively provided with connecting slots, and the connecting slots are connected to the connecting rods.
[0014] By adopting the technical solution provided by the utility model, compared with the prior art, the box girder and the steel cap beam form a more stable structural state, which can effectively resist the influence of external forces on the bridge, thereby improving the overall stability of the bridge, replacing the rubber bearings, and the structures between the box girder and the steel cap beam complement each other to jointly share the load of the bridge, improve the bearing capacity of the bridge, and enable the bridge to safely withstand more traffic flow. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is the overall structure diagram of the utility model;
[0016] Figure 2 This is a schematic diagram of the steel cap beam structure of the utility model;
[0017] Figure 3 This is a schematic diagram of the split structure of the first beam frame and the second beam frame of the utility model;
[0018] Figure 4 This is a schematic diagram of the connection slot structure of the utility model;
[0019] Figure 5 This is a schematic diagram of the bottom surface structure of the box beam of the utility model;
[0020] Figure 6 This is a schematic diagram of the matching disk structure of the utility model;
[0021] Figure 7 It is a schematic diagram of the matching steel ring structure of the utility model.
[0022] In the figure: 1. box girder; 11. center base column; 12. support groove; 2. steel cap beam; 21. first beam frame; 211. first semicircular plate; 212. first punching groove; 213. first wing plate; 214. track plate; 215. first mortise and tenon joint; 216. docking slot; 22. second beam frame; 221. second semicircular plate; 222. second punching groove; 223. second wing plate; 224. hook truss; 225. second mortise and tenon joint; 226. track groove; 23. base plate; 231. matching plate; 232. connecting rod; 233. matching steel ring; 234. third punching groove; 24. casting area; 25. connecting slot; 3. bridge column pier. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] In order to further understand the content of the utility model, the utility model is described in detail in conjunction with the accompanying drawings.
[0025] Combination Figure 1The utility model is a bridge single column pier reinforcement device, comprising a bridge column pier 3 and a box beam 1 arranged at the top of the bridge column pier 3, a steel cap beam 2 is arranged at the lower side of the box beam 1, and the steel cap beam 2 is sleeved on the outer surface of the bridge column pier 3, and the steel cap beam 2 comprises a first beam frame 21 and a second beam frame 22 arranged on both sides of the bridge column pier 3, and a base plate 23 is arranged below the first beam frame 21 and the second beam frame 22, and the base plate 23 is sleeved on the outer surface of the bridge column pier 3, so that the first beam frame 21 and the second beam frame 22 are initially fixed by supporting on the base plate 23. A first tenon 215 is provided at the top of the first beam frame 21, and a second tenon 225 is provided at the top of the second beam frame 22, and the first tenon 215 and the second tenon 225 cooperate to form a tenon structure for supporting the box beam 1.
[0026] The utility model supports the box girder through the mortise and tenon structure, thereby improving the connection strength between the bridge column pier 3 and the box girder 1, and then uses the first beam plate frame 21 and the second beam plate frame 22 to increase the supporting span of the bridge column pier 3 to the box girder 1 in the width direction of the bridge, thereby increasing the supporting strength in the width direction of the bridge, thereby improving the stability of the bridge.
[0027] The utility model is further described below in conjunction with embodiments.
[0028] Combination Figure 1-4 The first beam frame 21 and the second beam frame 22 are both attached to the outer surface of the bridge column pier 3. The first beam frame 21 includes a first semicircular plate 211 and a first wing plate 213 installed at both ends of the first semicircular plate 211. The surface of the first semicircular plate 211 is arranged with first punching grooves 212, and the first semicircular plate 211 is fixedly connected to the bridge column pier 3 through a connecting piece penetrating the first punching groove 212. A track plate 214 is fixedly installed on the inner surface of the first wing plate 213, and a first mortise and tenon joint 215 is arranged on the upper surface of the first wing plate 213. The first mortise and tenon joint 215 is staggered with the track plate 214, and a docking slot 216 is opened at the side end of the first wing plate 213.
[0029] The second beam frame 22 includes a second semicircular plate 221 opposite to the first semicircular plate 211 and second wing plates 223 installed on both side ends of the second semicircular plate 221. A second punching groove 222 is provided on the surface of the second semicircular plate 221, and the second semicircular plate 221 is fixedly connected to the bridge column pier 3 through a connecting piece penetrating the second punching groove 222. A hook truss 224 is provided at the side end of the second wing plate 223, a rail groove 226 is provided on the inner side surface of the second wing plate 223, and a second tenon 225 is installed on the upper surface of the second wing plate 223, and the second tenon 225 is staggered with the rail groove 226. The second tenon 225 fits the side surface of the first tenon 215, thereby forming a tenon structure with mutual support on the sides. The first semicircular plate 211 is fixedly connected to the side surface of the bridge column pier 3 by bolts passing through the first punched grooves 212, and the second semicircular plate 221 is fixedly connected to the side surface of the bridge column pier 3 by bolts passing through the second punched grooves 222, and the ends of the bolts are anchored into the bridge column pier 3. A casting area 24 is provided between the first semicircular plate 211 and the second semicircular plate 221 and the bridge column pier 3, and the casting area 24 is used for pouring concrete.
[0030] The rail plate 214 is a convex structure extending from the top to the middle of the first wing plate 213, and the rail groove 226 is a concave structure extending from the top to the middle of the second wing plate 223, so that the first wing plate 213 and the second wing plate 223 are installed and positioned by the concave-convex cooperation of the rail plate 214 and the rail groove 226, that is, the first beam frame 21 and the second beam frame 22 are positioned.
[0031] The docking slot 216 and the hook truss 224 extend along the up and down directions of the first beam frame 21 and the second beam frame 22 respectively. The docking slot 216 and the hook truss 224 can form a clamping structure to clamp and fix the first beam frame 21 and the second beam frame 22, which is beneficial to the power transfer between the two and plays a role in reinforcing the bridge column pier 3.
[0032] Combination Figure 1 and 5A central bottom column 11 is installed at the center of the lower surface of the box beam 1. The box beam 1 is fixedly connected to the upper surface of the bridge column pier 3 through the central bottom column 11. A support groove 12 is provided on both sides of the central bottom column 11. The support groove 12 is provided on the lower surface of the box beam 1. The first tenon joint 215 and the second tenon joint 225 are connected to the support groove 12. The base plate 23 includes a matching plate 231 sleeved on the surface of the bridge column pier 3 and a connecting rod 232 installed on the upper surface of the matching plate 231. A matching steel ring 233 is provided on the lower surface of the matching plate 231. The matching steel ring 233 is sleeved on the surface of the bridge column pier 3. A third punching groove 234 is provided on the surface of the matching steel ring 233. The third punching groove 234 is fixedly connected to the side surface of the bridge column pier 3 by anchoring bolts. A connecting slot 25 is provided on the lower surface of the first semicircular plate 211 and the second semicircular plate 221. The connecting slot 25 is connected to the connecting rod 232.
[0033] In this embodiment, at the beginning of construction, a temporary support is installed, a construction platform is set up, and the base plate 23 is sleeved from top to bottom at the designated position of the bridge column pier 3. The third punching groove 234 is fixedly connected to the side surface of the bridge column pier 3 by anchoring bolts to complete the installation of the preliminary base. The second beam frame 22 is connected to the connecting rod 232 according to the connecting slot 25, so as to complete the positioning and assembly of the second beam frame 22. The first beam frame 21 is connected to the connecting rod 232 according to the connecting slot 25, and the positioning and assembly of the first beam frame 21 and the second beam frame 22 are completed by connecting the rail plate 214 with the rail groove 226, and connecting the docking slot 216 with the hook truss 224. The first beam frame 21 and the second beam frame 22 are fitted together, and the base plate 23 is the base of the first beam frame 21 as a whole. The first punching groove 212 and the second punching groove 222 are fixedly connected to the side surface of the bridge column pier 3 by anchoring bolts through the casting area 24. Concrete is poured into the inner side of the pouring area 24, so that the steel cap beam 2 and the side surface of the bridge column pier 3 are solidified, and the steel cap beam 2 and the bridge column pier 3 are an integrated structure. The box beam 1 is installed on the upper surface of the bridge column pier 3 through the central bottom column 11. At the same time, the first tenon 215 and the second tenon 225 are engaged with the support groove 12, so that the box beam 1 and the steel cap beam 2 form a more stable structural state, effectively resisting the influence of external forces on the bridge, thereby improving the overall stability of the bridge, replacing the rubber bearing, and the structure between the box beam 1 and the steel cap beam 2 complement each other to share the load of the bridge together, improve the bearing capacity of the bridge, and enable the bridge to safely withstand more traffic flow.
[0034] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0035] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A bridge single-column pier reinforcement device, comprising a bridge column pier and a box beam arranged on the top of the bridge column pier, characterized in that: A steel cap beam is arranged at the lower side of the box beam, and the steel cap beam is sleeved on the outer surface of the bridge column pier. The steel cap beam includes a first beam frame and a second beam frame which are arranged relatively on both sides of the bridge column pier. A base plate is arranged below the first beam frame and the second beam frame, and the base plate is sleeved on the outer surface of the bridge column pier. A first mortise and tenon is arranged at the top end of the first beam frame, and a second mortise and tenon is arranged at the top end of the second beam frame. The first mortise and tenon and the second mortise and tenon cooperate to form a mortise and tenon structure for supporting the box beam.
2. A bridge single column pier reinforcement device according to claim 1, characterized in that: The first beam frame includes a first semicircular plate sleeved on the outside of the bridge column pier and a first wing plate installed on both side ends of the first semicircular plate. The surface of the first semicircular plate is arranged with first punched grooves. The first semicircular plate is fixedly connected to the bridge column pier through a connecting piece passing through the first punched groove. A track plate is fixedly installed on the inner surface of the first wing plate. A first mortise and tenon joint is arranged on the upper surface of the first wing plate. The first mortise and tenon joint is staggered with the track plate.
3. A bridge single column pier reinforcement device according to claim 2, characterized in that: The second beam frame includes a second semicircular plate opposite to the first semicircular plate and second wing plates installed on both side ends of the second semicircular plate. A second punching groove is provided on the surface of the second semicircular plate. The second semicircular plate is fixedly connected to the bridge column pier through a connecting piece passing through the second punching groove. A rail groove is provided on the inner surface of the second wing plate. A second mortise and tenon is installed on the upper surface of the second wing plate. The second mortise and tenon are staggered with the rail groove, and the second mortise and tenon are in contact with the side surface of the first mortise and tenon. The rail groove and the rail plate cooperate to form the positioning of the first beam frame and the second beam frame.
4. A bridge single column pier reinforcement device according to claim 3, characterized in that: A docking slot is provided at the side end of the first wing plate, and a hook truss is provided at the side end of the second wing plate. The hook truss cooperates with the docking slot to form a clamping connection between the first beam frame and the second beam frame.
5. The bridge single column pier reinforcement device according to claim 3, characterized in that: A pouring area is provided between the first semicircular plate and the bridge column pier and between the second semicircular plate and the bridge column pier, respectively, and the pouring area is used for pouring concrete.
6. A bridge single column pier reinforcement device according to claim 1, characterized in that: A central bottom column is installed in the center of the lower surface of the box girder, and the box girder is fixedly connected to the upper top surface of the bridge pier through the central bottom column. Support grooves are arranged on both sides of the central bottom column, and the support grooves are opened on the lower surface of the box girder, and the first mortise and tenon joints and the second mortise and tenon joints are connected to the support grooves.
7. The bridge single column pier reinforcement device according to claim 1, characterized in that: The base plate includes a matching plate that is sleeved on the surface of the bridge pier and a connecting rod installed on the upper surface of the matching plate. A matching steel ring is provided on the lower surface of the matching plate. The matching steel ring is sleeved on the surface of the bridge pier. A third punching groove is opened on the surface of the matching steel ring. The third punching groove is fixedly connected to the side surface of the bridge pier by anchor bolts.
8. A bridge single column pier reinforcement device according to claim 7, characterized in that: The lower surfaces of the first beam frame and the second beam frame are respectively provided with connecting slots, and the connecting slots are connected to the connecting rods.