Grouting material preparation device

By designing the batching components, adjustment parts and locking parts of the grouting material preparation device, the problem of artificial control of hardening dose can easily lead to excessive additions is solved, and the precise control of hardening dose and the improvement of grouting material molding quality is achieved.

CN222644979UActive Publication Date: 2025-03-21MONIER (HUBEI) CONSTR TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421339782.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-12
Publication Date
2025-03-21
Estimated Expiration
2034-06-12

AI Technical Summary

Technical Problem

Manually controlling the hardening dose with naked eyes can easily lead to excessive addition, affecting the quality of grouting materials and increasing production costs.

Method used

A grouting material preparation device is designed, including a dosing assembly, an adjustment part and a locking part, which achieves precise adjustment and locking of the hardening dose through the scale and threaded connection to prevent excessive addition.

Benefits of technology

The precise control of hardening dose is achieved, the problem of excessive hardening agent is avoided, the molding quality of grouting materials is improved, and the production cost is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222644979U_ABST
    Figure CN222644979U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of grouting, in particular to a grouting material preparation device which comprises a device body, a batching assembly is arranged on one side of the top of the device body, the batching assembly is composed of a batching barrel, a cover plate, an adjusting part and a locking part, the cover plate is arranged on the top of the batching barrel, the adjusting part is located on the top of the cover plate, and the locking part is located on the top of the cover plate. The locking part is located in an inner cavity of the batching barrel, a valve is arranged at the bottom of the batching barrel, scale marks are arranged on the side wall of the batching barrel, the adjusting part is composed of a connecting rod, an adjusting plate and a material guiding barrel, and the connecting rod movably penetrates through the cover plate; the batching assembly is arranged on the device main body, the volume in the batching barrel can be adjusted by utilizing the adjusting part in the batching assembly, and the scale marks are formed on the batching barrel, so that the adjusting plate can adjust the height of the adjusting plate according to the scale marks, and the effect of adjusting the volume in the batching barrel is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of grouting, in particular to a grouting material preparation device. Background Art

[0002] Grouting material is a new type of material with high strength, high durability, green and environmental protection. It is mainly used for reinforcement of equipment foundations and steel structure column bases, which can significantly improve the service life and safety factor of equipment foundations.

[0003] When preparing the grouting material, mixing equipment is used to stir it. During the stirring process, various hardeners are added. The amount of this hardener needs to be controlled to ensure the accuracy of the hardener dosage. The commonly used method is to control it manually with the naked eye. This control method can easily lead to excessive addition of hardener dosage, which in turn affects the quality of the final grouting material and also increases production costs. Utility Model Content

[0004] Based on the above description, the utility model provides a grouting material preparation device to solve the problem that the manual visual control method easily leads to excessive addition of hardening agent.

[0005] The utility model solves the above technical problems with the following technical solutions: a grouting material preparation device, comprising a device body;

[0006] A batching assembly is arranged on one side of the top of the device body, and the batching assembly consists of a batching barrel, a cover plate, an adjusting part and a locking part;

[0007] The cover plate is arranged on the top of the dispensing barrel, the adjusting part is located on the top of the cover plate, the locking part is located in the inner cavity of the dispensing barrel, a valve is arranged at the bottom of the dispensing barrel, and scale lines are arranged on the side wall of the dispensing barrel.

[0008] Furthermore, the adjustment part is composed of a connecting rod, an adjustment plate and a material guide cylinder. The connecting rod movably passes through the cover plate, and the connecting rod and the cover plate are threadedly connected. The top surface of the adjustment plate is fixedly connected to the end surface of the connecting rod.

[0009] On the basis of the above technical solution, the present invention can also be improved as follows.

[0010] Furthermore, one end of the material guide cylinder is fixedly mounted on the cover plate, and one end of the material guide cylinder is connected to the adjustment plate after passing through the cover plate, and one end of the material guide cylinder passes from the top of the adjustment plate to the bottom of the adjustment plate, and the connecting rod and the top of the adjustment plate are movably connected through a bearing.

[0011] Furthermore, the locking portion includes a first movable plate, a threaded rod, a second movable plate, a first clamping plate and a second clamping plate, the threaded rod threads through the second movable plate, and the first movable plate and the second movable plate are connected by a vertical rod.

[0012] Furthermore, a through groove is formed on the top surface of the cover plate, the inner wall of the through groove is movably fitted with the side wall of the vertical rod, and the vertical rod slides in the inner cavity of the through groove.

[0013] Furthermore, the locking portion further comprises a limiting rod and a protrusion, both ends of the limiting rod movably penetrate the first clamping plate and the second clamping plate, and the protrusion is fixedly mounted on the side walls of the first clamping plate and the second clamping plate.

[0014] Furthermore, the number of the protrusions is two, and the two protrusions are symmetrically distributed on both sides of the material guiding cylinder, and the two ends of the limit rod are fixedly connected to the adjustment plate through a fixing block.

[0015] Compared with the prior art, the technical solution of this application has the following beneficial technical effects:

[0016] 1. The utility model arranges a batching component on the device body, and can use the adjusting part in the batching component to adjust the capacity inside the batching barrel. A scale line is opened on the batching barrel, so that the adjustment plate can adjust its own height according to the scale line, so as to achieve the effect of adjusting the internal capacity of the batching barrel.

[0017] 2. By setting a locking part on the adjustment plate and rotating the threaded rod, the first movable plate and the second movable plate on the threaded rod can move closer to and away from each other, thereby driving the first clamping plate and the second clamping plate to move closer to and away from each other, so as to clamp and close the material guide barrel, so that the excessive hardener can be locked after entering the material guide barrel, thereby preventing the hardener from being added excessively. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 A schematic diagram of the structure of a grouting material preparation device provided in an embodiment of the utility model;

[0019] Figure 2 It is a three-dimensional structural schematic diagram of the dispensing barrel in the utility model;

[0020] Figure 3 It is a three-dimensional structural schematic diagram of the adjustment part and the cover plate in the utility model;

[0021] Figure 4 It is a schematic diagram of the three-dimensional structure of the adjusting part in the utility model;

[0022] Figure 5 It is a schematic diagram of the three-dimensional structure of the locking part in the utility model.

[0023] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0024] 1. Device body; 2. Dosing assembly; 201. Dosing barrel; 202. Cover plate; 203. Adjustment part; 2031. Connecting rod; 2032. Adjustment plate; 2033. Material guide barrel; 204. Locking part; 2041. First movable plate; 2042. Threaded rod; 2043. Second movable plate; 2044. First clamping plate; 2045. Limiting rod; 2046. Bump; 2047. Second clamping plate. DETAILED DESCRIPTION

[0025] In order to facilitate understanding of the present application, the present application will be described more fully below with reference to the relevant drawings. Embodiments of the present application are provided in the drawings. However, the present application can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present application more thorough and comprehensive.

[0026] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application.

[0027] It will be appreciated that spatial relationship terms such as "under," "beneath," "below," "under," "above," "above," etc., may be used herein to describe the relationship of an element or feature shown in the figures to other elements or features. It will be appreciated that, in addition to the orientations shown in the figures, spatial relationship terms also include different orientations of the device in use and operation. For example, if the device in the accompanying drawings is flipped, an element or feature described as "under other elements" or "under it" or "under it" will be oriented as being "above" the other elements or features. Thus, the exemplary terms "under" and "under" may include both upper and lower orientations. In addition, the device may also include additional orientations (e.g., rotated 90 degrees or other orientations), and the spatial descriptors used herein are interpreted accordingly.

[0028] It should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the technical product is usually placed when in use. They are only for the convenience of describing the present technology and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present technology. In addition, "first" and "second" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. Therefore, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance. In the description of the utility model, unless otherwise specified, the meaning of "multiple" is two or more.

[0029] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0030] In the description of this technology, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this technology can be understood according to specific circumstances.

[0031] See also Figure 1 and Figure 2 , a grouting material preparation device, comprising a device body 1;

[0032] A batching assembly 2 is provided on one side of the top of the device body 1, and the batching assembly 2 is composed of a batching barrel 201, a cover plate 202, an adjustment part 203 and a locking part 204;

[0033] The cover plate 202 is arranged on the top of the dispensing barrel 201 , the adjusting part 203 is located on the top of the cover plate 202 , the locking part 204 is located in the inner cavity of the dispensing barrel 201 , a valve is arranged at the bottom of the dispensing barrel 201 , and scale lines are arranged on the side wall of the dispensing barrel 201 .

[0034] A dosing component 2 is provided on the device body 1, and an adjusting portion 203 in the dosing component 2 is used to limit the capacity of the dosing barrel 201. Therefore, when manually pouring the hardener, the capacity of the dosing barrel 201 can be adjusted directly as needed without visual control, thereby preventing the problem of excessive addition of the hardener.

[0035] The valve is used to control when the hardener in the dispensing barrel 201 is discharged into the interior of the device body 1 , and the scale lines on the dispensing barrel 201 can cooperate with the adjustment part 203 to adjust the capacity inside the dispensing barrel 201 .

[0036] See also Figure 2 , Figure 3 and Figure 4 The adjusting portion 203 of this embodiment is composed of a connecting rod 2031, an adjusting plate 2032 and a material guide cylinder 2033. The connecting rod 2031 movably passes through the cover plate 202, and the connecting rod 2031 and the cover plate 202 are threadedly connected. The top surface of the adjusting plate 2032 is fixedly connected to the end surface of the connecting rod 2031.

[0037] A thread groove is provided on the connecting rod 2031 , and the connecting rod 2031 is rotated to move the height of the adjusting plate 2032 up and down through the threaded connection between the connecting rod 2031 and the cover plate 202 , so as to adjust the capacity inside the dispensing barrel 201 .

[0038] See also Figure 2 , Figure 3 and Figure 4 In this embodiment, one end of the material guide cylinder 2033 is fixedly mounted on the cover plate 202, and one end of the material guide cylinder 2033 passes through the cover plate 202 and is connected to the adjustment plate 2032, and one end of the material guide cylinder 2033 passes from the top of the adjustment plate 2032 to the bottom of the adjustment plate 2032, and the connecting rod 2031 and the top of the adjustment plate 2032 are movably connected through a bearing.

[0039] The hardener is introduced from the material guide barrel 2033 into the interior of the dosing barrel 201 , and by connecting the material guide barrel 2033 with the adjustment plate 2032 , the hardener can smoothly pass through the adjustment plate 2032 and enter under the adjustment plate 2032 .

[0040] The material guide tube 2033 is a bellows, which is convenient for being clamped and closed by the first clamping plate 2044 and the second clamping plate 2047, and also convenient for the material guide tube 2033 to shrink.

[0041] See also Figure 5The locking portion 204 of this embodiment includes a first movable plate 2041, a threaded rod 2042, a second movable plate 2043, a first clamping plate 2044 and a second clamping plate 2047. The threaded rod 2042 threads through the second movable plate 2043. The first movable plate 2041 and the second movable plate 2043 are connected by a vertical rod.

[0042] The threaded rod 2042 is rotated to allow the second movable plate 2043 to move closer to or away from the first movable plate 2041, thereby driving the first clamping plate 2044 and the second clamping plate 2047 at the bottom to move closer to or away from each other, thereby achieving the effect of clamping and closing the material guide barrel 2033 or releasing and unblocking it.

[0043] One side of the first movable plate 2041 is movably connected to the threaded rod 2042 via a bearing, so that when the threaded rod 2042 rotates, the second movable plate 2043 can be moved.

[0044] See also Figure 3 In this embodiment, a through groove is formed on the top surface of the cover plate 202, the inner wall of the through groove is movably fitted with the side wall of the vertical rod, and the vertical rod slides in the inner cavity of the through groove.

[0045] A through slot is provided on the cover plate 202 , and when the movable rod is rotated, the vertical rod can move along with the approach and separation of the first movable plate 2041 and the second movable plate 2043 .

[0046] See also Figure 5 The locking portion 204 of this embodiment also includes a limiting rod 2045 and a protrusion 2046. Both ends of the limiting rod 2045 are movable through the first clamping plate 2044 and the second clamping plate 2047. The protrusion 2046 is fixedly installed on the side walls of the first clamping plate 2044 and the second clamping plate 2047.

[0047] The setting of the limiting rod 2045 allows the first clamping plate 2044 and the second clamping plate 2047 to be in a stable state during the movement, thereby preventing the first clamping plate 2044 and the second clamping plate 2047 from being skewed.

[0048] See also Figure 3 , Figure 4 and Figure 5 In this embodiment, there are two protrusions 2046 symmetrically distributed on both sides of the material guide barrel 2033 , and both ends of the limit rod 2045 are fixedly connected to the adjustment plate 2032 through a fixing block.

[0049] A protrusion 2046 is provided on the first clamping plate 2044 and the second clamping plate 2047, so that the first clamping plate 2044 and the second clamping plate 2047 drive the protrusion 2046 to clamp the material guide cylinder 2033, so that the material guide cylinder 2033 is clamped and sealed by the protrusion 2046, and the hardener overflowing into the material guide cylinder 2033 will not be discharged into the interior of the device body 1, avoiding the problem of over-addition.

[0050] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A grouting material preparation device, comprising a device body (1), characterized in that: A batching assembly (2) is arranged on one side of the top of the device body (1), and the batching assembly (2) is composed of a batching barrel (201), a cover plate (202), an adjustment part (203) and a locking part (204); The cover plate (202) is arranged on the top of the dispensing barrel (201), the adjusting portion (203) is located on the top of the cover plate (202), the locking portion (204) is located in the inner cavity of the dispensing barrel (201), a valve is arranged at the bottom of the dispensing barrel (201), and scale lines are arranged on the side wall of the dispensing barrel (201).

2. A grouting material preparation device according to claim 1, characterized in that: The adjusting portion (203) is composed of a connecting rod (2031), an adjusting plate (2032) and a material guide cylinder (2033); the connecting rod (2031) movably penetrates the cover plate (202), and the connecting rod (2031) and the cover plate (202) are threadedly connected; the top surface of the adjusting plate (2032) is fixedly connected to the end surface of the connecting rod (2031).

3. A grouting material preparation device according to claim 2, characterized in that: One end of the material guide cylinder (2033) is fixedly mounted on the cover plate (202), and one end of the material guide cylinder (2033) passes through the cover plate (202) and is connected to the adjustment plate (2032), and one end of the material guide cylinder (2033) passes from the top of the adjustment plate (2032) to the bottom of the adjustment plate (2032), and the connecting rod (2031) and the top of the adjustment plate (2032) are movably connected via a bearing.

4. A grouting material preparation device according to claim 2, characterized in that: The locking portion (204) comprises a first movable plate (2041), a threaded rod (2042), a second movable plate (2043), a first clamping plate (2044) and a second clamping plate (2047); the threaded rod (2042) is threadedly passed through the second movable plate (2043); the first movable plate (2041) and the second movable plate (2043) are connected via a vertical rod.

5. A grouting material preparation device according to claim 1, characterized in that: The top surface of the cover plate (202) is provided with a through groove, the inner wall of the through groove is movably fitted with the side wall of the vertical rod, and the vertical rod slides in the inner cavity of the through groove.

6. A grouting material preparation device according to claim 1, characterized in that: The locking portion (204) further comprises a limiting rod (2045) and a protrusion (2046), both ends of the limiting rod (2045) movably penetrate the first clamping plate (2044) and the second clamping plate (2047), and the protrusion (2046) is fixedly mounted on the side walls of the first clamping plate (2044) and the second clamping plate (2047).

7. A grouting material preparation device according to claim 6, characterized in that: The number of the protrusions (2046) is two, and the two protrusions (2046) are symmetrically distributed on both sides of the material guide cylinder (2033). The two ends of the limit rod (2045) are fixedly connected to the adjustment plate (2032) via a fixing block.