Cast-in-place frame beam assembly type laminated waffle plate structure

By adopting cast-in-place frame beam prefabricated superimposed waffle slab structure in the construction of electronic factory floor slabs, the problems of low construction efficiency, difficulty in ensuring quality and pollution are solved, and high-quality and low-pollution building construction results are achieved.

CN222667267UActive Publication Date: 2025-03-25CHINA INST OF BUILDING STANDARD DESIGN & RES
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421483723.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2025-03-25
Estimated Expiration
2034-06-26

AI Technical Summary

Technical Problem

The construction efficiency of the existing electronic factory floor slabs is low, the quality is difficult to guarantee, and the construction pollution is high.

Method used

The cast-in-place frame beam prefabricated superimposed waffle slab structure is adopted. Through the orthogonal arrangement of the prefabricated part and the upper superimposed layer, combined with the combined waffle cylinder formwork, the overall cast concrete is realized to form a bidirectional stressed beam and slab floor system.

Benefits of technology

It improves the quality and efficiency of construction, reduces environmental pollution, achieves the design goal of "equivalent cast-in-place", and ensures the reliability and reasonable stress of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222667267U_ABST
    Figure CN222667267U_ABST
Patent Text Reader

Abstract

The utility model relates to a cast-in-place frame beam assembly type laminated waffle plate structure which comprises laminated waffle plates, a cast-in-place frame beam and a combined waffle cylinder formwork. The cast-in-place frame beams surround the periphery of the laminated waffle plate and form reliable connection; the laminated waffle plate is composed of a prefabricated part and an upper laminated layer. The prefabricated part comprises prefabricated ribbed beams, the upper laminated layer comprises cast-in-place ribbed beams, and the prefabricated ribbed beams and the cast-in-place ribbed beams are arranged in an orthogonal mode; the combined waffle cylinder formwork is composed of a bottom formwork and an upper barrel body, and after reinforcing steel bars in an upper laminated layer and the upper barrel body are installed in place, concrete is integrally poured into the upper laminated layer and the cast-in-place frame beam, so that a beam plate floor system which is integrally stressed in two directions is formed, namely, the cast-in-place frame beam assembly type laminated waffle plate structure is formed. By arranging the cast-in-place laminated layer, the weight of the prefabricated part is reasonable, an integral floor slab structure system with reliable node connection and bidirectional frame stress is formed, and the design target of equivalent cast-in-place is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building components, relates to an assembled structure, and in particular to an assembled composite waffle plate structure of a cast-in-place frame beam. Background Art

[0002] Electronic industrial plants have high requirements for the cleanliness of production areas. In order to meet this requirement, a large number of holes are usually reserved on the floor slabs of the production areas for establishing a clean air conditioning and ventilation system between the upper and lower floors. This type of floor slab with a large number of holes is called a waffle board.

[0003] The construction process of traditional cast-in-place waffle slabs is complicated, the on-site work is heavy, and it is highly dependent on professional construction teams and operators. At the same time, on-site cast-in-place work is greatly affected by actual working conditions, and the construction quality is difficult to guarantee. Summary of the invention

[0004] In order to overcome the shortcomings of the above-mentioned prior art, the purpose of the present invention is to provide a cast-in-place frame beam assembled composite waffle plate structure, which is designed with the design goal and construction measures of "equivalent to cast-in-place", and can solve the problems of low construction efficiency, difficult quality assurance, and high construction pollution in existing electronic factory floors.

[0005] In order to achieve the above object, the technical solution adopted by the present invention is:

[0006] In a first aspect, the present invention provides a cast-in-place frame beam assembled composite waffle plate structure.

[0007] A cast-in-place frame beam assembled composite waffle plate structure, comprising a composite waffle plate, a cast-in-place frame beam and a combined waffle tube formwork; the cast-in-place frame beam is surrounded by the composite waffle plate to form a reliable connection;

[0008] The laminated waffle plate is composed of a prefabricated part and an upper laminated layer; the prefabricated part includes a prefabricated rib beam, the upper laminated layer includes a cast-in-place rib beam, and the prefabricated rib beam and the cast-in-place rib beam are orthogonally arranged;

[0009] The combined waffle tube formwork consists of a bottom formwork and an upper barrel body. After the steel bars in the upper superimposed layer and the upper barrel body are installed in place, the upper superimposed layer and the cast-in-place frame beam are integrally poured with concrete to form an integral bidirectionally stressed beam-slab floor system, that is, a cast-in-place frame beam assembled superimposed waffle slab structure.

[0010] In one embodiment, the material of the combined waffle tube template is a composite material SMC made of glass fiber and unsaturated polyester resin as main materials and cured at high temperature, which has the characteristics of light weight, high strength, corrosion resistance, and fire resistance.

[0011] In one embodiment, the bottom mold and the upper barrel body are connected by a flange ring and self-tapping screws, or the bottom mold and the upper barrel body are connected by a socket-type connection structure.

[0012] In one embodiment, the prefabricated part is formed by splicing several prefabricated strip bottom plates, the prefabricated strip bottom plates are composed of prefabricated rib beams and prefabricated plate strips between the prefabricated rib beams, and the upper composite layer is composed of cast-in-place rib beams and cast-in-place plate strips between the cast-in-place rib beams.

[0013] In one embodiment, both ends of the prefabricated strip bottom plates are placed on the cast-in-place frame beams, and at the joints, the bottom distribution steel bars of adjacent prefabricated strip bottom plates are anchored upward into the upper laminated layer to achieve a reliable connection.

[0014] In one embodiment, prefabricated rib beams are arranged in the prefabricated strip bottom plate, the prefabricated rib beams are composed of a prefabricated part and an upper overlapping part, and the prefabricated rib beams are arranged between each row of waffle cones and are parallel to the long side direction of the prefabricated strip bottom plate.

[0015] In one embodiment, cast-in-place rib beams are arranged in the upper laminated layer, and the cast-in-place rib beams are arranged between each row of waffle cones and are perpendicular to the long side direction of the prefabricated strip bottom plate.

[0016] In one embodiment, the prefabricated rib beam has a top stress-bearing rib, a bottom stress-bearing rib and a rib beam stirrup. The bottom stress-bearing rib is arranged in the prefabricated strip bottom plate, and the top stress-bearing rib is arranged in the upper laminated layer. The top stress-bearing rib and the bottom stress-bearing rib are parallel to the long side direction of the prefabricated strip bottom plate. The rib beam stirrup has a lower portion located in the prefabricated strip bottom plate, and an upper portion extending into the upper laminated layer. The stirrup is arranged along a direction parallel to the length of the prefabricated rib beam and together with the bottom stress-bearing rib and the top stress-bearing rib form a steel skeleton of the prefabricated rib beam.

[0017] The cast-in-place rib beam has two top stress bars, two bottom stress bars and two rib beam stirrups, all of which are arranged in the upper laminated layer, and the two top stress bars and the two bottom stress bars are perpendicular to the long side direction of the prefabricated strip bottom plate; the two rib beam stirrups are arranged along the entire length parallel to the length direction of the cast-in-place rib beam and together with the two top stress bars and the two bottom stress bars form a steel skeleton of the cast-in-place rib beam;

[0018] When the upper composite layer is poured, a bidirectionally stressed floor structure is formed, which is composed of prefabricated rib beams and cast-in-place rib beams arranged orthogonally.

[0019] In one embodiment, the load-bearing top reinforcement 1 and the load-bearing bottom reinforcement 1 of the prefabricated rib beam are arranged between every two adjacent waffle tubes, and the ends of the steel bars extend into the adjacent cast-in-place frame beams and are bent and anchored.

[0020] In one embodiment, the prefabricated strip bottom plate is also provided with bottom distribution steel bars perpendicular to its long side direction, and the bottom distribution steel bars are arranged between every two adjacent waffle cones; at the joints of adjacent prefabricated strip bottom plates, the bottom distribution steel bars are bent upward and anchored in the upper superimposed layer, and at the intersection of the prefabricated strip bottom plate and the cast-in-place frame beam, the bottom distribution steel bars extend into the cast-in-place frame beam for anchoring.

[0021] A second aspect of the present invention provides a construction method for the cast-in-place frame beam assembled composite waffle plate structure according to the first aspect, comprising the following steps:

[0022] Preparation of the precast part in a factory or on site, wherein the base form is simultaneously machined into the precast part;

[0023] On site, the prefabricated part is hoisted to the designed position, and the steel bars of the upper superimposed layer are arranged thereon, so that the prefabricated rib beams and the cast-in-place rib beams can be arranged orthogonally, and the upper barrel body is connected with the bottom formwork reserved in the prefabricated part to form a combined waffle tube formwork as a waffle plate channel formwork, and finally the concrete of the cast-in-place frame beam and the upper superimposed layer is poured as a whole to form an overall bidirectionally stressed beam-slab floor system, that is, a cast-in-place frame beam assembled superimposed waffle plate structure.

[0024] Compared with the prior art, the cast-in-place frame beam assembled composite waffle plate structure provided by the present invention can promote the factory-prefabricated assembled construction of industrial buildings, especially electronic factory buildings using waffle plates, wherein the prefabricated strip bottom plate is produced in the prefabrication factory, and the concrete is poured on site to form the entire floor system, and the node connection is reliable and the structure is reasonably stressed, which conforms to the current design concept of "equivalent to cast-in-place" for assembled integral frame structures. At the same time, the application of the assembled composite waffle plate provided by the present invention can improve the building quality and construction efficiency, reduce environmental pollution, and is a reasonable promotion and application of assembly technology under current external conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 A three-dimensional axial schematic diagram of a structure provided in an embodiment of the present invention.

[0026] Figure 2 A structural plan view provided for an embodiment of the present invention.

[0027] Figure 3 Three views of the assembled overlapping waffle plate provided in an embodiment of the present invention.

[0028] Figure 4 Schematic diagram of node connection between adjacent prefabricated strip bottom plates of assembled composite waffle plate provided in an embodiment of the present invention

[0029] Figure 5 Schematic diagram of the combined waffle cone template provided in the embodiment of the present invention Figure 1 .

[0030] Figure 6 Schematic diagram of the combined waffle cone template provided in the embodiment of the present invention Figure 2 .

[0031] Among them, 1-composite waffle plate; 11-prefabricated part; 111-prefabricated strip bottom plate; 112-prefabricated rib beam; 113-prefabricated plate strip; 1121-stress top reinforcement one; 1122-stress bottom reinforcement one; 1123-rib beam stirrup one; 1131-plate bottom distribution reinforcement; 12-upper composite layer; 121-cast-in-place rib beam; 122-cast-in-place plate strip; 1211-stress top reinforcement two; 1212-stress bottom reinforcement two; 1213-rib beam stirrup two; 3-combined waffle tube formwork; 31-bottom formwork; 32-upper barrel body; 33-flange ring and self-tapping screws; 34-socket and spigot connection structure. DETAILED DESCRIPTION

[0032] The specific implementation of the present invention will be further analyzed below in conjunction with the schematic diagram. It should be noted that the drawings are partially simplified to facilitate further explanation of the embodiments of the present invention.

[0033] Please refer to Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 and Figure 6 , Figure 1 A three-dimensional axonometric schematic diagram of a structure provided by an embodiment of the present invention; Figure 2 A structural plan view provided for an embodiment of the present invention; Figure 3 Three views of the assembled overlapping waffle plate provided in the embodiment of the present invention; Figure 4 A schematic diagram of connection nodes between adjacent prefabricated strip bottom plates of an assembled composite waffle plate provided in an embodiment of the present invention; Figure 5 , Figure 6 A schematic diagram of a combined waffle cone template provided in an embodiment of the present invention.

[0034] An embodiment of the present invention provides a cast-in-place frame beam assembled composite waffle plate structure, which includes: a composite waffle plate 1, a cast-in-place frame beam 2 and a combined waffle tube formwork 3, and the cast-in-place frame beam 2 surrounds the composite waffle plate 1 and can form a reliable connection.

[0035] like Figure 1 , Figure 3As shown, the laminated waffle plate 1 is composed of a prefabricated part 11 and an upper laminated layer 12. The prefabricated part 11 is a prefabricated component produced in a factory to improve construction efficiency and reduce on-site construction time. It includes a prefabricated rib beam 112, and the upper laminated layer 12 is a cast-in-place part, which includes a cast-in-place rib beam 121. The prefabricated rib beam 112 and the cast-in-place rib beam 121 are arranged orthogonally.

[0036] The combined waffle cone template 3 is composed of a bottom mold 31 and an upper barrel body 32. The separate design of the bottom mold 31 and the upper barrel body 32 allows adjustment according to specific needs during the design stage, thereby increasing the flexibility of the design.

[0037] According to the above structure, the combined waffle tube formwork 3 is installed on the prefabricated part 11. When the steel bars in the upper superimposed layer 12 and the upper barrel body 32 are installed in place, the upper superimposed layer 12 and the cast-in-place frame beam 2 are integrally cast with concrete to form an integral bidirectionally stressed beam-slab floor system, that is, a cast-in-place frame beam assembled superimposed waffle slab structure. The present invention makes the weight of the prefabricated components reasonable by setting the cast-in-place upper superimposed layer 12, and forms an integral floor structure system with reliable node connection and bidirectional frame stress, thereby achieving the design goal of "equivalent to cast-in-place".

[0038] In the embodiment of the present invention, the material of the combined waffle tube template 3 is a composite material SMC made of glass fiber and unsaturated polyester resin as main materials and cured at high temperature, which has the characteristics of light weight, high strength, corrosion resistance, fire resistance and the like.

[0039] In an embodiment of the present invention, the prefabricated part 11 is formed by splicing a number of prefabricated strip bottom plates 111, and each prefabricated strip bottom plate 111 is composed of a prefabricated rib beam 112 and a prefabricated plate strip 113 between the prefabricated rib beams. After the construction is completed, the two ends of the prefabricated strip bottom plates 111 can be placed on the cast-in-place frame beam 2, and the bottom distribution steel bars can be extended into the cast-in-place frame beam 2 for anchoring, so as to ensure the reliability and safety of the node connection. In addition, two adjacent prefabricated strip bottom plates 111 are tightly spliced ​​together, and at the splicing of adjacent prefabricated strip bottom plates 111, the bottom distribution steel bars of the adjacent prefabricated strip bottom plates 111 are anchored upward into the upper composite layer 12, so as to ensure the reliable connection between adjacent prefabricated components. The upper composite layer 12 is arranged on the prefabricated strip bottom plates 111, so that the entire beam-slab floor system becomes an integrated two-way force system.

[0040] In the embodiment of the present invention, prefabricated rib beams 112 are arranged in the prefabricated strip bottom plate 111, or the prefabricated strip bottom plate 111 or its main part is directly used as the prefabricated rib beams 112, and the prefabricated rib beams 112 are at least arranged between each row of waffle cones, and their length direction is parallel to the long side direction of the prefabricated strip bottom plate 111. Correspondingly, cast-in-place rib beams 121 are arranged in the upper laminated layer 12, and preferably, the upper laminated layer 12 is composed of cast-in-place rib beams 121 and cast-in-place plate strips 122 between the cast-in-place rib beams 121. The cast-in-place rib beams 121 are at least arranged between each row of waffle cones and are perpendicular to the long side direction of the prefabricated strip bottom plate 111, thereby forming an orthogonal force-bearing structure of the prefabricated rib beams 112 and the cast-in-place rib beams 121.

[0041] The embodiment of the present invention can enhance the bearing capacity and anti-seismic performance of the entire structure by arranging prefabricated rib beams 112 and cast-in-place rib beams 121. In addition, it can help improve its structural rigidity, so that the structure has a higher anti-micro-vibration performance. Among them, multiple prefabricated rib beams 112 are integrated and arranged in the prefabricated strip bottom plate 111 and produced in the factory, which can reduce the on-site construction time, improve product quality and construction efficiency, and the size of the prefabricated strip bottom plate 111 can be customized according to design and construction requirements, with the flexibility of standardized components and modular combination of prefabricated structures.

[0042] In the embodiment of the present invention, the prefabricated rib beam 112 in the prefabricated strip bottom plate 111 can be regarded as a composite beam, which has a top stress-bearing rib 1121, a bottom stress-bearing rib 1122 and a rib beam stirrup 1123. The bottom stress-bearing rib 1122 is arranged in the prefabricated strip bottom plate 111, and the top stress-bearing rib 1121 is arranged in the upper composite layer 12. Further, the prefabricated strip bottom plate 111 is also arranged with a plate bottom distribution steel bar 1131, which is arranged between every two adjacent waffle tubes, one end of which extends into the cast-in-place frame beam 2 for reliable anchoring, and the other end is anchored upward into the upper composite layer 12. The bottom stress-bearing rib 1122 and the top stress-bearing rib 1121 are parallel to the long side direction of the prefabricated strip bottom plate 111, and the plate bottom distribution steel bar 1131 is perpendicular to the long side direction of the prefabricated strip bottom plate 111. The lower part of the rib beam stirrup 1123 is located at the prefabricated strip bottom plate 111, and the upper part extends into the upper composite layer 12, so that the prefabricated rib beam 112 and the upper composite layer 12 are well connected. The rib beam stirrup 1123 is arranged along the entire length parallel to the length direction of the prefabricated rib beam and together with the load-bearing bottom reinforcement 1122 and the load-bearing top reinforcement 1121, it forms the steel skeleton of the prefabricated rib beam 112, thereby ensuring the bearing capacity and deformation resistance of the structure.

[0043] In the embodiment of the present invention, the cast-in-place rib beam 121 has two top stress bars 1211, two bottom stress bars 1212 and two rib beam stirrups 1213, all of which are arranged in the upper laminated layer 12, and the two top stress bars 1211 and the two bottom stress bars 1212 are perpendicular to the long side direction of the prefabricated strip bottom plate 111; the two rib beam stirrups 1213 are arranged along the length direction parallel to the cast-in-place rib beam 121 and together with the two top stress bars 1211 and the two bottom stress bars 1212, form the steel skeleton of the cast-in-place rib beam 121. The arrangement of the two rib beam stirrups 1213 can be optimized according to the specific needs of the structure to achieve the best structural performance.

[0044] In an embodiment of the present invention, by arranging composite beams parallel to the long side direction of the bottom plate and cast-in-place rib beams 121 arranged in a perpendicular direction to the bottom plate in the prefabricated strip bottom plate 111, finally, when the upper composite layer 12 is cast, a bidirectionally stressed floor structure is formed by orthogonally arranged prefabricated rib beams 112 and cast-in-place rib beams 121. The bidirectionally stressed beam grid / beam-slab system improves the bidirectional bearing capacity and stiffness of the floor system, while improving the convenience and flexibility of factory processing and on-site construction of prefabricated components.

[0045] Furthermore, the prefabricated strip bottom plate 111 has bottom distribution steel bars and a load-bearing bottom bar 1122 adjacent to the cast-in-place frame beam 2 extending into the cast-in-place frame beam 2 for anchoring and forming a post-cast node area, which effectively combines the advantages of prefabrication and cast-in-place technology, improves construction efficiency and structural performance, and helps to achieve the integrity between the prefabricated strip bottom plate 111 and the cast-in-place frame beam 2, thereby improving the collaborative working ability of the entire structure.

[0046] In the embodiment of the present invention, at the joint of adjacent prefabricated strip bottom plates 111, the bottom plate distribution steel bars 1131 are bent upward and anchored in the upper superimposed layer 12. At the intersection of the prefabricated strip bottom plates 111 and the cast-in-place frame beam 2, the bottom plate distribution steel bars 1131 extend into the cast-in-place frame beam 2 for anchoring. In the upper superimposed layer 12, a reinforced concrete hidden beam is formed by arranging a force-bearing top bar 1121 and a rib beam stirrup 2 1213, thereby reliably connecting the adjacent prefabricated strip bottom plates 111. Specifically, Figure 4 This structure can effectively improve the connection performance between adjacent panels and the integrity of the floor system, so that the force of the floor is continuously transmitted.

[0047] A typical application of the present invention is as follows Figure 2 As shown, the assembled laminated waffle plate of the embodiment of the present invention is arranged in the standard column spacing of the electronic factory, and three prefabricated strip bottom plates 111 are installed in each span. After the installation is completed, the steel bars in the upper laminated layer 12 are arranged, as shown in FIG. Figure 1 As shown, it includes two stress-bearing bottom reinforcements 1212, two stress-bearing top reinforcements 1211, one stress-bearing top reinforcement 1121 and two rib stirrups 1213.

[0048] In order to meet the cleanliness requirements of the electronic factory, a series of through holes are set in the floor of the production area. The prefabricated part 11 of the present invention can be prepared in the factory or on site, wherein the bottom mold 31 is pre-buried in the prefabricated part 11. Specifically, a combined waffle tube template 3 is used for hole forming, wherein the bottom mold 31 is used as a hole forming template and also serves as a bottom mold of the strip bottom plate when processing the prefabricated strip bottom plate 111, and is buried in the prefabricated strip bottom plate 111. The upper barrel body 32 is connected to the bottom mold 31 at the top of the prefabricated strip bottom plate 111. Specifically, the bottom mold 31 and the upper barrel body 32 are connected by a flange ring and self-tapping screws 33, and can also be connected by other similar structures such as a socket connection structure 34, as shown in the following example. Figure 5 and Figure 6 As shown. The combined waffle tube template of the present invention can replace the template laid on site, reducing the support frame to a certain extent. In addition, the existing waffle tube templates are mostly made of SMC plastic material, which is easy to break during on-site construction. The combined waffle tube template can facilitate the replacement of the broken template later.

[0049] According to the above structure, on site, the prefabricated part 11 is hoisted to the designed position, and the steel bars of the upper superimposed layer 12 are arranged on the prefabricated strip bottom plate 111, so that the prefabricated rib beam 112 and the cast-in-place rib beam 121 can be arranged orthogonally, and the upper barrel 32 is connected to the bottom mold 31 reserved in the prefabricated part 11 to form a combined waffle tube template 3 as a waffle plate channel template, and finally the upper superimposed layer 12 and the cast-in-place frame beam 2 are integrally cast, and after curing and finishing, a bidirectional force-bearing assembled integral frame structure and assembled superimposed waffle plate floor system are formed. The present invention can realize the design concept of "equivalent to cast-in-place", the structural force is reasonable, the structural performance is safe and reliable, and the assembled construction technology is adopted at the same time, which can improve the construction quality and construction efficiency to a certain extent, reduce on-site operations and environmental pollution, and is conducive to the further promotion of assembled technology in the field of electronic industrial plants.

Claims

1. A cast-in-place frame beam assembled composite waffle plate structure, characterized in that: It comprises a laminated waffle plate (1), a cast-in-place frame beam (2) and a combined waffle tube formwork (3); the cast-in-place frame beam (2) surrounds the laminated waffle plate (1) and forms a reliable connection; The laminated waffle plate (1) is composed of a prefabricated part (11) and an upper laminated layer (12); the prefabricated part (11) includes a prefabricated rib beam (112), the upper laminated layer (12) includes a cast-in-place rib beam (121), and the prefabricated rib beam (112) and the cast-in-place rib beam (121) are arranged orthogonally; The combined waffle tube formwork (3) is composed of a bottom formwork (31) and an upper barrel body (32). After the steel bars in the upper superimposed layer (12) and the upper barrel body (32) are installed in place, the upper superimposed layer (12) and the cast-in-place frame beam (2) are integrally poured with concrete to form an integral bidirectionally stressed beam-slab floor system, i.e., a cast-in-place frame beam assembled superimposed waffle slab structure.

2. The cast-in-place frame beam assembled composite waffle plate structure according to claim 1 is characterized in that: The bottom mold (31) and the upper barrel body (32) are connected via a flange ring and self-tapping screws (33), or the bottom mold (31) and the upper barrel body (32) are connected via a socket-type connection structure (34).

3. The cast-in-place frame beam assembled composite waffle plate structure according to claim 1 is characterized in that: The prefabricated part (11) is formed by splicing a plurality of prefabricated strip bottom plates (111), wherein the prefabricated strip bottom plates (111) are composed of prefabricated rib beams (112) and prefabricated plate strips (113) between the prefabricated rib beams, and the upper laminated layer (12) is composed of cast-in-place rib beams (121) and cast-in-place plate strips (122) between the cast-in-place rib beams.

4. The cast-in-place frame beam assembled composite waffle plate structure according to claim 3 is characterized in that: Both ends of the prefabricated strip bottom plates (111) are placed on the cast-in-place frame beams (2). At the joints, the bottom distribution steel bars of adjacent prefabricated strip bottom plates (111) are anchored upward into the upper laminated layer (12) to achieve a reliable connection.

5. The cast-in-place frame beam assembled composite waffle plate structure according to claim 3 is characterized in that: A prefabricated rib beam (112) is arranged in the prefabricated strip bottom plate (111), and the prefabricated rib beam (112) is composed of a prefabricated part and an upper superimposed part; the prefabricated rib beam (112) is arranged between each row of waffle cones and is parallel to the long side direction of the prefabricated strip bottom plate (111); A cast-in-place rib beam (121) is arranged in the upper laminated layer (12), and the cast-in-place rib beam (121) is arranged between each row of waffle cones and is perpendicular to the long side direction of the prefabricated strip bottom plate (111).

6. The cast-in-place frame beam assembled composite waffle plate structure according to claim 3 is characterized in that: The prefabricated rib beam (112) comprises a top stress-bearing rib (1121), a bottom stress-bearing rib (1122) and a rib beam stirrup (1123), wherein the bottom stress-bearing rib (1122) is arranged in the prefabricated strip bottom plate (111), and the top stress-bearing rib (1121) is arranged in the upper laminated layer (12), and the top stress-bearing rib (1121) and the bottom stress-bearing rib (1122) are parallel to the long side direction of the prefabricated strip bottom plate (111); the bottom stress-bearing rib beam stirrup (1123) is located in the prefabricated strip bottom plate (111) at the bottom, and extends into the upper laminated layer (12), and is arranged along the length direction parallel to the prefabricated rib beam (112), and together with the bottom stress-bearing rib (1122) and the top stress-bearing rib (1121) form a steel skeleton of the prefabricated rib beam (112); The cast-in-place rib beam (121) comprises two top stress bars (1211), two bottom stress bars (1212) and two rib beam stirrups (1213), all of which are arranged in the upper laminated layer (12), the two top stress bars (1211) and the two bottom stress bars (1212) being perpendicular to the long side direction of the prefabricated strip bottom plate (111); the two rib beam stirrups (1213) are arranged along the entire length parallel to the length direction of the cast-in-place rib beam (121) and together with the two top stress bars (1211) and the two bottom stress bars (1212) form a steel skeleton of the cast-in-place rib beam (121); When the upper composite layer (12) is cast, a bidirectionally stressed floor structure is formed by orthogonally arranged prefabricated rib beams (112) and cast-in-place rib beams (121).

7. The cast-in-place frame beam assembled composite waffle plate structure according to claim 6 is characterized in that: The load-bearing top reinforcement (1121) and the load-bearing bottom reinforcement (1122) of the prefabricated rib beam (112) are arranged between every two adjacent waffle tubes, and the ends of the reinforcement extend into the adjacent cast-in-place frame beam (2) and are bent and anchored.

8. The cast-in-place frame beam assembled composite waffle plate structure according to claim 6, characterized in that: The prefabricated strip bottom plate (111) is also provided with bottom plate distribution steel bars (1131) perpendicular to its long side direction, and the bottom plate distribution steel bars (1131) are arranged between every two adjacent waffle cones; at the joint of adjacent prefabricated strip bottom plates (111), the bottom plate distribution steel bars (1131) are bent upward and anchored in the upper superimposed layer (12); at the intersection of the prefabricated strip bottom plate (111) and the cast-in-place frame beam (2), the bottom plate distribution steel bars (1131) extend into the cast-in-place frame beam (2) for anchoring.