Stabilizing mechanism of scaffold for engineering building construction

By designing a stable mechanism including mounting rods, sealing plates, clamping adjustment devices and protective covers, the problem of poor stability of the external scaffolding and building body is solved, and the stable connection between the scaffolding and the building is achieved, and construction safety is improved.

CN222667561UActive Publication Date: 2025-03-25FOSHAN LINYU CONSTRUCTION ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420852120.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-23
Publication Date
2025-03-25
Estimated Expiration
2034-04-23

AI Technical Summary

Technical Problem

The connection between the external scaffolding and the building body is poor, which causes the scaffolding to shake easily during use, affecting safety.

Method used

A stabilizing mechanism including a first mounting rod, a sealing plate, a clamping adjustment device and a protective cover is designed. The fixing of the external scaffolding is achieved through the cooperation of the first mounting rod and the sealing plate, and the clamping adjustment device and the protective cover are used to clamp and fix the columns of the building body to ensure a stable connection between the scaffolding and the building.

Benefits of technology

It effectively improves the connection stability between the external scaffolding and the building body, reduces the shaking of the scaffolding, and improves construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222667561U_ABST
    Figure CN222667561U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of scaffold stabilization, and discloses an engineering building construction scaffold stabilizing mechanism which comprises a first mounting rod, a sealing plate is arranged on the left side of the first mounting rod, a first containing cavity is formed in the right side of the first mounting rod, and a clamping adjusting device is arranged in the first containing cavity. The clamping adjusting device comprises a second mounting rod inserted into the first containing cavity, a first clamping rod fixedly mounted on the right side of the second mounting rod and a second clamping rod arranged on the right side of the second mounting rod and located on the front side of the first clamping rod, and a protective cover is arranged on the right side of the second clamping rod and the right side of the first clamping rod. According to the stabilizing mechanism of the scaffold for engineering building construction, an external scaffold is fixed through cooperation between the first mounting rod and the sealing plate, a stand column of a building body is clamped and fixed through cooperation between the first mounting rod and the clamping adjusting device, and then stable connection between the scaffold and the building is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of scaffold stabilization, in particular to a stabilizing mechanism of a scaffold used in engineering construction. Background Art

[0002] Scaffolding is a working platform set up to ensure the smooth progress of each construction process. It can be divided into external scaffolding and internal scaffolding according to the location of the scaffolding; it can be divided into wooden scaffolding, bamboo scaffolding, and steel pipe scaffolding according to different materials; it can be divided into pole scaffolding, bridge scaffolding, portal scaffolding, suspended scaffolding, hanging scaffolding, cantilever scaffolding, and climbing scaffolding according to the structural form.

[0003] Scaffolding is an important facility for safety protection in buildings, and its own stability is particularly important. A Chinese patent discloses a new cantilever scaffolding stabilizing mechanism for construction (authorization announcement number CN219343936U). The patented technology has the advantages of simple structure, easy disassembly and assembly, and can improve the stability of cantilever scaffolding installation and improve the safety of construction. The support plate assembly used can further support and fix the vertical rods and horizontal rods, and facilitates the disassembly and assembly of the oblique support rods to increase the internal stability of the scaffolding.

[0004] However, in actual use, the connection stability between the external scaffolding and the building is poor, and as a result, the external scaffolding shakes relative to the building, affecting safety and failing to meet actual use needs. Therefore, those skilled in the art have provided a stabilizing mechanism for scaffolding used in engineering construction to solve the problems raised in the above-mentioned background technology. Utility Model Content

[0005] The purpose of the utility model is to provide a stabilizing mechanism for a scaffold used in engineering construction to solve the problems raised in the above-mentioned background technology.

[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0007] A stabilizing mechanism for a scaffold for construction engineering, comprising a first mounting rod, a sealing plate is arranged on the left side of the first mounting rod, a first accommodating cavity is opened on the right side of the first mounting rod, and a clamping and adjusting device is arranged inside the first accommodating cavity;

[0008] The clamping and adjusting device includes a second mounting rod inserted into the first accommodating cavity, a first clamping rod fixedly mounted on the right side of the second mounting rod, and a second clamping rod arranged on the right side of the second mounting rod and located in front of the first clamping rod. Protective covers are arranged on the right sides of the second clamping rod and the first clamping rod.

[0009] As a further solution of the utility model: limiting rods are fixedly installed inside the first mounting rod and at the top and bottom of the first accommodating cavity, limiting grooves are provided at the top and bottom of the second mounting rod, and the limiting rods penetrate into the limiting grooves.

[0010] As a further solution of the utility model: the top and the bottom of the first mounting rod are both threadedly connected with two second bolts, and the second bolts penetrate into the interior of the first accommodating cavity and contact the surface of the second mounting rod.

[0011] As a further solution of the utility model: a groove is provided on the right side of the first mounting rod, and the second clamping rod passes through the groove to the inside of the first mounting rod.

[0012] As a further solution of the utility model: a sliding groove is opened on the right side of the second mounting rod, a sliding block is slidably connected inside the sliding groove, and one side of the sliding block is fixedly connected to the second clamping rod.

[0013] As a further solution of the utility model: the right side of the second mounting rod is rotatably connected to a second threaded rod via a bearing, and one side of the second threaded rod penetrates into the interior of the slide groove and is rotatably connected to the slider via a thread.

[0014] As a further solution of the utility model: a second accommodating cavity corresponding to the first clamping rod and the second clamping rod is opened on the left side of the protective cover, and the protective cover is sleeved on the outer sides of the first clamping rod and the second clamping rod through the second accommodating cavity.

[0015] As a further solution of the utility model: the right side of the protective cover is rotatably connected to two third bolts via a bearing, one side of the third bolt passes through the interior of the second accommodating cavity and is rotatably connected to the first clamping rod and the second clamping rod via a thread.

[0016] As a further solution of the utility model: four first bolts are interspersed inside the sealing plate, the rear side of the first bolts penetrates into the interior of the first mounting rod and is rotatably connected to the first mounting rod through a thread, and a through cavity is opened on the rear side of the sealing plate and the front side of the first mounting rod.

[0017] Compared with the prior art, the beneficial effects of the utility model are:

[0018] 1. The utility model fixes the external scaffolding through the cooperation between the first mounting rod and the sealing plate, and clamps and fixes the columns of the building through the cooperation between the first mounting rod and the clamping and adjusting device, thereby achieving a stable connection between the scaffolding and the building.

[0019] 2. The utility model realizes installation and fixation of the first clamping rod and the second clamping rod by setting the second mounting rod, fixes the column of the building body by the cooperation between the first clamping rod and the second clamping rod, fixes the scaffolding outside the wall by the cooperation with the first mounting rod and the sealing plate, and fixes the second clamping rod and the first clamping rod when they are sleeved on the outside of the column by setting the protective cover, thereby increasing the stability between the first clamping rod and the second clamping rod relative to the building column. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a structural schematic diagram of a stabilizing mechanism of a scaffold used in engineering construction;

[0021] Figure 2 It is a schematic diagram of the structure of the second mounting rod in a stabilizing mechanism of a scaffold for engineering construction;

[0022] Figure 3 It is a schematic diagram of the structure of the first mounting rod in a stabilizing mechanism of a scaffold for engineering construction;

[0023] Figure 4 It is a schematic diagram of the structure of a second clamping rod and an adjusting mechanism in a stabilizing mechanism of a scaffold for engineering construction;

[0024] Figure 5 The present invention is a schematic diagram of the protective cover structure in a stabilizing mechanism of a scaffold used in engineering construction.

[0025] In the figure: 1. first mounting rod; 2. sealing plate; 3. first bolt; 4. through cavity; 5. second bolt; 6. clamping and adjusting device; 601. second mounting rod; 602. limiting groove; 603. first clamping rod; 604. protective cover; 605. third bolt; 606. second clamping rod; 607. slide groove; 608. slider; 609. second threaded rod; 7. first accommodating cavity; 8. groove. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] See also Figure 1-5 A stabilizing mechanism for a scaffold for construction engineering, comprising a first mounting rod 1, a sealing plate 2 is arranged on the left side of the first mounting rod 1, a first accommodating cavity 7 is opened on the right side of the first mounting rod 1, and a clamping and adjusting device 6 is arranged inside the first accommodating cavity 7;

[0028] The clamping and adjusting device 6 includes a second mounting rod 601 inserted into the first accommodating cavity 7, a first clamping rod 603 fixedly mounted on the right side of the second mounting rod 601, and a second clamping rod 606 disposed on the right side of the second mounting rod 601 and located in front of the first clamping rod 603. A protective cover 604 is disposed on the right side of the second clamping rod 606 and the first clamping rod 603.

[0029] Specifically, limiting rods are fixedly installed inside the first mounting rod 1 and at the top and bottom of the first accommodating cavity 7 , limiting grooves 602 are provided at the top and bottom of the second mounting rod 601 , and the limiting rods penetrate into the limiting grooves 602 .

[0030] Through the above technical solution, the cooperation between the limiting groove 602 and the limiting rod increases the stability of the second mounting rod 601 relative to the first mounting rod 1, further increasing the stability of the external wall scaffolding.

[0031] Specifically, the top and the bottom of the first mounting rod 1 are both threadedly connected with two second bolts 5 , and the second bolts 5 penetrate into the interior of the first accommodating cavity 7 and contact the surface of the second mounting rod 601 .

[0032] Through the above technical solution, the second mounting rod 601 is squeezed by the setting of the second bolt 5, thereby fixing the second mounting rod 601. At the same time, the second mounting rod 601 can be adjusted by loosening the second bolt 5 to meet the needs of clamping and fixing columns in different positions.

[0033] Specifically, a groove 8 is formed on the right side of the first mounting rod 1 , and the second clamping rod 606 passes through the groove 8 to the inside of the first mounting rod 1 .

[0034] Through the above technical solution, the second clamping rod 606 is accommodated by the setting of the groove 8, thereby clamping and fixing the column close to the scaffolding outside the wall.

[0035] Specifically, a slide groove 607 is provided on the right side of the second mounting rod 601 , a slider 608 is slidably connected inside the slide groove 607 , and one side of the slider 608 is fixedly connected to the second clamping rod 606 .

[0036] Through the above technical solution, the slide block 608 is installed and fixed through the cooperation between the slide groove 607 and the slide block 608, and the second clamping rod 606 can clamp and fix the columns of different diameters relative to the movement of the second installation rod 601.

[0037] Specifically, the right side of the second mounting rod 601 is rotatably connected to the second threaded rod 609 via a bearing, and one side of the second threaded rod 609 penetrates into the interior of the slide groove 607 and is rotatably connected to the slider 608 via a thread.

[0038] Through the above technical solution, the second clamping rod 606 is adjusted and fixed at the same time through the cooperation between the second threaded rod 609, the slider 608 and the thread.

[0039] Specifically, a second accommodating cavity corresponding to the first clamping rod 603 and the second clamping rod 606 is opened on the left side of the protective cover 604, and the protective cover 604 is sleeved on the outer sides of the first clamping rod 603 and the second clamping rod 606 through the second accommodating cavity.

[0040] Through the above technical solution, the protective cover 604 is sleeved on the outer side of the first clamping rod 603 and the second clamping rod 606 through the setting of the second accommodating cavity to limit the first clamping rod 603 and the second clamping rod 606, thereby increasing the stability of the right side of the first clamping rod 603 and the second clamping rod 606.

[0041] Specifically, the right side of the protective cover 604 is rotatably connected to two third bolts 605 via a bearing, and one side of the third bolt 605 penetrates into the interior of the second accommodating cavity and is rotatably connected to the first clamping rod 603 and the second clamping rod 606 via a thread.

[0042] Through the above technical solution, the third bolt 605 is provided to achieve a stable connection between the protective cover 604 and the first clamping rod 603 and the second clamping rod 606 .

[0043] Specifically, four first bolts 3 are interspersed inside the sealing plate 2, and the rear side of the first bolt 3 passes through the interior of the first mounting rod 1 and is rotatably connected to the first mounting rod 1 through a thread, and a through cavity 4 is opened on the rear side of the sealing plate 2 and the front side of the first mounting rod 1.

[0044] Through the above technical scheme, the sealing plate 2 is fixed relative to the first mounting rod 1 by the setting of the first bolt 3, and at the same time, the sealing plate 2 and the first mounting rod 1 are sleeved on the outside of the external wall scaffolding steel pipe by the setting of the through cavity 4, thereby realizing the connection between the sealing plate 2 and the first mounting rod 1 and the scaffolding steel pipe.

[0045] The working principle of the utility model is as follows: the first bolt 3 is removed to separate the sealing plate 2 from the first mounting rod 1, and after the separation is completed, the whole is picked up, and the first mounting rod 1 and the sealing plate 2 are sleeved on the outer side of the scaffolding steel pipe through the through cavity 4. After the sleeve is completed, the sealing plate 2 is connected to the first mounting rod 1 through the first bolt 3. After the connection is completed, the second bolt 5 is loosened according to the position of the building column to make the second mounting rod 601 move relative to the first mounting rod 1, and the second bolt 5 is tightened after it moves to the desired position. After the tightening is completed, the third bolt 605 is rotated to make the third bolt 605 and the first clamp The holding rod 603 and the second clamping rod 606 are separated, so that the protective cover 604 is detached from the outside of the first clamping rod 603 and the second clamping rod 606. According to the width of the column, by rotating the second threaded rod 609, the slider 608 drives the second clamping rod 606 to move under the action of the second threaded rod 609 and the thread. After the adjustment is completed, the first clamping rod 603 and the second clamping rod 606 are sleeved on the outside of the column. After the sleeve is completed, the protective cover 604 is sleeved on the outside of the first clamping rod 603 and the second clamping rod 606 through the second accommodating cavity and tightened and fixed by the third bolt 605.

[0046] What is described above is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A stabilizing mechanism for a scaffold for construction engineering, comprising a first mounting rod (1), characterized in that: A sealing plate (2) is arranged on the left side of the first mounting rod (1), a first accommodating cavity (7) is opened on the right side of the first mounting rod (1), and a clamping adjustment device (6) is arranged inside the first accommodating cavity (7); The clamping and adjusting device (6) comprises a second mounting rod (601) inserted into the first accommodating cavity (7), a first clamping rod (603) fixedly mounted on the right side of the second mounting rod (601), and a second clamping rod (606) disposed on the right side of the second mounting rod (601) and located in front of the first clamping rod (603), and a protective cover (604) is disposed on the right side of the second clamping rod (606) and the first clamping rod (603).

2. The stabilizing mechanism for a scaffold for construction engineering according to claim 1, characterized in that: Limit rods are fixedly installed inside the first mounting rod (1) and at the top and bottom of the first accommodating cavity (7), and limiting grooves (602) are provided at the top and bottom of the second mounting rod (601), and the limiting rods penetrate into the limiting grooves (602).

3. The stabilizing mechanism for a scaffold for construction of an engineering building according to claim 1, characterized in that: Two second bolts (5) are threadedly connected to the top and bottom of the first mounting rod (1), and the second bolts (5) penetrate into the interior of the first accommodating cavity (7) and contact the surface of the second mounting rod (601).

4. The stabilizing mechanism for a scaffold for construction engineering according to claim 1, characterized in that: A groove (8) is provided on the right side of the first mounting rod (1), and the second clamping rod (606) passes through the groove (8) into the interior of the first mounting rod (1).

5. The stabilizing mechanism for a scaffold for construction engineering according to claim 1, characterized in that: A sliding groove (607) is provided on the right side of the second mounting rod (601), a sliding block (608) is slidably connected inside the sliding groove (607), and one side of the sliding block (608) is fixedly connected to the second clamping rod (606).

6. The stabilizing mechanism for a scaffold for construction of an engineering building according to claim 5, characterized in that: The right side of the second mounting rod (601) is rotatably connected to a second threaded rod (609) via a bearing, and one side of the second threaded rod (609) penetrates into the interior of the slide groove (607) and is rotatably connected to the slider (608) via a thread.

7. The stabilizing mechanism for a scaffold for construction of an engineering building according to claim 1, characterized in that: A second accommodating cavity corresponding to the first clamping rod (603) and the second clamping rod (606) is opened on the left side of the protective cover (604), and the protective cover (604) is sleeved on the outer sides of the first clamping rod (603) and the second clamping rod (606) through the second accommodating cavity.

8. The stabilizing mechanism for a scaffold for construction of an engineering building according to claim 7, characterized in that: The right side of the protective cover (604) is rotatably connected to two third bolts (605) via a bearing, and one side of the third bolt (605) penetrates into the interior of the second accommodating cavity and is rotatably connected to the first clamping rod (603) and the second clamping rod (606) via a thread.

9. The stabilizing mechanism for a scaffold for construction of an engineering building according to claim 1, characterized in that: Four first bolts (3) are inserted into the interior of the sealing plate (2); the rear side of the first bolts (3) penetrates into the interior of the first mounting rod (1) and is rotatably connected to the first mounting rod (1) via a thread; and a through cavity (4) is provided on the rear side of the sealing plate (2) and the front side of the first mounting rod (1).

Citation Information

Patent Citations

  • Novel cantilever scaffold stabilizing mechanism for building construction

    CN219343936U