Safety protection structure for bridge construction
By designing a bridge construction safety protection structure including support components and protective components, the existing construction site guardrails have poor stability and strong impact on the human body are solved, and more effective impact buffering and protection effects have been achieved.
Patent Information
- Application Number
- CN202421226104.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2034-05-31
AI Technical Summary
The guardrails at existing construction sites have poor stability and are easily dispersed when subjected to external forces. They have strong impact on the human body when subjected to human body, which can easily lead to injury to people.
A bridge construction safety protection structure is designed, including support components and protective components. The protective component is composed of a frame, a protective net and an elastic buffer layer. A protective net is set on one side of the frame, and the protective net covers the installation at the opening of the frame; the supporting component includes a support rod, a plug rod and a fixing member. Through the connection between the plug rod and the card slot and the coordination of the elastic connection layer, the tight connection between the protective component and the support component is achieved.
Through the combination of the protective net and the elastic buffer layer, external impact can be more effectively buffered, reducing the reaction force on the human body and objects, and improving the protection effect; the design of the support component makes the protection component more stable, avoiding the displacement of the protective component after being impacted, ensuring the protection effect.
Smart Images

Figure CN222685287U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of construction safety facilities, in particular to a bridge construction safety protection structure. Background Art
[0002] Roads and bridges are indispensable in people's lives and bring convenience to people. When constructing roads and bridges, protective equipment is needed to protect the construction site.
[0003] At present, the existing specific way to protect the construction site is: the workers place guardrails one by one on the construction site to enclose the construction site for protection. Most guardrails are placed directly on the ground, and a few guardrails are fixed to the ground by anchors to protect the construction site.
[0004] In the current existing technology, when protecting the construction site, since the guardrails are placed one by one by the workers at the construction site, most of the guardrails are placed directly on the ground and there is no connection between the guardrails, resulting in poor stability of the guardrails. When subjected to external forces, the guardrails will be dispersed, causing the protection site to be destroyed, thereby affecting the protection effect. In addition, when the existing guardrail structure is impacted by the human body, the impact on the human body is strong, and it is easy to cause injuries to people. The setting of the guardrail has the opposite effect. Therefore, in view of the above problems, it is urgent to propose a safety protection device. Utility Model Content
[0005] The utility model aims to solve at least one of the technical problems existing in the prior art. To this end, the utility model proposes a bridge construction safety protection structure, which solves the problem that the guardrail in the prior art has poor stability and has a strong impact on the human body when hit.
[0006] To achieve the above-mentioned purpose, according to an embodiment of the first aspect of the utility model, a bridge construction safety protection structure is provided, comprising a support assembly and a protection assembly, wherein the protection assembly comprises a frame and a protection net, wherein the frame is open on one side, and the protection net is covered and installed at the opening of the frame;
[0007] The support assembly includes a support rod, an insertion rod and a fixing member, wherein the fixing member is used to be installed on the construction bridge deck, one end of the support rod is connected to the fixing member, and the other end of the support rod is connected to the insertion rod;
[0008] A slot corresponding to the insertion rod is provided on one side of the frame away from the protective net, and one end of the insertion rod away from the support rod is plugged into the slot. Connecting components are installed at the edges of both ends of the frame, and the connecting components are used to connect adjacent frames together.
[0009] As a further technical solution of the utility model, the connection assembly includes a collar and a docking rod, the collar and the docking rod are respectively installed at the edges of both ends of the frame, and the docking rod is an inverted L-shaped structure.
[0010] As a further technical solution of the utility model, the inner diameter of the collar is equal to the cross-sectional diameter of the docking rod.
[0011] As a further technical solution of the utility model, a accommodating cavity is provided in the frame body, and the accommodating cavity is filled with an elastic buffer layer, one side of the elastic buffer layer is in contact with the protective net, and the other side of the elastic buffer layer is in contact with the bottom of the accommodating cavity.
[0012] As a further technical solution of the utility model, an elastic connection layer is provided at the connection between the insertion rod and the slot, and the elastic connection layer is fixedly sleeved on the insertion rod.
[0013] As a further technical solution of the utility model, the fixing part includes a connecting chassis and a positioning hole, the end of the support rod away from the insertion rod is fixedly welded to the center of the top of the connecting chassis, and the positioning hole is set in plurality, and the plurality of positioning holes are evenly distributed in a ring shape on the connecting chassis.
[0014] Compared with the prior art, the beneficial effects of the utility model are:
[0015] 1. In the present invention, the protective net of the protective assembly can more gently buffer the impact from the external environment, avoiding the occurrence of a large reaction force on the impacted object or human body, resulting in damage to the object or injury to the human body.
[0016] 2. In the utility model, the support rod is conveniently fixed on the construction bridge deck by the fixing parts, so that the protection component can be placed on the construction bridge deck more stably, avoiding the unfavorable situation that the protection component is displaced after being hit, resulting in the protection component being unable to provide good protection for personnel or vehicles. By using the connecting parts, on-site construction personnel can more conveniently connect multiple protection components together, so that multiple protection components can work together to form a protection system to better resist impacts from the external environment.
[0017] 3. In the utility model, the insertion rod in the support assembly can cooperate with the card slot of the protection assembly, so that the protection assembly and the support assembly are tightly connected. When the protection assembly is subjected to a large degree of impact, the support assembly can provide more powerful support for the protection assembly. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 This is a three-dimensional diagram of a bridge construction safety protection structure of the utility model;
[0019] Figure 2It is a three-dimensional diagram of a protection component in a bridge construction safety protection structure of the utility model;
[0020] Figure 3 This is a schematic cross-sectional view of a bridge construction safety protection structure of the utility model;
[0021] Figure 4 for Figure 3 Enlarged view of part A.
[0022] In the figure: 1. Support assembly; 101. Support rod; 102. Insert rod; 103. Fixing piece; 1031. Connecting chassis; 1032. Positioning hole; 2. Protection assembly; 201. Frame; 202. Protection net; 3. Slot; 4. Ring; 5. Docking rod; 6. Elastic buffer layer; 7. Elastic connecting layer. DETAILED DESCRIPTION
[0023] The technical solution of the utility model will be described clearly and completely in conjunction with the embodiments below. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] like Figure 1-4 As shown, a bridge construction safety protection structure includes a supporting component 1 and a protection component 2, the protection component 2 includes a frame 201 and a protection net 202, the frame 201 is set with an opening on one side, and the protection net 202 is covered and installed at the opening of the frame 201, the protection net 202 is a primary protection for personnel safety, a receiving cavity is provided in the frame 201, and the receiving cavity is filled with an elastic buffer layer 6, the elastic buffer layer 6 is a secondary protection for personnel safety, when a person or a vehicle collides with the protection component 2, the protection net 202 can provide preliminary buffering for it, and the elastic buffer layer 6 in the receiving cavity can form a secondary buffer, one side of the elastic buffer layer 6 is in contact with the protection net 202, and the other side of the elastic buffer layer 6 is in contact with the bottom of the receiving cavity.
[0025] The support assembly 1 includes a support rod 101, an insertion rod 102 and a fixing member 103. One end of the support rod 101 is connected to the fixing member 103, and the other end of the support rod 101 is connected to the insertion rod 102. The fixing member 103 is used to be installed on the construction bridge deck. In this embodiment, the fixing member 103 includes a connecting chassis 1031 and a positioning hole 1032. One end of the support rod 101 away from the insertion rod 102 is fixedly welded at the center of the top of the connecting chassis 1031. The positioning hole 1032 is set in plurality. With the positioning screw, it is passed through the positioning hole 1032 and the positioning screw is screwed into the construction bridge deck to achieve the positioning of the connecting chassis 1031, and the plurality of positioning holes 1032 are evenly distributed in a ring shape on the connecting chassis 1031.
[0026] A slot 3 corresponding to the insertion rod 102 is provided on one side of the frame 201 away from the protective net 202. The end of the insertion rod 102 away from the support rod 101 is plugged into the slot 3. An elastic connection layer 7 is provided at the connection between the insertion rod 102 and the slot 3. The elastic connection layer 7 is fixedly mounted on the insertion rod 102. During the connection process, the elastic connection layer 7 can adapt to the shape of the slot 3. Under the extrusion of the slot 3, the elastic connection layer 7 can be squeezed against the inner wall of the slot 3 through elastic force, thereby further ensuring the connection effect between the support component 1 and the protective component 2.
[0027] The frame 201 is provided with connecting components at the edges at both ends, and the connecting components are used to connect adjacent frames 201 together. The connecting components include a collar 4 and a docking rod 5, which are respectively installed at the edges at both ends of the frame 201, and the docking rod 5 is an inverted L-shaped structure. Between two adjacent frames 1, the docking rod 5 is plugged into the collar 4 to facilitate connecting multiple protection components 2 together, so that the multiple protection components 2 work together to form a protection system to better resist impact from the external environment. The inner diameter of the collar 4 is equal to the cross-sectional diameter of the docking rod 5, which not only ensures that the plug-in point is not prone to shaking, but also allows the docking rod 5 to rotate along the collar 4, which is convenient for adapting to docking at different angles.
[0028] The working principle of the utility model is as follows: the frame 201 of the protection component 2 is placed at a suitable position on the bridge, and the insertion rod 102 of the support component 1 is inserted into the slot 3 on the back of the frame 201, and the elastic connection layer 7 is used to realize the quick docking between the insertion rod 102 and the frame 201, and then the positioning screw is used to pass it through the positioning hole 1032 and the positioning screw is screwed into the construction bridge deck to realize the positioning of the connecting chassis 1031, and another frame 201 is combined and docked with the previously fixed frame 201, and the docking rod 5 and the ring 4 at the edge of the frame 201 can be used to achieve quick combination, and the combined frame 201 repeats the above operation to form multiple protection components 2 on the construction bridge deck. Multiple protection components 2 work together to form a protection system to better resist impact from the external environment, and the protection net 202 on the protection component 2 is used to facilitate preliminary buffering of external impact force, and the elastic buffer layer 6 in the accommodating cavity can further buffer the impact force, thereby effectively improving the protection effect.
[0029] The above embodiments are only used to illustrate the technical method of the utility model rather than to limit it. Although the utility model is described in detail with reference to the preferred embodiments, ordinary technicians in this field should understand that the technical method of the utility model can be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the utility model.
Claims
1. A bridge construction safety protection structure, comprising a support component (1) and a protection component (2), characterized in that: The protection component (2) comprises a frame (201) and a protection net (202); the frame (201) is provided with an opening on one side, and the protection net (202) is installed to cover the opening of the frame (201); The support assembly (1) comprises a support rod (101), an insertion rod (102) and a fixing member (103); the fixing member (103) is used for being installed on a construction bridge deck; one end of the support rod (101) is connected to the fixing member (103), and the other end of the support rod (101) is connected to the insertion rod (102); A slot (3) corresponding to the insertion rod (102) is provided on a side of the frame (201) away from the protective net (202); an end of the insertion rod (102) away from the support rod (101) is plugged into the slot (3); and connecting components are installed at the edges of both ends of the frame (201); the connecting components are used to connect adjacent frame bodies (201) together.
2. A bridge construction safety protection structure according to claim 1, characterized in that: The connection assembly comprises a collar (4) and a docking rod (5), wherein the collar (4) and the docking rod (5) are respectively mounted on the edges of both ends of the frame (201), and the docking rod (5) is an inverted L-shaped structure.
3. A bridge construction safety protection structure according to claim 2, characterized in that: The inner diameter of the collar (4) is equal to the cross-sectional diameter of the docking rod (5).
4. A bridge construction safety protection structure according to claim 1, characterized in that: The frame (201) is provided with a receiving cavity, and the receiving cavity is filled with an elastic buffer layer (6), one side of the elastic buffer layer (6) is in contact with the protective net (202), and the other side of the elastic buffer layer (6) is in contact with the bottom of the receiving cavity.
5. A bridge construction safety protection structure according to claim 1, characterized in that: An elastic connection layer (7) is provided at the connection between the insertion rod (102) and the clamping slot (3), and the elastic connection layer (7) is fixedly sleeved on the insertion rod (102).
6. A bridge construction safety protection structure according to claim 1, characterized in that: The fixing member (103) comprises a connecting chassis (1031) and a positioning hole (1032); one end of the supporting rod (101) away from the insertion rod (102) is fixedly welded to the center of the top of the connecting chassis (1031); a plurality of positioning holes (1032) are arranged, and the plurality of positioning holes (1032) are evenly distributed in a ring shape on the connecting chassis (1031).