Building construction scaffold and building construction bearing frame

By designing a construction scaffolding and carrier frame including bottom components, connecting components and protective components, the problems of single structure and insufficient safety protection in the prior art are solved, and higher construction safety and convenient position adjustment are achieved.

CN222686070UActive Publication Date: 2025-03-28SICHUAN HUASHENG ANJIA CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421808924.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2025-03-28
Estimated Expiration
2034-07-30

AI Technical Summary

Technical Problem

The existing construction scaffolding has a single structure and insufficient safety protection measures, which can easily lead to construction workers falling and falling from the scaffolding.

Method used

A construction scaffolding and carrier rack including bottom assembly, connecting assembly and protective assembly was designed. The bottom assembly achieves height adjustment through the adjustment rod and the connecting rod, the connecting assembly achieves stable connection through the card joint hole and the circular slot hole, and the protective assembly achieves a fixed guardrail through the movable rod and the arc block.

Benefits of technology

Through adjustable structure and fixed protective measures, the safety of construction workers is significantly improved, the injuries caused by accidental falls are prevented, and position adjustment during construction is facilitated.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222686070U_ABST
    Figure CN222686070U_ABST
Patent Text Reader

Abstract

The utility model discloses a building construction scaffold and a building construction bearing frame, and relates to the technical field of building construction bearing frames, and the building construction scaffold and the building construction bearing frame comprise a bottom assembly, a connecting assembly and a protection assembly. When construction needs to be conducted, two sets of arc blocks on two sets of movable rods are rotated to the positions corresponding to two sets of circular groove holes to be placed in, then the two sets of movable rods are rotated to rotate the two sets of arc blocks into the two sets of arc grooves, and two sets of clamping holes correspond to two sets of hole grooves in the two sets of arc blocks; and two groups of threaded fixing rods are fixedly connected with two groups of clamping holes and two groups of arc blocks, so that the protective fence can be fixed on the connecting plate, construction workers are protected, and the situation that the construction workers are injured due to accidental falling in the working process is prevented. And the protective fence can be taken out by rotating the two groups of movable rods to a non-shielding position, so that the safety of operators is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction bearing frames, in particular to a building construction scaffold and a building construction bearing frame. Background Art

[0002] During the construction process, due to the different heights of the floors, the positions of the construction workers need to be constantly adjusted to ensure that the work can be completed smoothly at different heights. In the traditional construction process, scaffolding is set up on the exterior wall, or the construction stairs are directly used for work.

[0003] However, in the prior art, when using a scaffold, the structure of the scaffold is simple, and during use, there are insufficient safety protection measures, which can easily cause injuries from falling from the scaffold, seriously endangering the health of construction workers. Utility Model Content

[0004] The purpose of the utility model is to solve the problems existing in the above-mentioned prior art, and to propose a building construction scaffold and a building construction bearing frame.

[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a construction scaffold and a construction bearing frame, including a bottom component, a connecting component and a protective component; the bottom component includes a bottom plate, two groups of connecting rods are installed at the bottom of the bottom plate, and multiple adjustment holes are provided on the outer wall of the two groups of connecting rods, two groups of adjusting rods are arranged at the bottom of the two groups of connecting rods, and two groups of fixing blocks are arranged on the outer wall of the two groups of adjusting rods; the connecting component includes a connecting plate, two groups of clamping holes are provided on one side of the connecting plate, two groups of circular groove holes are provided on one side of the connecting plate, and two groups of arc grooves are provided inside the two groups of circular groove holes; the protective component includes a guardrail, two groups of movable rods are installed at the bottom of the guardrail, two groups of protrusions are installed on the top of the two groups of movable rods, two groups of arc blocks are installed on the outer wall of the two groups of movable rods, and two groups of threaded fixing rods are arranged on one side of the two groups of arc blocks.

[0006] Preferably, the two groups of adjusting rods are sleeve-connected with the two groups of connecting rods, and the two groups of fixing blocks are movably installed with the two groups of adjusting rods.

[0007] Preferably, the two groups of fixing blocks are threadedly connected to the plurality of adjustment holes, and the two groups of circular slot holes are communicated with the interior of the connecting plate.

[0008] Preferably, the two groups of arc grooves are connected to the two groups of circular groove holes, and the two groups of clamping holes are connected to the two groups of arc grooves.

[0009] Preferably, the two groups of protrusions are rotatably connected to the guardrail, and the two groups of threaded fixing rods are threadedly connected to the two groups of arc blocks.

[0010] Preferably, the two groups of arc blocks are embedded and connected with the two groups of circular groove holes, and the two groups of arc grooves are rotatably connected with the two groups of arc blocks.

[0011] Preferably, the two groups of threaded fixing rods are threadedly connected to the two groups of clamping holes, and the base plate is fixedly installed to the connecting plate.

[0012] Compared with the prior art, the advantages and positive effects of the utility model are:

[0013] 1. In the utility model, when construction is required, the two groups of arc blocks on the two groups of movable rods are rotated to the positions corresponding to the two groups of circular groove holes and put in, and then the two groups of movable rods are rotated to rotate the two groups of arc blocks to the inside of the two groups of circular arc grooves, and the two groups of clamping holes are matched with the two groups of hole grooves on the two groups of arc blocks, and then the two groups of threaded fixing rods are fixedly connected to the two groups of clamping holes and the two groups of arc blocks, so that the guardrail can be fixed on the connecting plate to protect the construction workers and prevent them from being injured due to accidental falls during work. When it is not needed, the two groups of threaded fixing rods are disassembled, and the two groups of movable rods are rotated to move to an unobstructed place to take out the guardrail, thereby increasing the safety of the operators.

[0014] 2. In the utility model, two groups of connecting rods are installed at the bottom of the base plate. The outer walls of the two groups of connecting rods are provided with a plurality of adjustment holes which are threadedly connected with the two groups of fixing blocks on the adjusting rods. The two groups of connecting rods can be adjusted up and down according to the appropriate position. When the two groups of fixing blocks are adjusted to the appropriate position, they are fixed by tightening. The position can be adjusted to facilitate the construction work. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 The utility model provides an overall structural diagram of a construction scaffold and a construction bearing frame;

[0016] Figure 2 The utility model provides a structural schematic diagram of a bottom component of a building construction scaffold and a building construction bearing frame;

[0017] Figure 3 The utility model provides a structural schematic diagram of a connection assembly of a building construction scaffold and a building construction bearing frame;

[0018] Figure 4 The utility model provides a structural schematic diagram of a protective component of a building construction scaffold and a building construction bearing frame.

[0019] Legend: 1. Bottom component; 101. Bottom plate; 102. Connecting rod; 103. Adjusting hole; 104. Adjusting rod; 105. Fixing block; 2. Connecting component; 201. Connecting plate; 202. Snap-in hole; 203. Circular groove hole; 204. Arc groove; 3. Protective component; 301. Guardrail; 302. Movable rod; 303. Arc block; 304. Threaded fixing rod. DETAILED DESCRIPTION

[0020] In order to more clearly understand the above-mentioned purpose, features and advantages of the utility model, the utility model is further described below in conjunction with the accompanying drawings and embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0021] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways than those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure.

[0022] Embodiment 1, as Figure 1-Figure 4 As shown, the utility model provides a construction scaffold and a construction bearing frame, including a bottom component 1, a connecting component 2 and a protective component 3; the bottom component 1 includes a bottom plate 101, two groups of connecting rods 102 are installed at the bottom of the bottom plate 101, and the outer wall of the two groups of connecting rods 102 is provided with a plurality of adjustment holes 103, two groups of adjusting rods 104 are arranged at the bottom of the two groups of connecting rods 102, and the outer wall of the two groups of adjusting rods 104 is provided with two groups of fixing blocks 105; the connecting component 2 includes a connecting plate 201 Two groups of snap-in holes 202 are provided on one side of the connecting plate 201, two groups of circular groove holes 203 are provided on one side of the connecting plate 201, and two groups of arc grooves 204 are provided inside the two groups of circular groove holes 203; the protective component 3 includes a protective fence 301, two groups of movable rods 302 are installed at the bottom of the protective fence 301, two groups of protrusions are installed on the top of the two groups of movable rods 302, two groups of arc blocks 303 are installed on the outer wall of the two groups of movable rods 302, and two groups of threaded fixing rods 304 are arranged on one side of the two groups of arc blocks 303.

[0023] The effect achieved by the entire embodiment 1 is that two groups of connecting rods 102 are installed at the bottom of the bottom plate 101, and multiple adjustment holes 103 are provided on the outer wall of the two groups of connecting rods 102. Two groups of adjustment rods 104 are provided at the bottom of the two groups of connecting rods 102, and two groups of fixing blocks 105 are provided on the outer wall of the two groups of adjustment rods 104. Two groups of clamping holes 202 are provided on one side of the connecting plate 201, and two groups of circular groove holes 203 are provided on one side of the connecting plate 201. Two groups of arc grooves 204 are provided inside the two groups of circular groove holes 203, and two groups of movable rods 302 are installed at the bottom of the guardrail 301. Two groups of protrusions are installed on the top of the two groups of movable rods 302, two groups of arc blocks 303 are installed on the outer wall of the two groups of movable rods 302, two groups of threaded fixing rods 304 are set on one side of the two groups of arc blocks 303, and two groups of connecting rods 102 are installed at the bottom of the base plate 101. The outer wall of the two groups of connecting rods 102 is provided with a plurality of adjustment holes 103, which are threadedly connected with the two groups of fixing blocks 105 on the adjusting rods 104, and can be adjusted up and down according to the appropriate position. When adjusted to the appropriate position, the two groups of fixing blocks 105 are tightened to fix them. The position can be adjusted to facilitate the construction work.

[0024] Embodiment 2, as Figure 1-Figure 4 As shown, two groups of adjusting rods 104 are sleeve-connected with two groups of connecting rods 102, two groups of fixing blocks 105 are movably installed with two groups of adjusting rods 104, two groups of fixing blocks 105 are threadedly connected with multiple adjusting holes 103, two groups of circular groove holes 203 are connected with the interior of the connecting plate 201, two groups of arc grooves 204 are connected with two groups of circular groove holes 203, two groups of clamping holes 202 are connected with two groups of arc grooves 204, two groups of protrusions are rotatably connected with the guardrail 301, two groups of threaded fixing rods 304 are threadedly connected with two groups of arc blocks 303, two groups of arc blocks 303 are embedded and connected with two groups of circular groove holes 203, two groups of arc grooves 204 are rotatably connected with two groups of arc blocks 303, two groups of threaded fixing rods 304 are threadedly connected with two groups of clamping holes 202, and the bottom plate 101 is fixedly installed with the connecting plate 201.

[0025] The effect achieved by the entire embodiment 2 is that the two groups of arc grooves 204 are rotatably connected with the two groups of arc blocks 303, the two groups of threaded fixing rods 304 are threadedly connected with the two groups of clamping holes 202, the bottom plate 101 is fixedly installed with the connecting plate 201, and at the same time, two groups of circular groove holes 203 and two groups of arc grooves 204 are opened on the connecting plate 201, and two groups of protrusions are installed on the top of the two groups of movable rods 302 on the guardrail 301 and are rotatably connected with the guardrail 301. When construction is required, the two groups of arc blocks 303 on the two groups of movable rods 302 are rotated to the positions corresponding to the two groups of circular groove holes 203 and put in, and then the two groups of movable rods 302 are rotated. The rod 302 rotates the two groups of arc blocks 303 into the inside of the two groups of arc grooves 204, and the two groups of snap-in holes 202 correspond to the two groups of hole grooves on the two groups of arc blocks 303, and then the two groups of threaded fixing rods 304 fix the two groups of snap-in holes 202 and the two groups of arc blocks 303, so that the guardrail 301 can be fixed on the connecting plate 201 to protect the construction workers from accidental falls and injuries during work. When it is not needed, the two groups of threaded fixing rods 304 are disassembled, and the two groups of movable rods 302 are rotated to an unobstructed place to take out the guardrail 301, thereby increasing the safety of the operator.

[0026] Working principle: two groups of connecting rods 102 are installed at the bottom of the bottom plate 101, and multiple adjustment holes 103 are provided on the outer wall of the two groups of connecting rods 102. Two groups of adjusting rods 104 are provided at the bottom of the two groups of connecting rods 102, and two groups of fixing blocks 105 are provided on the outer wall of the two groups of adjusting rods 104. Two groups of clamping holes 202 are provided on one side of the connecting plate 201, and two groups of circular groove holes 203 are provided on one side of the connecting plate 201. Two groups of arc grooves 204 are provided inside the two groups of circular groove holes 203. Two groups of movable rods 302 are installed at the bottom of the guardrail 301, and two groups of protrusions are installed on the top of the two groups of movable rods 302. Two groups of arc blocks 303 are installed on the outer wall of the two groups of movable rods 302, and two groups of threaded fixings are provided on one side of the two groups of arc blocks 303. Fixed rod 304, two groups of connecting rods 102 are installed at the bottom of the bottom plate 101, and multiple adjustment holes 103 are opened on the outer wall of the two groups of connecting rods 102, which are threadedly connected with the two groups of fixing blocks 105 on the adjusting rods 104, and can be adjusted up and down according to the appropriate position. After adjusting to the appropriate position, tighten the two groups of fixing blocks 105 to fix them. The position can be adjusted to facilitate the construction work. The two groups of adjusting rods 104 are sleeved and connected with the two groups of connecting rods 102, and the two groups of fixing blocks 105 are movably installed with the two groups of adjusting rods 104. The two groups of fixing blocks 105 are threadedly connected with multiple adjustment holes 103, and the two groups of circular groove holes 203 are connected with the interior of the connecting plate 201, and the two groups of arc grooves 204 are connected with the two groups of circular groove holes 203. The two groups of snap-on holes 202 are connected with the two groups of circular arc grooves 204, the two groups of protrusions are rotatably connected with the guardrail 301, the two groups of threaded fixing rods 304 are threadedly connected with the two groups of circular arc blocks 303, the two groups of circular arc blocks 303 are embedded and connected with the two groups of circular groove holes 203, the two groups of circular arc grooves 204 are rotatably connected with the two groups of circular arc blocks 303, the two groups of threaded fixing rods 304 are threadedly connected with the two groups of snap-on holes 202, the bottom plate 101 is fixedly installed with the connecting plate 201, and at the same time, two groups of circular groove holes 203 and two groups of circular arc grooves 204 are opened on the connecting plate 201, and two groups of protrusions are installed on the top of the two groups of movable rods 302 on the guardrail 301 to be rotatably connected with the guardrail 301. When construction is required, the two groups of movable rods 302 are connected. The arc blocks 303 are rotated to the positions corresponding to the two groups of circular groove holes 203 and put in, and then the two groups of movable rods 302 are rotated to rotate the two groups of arc blocks 303 to the inside of the two groups of arc grooves 204, and the two groups of clamping holes 202 are matched with the two groups of hole grooves on the two groups of arc blocks 303, and then the two groups of threaded fixing rods 304 are fixedly connected to the two groups of clamping holes 202 and the two groups of arc blocks 303, so that the guardrail 301 can be fixed on the connecting plate 201 to protect the construction workers from accidental falls and injuries during work. When it is not needed, the two groups of threaded fixing rods 304 are disassembled, and the two groups of movable rods 302 are rotated to a place without obstruction to take out the guardrail 301, thereby increasing the safety of the operator.

[0027] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. Construction scaffolding and construction bearing frame, characterized in that: It comprises a bottom component (1), a connection component (2) and a protection component (3); The bottom assembly (1) comprises a bottom plate (101), two groups of connecting rods (102) are installed at the bottom of the bottom plate (101), a plurality of adjustment holes (103) are provided on the outer walls of the two groups of connecting rods (102), two groups of adjustment rods (104) are provided at the bottom of the two groups of connecting rods (102), and two groups of fixing blocks (105) are provided on the outer walls of the two groups of adjustment rods (104); The connection assembly (2) comprises a connection plate (201), two groups of snap-fit ​​holes (202) are provided on one side of the connection plate (201), two groups of circular slot holes (203) are provided on one side of the connection plate (201), and two groups of arc grooves (204) are provided inside the two groups of circular slot holes (203); The protection assembly (3) comprises a protection fence (301), two groups of movable rods (302) are installed at the bottom of the protection fence (301), two groups of protrusions are installed at the tops of the two groups of movable rods (302), two groups of arc blocks (303) are installed on the outer walls of the two groups of movable rods (302), and two groups of threaded fixing rods (304) are arranged on one side of the two groups of arc blocks (303).

2. The construction scaffold and construction bearing frame according to claim 1 are characterized in that: The two groups of adjusting rods (104) are sleeve-connected with the two groups of connecting rods (102), and the two groups of fixing blocks (105) are movably mounted with the two groups of adjusting rods (104).

3. The construction scaffold and construction bearing frame according to claim 1 are characterized in that: The two groups of fixing blocks (105) are threadedly connected to the plurality of adjustment holes (103), and the two groups of circular slot holes (203) are connected to the interior of the connecting plate (201).

4. The construction scaffold and construction bearing frame according to claim 1 are characterized in that: The two groups of circular arc grooves (204) are connected to the two groups of circular groove holes (203), and the two groups of clamping holes (202) are connected to the two groups of circular arc grooves (204).

5. The construction scaffold and construction bearing frame according to claim 1, characterized in that: The two groups of protrusions are rotatably connected to the guardrail (301), and the two groups of threaded fixing rods (304) are threadably connected to the two groups of arc blocks (303).

6. The construction scaffold and construction bearing frame according to claim 1, characterized in that: The two groups of circular arc blocks (303) are embedded and connected with the two groups of circular groove holes (203), and the two groups of circular arc grooves (204) are rotatably connected with the two groups of circular arc blocks (303).

7. The construction scaffold and construction bearing frame according to claim 1, characterized in that: The two groups of threaded fixing rods (304) are threadedly connected to the two groups of clamping holes (202), and the bottom plate (101) and the connecting plate (201) are fixedly installed.