A kind of waste separation and crushing processing equipment

By designing dirt separation and crushing treatment equipment that integrates crushing devices and separation devices, the problem of equipment stuck due to foreign matter in the railway dust unloading system is solved, and the equipment is long life, low maintenance costs and efficient operation is achieved.

CN222694925UActive Publication Date: 2025-04-01NANAN YICHEN IND & TRADE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421201452.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-29
Publication Date
2025-04-01
Estimated Expiration
2034-05-29

AI Technical Summary

Technical Problem

The existing railway pollution-unloading system is prone to being stuck or damaged by foreign objects during the pollution-unloading process, resulting in abnormal equipment operation, increasing maintenance costs, and reducing system reliability and safety.

Method used

A dirt separation and crushing treatment equipment is designed, including a separation tank and crushing box. Through the integrated crushing device and separation device, the cam pump is effectively prevented from being stuck, and the heavier and lighter debris are crushed separately.

Benefits of technology

Effectively prevent cam pump from getting stuck, protect equipment accessories, extend equipment service life, reduce maintenance costs, and improve system stability, safety and overall efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222694925U_ABST
    Figure CN222694925U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of waste treatment, and discloses a waste separation and crushing treatment equipment, including a separation tank and a crushing box, wherein a sewage inlet and a sewage guide pipe are provided in the middle of the separation tank, an inclined plate is connected to the inner wall of the separation tank below the sewage inlet, a blocking plate is fixedly connected to the inner wall of the separation tank between the sewage guide pipe and the sewage inlet, and the left and right chambers of the blocking plate are connected, a primary crushing assembly is arranged inside the crushing box, a slag discharge pipe is fixedly connected to the bottom of the separation tank, and a secondary separation assembly is fixedly connected to the other end of the slag discharge pipe, and the secondary separation assembly includes a separation box, and the outer wall of the separation box is fixedly connected to the bottom end of the slag discharge pipe. In the utility model, by integrating the crushing device and the separation device, the cam pump is effectively prevented from getting stuck, and the key parts in the cam pump are protected, thereby increasing the service life, stability, and safety of the equipment and reducing the maintenance cost of the equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of waste treatment, in particular to waste separation and crushing treatment equipment. Background Art

[0002] In the existing railway industry, the sewage unloading system is one of the most important facilities, which is used to extract sewage from the train's toilet collection tank and transfer it safely and effectively to the septic tank for treatment. It is mainly composed of a cam main unit and a vacuum pipeline, and a sewage unloading unit is connected. The sewage unloading unit is connected to the train toilet collection tank, and the cam main unit generates negative pressure. The sewage in the train toilet collection tank is sucked by the sewage unloading unit through the sewage discharge pipeline and discharged to the septic tank by the cam main unit. These systems usually rely on the negative pressure generated by the cam pump unit to attract the sewage to be transferred through the pipeline. However, the existing sewage unloading system faces a significant problem: during the sewage unloading process, the sewage often contains various foreign objects, such as towels, sanitary napkins, coins, etc. These foreign objects may cause the cam pump to get stuck or damage its accessories.

[0003] The presence of foreign matter not only affects the normal operation of equipment, but also increases maintenance costs and reduces the overall reliability and safety of the system. In the sewage unloading system currently used in railway stations, although there are certain basic filtering measures, these measures are not sufficient to completely prevent the interference of foreign matter, especially when dealing with large or dense foreign matter. In addition, the maintenance of existing systems usually requires manual intervention, which is not only inefficient, but also may expose maintenance personnel to pollutants, posing health risks. Utility Model Content

[0004] In order to make up for the above shortcomings, the utility model provides a waste separation and crushing processing equipment, which aims to improve the problem in the prior art that during the waste unloading process, the waste often contains various foreign objects, such as towels, sanitary napkins, coins, etc., and these foreign objects may cause the cam pump to get stuck or damage its accessories.

[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a waste separation and crushing processing equipment, including a separation tank and a crushing box, a sewage inlet and a sewage guide pipe are penetrated in the middle of the separation tank, an inner wall of the separation tank is connected with an inclined plate below the sewage inlet, a baffle plate is fixedly connected with the inner wall of the separation tank between the sewage guide pipe and the sewage inlet, the left and right chambers of the baffle plate are connected, a primary crushing assembly is arranged inside the crushing box, a slag discharge pipe is fixedly connected to the bottom of the separation tank, and a secondary separation assembly is fixedly connected to the other end of the slag discharge pipe.

[0006] Furthermore, the secondary separation component includes a separation box, the outer wall of the separation box is fixedly connected to the bottom end of the slag discharge pipe, the upper surface of the separation box is penetrated by a material guide box, a conveying component is arranged between the separation box and the material guide box, the outer wall of the separation box is fixedly connected to motor three, the driving end of motor three is fixedly connected to a rotating rod, the outer wall of the rotating rod is fixedly connected to a plurality of lifting rods, the outer wall of the rotating rod is rotatably connected to the interior of the separation box, the inner wall of the separation box is fixedly connected to a plurality of obstruction rods, and the plurality of lifting rods and obstruction rods are staggered.

[0007] Furthermore, the outer wall of the material guide box is fixedly connected with a discharge port, the outer wall of the discharge port is fixedly connected with a material guide pipe, the other end of the material guide pipe is fixedly connected with a crushing tank, a secondary crushing assembly is arranged inside the crushing tank, and the bottom of the crushing tank is fixedly connected with a sewage pipe.

[0008] Furthermore, the conveying assembly includes a second motor, an outer wall of which is fixedly connected to the connection between the separation box and the outer wall of the material guide box, a driving end of the second motor is fixedly connected to a main transmission roller, a plurality of secondary transmission rollers are rotatably connected to the connection between the separation box and the material guide box, the outer walls of the main transmission roller and the plurality of secondary transmission rollers are fixedly connected to pulleys, the outer walls of the pulleys are sleeved with belts, the outer walls of the plurality of secondary transmission rollers are fixedly connected to gear two, and the outer walls of two adjacent gear twos are meshingly connected.

[0009] Furthermore, the secondary crushing assembly includes a motor four, the outer wall of which is fixedly connected to the upper surface of the crushing tank, the driving end of the motor four is fixedly connected to a movable rod, the outer wall of the movable rod is fixedly connected to multiple groups of cutting blades, the inner wall of the crushing tank is fixedly connected to a T-shaped filter bucket, and the bottom of the movable rod is rotatably connected to the middle of the T-shaped filter bucket.

[0010] Furthermore, the primary crushing assembly includes two rotating shafts, the outer walls of the two rotating shafts are rotatably connected to the inside of the crushing box, the upper surface of the crushing box is fixedly connected to an inlet flange, the lower surface of the crushing box is fixedly connected to an outlet flange, the other end of the inlet flange is fixedly connected to the other end of the sewage guide pipe, the outer walls of the two rotating shafts are fixedly connected to a plurality of crushing blades, the two groups of crushing blades are staggered inside the crushing box, the outer walls of the two rotating shafts are fixedly connected to gear 1, the outer walls of the two gears 1 are meshingly connected, the end of one of the rotating shafts is fixedly connected to the outer wall of motor 1, and a plurality of scrapers are fixedly connected, and the inclined portions of the plurality of scrapers are attached to the outer wall of the T-shaped filter bucket.

[0011] The utility model has the following beneficial effects:

[0012] 1. In the utility model, by integrating the crushing device and the separation device, the cam pump is effectively prevented from getting stuck, and the key parts in the cam pump are protected, thereby increasing the service life, stability and safety of the equipment and reducing the maintenance cost of the equipment.

[0013] 2. In the utility model, by designing two crushing components, the lighter debris and heavier debris produced by separation can be crushed separately, thereby increasing the decomposition rate of the heavier debris in the septic tank, and the lighter debris can meet the passing conditions of the cam pump and be smoothly discharged into the septic tank.

[0014] 3. In the utility model, a component is designed to separate soft objects from heavier debris, so that soft debris, such as towels, etc., do not need to be discharged into the septic tank, but are collected and processed separately, effectively maintaining the smooth operation of the sewage unloading system, thereby improving the overall efficiency and reliability of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a three-dimensional front view of a waste separation and crushing processing device proposed by the utility model;

[0016] Figure 2 This is a schematic diagram of a rear view of a waste separation and crushing processing device proposed by the utility model;

[0017] Figure 3 This is a schematic diagram of the internal structure of a separation box of a waste separation and crushing treatment equipment proposed by the utility model;

[0018] Figure 4 This is a schematic diagram of the internal structure of a crushing tank of a waste separation and crushing processing equipment proposed by the utility model;

[0019] Figure 5 This is a top view of the interior of a separation tank of a waste separation and crushing treatment equipment proposed by the utility model;

[0020] Figure 6 This is a top view of the interior of a crushing box of a waste separation and crushing processing equipment proposed by the utility model;

[0021] Figure 7 This is a structural schematic diagram of a secondary conveying roller of a dirt separation and crushing processing equipment proposed by the utility model;

[0022] Figure 8 The utility model is a schematic diagram of the structure of a lifting rod of a waste separation and crushing processing equipment.

[0023] Legend:

[0024] 1. Separation tank; 2. Crushing box; 3. Sewage guide pipe; 4. Sewage inlet; 5. Slag discharge pipe; 6. Inclined plate; 7. Blocking plate; 8. Inlet flange; 9. Outlet flange; 10. Rotating shaft; 11. Gear 1; 12. Motor 1; 13. Crushing blade; 14. Separation tank; 15. Guide box; 16. Secondary conveying roller; 17. Gear 2; 18. Pulley; 19. Belt; 20. Motor 2; 21. Main transmission roller; 22. Motor 3; 23. Rotating rod; 24. Lifting rod; 25. Obstructing rod; 26. Discharge port; 27. Guide pipe; 28. Crushing tank; 29. ​​Motor 4; 30. Movable rod; 31. Cutting blade; 32. Scraper; 33. T-type filter bucket; 34. Sewage pipe. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0026] Please see attached Figure 1 , Attachment Figure 2 and attached Figure 5 The utility model provides an embodiment: a waste separation and crushing processing equipment, including a separation tank 1 and a crushing box 2, a sewage inlet 4 and a sewage guide pipe 3 are penetrated in the middle of the separation tank 1, an inclined plate 6 is connected to the inner wall of the separation tank 1 below the sewage inlet 4, a blocking plate 7 is fixedly connected to the inner wall of the separation tank 1 between the sewage guide pipe 3 and the sewage inlet 4, and the left and right chambers of the blocking plate 7 are connected, a primary crushing assembly is arranged inside the crushing box 2, a slag discharge pipe 5 is fixedly connected to the bottom of the separation tank 1, and a secondary separation assembly is fixedly connected to the other end of the slag discharge pipe 5.

[0027] Specifically, the waste first enters the separation tank 1 from the sewage inlet 4 through the main pipeline for sedimentation. Through the isolation and blocking of the inclined plate 6 and the blocking plate 7, the fluid enters the lower part from the inlet and then flows upward from the sewage pipe 3 into the crushing box 2. At this time, the heavier foreign matter remains at the bottom of the separation tank 1 and the slag discharge pipe 5, and is discharged to the septic tank from the bottom slag discharge port without sewage unloading. By integrating the crushing device and the separation device, the cam pump is effectively prevented from getting stuck, and the key parts in the cam pump are protected, which increases the service life, stability and safety of the equipment and reduces the maintenance cost of the equipment.

[0028] Please see attached Figure 3 and attached Figure 8The secondary separation component includes a separation box 14, the outer wall of the separation box 14 is fixedly connected to the bottom end of the slag discharge pipe 5, the upper surface of the separation box 14 is penetrated by a material guide box 15, a conveying component is arranged between the separation box 14 and the material guide box 15, the outer wall of the separation box 14 is fixedly connected to a motor three 22, the driving end of the motor three 22 is fixedly connected to a rotating rod 23, the outer wall of the rotating rod 23 is fixedly connected to a plurality of lifting rods 24, the outer wall of the rotating rod 23 is rotatably connected to the inside of the separation box 14, the inner wall of the separation box 14 is fixedly connected to a plurality of blocking rods 25, and the plurality of lifting rods 24 and the blocking rods 25 are alternately arranged.

[0029] Specifically, heavier foreign matter will enter the separation box 14 through the slag discharge pipe 5, and after being blocked by multiple lifting rods 24 and blocking rods 25, debris that is difficult to separate, such as towels, will be left behind, while smaller debris will enter the guide pipe 27 for processing in the next link. The motor 3 22 is started to drive the rotating rod 23 to drive the multiple lifting rods 24 to rotate, and the larger and softer debris left behind will be carried to the conveying platform composed of multiple secondary conveying rollers 16 and the main drive roller 21. Under the conveyance of the conveying platform, the debris is conveyed to the discharge port 26 and then collected for recycling. In the process of the multiple lifting rods 24 lifting the debris, some of the debris will continue to be blocked by the blocking rods 25. After the debris on the conveying platform is conveyed away, the multiple lifting rods 24 continue to rotate through the middle gap of the conveying platform, and pass through the gaps between the multiple blocking rods 25 to lift up the subsequent debris. This is repeated to complete the conveying of the debris. By designing components to separate soft objects from heavier debris, soft debris such as towels do not need to be discharged into the septic tank, but are collected and processed separately, effectively maintaining the smooth operation of the sewage unloading system, thereby improving the overall efficiency and reliability of the system.

[0030] Please see attached Figure 1 -Attached Figure 2 The outer wall of the material guide box 15 is fixedly connected with a discharge port 26, the outer wall of the discharge port 26 is fixedly connected with a material guide pipe 27, the other end of the material guide pipe 27 is fixedly connected with a crushing tank 28, a secondary crushing assembly is arranged inside the crushing tank 28, and a sewage pipe 34 is fixedly connected to the bottom of the crushing tank 28.

[0031] Please see attached Figure 7 The conveying assembly includes a motor 20, the outer wall of the motor 20 is fixedly connected to the connection between the outer walls of the separation box 14 and the material guide box 15, the driving end of the motor 20 is fixedly connected to the main transmission roller 21, and the connection between the separation box 14 and the material guide box 15 is rotatably connected to multiple secondary transmission rollers 16, the outer walls of the main transmission roller 21 and the multiple secondary transmission rollers 16 are fixedly connected to pulleys 18, and the outer walls of the two pulleys 18 are sleeved with belts 19, the outer walls of the multiple secondary transmission rollers 16 are fixedly connected to gears 2 17, and the outer walls of two adjacent gears 2 17 are meshed and connected.

[0032] Specifically, when soft debris is brought onto the conveying platform, motor 20 drives the main drive roller 21 to rotate, so that the pulley 18 on the outer wall drives the belt 19 to run, and then the pulley 18 on the outer wall of the adjacent secondary conveying roller 16 rotates synchronously, and then the secondary conveying roller 16 rotates and drives the outer wall gear 2 17 to rotate, thereby driving the adjacent meshing gear 2 17 to rotate, and the connected secondary conveying roller 16 rotates, so that under the transmission of the pulley 18, belt 19 and gear 2 17, multiple secondary conveying rollers 16 rotate synchronously to input the upper debris into the discharge port 26.

[0033] Please see attached Figure 4 The secondary crushing assembly includes a motor 29, the outer wall of the motor 29 is fixedly connected to the upper surface of the crushing tank 28, the driving end of the motor 29 is fixedly connected to a movable rod 30, the outer wall of the movable rod 30 is fixedly connected to multiple groups of cutting blades 31, the inner wall of the crushing tank 28 is fixedly connected to a T-shaped filter bucket 33, and the bottom of the movable rod 30 is rotatably connected to the middle of the T-shaped filter bucket 33.

[0034] Specifically, the motor 29 is started to make the multiple sets of cutting blades 31 crush and cut the debris. The cut debris falls into the top of the T-shaped filter 33 for screening. The debris particles that meet the crushing size will fall into the sewage pipe 34 for discharge, and those that do not meet the crushing size will continue to be crushed under the rotation of the multiple scrapers 32. By designing two crushing components, the lighter debris and heavier debris generated by separation can be crushed separately, thereby increasing the decomposition rate of the heavier debris in the septic tank, and the lighter debris can meet the passing conditions of the cam pump and be smoothly discharged into the septic tank.

[0035] Please see attached Figure 6 The primary crushing assembly includes two rotating shafts 10, the outer walls of the two rotating shafts 10 are rotatably connected to the inside of the crushing box 2, the upper surface of the crushing box 2 is fixedly connected with an inlet flange 8, the lower surface of the crushing box 2 is fixedly connected with an outlet flange 9, the other end of the inlet flange 8 is fixedly connected to the other end of the sewage guide pipe 3, the outer walls of the two rotating shafts 10 are fixedly connected with a plurality of crushing blades 13, the two groups of crushing blades 13 are staggered inside the crushing box 2, the outer walls of the two rotating shafts 10 are fixedly connected with gears 11, the outer walls of the two gears 11 are meshed and connected, and the end of one of the rotating shafts 10 is fixedly connected with a motor 12.

[0036] Specifically, the suspended foreign matter contained in the sewage will enter the crushing device with the water flow for crushing, and the motor 12 will be started to rotate the rotating shaft 10. Under the transmission of the two gears 11, the two rotating shafts 10 will rotate synchronously, driving the two sets of crushing blades 13 to rotate and crush the sewage entering the crushing box 2. The crushed sewage will be discharged into the next link through the outlet flange 9, meeting the technical conditions of the pass rate of the cam pump, without causing the pump to get stuck or the parts to be damaged, and can be smoothly discharged into the septic tank.

[0037] A plurality of scrapers 32 are fixedly connected to the outer wall of the movable rod 30 , and the inclined portions of the plurality of scrapers 32 are attached to the outer wall of the T-shaped filter bucket 33 .

[0038] Specifically, during the crushing process, the movable rod 30 drives the plurality of scrapers 32 to move along the outer wall of the T-shaped filter hopper 33, thereby preventing the T-shaped filter hopper 33 from being blocked by impurities and affecting the subsequent filtering efficiency. In addition, the rotation of the plurality of scrapers 32 can cause the impurities to rise in the liquid, thereby preventing the unqualified impurities from being brought back into the plurality of cutting blades 31 for crushing.

[0039] Working principle: When the waste is processed, the waste enters the separation tank 1 from the waste inlet 4 for sedimentation. Through the isolation and blocking of the inclined plate 6 and the blocking plate 7, the fluid enters the lower part from the inlet and then is discharged upward from the sewage guide pipe 3 into the crushing box 2. At this time, the heavier foreign matter remains at the bottom of the separation tank 1 and the slag discharge pipe 5. The motor 12 is started to rotate the shaft 10. Under the transmission of the two gears 11, the two shafts 10 rotate synchronously, driving the two sets of crushing blades 13 to rotate and crush the waste entering the crushing box 2. The crushed waste is discharged from the outlet flange 9 to the next link. The heavier foreign matter will enter the separation box 14 through the slag discharge pipe 5. After being blocked by multiple lifting rods 24 and the blocking rod 25, the sundries that are not easy to separate, such as towels, can be left behind, while the smaller sundries will enter the inside of the guide pipe 27 for the next link. The motor 3 22 is started to drive the rotating rod 23 to drive the multiple lifting rods 24 to rotate. The larger soft debris left behind is carried to the conveying platform composed of multiple secondary conveying rollers 16 and the main driving roller 21. Under the conveying of the conveying platform, the debris is conveyed to the discharge port 26 and then collected for recycling. In the process of multiple lifting rods 24 lifting the debris, some of the debris will continue to be blocked by the blocking rod 25. After the debris on the conveying platform is conveyed away, the multiple lifting rods 24 continue to rotate through the middle gap of the conveying platform, and pass through the gaps between the multiple blocking rods 25 to lift the subsequent debris. This is repeated to complete the transmission of the debris. The smaller debris entering the guide pipe 27 will enter the crushing tank 28. At this time, the motor 29 is started to make the multiple groups of cutting blades 31 crush and cut it. The cut debris falls into the top of the T-shaped filter bucket 33 for screening. The debris particles that meet the crushing size will fall into the sewage pipe 34 for discharge, and those that do not meet the crushing size will continue to be crushed under the rotation of the multiple scrapers 32.

[0040] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A waste separation and pulverization treatment device, comprising a separation tank (1) and a pulverization box (2), characterized in that: A sewage inlet (4) and a sewage guide pipe (3) are provided in the middle of the separation tank (1); an inclined plate (6) is connected to the inner wall of the separation tank (1) below the sewage inlet (4); a blocking plate (7) is fixedly connected to the inner wall of the separation tank (1) between the sewage guide pipe (3) and the sewage inlet (4); the left and right chambers of the blocking plate (7) are connected; a primary crushing assembly is provided inside the crushing box (2); a slag discharge pipe (5) is fixedly connected to the bottom of the separation tank (1); and a secondary separation assembly is fixedly connected to the other end of the slag discharge pipe (5).

2. The waste separation and crushing processing equipment according to claim 1, characterized in that: The secondary separation component comprises a separation box (14), the outer wall of which is fixedly connected to the bottom end of the slag discharge pipe (5), the upper surface of which is provided with a material guide box (15), a conveying component is provided between the separation box (14) and the material guide box (15), the outer wall of which is fixedly connected to a motor three (22), the driving end of which is fixedly connected to a rotating rod (23), the outer wall of which is fixedly connected to a plurality of lifting rods (24), the outer wall of which is rotatably connected to the interior of the separation box (14), the inner wall of which is fixedly connected to a plurality of obstruction rods (25), the plurality of lifting rods (24) and the obstruction rods (25) being arranged alternately.

3. The waste separation and pulverization processing equipment according to claim 2 is characterized in that: The outer wall of the material guide box (15) is fixedly connected with a discharge port (26), the outer wall of the discharge port (26) is fixedly connected with a material guide pipe (27), the other end of the material guide pipe (27) is fixedly connected with a crushing tank (28), a secondary crushing assembly is arranged inside the crushing tank (28), and the bottom of the crushing tank (28) is fixedly connected with a sewage discharge pipe (34).

4. The waste separation and pulverization processing equipment according to claim 2, characterized in that: The conveying assembly comprises a second motor (20), the outer wall of the second motor (20) is fixedly connected to the connection between the outer walls of the separation box (14) and the material guide box (15), the driving end of the second motor (20) is fixedly connected to a main transmission roller (21), the connection between the separation box (14) and the material guide box (15) is rotatably connected to a plurality of secondary transmission rollers (16), the outer walls of the main transmission roller (21) and the plurality of secondary transmission rollers (16) are fixedly connected to pulleys (18), the outer walls of the pulleys (18) are sleeved with belts (19), the outer walls of the plurality of secondary transmission rollers (16) are fixedly connected to gears (17), and the outer walls of two adjacent gears (17) are meshingly connected.

5. The waste separation and pulverization processing equipment according to claim 3, characterized in that: The secondary crushing assembly comprises a motor four (29), the outer wall of the motor four (29) is fixedly connected to the upper surface of the crushing tank (28), the driving end of the motor four (29) is fixedly connected to a movable rod (30), the outer wall of the movable rod (30) is fixedly connected to a plurality of groups of cutting blades (31), the inner wall of the crushing tank (28) is fixedly connected to a T-shaped filter bucket (33), and the bottom of the movable rod (30) is rotatably connected to the middle part of the T-shaped filter bucket (33).

6. The waste separation and pulverization processing equipment according to claim 1, characterized in that: The primary crushing assembly comprises two rotating shafts (10), the outer walls of the two rotating shafts (10) are rotatably connected to the inside of the crushing box (2), the upper surface of the crushing box (2) is fixedly connected to an inlet flange (8), the lower surface of the crushing box (2) is fixedly connected to an outlet flange (9), the other end of the inlet flange (8) is fixedly connected to the other end of the sewage guide pipe (3), the outer walls of the two rotating shafts (10) are fixedly connected to a plurality of crushing blades (13), the two groups of crushing blades (13) are staggeredly arranged inside the crushing box (2), the outer walls of the two rotating shafts (10) are fixedly connected to a gear one (11), the outer walls of the two gears one (11) are meshedly connected, and the end of one of the rotating shafts (10) is fixedly connected to a motor one (12).

7. The waste separation and pulverization processing equipment according to claim 5, characterized in that: A plurality of scrapers (32) are fixedly connected to the outer wall of the movable rod (30), and the inclined portions of the plurality of scrapers (32) are fitted to the outer wall of the T-shaped filter bucket (33).