A boiler water circulation treatment device

By designing a boiler water circulation treatment device including absorber, evaporator, refrigerator and heater, the heat exchange tube combination is used to solve the problem of low heat energy recovery efficiency of boiler, waste heat recovery and waste heat utilization are realized, and energy consumption and production costs are reduced.

CN222733040UActive Publication Date: 2025-04-08JILIN JINQIU PESTICIDE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421500479.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-27
Publication Date
2025-04-08
Estimated Expiration
2034-06-27

AI Technical Summary

Technical Problem

The existing boiler water circulation treatment device is inefficient in thermal energy recovery, resulting in a large amount of heat being directly released into the environment, and the waste heat utilization rate is low, which increases production costs.

Method used

A boiler water circulation treatment device is designed, including an absorber, an evaporator, a refrigerator and a heater, and waste heat recovery and waste heat utilization are achieved through the combination of the first and second heat exchange pipes.

Benefits of technology

Effectively recycle waste heat in boiler water, reduce energy consumption, improve energy utilization, realize heating and cooling functions, and reduce production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222733040U_ABST
    Figure CN222733040U_ABST
Patent Text Reader

Abstract

The utility model discloses a boiler water circulation treatment device, comprising a base, an absorber is fixedly installed on one side of the top of the base, an evaporator is fixedly installed on the middle of the top of the base, a refrigerator is fixedly installed on the other side of the top of the base, a generator is fixedly installed on the top of the absorber, a condenser is fixedly installed on the top of the evaporator, a heater is fixedly installed on the top of the refrigerator, a first heat exchange tube is fixedly installed in the absorber and the evaporator, and a second heat exchange tube is fixedly installed in the generator and the condenser. The device can effectively recover waste heat in boiler water, significantly reduce energy consumption, reduce fuel use, achieve energy conservation and emission reduction, and improve energy utilization rate. A refrigerator is also designed in the device, which achieves cooling by absorbing the medium temperature in the refrigerator through the low-temperature and low-pressure mist liquid in the evaporator. Therefore, the device can heat and cool, improve the utilization rate of waste heat, and reduce factory production costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of water circulation equipment, in particular to a boiler water circulation treatment device. Background Art

[0002] The function of the boiler water circulation treatment device is to ensure the stable circulation and clean water quality of the water in the boiler, and effectively prevent the accumulation of corrosion, scaling and other pollutants, thereby extending the service life of the boiler equipment, improving energy utilization efficiency, and ensuring safe and stable industrial production.

[0003] Most of the existing boilers do not recover enough heat when in use, and fail to effectively recover and utilize the waste heat in the boiler circulating water, resulting in a large amount of heat being released directly into the environment without being fully utilized. At the same time, the few boilers that can recover a certain amount of heat can only recover heat for heating and cannot use waste heat for cooling. Therefore, the utilization rate of waste heat is very low, which in turn causes a waste of resources. At the same time, adding additional cooling and heating equipment will lead to higher production costs. Utility Model Content

[0004] The purpose of the utility model is to provide a boiler water circulation treatment device to solve the problems raised in the above background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a boiler water circulation treatment device, comprising a base, an absorber is fixedly installed on one side of the top of the base, an evaporator is fixedly installed in the middle of the top of the base, a refrigerator is fixedly installed on the other side of the top of the base, a generator is fixedly installed on the top of the absorber, a condenser is fixedly installed on the top of the evaporator, a heater is fixedly installed on the top of the refrigerator, a first heat exchange tube is fixedly installed in both the absorber and the evaporator, and a second heat exchange tube is fixedly installed in both the generator and the condenser.

[0006] As a preferred technical solution of the utility model, a dilute lithium bromide solution is stored in the generator, a concentrated lithium bromide solution is stored in the absorber, a cold medium is stored in the heater, and a hot medium is stored in the refrigerator.

[0007] As the preferred technical solution of the utility model, a boiler water pipe is fixedly installed on the top of the generator and connected to the second heat exchange tube inside, the top of the generator is connected to the top of the condenser through a first pipeline, and an expansion valve is arranged between the bottom of the condenser and the top of the evaporator.

[0008] As a preferred technical solution of the utility model, a second pipe is installed between the top of the condenser and the top of the heater, and the second pipe is connected to the second heat exchange tube in the condenser. A pair of third pipes are installed between the side of the evaporator and the side of the refrigerator, and the third pipes are connected to the first heat exchange tube in the evaporator.

[0009] As a preferred technical solution of the utility model, a fourth pipe is installed on the evaporator side and the absorber side, a fifth pipe is installed between the absorber side and the heater side, the fifth pipe is connected to the first heat exchange tube in the absorber, and the middle part of the fifth pipe is connected to the first water pump.

[0010] As a preferred technical solution of the utility model, a sixth pipe is installed between the side of the absorber and the side of the condenser, and the sixth pipe is respectively connected to the first heat exchange tube in the absorber and the second heat exchange tube in the condenser. A pair of seventh pipes are fixedly connected between the generator and the side of the absorber, and the middle part of the seventh pipe is connected to the second water pump.

[0011] Compared with the prior art, the utility model has the following beneficial effects:

[0012] This device can effectively recover waste heat from boiler water, significantly reduce energy consumption, reduce fuel use, achieve energy conservation and emission reduction, and improve energy utilization. A refrigerator is also designed in this device, which absorbs the medium temperature in the refrigerator through the low-temperature and low-pressure mist liquid in the evaporator to achieve cooling. Therefore, the device can heat and cool, improve the utilization rate of waste heat, and reduce factory production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0014] Figure 1 It is a schematic diagram of the overall structure of a boiler water circulation treatment device according to an embodiment of the utility model;

[0015] Figure 2 It is a structural schematic diagram of a cross section of a first heat exchange tube of a boiler water circulation treatment device according to an embodiment of the utility model;

[0016] Figure 3 It is a structural schematic diagram of the second heat exchange tube cross section of a boiler water circulation treatment device according to an embodiment of the utility model.

[0017] Reference numerals:

[0018] 1. Base; 2. Absorber; 3. Evaporator; 4. Refrigerator; 5. Generator; 6. Condenser; 7. Heater; 8. First heat exchange tube; 9. Second heat exchange tube; 10. First pipeline; 11. Expansion valve; 12. Second pipeline; 13. Third pipeline; 14. Fourth pipeline; 15. Fifth pipeline; 16. Sixth pipeline; 17. First water pump; 18. Seventh pipeline; 19. Second water pump. DETAILED DESCRIPTION

[0019] Below, in conjunction with the accompanying drawings and specific implementation methods, the utility model is further described:

[0020] See also Figure 1-3 According to an embodiment of the utility model, a boiler water circulation treatment device includes a base 1, an absorber 2 is fixedly installed on one side of the top of the base 1, an evaporator 3 is fixedly installed on the middle of the top of the base 1, a refrigerator 4 is fixedly installed on the other side of the top of the base 1, a generator 5 is fixedly installed on the top of the absorber 2, a condenser 6 is fixedly installed on the top of the evaporator 3, a heater 7 is fixedly installed on the top of the refrigerator 4, a first heat exchange tube 8 is fixedly installed in both the absorber 2 and the evaporator 3, and a second heat exchange tube 9 is fixedly installed in both the generator 5 and the condenser 6.

[0021] Among them, the first heat exchange tube 8 and the second heat exchange tube 9 can maximize the heat conduction efficiency.

[0022] In this embodiment, the generator 5 stores a dilute lithium bromide solution, the absorber 2 stores a concentrated lithium bromide solution, the heater 7 stores a cold medium, and the refrigerator 4 stores a hot medium.

[0023] Among them, heating the lithium bromide solution can promote the evaporation of water. Heating will increase the kinetic energy of water molecules in the solution, making it easier to evaporate.

[0024] In this embodiment, a boiler water pipe is fixedly installed on the top of the generator 5 and connected to the second heat exchange tube 9 inside. The top of the generator 5 is connected to the top of the condenser 6 through a first pipe 10, and an expansion valve 11 is arranged between the bottom of the condenser 6 and the top of the evaporator 3.

[0025] The boiler water utilizes waste heat to heat the dilute lithium bromide solution in the generator 5 to generate high-temperature and high-pressure steam, which enters the condenser 6 through the first pipe 10, and the low-temperature liquid water is converted into mist-like low-temperature and low-pressure water through the expansion valve 11 and enters the evaporator 3.

[0026] In this embodiment, a second pipe 12 is installed between the top of the condenser 6 and the top of the heater 7, and the second pipe 12 is connected to the second heat exchange tube 9 in the condenser 6. A pair of third pipes 13 are installed between the side of the evaporator 3 and the side of the refrigerator 4, and the third pipe 13 is connected to the first heat exchange tube 8 in the evaporator 3.

[0027] Among them, high-temperature and high-pressure water vapor heats the cold medium of the heater 7 in the second heat exchange tube 9 in the condenser 6, and then turns into low-temperature liquid water. The misty low-temperature and low-pressure water absorbs the hot medium temperature of the refrigerator 4 in the first heat exchange tube 8 in the evaporator 3, and then turns into high-temperature water vapor.

[0028] In this embodiment, a fourth pipe 14 is installed on the side of the evaporator 3 and the side of the absorber 2, and a fifth pipe 15 is installed between the side of the absorber 2 and the side of the heater 7. The fifth pipe 15 is connected to the first heat exchange tube 8 in the absorber 2, and the middle part of the fifth pipe 15 is connected to the first water pump 17.

[0029] The high-temperature water vapor enters the absorber 2 through the fourth pipe 14, and the first water pump 17 circulates the cooling medium in the heater 7 in the absorber 2 and the condenser 6 to achieve continuous heating.

[0030] In this embodiment, a sixth pipe 16 is installed between the side of the absorber 2 and the side of the condenser 6, and the sixth pipe 16 is respectively connected to the first heat exchange tube 8 in the absorber 2 and the second heat exchange tube 9 in the condenser 6. A pair of seventh pipes 18 are fixedly connected between the generator 5 and the side of the absorber 2, and the middle part of the seventh pipe 18 is connected to the second water pump 19.

[0031] Among them, the high-temperature water vapor heats the cold medium of the heater 7 in the first heat exchange tube 8 in the absorber 2, and then turns into liquid water and dissolves in the concentrated lithium bromide solution. The second water pump 19 exchanges the gradually diluted lithium bromide solution in the absorber 2 with the gradually concentrated lithium bromide solution in the generator 5 through the seventh pipeline 18 to maintain a stable concentration.

[0032] In specific application, firstly, the device is installed and fixed through the base 1, and the refrigerator 4 and the heater 7 are connected to related equipment. Then, the high-temperature boiler water is connected to the second heat exchange tube 9 in the generator 5. The high-temperature boiler water heats the dilute lithium bromide solution in the generator 5 to generate high-temperature and high-pressure water vapor, which enters the condenser 6 through the first pipeline 10. The high-temperature and high-pressure water vapor heats the medium of the heater 7 in the second heat exchange tube 9 in the condenser 6, and then becomes low-temperature liquid water, which is converted into mist-like low-temperature and low-pressure water through the expansion valve 11 and enters the evaporator 3. The mist-like low-temperature and low-pressure water absorbs the medium temperature of the refrigerator 4 in the first heat exchange tube 8 in the evaporator 3. The temperature of the refrigerator 4 is continuously reduced by circulating through the third pipe 13. The mist-like low-temperature and low-pressure water is then changed into high-temperature water vapor and enters the absorber 2 through the fourth pipe 14. The high-temperature water vapor heats the medium of the heater 7 in the first heat exchange tube 8 in the absorber 2, and then becomes liquid water and dissolves in the lithium bromide concentrated solution. The medium is started, and the first water pump 17 drives the medium in the heater 7 to circulate in the absorber 2 and the condenser 6 to achieve continuous heating. The second water pump 19 is started to exchange the gradually diluted lithium bromide solution in the absorber 2 with the gradually concentrated lithium bromide solution in the generator 5 through the seventh pipe 18 to keep the concentration stable.

[0033] In the description of the present invention, it should be noted that the orientation or positional relationship indicated by the terms "top", "bottom", "one side", "the other side", "front", "back", "middle part", "inside", "top end", "bottom end", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention; the terms "first", "second", and "third" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance; in addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a communication between the two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0034] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A boiler water circulation treatment device, characterized in that: The invention comprises a base (1), wherein an absorber (2) is fixedly mounted on one side of the top of the base (1), an evaporator (3) is fixedly mounted on the middle of the top of the base (1), a refrigerator (4) is fixedly mounted on the other side of the top of the base (1), a generator (5) is fixedly mounted on the top of the absorber (2), a condenser (6) is fixedly mounted on the top of the evaporator (3), a heater (7) is fixedly mounted on the top of the refrigerator (4), a first heat exchange tube (8) is fixedly mounted in both the absorber (2) and the evaporator (3), and a second heat exchange tube (9) is fixedly mounted in both the generator (5) and the condenser (6).

2. A boiler water circulation treatment device according to claim 1, characterized in that: The generator (5) stores a dilute lithium bromide solution, the absorber (2) stores a concentrated lithium bromide solution, the heater (7) stores a cold medium, and the refrigerator (4) stores a hot medium.

3. A boiler water circulation treatment device according to claim 1, characterized in that: A boiler water pipe is fixedly installed on the top of the generator (5) and is connected to a second heat exchange pipe (9) inside. The top of the generator (5) is connected to the top of the condenser (6) via a first pipe (10). An expansion valve (11) is provided between the bottom of the condenser (6) and the top of the evaporator (3).

4. A boiler water circulation treatment device according to claim 1, characterized in that: A second pipe (12) is installed between the top of the condenser (6) and the top of the heater (7), and the second pipe (12) is connected to the second heat exchange tube (9) in the condenser (6). A pair of third pipes (13) are installed between the side of the evaporator (3) and the side of the refrigerator (4), and the third pipes (13) are connected to the first heat exchange tube (8) in the evaporator (3).

5. A boiler water circulation treatment device according to claim 1, characterized in that: A fourth pipe (14) is installed on the side of the evaporator (3) and the side of the absorber (2), a fifth pipe (15) is installed between the side of the absorber (2) and the side of the heater (7), the fifth pipe (15) is connected to the first heat exchange pipe (8) in the absorber (2), and the middle part of the fifth pipe (15) is connected to the first water pump (17).

6. A boiler water circulation treatment device according to claim 1, characterized in that: A sixth pipe (16) is installed between the side of the absorber (2) and the side of the condenser (6), and the sixth pipe (16) is respectively connected to the first heat exchange pipe (8) in the absorber (2) and the second heat exchange pipe (9) in the condenser (6). A pair of seventh pipes (18) are fixedly connected between the generator (5) and the side of the absorber (2), and the middle part of the seventh pipe (18) is connected to the second water pump (19).