Quick mounting structure for arch frame connecting rib of gas tunnel
By adopting a quick installation structure of connecting sleeves and fixtures on the gas tunnel arch, the existing cumbersome welding operations are solved, and the rapid and convenient connection between the connecting ribs and the arch frame is achieved, and the working efficiency is improved.
Patent Information
- Application Number
- CN202421645708.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2025-04-11
- Estimated Expiration
- 2034-07-11
AI Technical Summary
The welding operation of the connecting ribs of the existing gas tunnel arch is complicated, resulting in low working efficiency.
The rapid installation structure is adopted to achieve a quick connection between the connecting ribs and the arch frame through the connecting sleeve and the fixture. The connecting ribs pass through the vias of the connecting sleeve and are fixed through the fixture to avoid welding operations.
The connection process between the connecting ribs and the arch frame is simplified, the working efficiency is improved, the operation is more convenient and the applicability is strong.
Smart Images

Figure CN222746093U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of tunnel construction, and in particular to a quick installation structure for connecting ribs of a gas tunnel arch frame. Background Art
[0002] The gas tunnel arch is an arch support structure used in gas tunnels. It is usually made of materials such as steel or steel bars, and is made into unit components according to a certain curvature and length, and then installed at the construction site. These arches, anchor rods, steel mesh, connecting steel bars and concrete together form a rigid structure to support and stabilize the tunnel body and prevent it from collapsing.
[0003] In the prior art, in order to enhance the connection strength between adjacent gas tunnel arch frames and prevent the gas tunnel arch frames from being displaced or deformed due to external forces during tunnel construction, such as subsequent concrete pouring, connecting ribs are usually provided on the gas tunnel arch frames. A plurality of connecting ribs are usually distributed along the length direction of the arch frames, and each connecting rib is fixed to each gas tunnel arch frame in turn by welding.
[0004] With regard to the above-mentioned prior art, the connection operation between the connecting ribs and the gas tunnel arches by welding is complicated and has low working efficiency. Utility Model Content
[0005] In order to facilitate the connection between each connecting rib and each gas tunnel arch frame and improve work efficiency, the present application provides a quick installation structure for connecting ribs of a gas tunnel arch frame.
[0006] The present application provides a gas tunnel arch frame connecting reinforcement quick installation structure adopts the following technical solution:
[0007] A quick installation structure for connecting ribs of a gas tunnel arch frame comprises an arch frame and connecting ribs, wherein a plurality of the arch frames are distributed in the horizontal direction, a plurality of the connecting ribs are located on the outside of the arch frame and are distributed circumferentially around the axis of the arch frame, a plurality of connecting sleeves are arranged on the outside of each arch frame, each connecting sleeve corresponds to a plurality of connecting ribs one by one, the connecting sleeves have through holes for the connecting ribs to pass through, and the connecting sleeves are provided with fixings for fixing the connecting ribs.
[0008] By adopting the above technical scheme, when connecting the connecting ribs and the arch frames, the connecting ribs are sequentially passed through the connecting sleeves of the arch frames, and the positions of the connecting sleeves and the connecting ribs are fixed by fixing parts, so as to achieve the connection between the connecting ribs and the arch frames. In the process of connecting the connecting ribs and the arch frames, there is no need to fix them to the arch frames in turn by welding. The connecting ribs can be inserted into the through holes in the connecting sleeves and fixed by fixing parts. The operation is convenient, which is conducive to improving the work efficiency when connecting the connecting ribs and the arch frames.
[0009] Optionally, the fixing member includes a fixing bolt, the fixing bolt threadably engages with the connecting sleeve, and one end of the fixing bolt is inserted into the through hole.
[0010] By adopting the above technical solution, when the connecting rib is located in the through hole of the connecting sleeve, the fixing bolt can be screwed to make the fixing bolt press against the connecting rib to fix the connecting rib and the arch frame, which is convenient and quick.
[0011] Optionally, an arc-shaped clamping plate is rotatably provided on one end of the fixing bolt extending into the through hole, and the arc-shaped clamping plate is slidably fitted in the through hole.
[0012] By adopting the above technical solution, the provision of the arc-shaped clamping plate facilitates more comprehensive positioning of the connecting ribs when they are fixed, which is beneficial to further ensure the stability of the position of the connecting ribs when they are fixed.
[0013] Optionally, an adjustment hole is opened on the outside of the arch frame, which passes through and extends circumferentially around its own axis. The connecting sleeve is fixedly installed with a mounting screw, and the mounting screw is slidingly fitted in the adjustment hole. One end of the mounting screw is threadedly fitted with a mounting nut through the adjustment hole.
[0014] By adopting the above technical solution, the installation screw is passed through the adjustment hole and the installation nut is screwed so that the installation nut is pressed against the arch frame to fix the position of the connecting sleeve. This is convenient and quick. At the same time, the installation screw can be moved in the adjustment hole to achieve slight adjustment of the position of the connecting sleeve. This is convenient for adapting to different installation conditions and has strong applicability.
[0015] Optionally, an abutment pad is fixedly connected to a side of the mounting nut close to the arch.
[0016] By adopting the above technical solution, the provision of the abutment pad facilitates increasing the contact area when the mounting nut and the arch are fixed, thereby facilitating further ensuring the position stability of the connecting sleeve when it is fixed.
[0017] Optionally, the mounting screw thread is matched with an adjusting nut, and the adjusting nut is located on a side of the arch away from the mounting nut.
[0018] By adopting the above technical solution, when screwing the adjusting nut, the connecting sleeve can be fixed at different radial positions of the arch frame through the cooperation of the adjusting nut and the mounting nut, which is beneficial to further enhance the flexibility of the installation of the connecting sleeve and improve the applicability of the connecting sleeve and the connecting rib during installation.
[0019] Optionally, the openings at both ends of the via hole are rounded.
[0020] By adopting the above technical solution, the rounded corners are set so that the aperture at the through hole mouth is larger than the aperture of the through hole, so that there is a certain gap transition when the connecting rib is inserted into the through hole, which facilitates the installation between the connecting rib and the connecting sleeve.
[0021] Optionally, limiting steel wires are provided on both sides of each connecting sleeve, and the limiting steel wires are tied and fixed to the connecting ribs.
[0022] By adopting the above technical solution, the setting of the limiting steel wire plays a further limiting role on the connecting sleeve and the connecting rib, which is beneficial to further ensure the relative position stability between the connecting sleeve and the connecting rib, and the limiting steel wire is fixed to the connecting rib by binding in a quick and easy manner.
[0023] In summary, the present application includes at least one of the following beneficial technical effects:
[0024] 1. During the connection between the connecting ribs and the arch frames, there is no need to fix them to the arch frames in sequence through welding. The connecting ribs can be inserted into the through holes in the connecting sleeves and fixed through the fixing parts. This is convenient to operate and is conducive to improving the work efficiency when connecting the connecting ribs and the arch frames.
[0025] 2. The setting of the arc-shaped splint facilitates more comprehensive limiting of the connecting ribs when they are fixed, which is beneficial to further ensure the stability of the position of the connecting ribs when they are fixed.
[0026] 3. By moving the mounting screw in the adjustment hole, the position of the connecting sleeve can be slightly adjusted, which is convenient for adapting to different installation conditions and has strong applicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.
[0028] Figure 2 yes Figure 1 A partial enlarged schematic diagram of part A.
[0029] Figure 3 It is a partial cross-sectional schematic diagram of the overall structure in the embodiment of the present application.
[0030] Description of reference numerals:
[0031] 1. Arch frame; 101. Inner wing plate; 102. Outer wing plate; 103. Web plate; 2. Connecting ribs; 3. Connecting sleeve; 4. Through hole; 5. Adjusting hole; 6. Mounting screw; 7. Mounting nut; 8. Adjusting nut; 9. Abutment pad; 10. Fixing bolt; 11. Arc splint; 12. Limiting wire. DETAILED DESCRIPTION
[0032] The following is combined with Figure 1-3This application is described in further detail.
[0033] The present application embodiment discloses a quick installation structure for connecting ribs of a gas tunnel arch frame. Figure 1 The quick installation structure of the gas tunnel arch connecting rib comprises an arch 1 and connecting ribs 2, wherein the arch 1 has a plurality of connecting ribs distributed in the horizontal direction. In the embodiment of the present application, the arch 1 is selected as an I-shaped steel arch. Specifically, the arch 1 comprises two wing plates and a web 103. In the embodiment of the present application, the wing plate located inside the arch 1 is set as an inner wing plate 101, and the wing plate located outside the arch 1 is set as an outer wing plate 102. Both sides of the web 103 are fixedly mounted on the inner wing plate 101 and the outer wing plate 102, respectively.
[0034] Reference Figure 1 and Figure 2 The connecting ribs 2 are located on the outside of the arch frame 1, that is, on the side of the outer wing plate 102 away from the inner wing plate 101. There are multiple connecting ribs 2 evenly distributed around the axis of the arch frame 1. To facilitate the connection between the arch frame 1 and each connecting rib 2, a plurality of connecting sleeves 3 are provided on the side of the outer wing plate 102 away from the inner wing plate 101. The plurality of connecting sleeves 3 and the connecting ribs 2 are provided one by one. Each connecting sleeve 3 has a through hole 4 provided along its own axis for the connecting rib 2 to pass through. When the connecting rib 2 passes through the through hole 4 of each connecting sleeve 3, the connection between the connecting rib 2 and each arch frame 1 is realized.
[0035] Reference Figure 1 and Figure 3 Specifically, the outer wing plate 102 is provided with a plurality of adjustment holes 5 which are arranged through the outer wing plate 102. A plurality of adjustment holes 5 are arranged corresponding to the connecting sleeve 3 one by one, and each adjustment hole 5 extends circumferentially around the axis of the outer wing plate 102. The connecting sleeve 3 is fixedly provided with a mounting screw 6 which is slidably fitted in the adjustment hole 5. One end of the mounting screw 6 which is passed through the adjustment hole 5 is threadedly fitted with a mounting nut 7, so that the mounting screw 6 and the connecting sleeve 3 can be fixed in position by screwing the mounting nut 7.
[0036] Reference Figure 2 and Figure 3 In addition, the mounting screw 6 is also threadedly matched with an adjusting nut 8, which is located on the side of the outer wing plate 102 away from the mounting nut 7. The mounting nut 7 and the adjusting nut 8 are both fixedly connected with abutment pads 9 on the side close to the outer wing plate 102. The material of the abutment pads 9 is selected as rubber to increase the contact area between the mounting nut 7 and the adjusting nut 8 and the outer wing plate 102 when the connecting sleeve 3 is fixed, thereby fully ensuring the stability of the position of the connecting sleeve 3 when it is fixed. The setting of the adjusting nut 8 facilitates the connection sleeve 3 to be fixed at different radial positions of the arch frame 1 through the adjusting nut 8, thereby facilitating the full flexibility of the installation position of the connecting sleeve 3 and facilitating adaptation to different installation situations.
[0037] Reference Figure 3 In order to fully ensure the stability of the connection rib 2 and the connection sleeve 3 when they are fixed, the connection sleeve 3 is provided with a fixing part, which includes a fixing bolt 10. The fixing bolt 10 is passed along an axis perpendicular to the connection sleeve 3 and threadedly engaged with the connection sleeve 3. One end of the fixing bolt 10 is passed through the through hole 4, so that the connection rib 2 in the connection sleeve 3 is tightly fixed by the fixing bolt 10 to ensure the stability of the position of the connection rib 2. The end of the fixing bolt 10 extending into the through hole 4 is rotatably provided with an arc clamping plate 11, and the arc clamping plate 11 is slidably engaged with the through hole 4 along the axis direction perpendicular to the connection sleeve 3. When the fixing bolt 10 is pressed against the connection rib 2 to fix it, the connection rib 2 is located in the area surrounded by the arc clamping plate 11, so as to further limit the position of the connection rib 2 when it is fixed.
[0038] Reference Figure 2 and Figure 3 In order to facilitate the insertion of the connecting rib 2 into the through hole 4 of the connecting sleeve 3, the openings of the through hole 4 at both ends are rounded, so that the aperture of the through hole 4 near its own opening is larger than the aperture of the through hole 4, so that there is a certain gap transition when the connecting rib 2 is inserted into the through hole 4. Limiting steel wires 12 are provided on both sides of each connecting sleeve 3, and the limiting steel wires 12 are fixed to the connecting rib 2 by binding, so that the relative position stability of the connecting rib 2 and the connecting sleeve 3 when the connecting rib 2 is fixed is further ensured by the limiting effect of the limiting steel wires 12 on the connecting sleeve 3.
[0039] The implementation principle of the quick installation structure of the connecting rib of the gas tunnel arch frame of the present application embodiment is as follows: when it is necessary to connect the connecting rib 2 and each arch frame 1, firstly, the connecting rib 2 is sequentially inserted into the connecting sleeve 3 of each arch frame 1, and the connecting sleeve 3 and the connecting rib 2 are fixed by the fixing bolt 10 to realize the connection between the connecting rib 2 and each arch frame 1. During the connection process of the connecting rib 2 and each arch frame 1, it is not necessary to fix them with each arch frame 1 sequentially by welding. The connecting rib 2 is inserted into the through hole 4 in each connecting sleeve 3 and fixed by the fixing member. The operation is convenient, which is conducive to improving the working efficiency of the connection between the connecting rib 2 and each arch frame 1. In addition, the setting of the adjustment hole 5 and the adjustment bolt facilitates the multi-directional micro-adjustment of the position of the connecting sleeve 3 during installation, which facilitates the adaptability of the connecting sleeve 3 to different installation conditions, and has strong applicability. The setting of the limiting steel wire 12 plays a further limiting role on the connecting sleeve 3 and the connecting rib 2, so as to further ensure the stability of the relative position of the connecting sleeve 3 and the connecting rib 2 when they are fixed.
[0040] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A quick installation structure for connecting ribs of a gas tunnel arch frame, comprising an arch frame (1) and connecting ribs (2), wherein the arch frame (1) is provided with a plurality of connecting ribs distributed in a horizontal direction, and the connecting ribs (2) are located outside the arch frame (1) and are distributed circumferentially around the axis of the arch frame (1), characterized in that: A plurality of connecting sleeves (3) are arranged on the outside of each of the arch frames (1), each of the connecting sleeves (3) corresponds one-to-one to a plurality of connecting ribs (2), the connecting sleeves (3) have through holes (4) for the connecting ribs (2) to pass through, and the connecting sleeves (3) are provided with fixing parts for fixing the connecting ribs (2).
2. A quick installation structure for connecting ribs of a gas tunnel arch according to claim 1, characterized in that: The fixing member comprises a fixing bolt (10), wherein the fixing bolt (10) is threadably engaged with the connecting sleeve (3), and one end of the fixing bolt (10) is inserted into the through hole (4).
3. A quick installation structure for connecting ribs of a gas tunnel arch according to claim 2, characterized in that: One end of the fixing bolt (10) that extends into the through hole (4) is rotatably provided with an arc-shaped clamping plate (11), and the arc-shaped clamping plate (11) is slidably fitted in the through hole (4).
4. A quick installation structure for connecting ribs of a gas tunnel arch according to claim 1, characterized in that: The outer side of the arch frame (1) is provided with an adjustment hole (5) which penetrates through and extends circumferentially around its own axis. The connecting sleeve (3) is fixedly mounted with a mounting screw (6), and the mounting screw (6) is slidably engaged with the adjustment hole (5). One end of the mounting screw (6) which passes through the adjustment hole (5) is threadedly engaged with a mounting nut (7).
5. A quick installation structure for connecting ribs of a gas tunnel arch according to claim 4, characterized in that: A contact pad (9) is fixedly connected to the side of the mounting nut (7) close to the arch frame.
6. A quick installation structure for connecting ribs of a gas tunnel arch according to claim 4, characterized in that: The mounting screw rod (6) is threadably matched with an adjusting nut (8), and the adjusting nut (8) is located on a side of the arch away from the mounting nut (7).
7. A quick installation structure for connecting ribs of a gas tunnel arch according to claim 1, characterized in that: The openings at both ends of the through hole (4) are rounded.
8. A quick installation structure for connecting ribs of a gas tunnel arch according to claim 1, characterized in that: Limiting steel wires (12) are provided on both sides of each connecting sleeve (3), and the limiting steel wires (12) are tied and fixed to the connecting ribs (2).