Pile foundation hole construction equipment

By designing a pile foundation hole construction equipment for pile foundation construction and using an annular bottom plate and guide structure to guide the pipeline, the problem of inaccurate or stuck pipe placement in pile foundation construction is solved, and the accuracy and smoothness of pipeline placement are achieved.

CN222758884UActive Publication Date: 2025-04-15SHANGHAI YUANDA BASIC ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421336490.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-13
Publication Date
2025-04-15
Estimated Expiration
2034-06-13

AI Technical Summary

Technical Problem

During pile foundation construction, when using lifting equipment to place the pipe into the pile foundation hole, the pipe is easily stuck due to inaccurate position or tilt, resulting in inconvenient construction.

Method used

A pile foundation hole construction equipment is designed, including an annular base plate and a guide structure. The annular base plate is fixedly connected to the ground around the orifice. The guide structure consists of an annular outer plate, a side block, a connecting plate and an annular inner plate. The annular inner plate is cooperated with the pipe for the placement of the guide pipe.

Benefits of technology

By using this equipment, the pipe can be guided by the annular inner plate during the placement process, avoiding inaccurate position or obliquely stuck, and ensuring the accuracy and smoothness of the pipe placement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222758884U_ABST
    Figure CN222758884U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pile foundation construction, and discloses pile foundation hole construction equipment which comprises an annular bottom plate and at least one guide structure which is evenly arranged, the annular bottom plate is fixedly connected with the ground on the periphery of a hole opening, the upper end of the annular bottom plate is fixedly connected with vertical rods which are oppositely arranged, and each guide structure comprises an annular outer plate. Side blocks are fixedly connected to the two sides of the annular outer plate, through holes matched with the vertical rods are formed in the side blocks on the two sides, one or more evenly-arranged connecting plates are arranged in the annular outer plate, annular inner plates are fixedly connected into the connecting plates, and the annular inner plates are matched with pipelines. Compared with the prior art, the pipeline guiding device has the advantage of being capable of guiding a pipeline.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pile foundation construction, in particular to pile foundation hole construction equipment. Background Art

[0002] During the pile foundation construction process, it is necessary to first use a rotating drill to create holes in the rock and soil layer to facilitate pile foundation construction. Before drilling construction, a geological survey must be conducted first to understand the composition and properties of the stratum in order to reasonably select the drilling method and process. Based on the results of the geological survey, a drilling design can be carried out. The drilling design includes determining parameters such as the pile diameter, hole depth, and drilling straightness, which will facilitate the subsequent selection of appropriate drilling machinery and debugging.

[0003] After the drilling of the pile foundation hole is completed, the pipe needs to be inserted into the hole, and then a steel cage is placed in the pipe and concrete is poured to form a pile foundation. During the process of inserting the pipe, a lifting device is needed to lift the pipe and insert it vertically into the hole. However, when the lifting device lifts the upper end of the pipe, it is connected with a wire rope. The pipe will shake during the process of being placed in the hole, which will cause the pipe to be placed in an inaccurate position or get stuck during the placement process. Utility Model Content

[0004] 1. Technical issues to be solved

[0005] The technical problem to be solved by the utility model is that when a lifting device is currently used to put a pipe into a pile foundation hole, since the lifting device uses a steel wire rope to lift the pipe, the pipe may be inaccurately positioned during the putting process, or may get stuck due to tilting.

[0006] (II) Technical solution

[0007] In order to solve the above technical problems, the technical solution provided by the utility model is: a pile foundation hole construction equipment, including an annular bottom plate and at least one and evenly arranged guide structure, the annular bottom plate is fixedly connected to the ground around the hole mouth, the upper end of the annular bottom plate is fixedly connected to relatively arranged vertical poles, the guide structure includes an annular outer plate, both sides of the annular outer plate are fixedly connected to side blocks, the side blocks on both sides are provided with through holes matching with the vertical poles, the annular outer plate is provided with at least one and evenly arranged connecting plate, the connecting plate is fixedly connected to an annular inner plate, and the annular inner plate matches with the pipeline.

[0008] As an improvement, reinforcing round steel bars are fixedly connected to the connecting plates, and the reinforcing round steel bars penetrate through each of the annularly arranged connecting plates.

[0009] As an improvement, the upper ends of the vertical poles are threadedly connected with top plugs that cooperate with the side blocks.

[0010] As an improvement, mounting plates are fixedly connected to both sides of the annular bottom plate, mounting holes are provided on the mounting plates, and the mounting holes are connected to the ground using expansion bolts.

[0011] As an improvement, a spacer is bonded to the lower end of the annular bottom plate.

[0012] (III) Beneficial effects

[0013] Compared with the prior art, the utility model has the following advantages: the annular bottom plate is placed beside the drilled hole, and the mounting plate is fixedly connected to the ground, and then a suitable number of guide structures are selected and installed according to the required length of the pipe to be inserted, and then the pipe is lifted and lowered using a lifting device. During the insertion process, the annular inner plate can guide the pipe, and the situation that the pipe is not positioned accurately during the insertion process, is stuck due to tilting, etc. can be avoided. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the structure of a guide structure of a pile foundation hole construction equipment of the utility model. Figure 1 .

[0015] Figure 2 This is a schematic diagram of the structure of a guide structure of a pile foundation hole construction equipment of the utility model. Figure 2 .

[0016] Figure 3 The utility model is a schematic diagram of an assembly state of a pile foundation hole construction device.

[0017] Figure 4 The utility model is a top view of a guide structure of pile foundation hole construction equipment.

[0018] As shown in the figure: 1. Guide structure; 2. Annular outer plate; 3. Connecting plate; 4. Annular inner plate; 5. Reinforcing round steel bars; 6. Side blocks; 7. Through holes; 8. Annular bottom plate; 9. Mounting plate; 10. Mounting holes; 11. Vertical pole; 12. Top plug. DETAILED DESCRIPTION

[0019] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments; based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.

[0020] Embodiment 1

[0021] like Figure 1 , Figure 2 and Figure 3As shown, a pile foundation hole construction equipment includes an annular bottom plate 8 and at least one and evenly arranged guide structure 1, the lower end of the annular bottom plate 8 is adhered with a spacer, the spacer can prevent the bottom surface of the annular bottom plate 8 from being worn during use, the annular bottom plate 8 is fixedly connected to the ground around the hole mouth, both sides of the annular bottom plate 8 are fixedly connected with mounting plates 9, the mounting plates 9 are provided with mounting holes 10, the mounting holes 10 are connected to the ground with expansion bolts, and the upper end of the annular bottom plate 8 is fixedly connected with oppositely arranged vertical poles 11.

[0022] Through the above structure, the annular bottom plate 8 is installed around the orifice to guide the pipeline. The specific structure is as follows:

[0023] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, the guide structure 1 includes an annular outer plate 2, and side blocks 6 are fixedly connected on both sides of the annular outer plate 2. Through holes 7 cooperating with the vertical poles 11 are provided on the side blocks 6 on both sides. At least one and evenly arranged connecting plates 3 are provided in the annular outer plate 2, and an annular inner plate 4 is fixedly connected in the connecting plate 3. The annular inner plate 4 cooperates with the pipeline, and reinforcing round steel bars 5 are fixedly connected to the connecting plate 3. The reinforcing round steel bars 5 penetrate through the connecting plates 3 arranged in an annular manner, which can improve the stability of the guide structure 1.

[0024] Through the above structure, the pipe is placed into the hole along the inner cavity of the annular inner plate 4, which can avoid the pipe being placed in an inaccurate position or getting stuck due to tilting.

[0025] Embodiment 2

[0026] like Figure 1 , Figure 2 and Figure 3 As shown, the upper ends of the vertical rods 11 are threadedly connected with top plugs 12 that cooperate with the side blocks 6.

[0027] Through the above structure, the top plug 12 can block the upper end of the vertical rod 11.

[0028] When the utility model is implemented, after the drilling is completed, a pipe needs to be placed therein. The length of the pipe is determined by the depth of the drilling. After selecting the pipe of appropriate length, the height of the stacking guide structure is selected according to the length of the pipe. Specifically, the annular bottom plate is first placed around the hole, and after adjusting the position, the installation hole is fixedly connected to the ground with expansion bolts, and the installation plate can be fixed on the ground.

[0029] Then the guiding structure can be inserted into the vertical poles on both sides. Specifically, the through holes on the side blocks on both sides of the annular outer plate are respectively aligned with the vertical poles on both sides, and then the side blocks are moved down along the vertical poles, and finally a suitable number of annular outer plates are inserted. At this time, the annular inner plate can form a channel for guiding the pipeline. Use a lifting device to lift one end of the pipeline and insert it into the area surrounded by the annular inner plate. The annular inner plate can be used to guide the pipeline to ensure that the pipeline is in a vertical state above the orifice, thereby avoiding the situation where the pipeline is placed in an inaccurate position or gets stuck due to tilting.

[0030] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0031] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

[0032] The above description of the utility model and its implementation methods is not restrictive. The drawings show only one implementation method of the utility model, and the actual structure is not limited thereto. In short, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention of the utility model, they should all fall within the protection scope of the utility model.

Claims

1. A pile foundation hole construction equipment, characterized in that: It comprises an annular bottom plate (8) and at least one uniformly arranged guide structure (1), wherein the annular bottom plate (8) is fixedly connected to the ground around the hole opening, and the upper end of the annular bottom plate (8) is fixedly connected to oppositely arranged vertical poles (11); The guide structure (1) comprises an annular outer plate (2), side blocks (6) are fixedly connected to both sides of the annular outer plate (2), through holes (7) cooperating with the vertical rods (11) are provided on the side blocks (6) on both sides, and at least one evenly arranged connecting plate (3) is provided inside the annular outer plate (2), an annular inner plate (4) is fixedly connected to the connecting plate (3), and the annular inner plate (4) cooperates with the pipeline.

2. A pile foundation hole construction equipment according to claim 1, characterized in that: Reinforcing round steel bars (5) are fixedly connected to the connecting plates (3), and the reinforcing round steel bars (5) penetrate through each of the connecting plates (3) arranged in a ring shape.

3. A pile foundation hole construction equipment according to claim 1, characterized in that: The upper ends of the vertical rods (11) are threadedly connected with top plugs (12) that cooperate with the side blocks (6).

4. A pile foundation hole construction equipment according to claim 1, characterized in that: Mounting plates (9) are fixedly connected to both sides of the annular bottom plate (8), and mounting holes (10) are provided on the mounting plates (9). The mounting holes (10) are connected to the ground using expansion bolts.

5. The pile foundation hole construction equipment according to claim 1, characterized in that: A spacer is bonded to the lower end of the annular bottom plate (8).