Building template fixing structure
By using a combined structure of double-piece channel steel and tie bolts on the building formwork, the problem of unstable large-size column formwork in the prior art is solved, and the strength of the formwork fixation and the construction efficiency are improved.
Patent Information
- Application Number
- CN202420713975.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-09
- Publication Date
- 2025-04-15
- Estimated Expiration
- 2034-04-09
AI Technical Summary
In the prior art, the building formwork that uses pull-on water stop bolts to fix large-size columns is unstable, prone to deformation or explosion, and has a long construction period, which affects the load-bearing capacity of the formwork and leaves unnecessary holes.
A combined structure of double-molded channel steel and tie bolts is adopted. The double-molded channel steel is distributed on the two opposite surfaces of the building formwork in the horizontal direction. It is fixed to the formwork by double-molded bolts to form a tightly fitted structure to improve the overall strength of the fixed formwork.
Through this structure, the overall strength of the fixed formwork is significantly improved, avoiding the problem of unstable formwork and long construction cycle, shortening the construction time, reducing the floor area of the construction work surface, and making the column surface smooth and complete.
Smart Images

Figure CN222759376U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of construction, in particular to a building template fixing structure. Background Art
[0002] With the development of science and technology, the performance of ordinary concrete has been greatly improved, and its finished product has a high density. For concrete structures with air defense requirements, great strength and rigidity are required. In actual engineering applications, the requirements of resisting special loads or deformation can be met by increasing the thickness. Usually, the thickness of components in such buildings needs to be increased to 3-10 times the thickness of ordinary building components, so there are higher rigidity requirements for large-size concrete structural walls or structural column support formwork.
[0003] In the prior art, the support and fixation of the building structure support column formwork mainly relies on the tension water stop bolts. This traditional process can play a good fixing role for the conventional size of the structural column formwork, but for the columns that are 2-3 times the size of ordinary building structure columns, this fixing method makes the formwork unstable and prone to deformation, and even explosion. After the construction is completed, there are more traces of tension steel bars, which weakens the structural section. Utility Model Content
[0004] The utility model aims to provide a building template fixing structure to solve the technical problems that the template is unstable, easily deformed, and even exploded when using tension water stop bolts to fix large-sized columns.
[0005] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is: to provide a building template fixing structure, the building template fixing structure comprising:
[0006] A plurality of double-jointed channel steels, wherein the double-jointed channel steels include a first channel steel and a second channel steel, a gap is reserved between the first channel steel and the second channel steel, and the first channel steel and the second channel steel are connected via a connecting portion; the double-jointed channel steels are distributed on two opposite surfaces of the building template along the horizontal direction;
[0007] The tension bolts have two ends respectively connected to the double-jointed channel steels on two opposite surfaces of the building template, and the tension bolts lock the double-jointed channel steels.
[0008] In one embodiment, the first channel steel and the second channel steel are arranged in parallel, and the double-jointed channel steels are arranged at equal distances.
[0009] In one embodiment, the tension bolt comprises:
[0010] A screw rod, both ends of which extend out from the middle gap of the double-jointed channel steel on opposite surfaces;
[0011] a nut, wherein the nut threadably engages with the end of the screw,
[0012] A gasket is sleeved on both ends of the screw rod, and the gasket is located between the nut and the double-jointed channel steel.
[0013] In one embodiment, the connecting portion is a steel bar.
[0014] In one embodiment, the reinforcement member is connected to the first channel steel and the second channel steel by welding.
[0015] In one embodiment, a plurality of supporting angle steels are arranged between the double-jointed channel steel and the building formwork.
[0016] In one embodiment, the support angle steels are arranged equidistantly along the vertical direction.
[0017] One or more of the above technical solutions in the embodiments of the present utility model have at least the following technical effects or advantages:
[0018] The building formwork fixing structure provided by the embodiment of the utility model fixes the double-jointed channel steel on the building formwork through tension bolts, so that the double-jointed channel steel and the building formwork are tightly fitted, and then the pressure on the formwork generated by pouring concrete can be transmitted to the double-jointed channel steel through the building formwork, and the overall strength of the building formwork fixing is improved by the double-jointed channel steel, thereby replacing the tension waterstop bolts, eliminating the need to open tension bolt holes on the building formwork, which can shorten the construction time, reduce the floor space occupied by the construction work surface, shorten the time for assembling and fixing the building formwork, increase the bearing capacity of the building formwork, and make the surface of the column smooth and complete (when the tension waterstop bolts are used to fix the building formwork, it is necessary to open tension bolt holes on the building formwork, and the tension waterstop bolts penetrate the building formwork for fixing, so the construction period is long and affects the bearing capacity of the building formwork. In addition, after the concrete in the building formwork is solidified, after the tension waterstop bolts are taken out, tension bolt holes will be left on the columns, resulting in an uneven and complete surface of the column). BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0020] Figure 1 A side view of a template fixing structure provided by an embodiment of the utility model;
[0021] Figure 2A front view of a template fixing structure provided in an embodiment of the utility model.
[0022] The respective reference numerals are as follows:
[0023] 1. Double-jointed channel steel; 11. First channel steel; 12. Second channel steel; 13. Connection part; 2. Tension bolts; 21. Screw rod; 22. Washer; 23. Nut; 3. Support angle steel; 4. Building formwork. DETAILED DESCRIPTION
[0024] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0025] In the description of the present invention, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0026] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0027] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0028] See also Figure 1 to Figure 2The embodiment of the present application provides a fixing structure of a building formwork 4, including tension bolts 2 and a plurality of double-jointed channel steels 1, wherein the double-jointed channel steel 1 includes a first channel steel 11 and a second channel steel 12, a gap is reserved between the first channel steel 11 and the second channel steel 12, and the first channel steel 11 and the second channel steel 12 are connected by a connecting portion 13; the double-jointed channel steels 1 are distributed on two opposite surfaces of the building formwork 4 along the horizontal direction; the two ends of the tension bolts 2 are respectively connected to the double-jointed channel steels 1 on the two opposite surfaces of the building formwork 4, and the tension bolts 2 lock the double-jointed channel steel 1.
[0029] The fixing structure of the building formwork 4 provided in the present embodiment fixes the double-jointed channel steel 1 on the building formwork 4 by the tension bolts 2, so that the double-jointed channel steel 1 and the building formwork 4 are closely fitted, and then the pressure on the formwork generated by pouring concrete can be transmitted to the double-jointed channel steel 1 through the building formwork 4, and the overall strength of the fixing of the building formwork 4 is improved by the double-jointed channel steel 1, thereby replacing the tension water stop bolts, eliminating the need to open two tension bolt holes on the building formwork 4, which can shorten the construction time, reduce the floor space occupied by the construction work surface, shorten the time for assembling and fixing the building formwork 4, increase the bearing capacity of the building formwork 4, and make the surface of the column smooth and complete (when the tension water stop bolts are used to fix the building formwork 4, two tension bolt holes need to be opened on the building formwork 4, and the tension water stop bolts penetrate the building formwork 4 for fixing, so the construction period is long and affects the bearing capacity of the building formwork 4. In addition, after the concrete in the building formwork 4 solidifies, after the tension water stop bolts are taken out, two tension bolt holes will be left on the column, resulting in an uneven and complete surface of the column).
[0030] In one embodiment, the first channel steel 11 and the second channel steel 12 are arranged in parallel, and the double-jointed channel steels 1 are arranged at equal distances. By arranging the double-jointed channel steels 1 at equal distances, the fastening force of the double-jointed channel steels 1 on the building formwork 4 can be evenly distributed.
[0031] In one embodiment, the tension bolt 2 includes a gasket 22, a nut 23, and a screw rod 21, and the two ends of the screw rod 21 extend from the middle gap of the double-jointed channel steel 1 on the opposite surface respectively; the nut 23 is threadedly engaged with the end of the screw rod 21, and the gasket 22 is sleeved on the two ends of the screw rod 21, and the gasket 22 is located between the nut 23 and the double-jointed channel steel 1.
[0032] In one embodiment, the connection portion 13 is a steel bar, and the steel bar is connected to the first channel steel 11 and the second channel steel 12 by welding.
[0033] In one embodiment, a plurality of supporting angle steels 3 are arranged between the double-jointed channel steel 1 and the building formwork 4. By spacing a plurality of angle steels between the building formwork 4 and the double-jointed channel steel 1, the force bearing area of the double-jointed channel steel 1 fixed on the building formwork 4 is increased, thereby further increasing the stability of the fixing of the building formwork 4. Optionally, the supporting angle steels 3 are arranged equidistantly along the vertical direction.
[0034] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A building template fixing structure, characterized in that: The building template fixing structure comprises: A plurality of double-jointed channel steels, wherein the double-jointed channel steels include a first channel steel and a second channel steel, a gap is reserved between the first channel steel and the second channel steel, and the first channel steel and the second channel steel are connected via a connecting portion; the double-jointed channel steels are distributed on two opposite surfaces of the building template along the horizontal direction; The tension bolts have two ends respectively connected to the double-jointed channel steels on two opposite surfaces of the building template, and the tension bolts lock the double-jointed channel steels.
2. A building template fixing structure according to claim 1, characterized in that: The first channel steel and the second channel steel are arranged in parallel, and the double-jointed channel steels are arranged at equal distances.
3. A building template fixing structure according to claim 1, characterized in that: The tension bolts include: A screw rod, both ends of which extend out from the middle gap of the double-jointed channel steel on opposite surfaces; a nut, wherein the nut threadably engages with the end of the screw, A gasket is sleeved on both ends of the screw rod, and the gasket is located between the nut and the double-jointed channel steel.
4. A building template fixing structure according to claim 1, characterized in that: The connecting portion is a steel bar.
5. A building template fixing structure according to claim 4, characterized in that: The reinforcement member is connected to the first channel steel and the second channel steel by welding.
6. A building template fixing structure according to claim 1, characterized in that: A plurality of supporting angle steels are arranged between the double-jointed channel steel and the building formwork.
7. A building template fixing structure according to claim 6, characterized in that: The supporting angle steels are arranged equidistantly along the vertical direction.