Municipal drainage pipeline laying device
By designing a municipal drainage pipeline laying device with multiple components, the problems of pipeline slipping and safety risks caused by unstable traditional lifting methods are solved, and the stable clamping and laying efficiency of pipelines of different specifications and sizes are improved.
Patent Information
- Application Number
- CN202421889208.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2025-04-25
- Estimated Expiration
- 2034-08-06
AI Technical Summary
The traditional drainage pipe lifting method is not stable enough, which can easily cause the pipe to slide, cause damage and safe construction risks, and it is difficult to achieve stable clamping of pipes of different specifications and sizes, which in turn affects the laying efficiency.
A municipal drainage pipeline laying device is designed, including lifting plates, mounting gears, mounting shafts, mounting blocks, guiding tooth plates, positioning clips, lifting components, lifting components, clamping components, drive components and adjustment components. Through the synergy of these components, stable clamping and adjustment of the pipeline can be achieved.
It effectively solves the problems of pipeline slippage and safe construction risks, achieves stable clamping of pipelines of different specifications and sizes, and improves pipeline laying efficiency.
Smart Images

Figure CN222794961U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipeline laying devices, in particular to a municipal drainage pipeline laying device. Background Art
[0002] Municipal engineering generally refers to the construction of various public transportation facilities, water supply, drainage, gas, urban flood control, environmental sanitation, lighting and other infrastructure in urban construction. Municipal engineering is an indispensable material basis for the survival and development of cities, and is the basic condition for improving people's living standards and opening up to the outside world. When laying water supply and drainage pipes in municipal engineering, the current construction mainly involves building a brick structure support foundation in the pipe pit, and then fixing the water supply and drainage pipes on the brick structure support foundation. In actual use, the traditional drainage pipe hoisting method is not stable enough, which may cause the drainage pipe to slip during the hoisting process, which will not only cause damage to the pipe, but also pose a high safety construction risk, making it inconvenient to achieve a stable clamping effect for pipes of different specifications and sizes, and thus inconvenient to improve the efficiency of pipe laying;
[0003] Therefore, in order to solve the above-mentioned problem of inconvenience in improving pipeline laying efficiency, a municipal drainage pipeline laying device can be designed. Utility Model Content
[0004] In order to overcome the problem that the traditional drainage pipe lifting method is not stable enough during use of the pipe laying device, the drainage pipe may slip during the lifting process, which will not only cause damage to the pipe, but also pose a high safety construction risk, making it inconvenient to achieve a firm clamping effect on pipes of different specifications and sizes, thereby making it inconvenient to improve the efficiency of pipe laying.
[0005] The technical solution of the utility model is: a municipal drainage pipe laying device, including a lifting plate, a mounting gear, a mounting shaft, a mounting block, a guide tooth plate, a positioning clamp, a lifting assembly, a lifting assembly, a clamping assembly, a driving assembly and an adjusting assembly; a lifting assembly is arranged above the lifting plate, a lifting assembly is arranged below the lifting plate, a clamping assembly is arranged below the lifting assembly, a driving assembly is arranged on the side wall of the lifting assembly, an adjusting assembly is arranged at the output end of the driving assembly, the adjusting assembly is arranged inside the lifting assembly, a guide tooth plate is arranged below the adjusting assembly, two groups of guide tooth plates are arranged, a mounting block is arranged below the lifting assembly, multiple groups of mounting blocks are arranged, a mounting shaft is arranged inside the mounting block, a mounting gear is arranged on the side wall of the mounting shaft, the mounting gear is meshed with the guide tooth plate, and positioning clamps are arranged at both ends of the mounting shaft.
[0006] Preferably, when using the pipe laying device, first, the driving component is started to drive the two groups of guide tooth plates to move relative to each other through the adjusting component, and the two groups of guide tooth plates can respectively drive the two groups of adjusting gears to adjust and rotate, and the two groups of adjusting gears can respectively drive the two groups of installation shafts to adjust and rotate, and the two groups of installation shafts can drive multiple groups of positioning clamps to adjust and rotate synchronously, and the pipeline can be firmly clamped by the multiple groups of positioning clamps, and the two sides of the pipeline can be positioned and clamped by the clamping component. In addition, through the cooperation of the above-mentioned structures, the effect of firmly clamping pipes of different specifications and sizes can be achieved, thereby improving the efficiency of pipe laying, and then, the lifting equipment is used to lift the lifting plate through the lifting component, and then, the lifting component is started to drive the pipeline to be lifted and adjusted to the required laying position for laying and installation.
[0007] Preferably, the lifting assembly includes lifting ears and lifting holes; a lifting ear is arranged above the lifting plate, a plurality of groups of lifting ears are arranged, and a lifting hole is opened inside the lifting ear.
[0008] Preferably, the lifting assembly includes an electric-controlled lifting rod and a lifting plate; the electric-controlled lifting rod is arranged below the lifting plate, two groups of the electric-controlled lifting rod are arranged, and a lifting plate is arranged below the electric-controlled lifting rod.
[0009] Preferably, the clamping assembly includes a support plate and an electrically controlled push rod; a support plate is arranged below the lifting plate, two groups of support plates are arranged, and an electrically controlled push rod is arranged on the side wall of the support plate.
[0010] Preferably, the clamping assembly further includes an arc-shaped groove and an arc-shaped clamp; an arc-shaped clamp is provided at one end of the electric control push rod, and an arc-shaped groove is provided on the inner wall of the arc-shaped clamp.
[0011] Preferably, the driving assembly includes a protective shell and a rotating motor; the protective shell is arranged on the side wall of the lifting plate, and the rotating motor is arranged inside the protective shell.
[0012] Preferably, the adjustment component includes a rotating shaft and a bidirectional screw; the output end of the rotating motor is provided with a rotating shaft, and one end of the rotating shaft is provided with a bidirectional screw.
[0013] Preferably, the adjustment component also includes a sliding groove and a sliding block; a sliding groove is opened inside the lifting plate, one end of the bidirectional screw is rotatably connected to the inner wall of the sliding groove, a sliding block is arranged on the side wall of the bidirectional screw, two groups of sliding blocks are arranged, the sliding block is threadedly connected to the bidirectional screw, and the guide tooth plate is fixedly connected to the bottom wall of the sliding block.
[0014] Beneficial effects of the utility model:
[0015] 1. When using the pipeline laying device, first, the starting driving component can drive the two sets of guide tooth plates to move relative to each other through the adjusting component, and the two sets of guide tooth plates can respectively drive the two sets of adjusting gears to adjust and rotate, and the two sets of adjusting gears can respectively drive the two sets of installation shafts to adjust and rotate, and the two sets of installation shafts can drive multiple sets of positioning clamps to adjust and rotate synchronously, and the pipeline can be firmly clamped by the multiple sets of positioning clamps, and the two sides of the pipeline can be positioned and clamped by the clamping component. In addition, through the cooperation of the above structures, the pipelines of different specifications and sizes can be firmly clamped, thereby improving the efficiency of pipeline laying. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 What is shown is a first three-dimensional structural schematic diagram of a municipal drainage pipe laying device of the utility model;
[0017] Figure 2 What is shown is a schematic diagram of a first partial three-dimensional structure of a municipal drainage pipe laying device of the utility model;
[0018] Figure 3 What is shown is a schematic diagram of a second partial three-dimensional structure of a municipal drainage pipe laying device of the utility model;
[0019] Figure 4 What is shown is a third partial three-dimensional structural schematic diagram of a municipal drainage pipe laying device of the utility model;
[0020] Explanation of the reference numerals in the accompanying drawings: 1. lifting plate; 2. mounting gear; 3. mounting shaft; 4. mounting block; 5. guide tooth plate; 6. positioning clamp; 101. lifting ear; 102. lifting hole; 201. electric lifting rod; 202. lifting plate; 301. supporting plate; 302. electric push rod; 303. arc groove; 304. arc clamp; 401. protective shell; 402. rotating motor; 501. rotating shaft; 502. bidirectional screw; 503. sliding groove; 504. sliding block. DETAILED DESCRIPTION
[0021] The utility model is further described below in conjunction with the accompanying drawings and embodiments.
[0022] See also Figure 1The utility model provides an embodiment: a municipal drainage pipe laying device, including a lifting plate 1, a mounting gear 2, a mounting shaft 3, a mounting block 4, a guide tooth plate 5, a positioning clamp 6, a lifting assembly, a lifting assembly, a clamping assembly, a driving assembly and an adjusting assembly; a lifting assembly is arranged above the lifting plate 1, a lifting assembly is arranged below the lifting plate 1, a clamping assembly is arranged below the lifting assembly, a driving assembly is arranged on the side wall of the lifting assembly, an adjusting assembly is arranged at the output end of the driving assembly, the adjusting assembly is arranged inside the lifting assembly, a guide tooth plate 5 is arranged below the adjusting assembly, two groups of guide tooth plates 5 are arranged, a mounting block 4 is arranged below the lifting assembly, and multiple groups of mounting blocks 4 are arranged inside the mounting block 4, a mounting shaft 3 is arranged on the side wall of the mounting shaft 3, the mounting gear 2 is meshed with the guide tooth plate 5, and positioning clamps 6 are arranged at both ends of the mounting shaft 3.
[0023] See also Figure 2 The lifting assembly includes a lifting ear 101 and a lifting hole 102; a lifting ear 101 is arranged above the lifting plate 1, and the lifting ear 101 is provided with multiple groups, and a lifting hole 102 is opened inside the lifting ear 101; the lifting rope or chain is passed through the lifting hole 102 inside the lifting ear 101, and the length and angle of the rope or chain are adjusted as needed to ensure that the object to be lifted can be lifted and moved smoothly. During the lifting process, the lifting ear 101 and the lifting hole 102 bear the tension from the lifting rope or chain, and transmit the tension to the lifting plate 1 and the object to be lifted, so that the lifting equipment can be used to lift the lifting plate 1 through multiple groups of lifting ears 101; the lifting assembly includes an electric-controlled lifting rod 201 and a lifting plate 202; an electric-controlled lifting rod 201 is arranged below the lifting plate 1, and two groups of electric-controlled lifting rods 201 are arranged, and a lifting plate is arranged below the electric-controlled lifting rod 201 202; starting the electric-controlled lifting rod 201 can drive the pipeline to be lifted and adjusted to the required laying position through the lifting plate 202 for laying and installation; the clamping assembly includes a support plate 301 and an electric-controlled push rod 302; a support plate 301 is arranged below the lifting plate 202, and two groups of support plates 301 are arranged, and an electric-controlled push rod 302 is arranged on the side wall of the support plate 301; starting the electric-controlled push rod 302 can drive the arc clamp 304 to move, and the two groups of arc clamps 304 can be used to position and clamp the two sides of the pipeline, thereby improving the stability of the clamping structure; the clamping assembly also includes an arc groove 303 and an arc clamp 304; an arc clamp 304 is arranged at one end of the electric-controlled push rod 302, and an arc groove 303 is opened on the inner wall of the arc clamp 304; the two groups of arc clamps 304 can be used to position and clamp the two sides of the pipeline.
[0024] See also Figure 3-4In this embodiment, the driving component includes a protective shell 401 and a rotating motor 402; a protective shell 401 is provided on the side wall of the lifting plate 202, and a rotating motor 402 is provided inside the protective shell 401; starting the rotating motor 402 can drive the adjusting component to rotate through the rotating shaft 501, and the protective shell 401 can provide dust protection for the rotating motor 402; the adjusting component includes a rotating shaft 501 and a bidirectional screw 502; the output end of the rotating motor 402 is provided with a rotating shaft 501, and one end of the rotating shaft 501 is provided with a bidirectional screw 502; starting the rotating motor 402 can drive the bidirectional screw 502 to rotate through the rotating shaft 501, and the bidirectional screw 502 can drive the two sets of adjusting components to move relative to each other ; The adjustment component also includes a sliding groove 503 and a sliding block 504; a sliding groove 503 is opened inside the lifting plate 202, one end of the bidirectional screw 502 is rotatably connected to the inner wall of the sliding groove 503, and a sliding block 504 is arranged on the side wall of the bidirectional screw 502, and two groups of sliding blocks 504 are arranged, and the sliding blocks 504 are threadedly connected to the bidirectional screw 502, and the guide tooth plate 5 is fixedly connected to the bottom wall of the sliding block 504; starting the rotating motor 402 can drive the bidirectional screw 502 to rotate through the rotating shaft 501, and the bidirectional screw 502 can drive the two groups of sliding blocks 504 to move relative to each other, and the two groups of sliding blocks 504 can respectively drive the two groups of guide tooth plates 5 to move relative to each other, thereby driving the two groups of positioning clamps 6 to achieve the effect of synchronous adjustment.
[0025] When the pipeline laying device is used, first, the rotating motor 402 is started to drive the bidirectional screw 502 to rotate through the rotating shaft 501, and the bidirectional screw 502 can drive the two sets of sliding blocks 504 to move relative to each other, and the two sets of sliding blocks 504 can respectively drive the two sets of guide tooth plates 5 to move relative to each other, and the two sets of guide tooth plates 5 can respectively drive the two sets of adjustment gears to adjust and rotate;
[0026] The two sets of adjustment gears can respectively drive the two sets of installation shafts 3 to adjust and rotate, and the two sets of installation shafts 3 can drive multiple sets of positioning clamps 6 to adjust and rotate synchronously, and the multiple sets of positioning clamps 6 can be used to firmly clamp the pipeline, and the two sides of the pipeline can be positioned and clamped by the clamping assembly;
[0027] In addition, through the cooperation of the above structures, the pipelines of different specifications and sizes can be firmly clamped, thereby improving the efficiency of pipeline laying;
[0028] Then, the lifting equipment is used to lift the lifting plate 1 through the multiple sets of lifting ears 101. Subsequently, the electrically controlled lifting rod 201 is started to drive the pipeline to be lifted and adjusted to the desired laying position through the lifting plate 202 for laying and installation.
[0029] Through the above steps, when the pipeline laying device is used, first, the starting driving component can drive the two groups of guide tooth plates 5 to move relative to each other through the adjusting component, and the two groups of guide tooth plates 5 can respectively drive the two groups of adjusting gears to adjust and rotate, and the two groups of adjusting gears can respectively drive the two groups of installation shafts 3 to adjust and rotate, and the two groups of installation shafts 3 can drive multiple groups of positioning clamps 6 to adjust and rotate synchronously, and the pipeline can be firmly clamped by the multiple groups of positioning clamps 6, and the two sides of the pipeline can be positioned and clamped by the clamping component. In addition, through the cooperation of the above structures, the effect of firmly clamping pipelines of different specifications and sizes can be achieved, thereby improving the efficiency of pipeline laying, and then, the lifting equipment is used to lift the lifting plate 1 through the lifting component, and then, the starting lifting component can drive the pipeline to lift and adjust to the required laying position for laying and installation.
[0030] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the purpose of the present invention.
Claims
1. A municipal drainage pipe laying device, comprising a hanging plate (1); characterized in that: The utility model also comprises a mounting gear (2), a mounting shaft (3), a mounting block (4), a guide tooth plate (5), a positioning clamp (6), a lifting assembly, a lifting assembly, a clamping assembly, a driving assembly and an adjusting assembly; a lifting assembly is arranged above the lifting plate (1), a lifting assembly is arranged below the lifting plate (1), a clamping assembly is arranged below the lifting assembly, a driving assembly is arranged on the side wall of the lifting assembly, an adjusting assembly is arranged at the output end of the driving assembly, the adjusting assembly is arranged inside the lifting assembly, a guide tooth plate (5) is arranged below the adjusting assembly, two groups of guide tooth plates (5) are arranged, a mounting block (4) is arranged below the lifting assembly, a plurality of groups of mounting blocks (4) are arranged inside the mounting block (4), a mounting shaft (3) is arranged on the side wall of the mounting shaft (3), the mounting gear (2) is meshed with the guide tooth plate (5), and positioning clamps (6) are arranged at both ends of the mounting shaft (3).
2. A municipal drainage pipe laying device according to claim 1, characterized in that: The lifting assembly comprises a lifting lug (101) and a lifting hole (102); a lifting lug (101) is arranged above the lifting plate (1), a plurality of groups of lifting lugs (101) are arranged, and a lifting hole (102) is opened inside the lifting lug (101).
3. A municipal drainage pipe laying device according to claim 1, characterized in that: The lifting assembly comprises an electric-controlled lifting rod (201) and a lifting plate (202); the electric-controlled lifting rod (201) is arranged below the lifting plate (1); two groups of the electric-controlled lifting rod (201) are arranged; and the lifting plate (202) is arranged below the electric-controlled lifting rod (201).
4. A municipal drainage pipe laying device according to claim 3, characterized in that: The clamping assembly comprises a support plate (301) and an electric control push rod (302); a support plate (301) is arranged below the lifting plate (202), two groups of support plates (301) are arranged, and an electric control push rod (302) is arranged on the side wall of the support plate (301).
5. A municipal drainage pipe laying device according to claim 4, characterized in that: The clamping assembly also includes an arc-shaped groove (303) and an arc-shaped clamp (304); one end of the electric control push rod (302) is provided with the arc-shaped clamp (304), and the inner wall of the arc-shaped clamp (304) is provided with the arc-shaped groove (303).
6. A municipal drainage pipe laying device according to claim 3, characterized in that: The driving assembly comprises a protective shell (401) and a rotating motor (402); the protective shell (401) is arranged on the side wall of the lifting plate (202), and the rotating motor (402) is arranged inside the protective shell (401).
7. A municipal drainage pipe laying device according to claim 6, characterized in that: The adjustment component comprises a rotating shaft (501) and a bidirectional screw (502); the output end of the rotating motor (402) is provided with the rotating shaft (501), and one end of the rotating shaft (501) is provided with the bidirectional screw (502).
8. A municipal drainage pipe laying device according to claim 3, characterized in that: The adjustment component also includes a sliding groove (503) and a sliding block (504); the lifting plate (202) is provided with a sliding groove (503) inside, one end of the bidirectional screw (502) is rotatably connected to the inner wall of the sliding groove (503), a sliding block (504) is arranged on the side wall of the bidirectional screw (502), two groups of sliding blocks (504) are arranged, the sliding blocks (504) are threadedly connected to the bidirectional screw (502), and the guide tooth plate (5) is fixedly connected to the bottom wall of the sliding block (504).