Transportation trolley for dismantling concrete bridge
By designing a transport trolley for concrete bridge removal using main frame, suspended beam and hook structure, the problem of the main beam removal transportation equipment in the prior art needs to be treated or temporary facilities are set up, transportation without foundation treatment is achieved, construction costs are reduced, and the characteristics of simple structure and easy to use are provided.
Patent Information
- Application Number
- CN202422151574.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2025-04-25
- Estimated Expiration
- 2034-09-03
AI Technical Summary
The existing main beam removal and transportation equipment requires the treatment of the foundation or the establishment of temporary construction facilities, resulting in high construction costs and limited equipment usage range.
A transport trolley for demolition of concrete bridges was designed, using the main frame, hanging beam and hook structure. The hanging beam is a right triangle triangular prism truss structure. A spool is set at the upper end of the hook, and multiple universal wheels are set at the bottom end of the main frame. The existing beam body bearing capacity is used as a temporary structure, without the need to deal with the foundation or the installation of temporary equipment.
It realizes the removal and transportation of main beams without foundation treatment or temporary equipment, reduces temporary construction costs, the equipment structure is simple, easy to disassemble and reuse, and is suitable for a wide range of bridge demolition and heavy lifting operations.
Smart Images

Figure CN222796228U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction, in particular to a transport trolley for dismantling a concrete bridge. Background Art
[0002] After long-term vehicle loads and external environment, the working performance and completion time of concrete cable-stayed bridges have been greatly degraded; at the same time, faced with the increasing traffic volume, they are facing demolition operations. Among them, the main beam removal operation is the most critical part of the concrete cable-stayed bridge demolition operation. The main transportation methods after the main beam is removed are as follows: truck crane or crawler crane method. In actual production, truck crane or crawler crane usually needs to treat the foundation to meet its requirements for the bearing capacity of the foundation. If it is in the water, it is necessary to build a temporary construction bridge or construction ship, which makes the temporary construction cost higher; gantry crane, it needs to lay tracks at the demolition site, and its scope of use is limited.
[0003] Based on the above, it can be seen that the existing technologies have the following technical problems: truck cranes or crawler cranes usually need to treat the site foundation, and their arms are long, which makes them difficult to use in narrow spaces; gantry cranes need to set up tracks, and they are only used on land or need to set up temporary bridges. Therefore, there is an urgent need for a transport trolley for main beam removal that can utilize the existing bearing capacity of the beam body and can achieve the purpose of removing the main beam without treating the foundation or setting up temporary construction facilities to increase temporary construction costs. Utility Model Content
[0004] Aiming at the deficiencies of the prior art, the present invention solves the problems that the dismantled blocks of the main beam are inconvenient to transport and the available transportation equipment is large in size and complex to install.
[0005] The utility model provides a transport trolley for dismantling a concrete bridge, comprising a main frame, a suspension beam and a hook, wherein the suspension beam is arranged on the side of the main frame, the hook is arranged on the outer end of the suspension beam, a wire shaft is arranged on the upper end of the hook, the wire shaft is rotatably arranged on the suspension beam, and a plurality of universal wheels are arranged on the bottom end of the main frame; the main frame and the suspension beam are composed of a truss structure, the suspension beam is a triangular prism truss structure with a right-angled triangle cross-section, a right-angled side of one side of the suspension beam is fixedly connected to the main frame, and the right-angled side of the other side is the upper side; a counterweight block is arranged in the main frame.
[0006] As a preferred solution, the spool is rotatably arranged on the two ends of the outermost rods of the suspension beam, and a handle for easy rotation is arranged on the side of the spool.
[0007] As a preferred solution, the counterweight block is arranged on a side of the center line of the main frame away from the cantilever beam.
[0008] As a preferred solution, the counterweight block with variable height gradually decreases in height from the side away from the cantilever beam to the side of the cantilever beam.
[0009] As a preferred solution, the counterweight block is a cast concrete block, and the concrete block and the truss connecting rod are cast into one piece.
[0010] As a preferred solution, handles are symmetrically arranged on both sides of the top of the main frame.
[0011] As a preferred solution, a plurality of universal wheels are arranged at the bottom end of the main frame.
[0012] The beneficial effects of the utility model are:
[0013] (1) The utility model uses a simplified structure and, under the premise of ensuring the bearing capacity, utilizes the existing beam bearing capacity as a temporary structure. There is no need to treat the foundation or set up temporary equipment, which greatly reduces the temporary construction cost.
[0014] (2) The equipment provided by the utility model is assembled from trusses, which is easy to disassemble and can be reused. It has a simple structure, clear force transmission, and convenient operation, and has a prospect of wide promotion. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to make the content of the utility model easier to understand, the utility model is further described in detail below according to specific embodiments and in conjunction with the accompanying drawings, wherein
[0016] Figure 1 It is a structural schematic diagram of the utility model.
[0017] Figure 2 It is a structural schematic diagram of the utility model from another angle.
[0018] The reference numerals in the accompanying drawings are:
[0019] 1-main frame; 2-suspension beam; 3-hook; 4-spool; 5-counterweight; 6-handle; 7-universal wheel; 8-handle. DETAILED DESCRIPTION
[0020] To illustrate the features of the present invention, the present invention is further described below with reference to the accompanying drawings and embodiments.
[0021] Example:
[0022] See also Figure 1 to Figure 2 The present embodiment provides a transport trolley for dismantling a concrete bridge, comprising a main frame 1, a suspension beam 2 and a hook 3, wherein the suspension beam 2 is arranged on a side of the main frame 1, the hook 3 is arranged on an outer end of the suspension beam 2, a bobbin 4 is arranged on an upper end of the hook 3, and the bobbin 4 is rotatably arranged on the suspension beam 2, specifically, the bobbin 4 is rotatably arranged on both ends of the outermost rod of the suspension beam 2, and a handle 6 for easy rotation is arranged on the side of the bobbin 4.
[0023] The main frame 1 and the suspension beam 2 are composed of a truss structure. The suspension beam 2 is a triangular prism truss structure with a right triangle cross section. One right-angled side of the suspension beam 2 is fixedly connected to the main frame 1, and the other right-angled side is the upper side. A counterweight 5 is arranged in the main frame 1. In this embodiment, the counterweight 5 is arranged on the side of the center line of the main frame 1 away from the suspension beam 2. In order to ensure the integrity of the counterweight 5 and the main frame 1, the counterweight 5 used in this embodiment is a cast concrete block, and the concrete block is cast as a whole with the truss connecting rod. Through a streamlined structure, under the premise of ensuring the bearing capacity, the existing beam bearing capacity is used as a temporary structure, and there is no need to treat the foundation or set up temporary equipment, so that the temporary construction cost is greatly reduced.
[0024] In addition, this embodiment has made adaptive improvements based on technical problems discovered during actual application, including providing a plurality of universal wheels 7 at the bottom of the main frame 1 to facilitate the movement of the trolley; and providing handles 8 symmetrically on both sides of the top of the main frame 1 to facilitate the operator's use.
[0025] The equipment provided in this embodiment is assembled from trusses, a structure known for its stability and load-bearing capacity. The trusses are composed of a plurality of triangular units, which provide solid support through their geometric stability, so that the entire transport trolley exhibits excellent load-bearing characteristics when carrying heavy objects. And due to its high efficiency, economy and ease of operation, this transport trolley has a wide range of application potentials in bridge demolition and other heavy lifting operations. With the increasing emphasis on environmental protection and resource recycling in the construction industry, this detachable and reusable equipment will become more and more popular in the market and have long-term market competitiveness.
[0026] The above embodiments and drawings are only used to illustrate the technical solution of the utility model, and are not intended to limit the utility model. The utility model is described in detail with reference to the preferred embodiments. It should be understood by ordinary technicians in this field that the changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the utility model do not deviate from the purpose of the utility model and should also fall within the scope of protection of the claims of the utility model. Other related technical structures not fully disclosed in the utility model are prior art in the field.
Claims
1. A transport trolley for dismantling a concrete bridge, comprising a main frame (1), a suspension beam (2) and a hook (3), wherein the suspension beam (2) is arranged on the side of the main frame (1), the hook (3) is arranged at the outer end of the suspension beam (2), a bobbin (4) is arranged at the upper end of the hook (3), the bobbin (4) is rotatably arranged on the suspension beam (2), and a plurality of universal wheels (7) are arranged at the bottom end of the main frame (1); Features: The main frame (1) and the suspension beam (2) are composed of a truss structure; the suspension beam (2) is a triangular prism truss structure with a right-angled triangle cross-section; one right-angled side of the suspension beam (2) is fixedly connected to the main frame (1), and the other right-angled side is the upper side; a counterweight block (5) is arranged inside the main frame (1).
2. The concrete bridge dismantling transport vehicle according to claim 1 is characterized in that: The spool (4) is rotatably arranged on the two ends of the outermost rod of the suspension beam (2), and a handle (6) for easy rotation is arranged on the side of the spool (4).
3. The concrete bridge dismantling transport vehicle according to claim 1 is characterized in that: The counterweight block (5) is arranged on a side of the center line of the main frame (1) away from the suspension beam (2).
4. The concrete bridge dismantling transport vehicle according to claim 1 is characterized in that: The counterweight block (5) is a counterweight block with a variable height, and its height gradually decreases from a side away from the suspension beam (2) to a side of the suspension beam (2).
5. The concrete bridge dismantling transport vehicle according to claim 3 or 4, characterized in that: The counterweight block (5) is a cast concrete block, and the concrete block and the truss connecting rod are cast into one piece.
6. The concrete bridge dismantling transport vehicle according to claim 1 is characterized in that: Handles (8) are symmetrically arranged on both sides of the top of the main frame (1).
7. The concrete bridge dismantling transport vehicle according to claim 1 is characterized in that: A plurality of universal wheels (7) are arranged at the bottom end of the main frame (1).