Multi-row pile supporting structure for ground heightening

By setting up a high-position support structure and hydraulic rod mechanism at the edge of the foundation pit, the problem of insufficient support during the accumulation of the foundation pit edge in the prior art is solved, and the safety and stability of the foundation pit are improved.

CN222796446UActive Publication Date: 2025-04-25HUBEI ZHONGNAN GEOTECHNICAL ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421786012.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2025-04-25
Estimated Expiration
2034-07-25

AI Technical Summary

Technical Problem

When the existing vertical support system accumulates in the edge of the foundation pit, the original support system cannot meet the requirements of sufficient support, resulting in the deepening of the support depth of the foundation pit and the failure to meet the safety and stability requirements.

Method used

Multi-row pile support structure is adopted, including setting up a high-level support structure at the edge of the foundation pit, using high-level support piles to support the high-level soil layer accumulated in the earth, and actively controlling the force applied to the high-level support structure through the hydraulic rod mechanism to enhance the integrity of the support structure.

Benefits of technology

Through the installation of the high-position support structure, the possibility of the high-position soil layer moving towards the foundation pit is reduced, sufficient resistance is provided for foundation pit support, the safety and stability of the foundation pit is improved, and the safety of the surrounding environment of the foundation pit is protected.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222796446U_ABST
    Figure CN222796446U_ABST
Patent Text Reader

Abstract

The utility model discloses a multi-row pile supporting structure for ground heightening, and relates to the field of foundation pit supporting, the multi-row pile supporting structure for ground heightening comprises a foundation pit, a plurality of evenly distributed first supporting piles are fixed to the edge of the foundation pit, a first enclosing purlin is arranged on the edge of the foundation pit and fixedly connected with the plurality of first supporting piles, a plurality of supporting beams are fixed to the first enclosing purlin, and the supporting beams are fixedly connected with the first supporting piles. A heightening soil layer is arranged on the edge of the foundation pit, a high-position supporting structure is arranged on the first enclosing purlin, and a safety guardrail is installed on the heightening soil layer. When earthwork accumulation occurs on the edge of the foundation pit, a high-position supporting structure is arranged between the earthwork accumulation and the first supporting piles, the high-position supporting structure is used for supporting a high-position soil layer, higher than the edge of the foundation pit, of the earthwork accumulation, and then a safety fence is installed on the high-position soil layer. And therefore, the high-position supporting structure can support and block newly-added earthwork accumulation, and the safety and stability of the foundation pit are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of foundation pit support, and in particular to a multi-row pile support structure for raising the ground. Background Art

[0002] With the rapid development of urban construction, there are more and more deep foundation pit projects, and the construction difficulty is getting greater and greater. Various foundation pit support methods have emerged. Pile structure is widely used in the field of domestic deep foundation pit engineering due to its good deformation control effect, strong support structure stability and strong applicability.

[0003] Among the existing vertical support systems, the most common method is to use reinforced concrete piles for support. Generally, the location of the foundation pit is determined first, and then evenly distributed deep holes are drilled at the edge of the foundation pit area. Then, reinforced concrete piles are poured in the holes, and then the foundation pit is excavated.

[0004] At present, for foundation pit support projects with constructed vertical support systems, if there is an increase in ground elevation, such as earth accumulation caused by changes in development plans, new roads built in the surrounding area, etc., if the original vertical support pile structure design remains unchanged, the foundation pit support depth will be deepened, and the original support system will not be able to provide sufficient support. Utility Model Content

[0005] The purpose of the present application is to solve the problem raised in the above-mentioned background technology that if there is an increase in ground elevation, such as earth accumulation caused by changes in development plans, new roads built in the surrounding area, etc., if the original vertical support pile structure design remains unchanged, the foundation pit support depth will be deepened, and the original support system will be unable to provide sufficient support. The present application provides a multi-row pile support structure for increasing the ground elevation.

[0006] In order to achieve the above-mentioned purpose, this application specifically adopts the following technical solutions:

[0007] A multi-row pile support structure for raising the ground comprises a foundation pit, a plurality of evenly distributed support piles are fixed at the edge of the foundation pit, a perimeter purlin is arranged at the edge of the foundation pit, the perimeter purlin is fixedly connected to the plurality of support piles, a plurality of support beams are fixed on the perimeter purlin, a retaining wall is arranged on the side of the support piles away from the foundation pit, a raised soil layer is arranged at the edge of the foundation pit, a high-position support structure is arranged on the perimeter purlin, and a safety guardrail is installed on the raised soil layer.

[0008] By adopting the above technical solution, when earth accumulation appears at the edge of the foundation pit, an upper high-position support structure is set between the earth accumulation and a number of support piles, and the high-position support structure is used to block the high-position soil layer of the earth accumulation higher than the edge of the foundation pit, and then a safety guardrail is installed on the high-position soil layer, so that the high-position support structure can support the earth accumulation and improve the safety and stability of the foundation pit.

[0009] Furthermore, the high-position support structure includes a plurality of high-position support piles evenly arranged on one side of the increased soil layer, the high-position support piles penetrate into the edge of the foundation pit, a waist beam is fixed between the high-position support piles and support pile one, a surrounding purlin two is arranged on one side of the increased soil layer, the surrounding purlin two is fixedly connected to a plurality of high-position support piles, and the increased soil layer is supported by the high-position support piles.

[0010] By adopting the above technical scheme, evenly distributed high-position support piles are poured between the support piles and the elevated soil layer of the earth accumulation, so that the high-position support piles can support the high-position soil layer of the earth accumulation, thereby reducing the movement of the high-position soil layer toward the foundation pit, providing sufficient resistance for the foundation pit support, improving the protection of the environment around the foundation pit, and ensuring the safety and stability of the foundation pit.

[0011] Furthermore, a top support plate is slidably connected to the waist beam, connecting short beams are arranged at intervals on the waist beam, and a plurality of top support hydraulic rods are arranged at fixed intervals on the waist beam, and the telescopic ends of the top support hydraulic rods are fixedly connected to the top support plate.

[0012] By adopting the above technical scheme, the telescopic end of the top support hydraulic rod is used to drive the top support plate to contact the surrounding purlin one, so that the surrounding purlin one waist beam is further supported, and then the corresponding connecting short beam is installed according to the width between the surrounding purlin one and the waist beam, so that the connecting short beam can be used to connect the surrounding purlin one and the waist beam, and the supporting force is transmitted to the waist beam, thereby strengthening the integrity of the support structure. The hydraulic rod mechanism can actively control the force applied to the high-position support structure, effectively protect the safety of the surrounding environment of the foundation pit, and improve the safety and stability of the foundation pit.

[0013] In summary, the present application includes at least one of the following beneficial effects:

[0014] 1. In the present application, when soil accumulation occurs at the edge of the foundation pit, firstly, evenly distributed high-position support piles are poured between the support piles 1 and the increased soil layer of the earth accumulation, so that the high-position support piles support the high-position soil layer of the earth accumulation, and then the upper surrounding purlin 2 is fixed on a number of evenly distributed high-position support piles, and the surrounding purlin 2 is used to strengthen the stability of the high-position support piles, and then the upper waist beam is fixed on the side of the high-position support piles facing the pit, and the waist beam is used to further restrict the high-position support piles, thereby achieving the purpose of reducing the movement of the high-position soil layer toward the foundation pit, providing sufficient resistance for the foundation pit support, and improving the safety and stability of the foundation pit.

[0015] 2. In the present application, a number of top support hydraulic rods are fixed on the waist beam, and then a top support plate is fixed on the telescopic end of the top support hydraulic rod. Then, the telescopic end of the top support hydraulic rod is used to drive the top support plate to contact the surrounding purlin one, so that the surrounding purlin one further supports the waist beam, and then the corresponding connecting short beam is installed according to the width between the surrounding purlin one and the waist beam, thereby achieving the purpose of actively controlling the deformation of the high-position support structure as needed, improving the protection of the surrounding environment of the foundation pit, and enhancing the safety and stability of the support structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a first three-dimensional structural schematic diagram of the support structure in this application;

[0017] Figure 2 This application Figure 1 Enlarged schematic diagram at point A in the middle.

[0018] Description of reference numerals:

[0019] 1. Foundation pit; 2. One supporting pile; 3. One purlin; 4. Support beam; 5. Retaining wall; 6. High-position supporting structure; 61. High-position supporting pile; 62. Two purlins; 63. Waist beam; 64. Connecting short beam; 65. Top support plate; 66. Top support hydraulic rod; 7. Safety guardrail; 8. Increase soil layer. DETAILED DESCRIPTION

[0020] The following is combined with Figure 1 —2 Provide further details of this application.

[0021] The embodiment of the present application discloses a multi-row pile support structure for raising the ground.

[0022] Reference Figure 1 and Figure 2 A multi-row pile support structure for raising the ground comprises a foundation pit 1, a plurality of evenly distributed support piles 2 are fixed at the edge of the foundation pit 1, a perimeter purlin 3 is arranged at the edge of the foundation pit 1, the perimeter purlin 3 is fixedly connected to the plurality of support piles 2, a plurality of support beams 4 are fixed on the perimeter purlin 3, a retaining wall 5 is arranged on the side of the support piles 2 away from the foundation pit 1, a raised soil layer 8 is arranged at the edge of the foundation pit 1, a high-position support structure 6 is arranged on the perimeter purlin 3, and a safety guardrail 7 is installed on the raised soil layer 8.

[0023] After the construction of the support piles 2 is completed in the foundation pit 1, when the site conditions change and earthwork piles appear at the edge of the foundation pit 1, an upper high-position support structure 6 is set between the earthwork piles and the plurality of support piles 2, and the high-position support structure 6 is used to block the earthwork piles above the edge of the foundation pit 1. At the same time, a purlin 3 is constructed on the plurality of support piles 2 as the earthwork is excavated, and then the purlin 3 is supported by the support beam 4, and then a retaining wall 5 is constructed on the side of the plurality of support piles away from the foundation pit 1, and the retaining wall 5 is used to block the water in the soil, and then a safety guardrail 7 is installed on the high soil layer to support the edge of the foundation pit 1. That is, when earthwork increases at the edge of the foundation pit 1, an upper high-position support structure 6 is set between the original support piles 2 and the earthwork piles, so that the high-position support structure 6 can support the earthwork piles, reduce the possibility of earthwork falling into the foundation pit 1, improve the safety and stability of the foundation pit 1, and protect the safety of the surrounding environment of the foundation pit 1.

[0024] Reference Figure 1 and Figure 2 The high-position support structure 6 includes a plurality of high-position support piles 61 evenly arranged on one side of the increased soil layer 8. The high-position support piles 61 penetrate into the edge of the foundation pit 1. A waist beam 63 is fixed between the high-position support piles 61 and the support piles 1 2. A purlin 2 62 is arranged on one side of the increased soil layer 8. The purlin 2 62 is fixedly connected to the plurality of high-position support piles 61. The increased soil layer 8 is supported by the high-position support piles 61.

[0025] In addition, a top support plate 65 is slidably connected to the waist beam 63, connecting short beams 64 are arranged at intervals on the waist beam 63, and a number of top support hydraulic rods 66 are arranged at fixed intervals on the waist beam 63. The telescopic ends of the top support hydraulic rods 66 are fixedly connected to the top support plate 65. Pads can be added between the waist beam 63 and the connecting short beams 64 as needed to fill the gaps generated after the top support hydraulic rods 66 are loaded, thereby ensuring stable force transmission.

[0026] When soil is piled up at the edge of the foundation pit 1, firstly, evenly distributed high-position support piles 61 are poured between the support piles 1 2 and the increased soil layer 8 of the earthwork accumulation, so that the high-position support piles 61 can support the high-position soil layer of the earthwork accumulation, and then the upper surrounding purlins 62 are fixed on a plurality of evenly distributed high-position support piles 61, and the surrounding purlins 62 are used to strengthen the stability of the high-position support piles 61, and then the upper waist beam 63 is fixed on one side of the high-position support piles 61, and the waist beam 63 is used to further restrict the high-position support piles 61, and then a plurality of top support hydraulic rods 66 are fixed on the waist beam 63, and then the top support plate 65 is fixed on the telescopic end of the top support hydraulic rod 66, and then the top support plate 65 is used to fix the top support plate 65. The telescopic end of the top support hydraulic rod 66 drives the top support plate 65 to contact the surrounding purlin 3, so that the surrounding purlin 3 further supports the waist beam 63, and then the corresponding connecting short beam 64 is installed according to the width between the surrounding purlin 3 and the waist beam 63. The connecting short beam 64 is used to increase the integrity between the surrounding purlin 3 and the waist beam 63. By setting a number of high-position support piles 61 between the high-position soil layer of the earth accumulation and the support pile 2, the high-position support piles 61 are used to support the high-position soil layer, thereby reducing the movement of the high-position soil layer toward the foundation pit 1, providing sufficient resistance for the support of the foundation pit 1, improving the stability and safety of the use of the foundation pit 1, and protecting the safety of the surrounding environment of the foundation pit 1.

[0027] Working principle: After the excavation of the foundation pit 1 is completed, a number of evenly distributed support piles 2 are inserted at the edge of the foundation pit 1, and then the upper purlin 3 is fixed on the several support piles 2, and then the support beam 4 is used to support the purlin 3, and then the retaining wall 5 is constructed on the side of the several support piles away from the foundation pit 1, and the evenly distributed high-position support piles 61 are poured between the support piles 2 and the increased soil layer 8 of the earthwork accumulation, so that the high-position support piles 61 support the high-position soil layer of the earthwork accumulation, and then the upper purlin 2 62 is fixed on the several evenly distributed high-position support piles 61, and the purlin 2 62 is used to strengthen the stability of the high-position support piles 61. Then, fix a waist beam 63 on one side of the high-position supporting pile 61, use the waist beam 63 to further restrict the high-position supporting pile 61, and then fix a number of top support hydraulic rods 66 on the waist beam 63, and then fix a top support plate 65 on the telescopic end of the top support hydraulic rod 66, and then use the telescopic end of the top support hydraulic rod 66 to drive the top support plate 65 to contact the surrounding purlin 3, so that the surrounding purlin 3 further supports the waist beam 63, and then according to the width between the surrounding purlin 3 and the waist beam 63, install the corresponding connecting short beam 64, and use the connecting short beam 64 to increase the integrity between the surrounding purlin 3 and the waist beam 63 to complete the support of the foundation pit 1.

Claims

1. A multi-row pile support structure for raising the ground, comprising a foundation pit (1), characterized in that: A plurality of evenly distributed support piles (2) are fixed at the edge of the foundation pit (1); a purlin (3) is arranged at the edge of the foundation pit (1); the purlin (3) is fixedly connected to the plurality of support piles (2); a plurality of support beams (4) are fixed on the purlin (3); a retaining wall (5) is arranged on the side of the support piles (2) away from the foundation pit (1); a heightened soil layer (8) is arranged at the edge of the foundation pit (1); a high-position support structure (6) is arranged on the purlin (3); and a safety guardrail (7) is arranged on the high-position support structure (6).

2. A multi-row pile support structure for ground elevation according to claim 1, characterized in that: The high-position support structure (6) comprises a plurality of high-position support piles (61) evenly arranged on one side of the elevated soil layer (8), the high-position support piles (61) extending deep into the edge of the foundation pit (1), a waist beam (63) being fixed between the high-position support piles (61) and support pile one (2), a second surrounding purlin (62) being arranged on one side of the elevated soil layer (8), the second surrounding purlin (62) being fixedly connected to the plurality of high-position support piles (61), and the elevated soil layer (8) being supported by the high-position support piles (61).

3. A multi-row pile support structure for ground elevation according to claim 2, characterized in that: A supporting plate (65) is slidably connected to the waist beam (63), connecting short beams (64) are arranged at intervals on the waist beam (63), and a plurality of supporting hydraulic rods (66) are arranged at fixed intervals on the waist beam (63), and the telescopic ends of the supporting hydraulic rods (66) are fixedly connected to the supporting plate (65).