Temporary supporting auxiliary device capable of being turned over and used for steel structure engineering

By designing a turnaroundable temporary support auxiliary device for steel structure engineering, the existing temporary support system has been solved for complex operation, safety hazards and resource waste, and the effects of convenient operation, high safety and resource conservation are achieved.

CN222797153UActive Publication Date: 2025-04-25CHINA CONSTR FOURTH ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421458789.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2025-04-25
Estimated Expiration
2034-06-25

AI Technical Summary

Technical Problem

The temporary support systems in existing steel structure projects have problems such as complex operation, safety hazards, limited stiffness and waste of resources.

Method used

A turnaround temporary support auxiliary device is designed, including multiple steel pillars, connecting plates, steel cross beams, steel inclined beams and work-formed steel. The erection process is simplified by pre-assembly and high-strength bolted connections, and the adaptability and stability are improved by height adjustment of the cylinder and top steel sheets.

Benefits of technology

It achieves temporary support effects with convenient operation, high safety, resource conservation and strong adaptability, reducing construction risks and costs, and reducing resource waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222797153U_ABST
    Figure CN222797153U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of temporary supporting, in particular to a temporary supporting auxiliary device capable of being turned over and used for steel structure engineering, which comprises a plurality of steel supporting columns, at least three connecting plates are arranged on one side of each steel supporting column, and a base of each steel supporting column is fixed with the ground through expansion bolts. Corresponding upper, middle and lower parts between two adjacent steel struts are connected with the steel cross beams through connecting plates and fasteners; every two adjacent steel cross beams are connected through a connecting plate, a fastener and a steel oblique beam. I-shaped steel is welded at the tops of the adjacent steel struts. The construction efficiency is improved, and the construction period is shortened. The construction safety is improved, and the accident risk is reduced. The material waste is reduced, and the construction cost is reduced. And the method is green and environment-friendly and meets the sustainable development requirement. By using the temporary supporting auxiliary device, the temporary supporting problem in the steel structure engineering construction process can be effectively solved, the construction efficiency and quality are improved, and the construction cost and risk are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of temporary support, and more specifically to a temporary support auxiliary device which can be circulated and used in steel structure engineering. Background Art

[0002] In the construction of building structures, steel structures are widely used due to their high strength, large span, good seismic resistance and other advantages. However, during the construction of steel structures, temporary supports are required for auxiliary fixation to ensure the safety and accuracy of the construction. The traditional solution is usually to use steel pipe scaffolding for temporary support. This method is to connect multiple steel pipes and connectors through fasteners and rotating fasteners. There are certain requirements at the connection nodes, and the connection process is complicated to form a stable support structure. However, the existing steel pipe scaffolding temporary support system has the following main problems:

[0003] 1. Due to the uneven skills of workers who temporarily set up scaffolding, they often make repeated corrections, which not only delays the construction period but also poses safety hazards;

[0004] Second, the rigidity of steel pipe scaffolding is limited, the requirements for technical control are high, the quality and safety risks of the installation and disassembly process are high, and it is time-consuming and labor-intensive;

[0005] 3. Traditional scaffolding systems are usually discarded after use, resulting in waste of resources and environmental pollution.

[0006] Therefore, there is an urgent need to provide a temporary support frame with low operating difficulty, high safety and convenient turnover to replace the existing scaffolding. Utility Model Content

[0007] Therefore, the purpose of the utility model is to provide a temporary support auxiliary device that can be used in steel structure projects, so as to solve the above-mentioned problems existing in the temporary support of existing steel structure projects using temporary scaffolding.

[0008] The utility model provides a temporary support auxiliary device that can be used in steel structure engineering, including:

[0009] A plurality of steel pillars, each of which has at least three connecting plates on one side, and its base is fixed to the ground by expansion bolts;

[0010] A steel cross beam, wherein the upper, middle and lower parts of two adjacent steel pillars are connected to the steel cross beam through the connecting plate and fasteners;

[0011] Steel oblique beams, each two adjacent steel cross beams are connected to the steel oblique beams through the connecting plates and fasteners;

[0012] I-shaped steel, the I-shaped steel is welded to the top of the adjacent steel pillars.

[0013] Furthermore, the utility model provides a temporary support auxiliary device that can be used cyclically in steel structure projects, and also includes a height-adjusting cylinder, which is welded between the top of the steel support and the I-shaped steel, and the height of which is determined according to the operation requirements.

[0014] Furthermore, the utility model also includes a top steel sheet, and the top steel sheet is fixed to the top of the steel pillar.

[0015] Furthermore, the top steel sheet and the steel support column are connected by using first high-strength bolts.

[0016] Furthermore, the connecting plate includes a first connecting plate and a second connecting plate, the first connecting plate is welded to the upper and bottom parts of one side of the steel pillar, and at least four first bolt holes are reserved thereon, corresponding to the corresponding second bolt holes on the steel cross beam, and are connected and fixed by second high-strength bolts; the second connecting plate is welded to the middle part of one side of the steel pillar, and at least six third bolt holes are reserved thereon, corresponding to the fourth bolt holes on the steel inclined beam, and are also fixed by second high-strength bolts, and the fastener is a second high-strength bolt.

[0017] Furthermore, the connecting plate is a rectangular connecting steel plate, and the corners are cut off to form the connecting position.

[0018] Furthermore, the base of the steel pillar is a supporting steel plate.

[0019] It can be seen from the above technical solution that compared with the prior art, the utility model has the following beneficial effects:

[0020] 1. Convenient operation: The utility model can pre-assemble and weld the steel pillars, connecting plates and supporting steel plates. Only high-strength bolts and expansion bolts are needed for connection and fixing on site. The operation is simple, saving a lot of manpower and time. It does not require high experience of operators, and does not require repeated rectification, which improves the efficiency of temporary erection.

[0021] 2. Strong and durable: The utility model adopts high-strength steel and bolts, making the whole structure strong and durable, able to withstand heavy pressure and impact, ensuring the safety of construction.

[0022] 3. Reusable: The design of the utility model takes into account the possibility of reuse. After use, it can be cut and dismantled to avoid waste of resources and environmental pollution.

[0023] 4. Strong adaptability: The design of the utility model can select the height and quantity of the height-adjustable cylinders according to actual needs to meet different construction needs and has strong adaptability.

[0024] 5. Energy saving: The utility model has a simple design, saves materials, consumes less energy during production and use, and is in line with the current green environmental protection concept. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0026] Figure 1 A schematic diagram of the structure of a temporary support auxiliary device provided by the utility model that can be used cyclically in steel structure engineering;

[0027] Figure 2 for Figure 1 Bottom view of

[0028] Figure 3 The structural diagram of the steel support and the connecting plate is shown;

[0029] Figure 4 The schematic diagram of the connection between the second connecting plate, the steel cross beam, the steel inclined beam and the second high-strength bolt is shown. DETAILED DESCRIPTION

[0030] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.

[0031] During the construction of building structure projects, steel structure projects need to use temporary supports for auxiliary fixation. During the construction process, existing steel pipe scaffolding is generally used for erection. Since the workers' skills of the temporary scaffolding are uneven, they often have to make repeated corrections, which not only delays the construction period but also poses a safety hazard. In addition, the steel pipe scaffolding itself has limited rigidity and requires strict technical control. The quality and safety risks during the installation and disassembly process are relatively large, time-consuming and labor-intensive. At today's construction sites, a scaffolding with low operating difficulty, high safety and convenient turnover is needed.

[0032] In view of this, the utility model provides a temporary support auxiliary device that can be used in steel structure engineering. Figure 1-4, including: multiple steel pillars 1, each of which has at least three connecting plates on one side, and its base is fixed to the ground by expansion bolts 4; steel beams 2, the upper, middle and lower corresponding parts between two adjacent steel pillars 1 are connected to the steel beams 2 by the connecting plates and fasteners; steel oblique beams 3, every two adjacent steel beams 2 are connected to the steel oblique beams 3 by the connecting plates and fasteners; I-shaped steels 7, the I-shaped steels 7 are welded to the tops of adjacent steel pillars 1.

[0033] In the above embodiment, the steel support 1, the connecting plate and the base can be pre-welded together. When splicing on site, they only need to be fixed to the ground by expansion bolts 4, and the steel cross beams, steel inclined beams and the connecting plates are fixed by fasteners, which reduces the difficulty of operation and can be operated without experienced workers. The rigidity is guaranteed after splicing, and there is no need for repeated rectification, which reduces working hours, improves erection efficiency, and improves safety.

[0034] In the description of the present invention, it is necessary to understand that the terms "upper", "middle", "lower", etc., indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0035] In one embodiment of the utility model, a height adjustment cylinder 6 is further included, which is welded between the top of the steel support 1 and the I-shaped steel 7, and the height thereof is cut according to the operation requirements. Thus, the operation flexibility of different requirements is improved, and the use in more scenarios is met.

[0036] In another embodiment of the utility model, if the height is insufficient, a top steel sheet 5 may be further included, wherein the top steel sheet 5 is fixed to the top of the steel pillar 1, and the top steel sheet 5 is connected to the steel pillar 1 by four first high-strength bolts.

[0037] In a specific embodiment of the present invention, see the attached Figure 3 and 4 The connecting plate includes a first connecting plate 11 and a second connecting plate 12. The first connecting plate 11 is welded to the upper and bottom of one side of the steel pillar 1, and at least four first bolt holes are reserved thereon, corresponding to the corresponding second bolt holes on the steel beam 2, and connected and fixed by the second high-strength bolts 8; the second connecting plate 12 is welded to the middle of one side of the steel pillar 1, and at least six third bolt holes are reserved thereon, corresponding to the fourth bolt holes on the steel inclined beam 3, and also fixed by the second high-strength bolts 8, and the fastener is the second high-strength bolt 8. Thus, the steel beam and the steel inclined beam are smoothly connected by the second high-strength bolts 8, and the connection strength is improved.

[0038] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0039] Advantageously, see Appendix Figure 3 and 4 The connecting plate is a rectangular connecting steel plate, and the corners are cut to form the connecting position. The installation position formed by the cut corners just corresponds to the connecting direction of the steel beam to be connected, which not only has a prompting effect, but also reduces unnecessary materials and reduces weight.

[0040] In the above embodiments, the base of the steel pillar 1 is a supporting steel plate, the area of ​​the supporting steel plate is larger than the bottom area of ​​the steel pillar, and bolt holes are provided on the supporting steel plate to connect expansion bolts for easy fixing to the ground.

[0041] It is worth noting that the high-strength bolts in the present invention generally refer to bolts that are grade 8.8 or above, are made of low-carbon alloy steel or medium-carbon steel, and have been heat-treated (quenched and tempered).

[0042] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0043] Specifically, when or before erection, first weld the steel support 1, the connecting plate, and the base together in advance. The height of a single set of steel supports can be 4420mm, the length of the steel beam can be 1537mm, the length of the steel inclined beam can be 2325mm, and the supporting steel plate can be 500mm*500mm*10mm with 4 bolt holes reserved. If the height is insufficient, continue to install a set of top steel plates on the upper part, and use 4 second high-strength bolts for connection.

[0044] Then, after the single set of steel pillars are assembled, they are placed on the working ground, and 4 M20 expansion bolts are used to fix the bottom support steel plate to the working surface.

[0045] According to the operation requirements, install the height-adjusting cylinder and weld it to the top steel plate of the steel support. After the installation is completed, use I-shaped steel 400*400*13*21 to weld and connect it to the height-adjusting cylinder.

[0046] In the above steps, the steel pillars are assembled and welded as a whole, and then set up in single or double groups according to the requirements of the fixed structure. Before construction, the steel pillars are placed on the working ground and fixed with M20 expansion bolts. Finally, the height adjustment cylinders are installed according to the height requirements and cut and removed after use.

[0047] The utility model improves construction efficiency and shortens construction period. It improves construction safety and reduces accident risks. It reduces material waste and construction costs. It is green and environmentally friendly and meets the requirements of sustainable development. Through the use of this temporary support auxiliary device, the temporary support problem in the construction process of steel structure engineering can be effectively solved, the construction efficiency and quality can be improved, and the construction cost and risk can be reduced.

[0048] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine different embodiments or examples described in this specification.

[0049] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A temporary support auxiliary device that can be used in steel structure engineering, characterized in that: include: A plurality of steel pillars (1), each of the steel pillars (1) having at least three connecting plates on one side, and a base thereof being fixed to the ground via expansion bolts (4); A steel crossbeam (2), wherein the upper, middle and lower portions of two adjacent steel pillars (1) are connected to the steel crossbeam (2) via the connecting plates and fasteners; Steel oblique beams (3), each two adjacent steel cross beams (2) are connected to the steel oblique beams (3) via the connecting plates and fasteners; I-shaped steel (7), the I-shaped steel (7) is welded to the top of the adjacent steel pillars (1).

2. The temporary support auxiliary device that can be used for steel structure engineering according to claim 1 is characterized in that: It also includes a height-adjusting cylinder (6), which is welded between the top of the steel support (1) and the I-shaped steel (7), and the height of which is determined according to the operation requirements.

3. The temporary support auxiliary device that can be used for steel structure engineering according to claim 2 is characterized in that: It also comprises a top steel sheet (5), which is fixed to the top of the steel pillar (1).

4. The temporary support auxiliary device that can be used for steel structure engineering according to claim 3 is characterized in that: The top steel sheet (5) and the steel support column (1) are connected by first high-strength bolts.

5. A temporary support auxiliary device that can be used in steel structure engineering according to any one of claims 1 to 4, characterized in that: The connecting plate comprises a first connecting plate (11) and a second connecting plate (12), wherein the first connecting plate (11) is welded to the upper and bottom parts of one side of the steel pillar (1), and is provided with at least four first bolt holes corresponding to the second bolt holes on the steel beam (2), and is connected and fixed by second high-strength bolts (8); the second connecting plate (12) is welded to the middle part of one side of the steel pillar (1), and is provided with at least six third bolt holes corresponding to the fourth bolt holes on the steel inclined beam (3), and is also fixed by second high-strength bolts (8), and the fastener is a second high-strength bolt (8).

6. A temporary support auxiliary device that can be used in steel structure engineering according to any one of claims 1 to 4, characterized in that: The connecting plate is a rectangular connecting steel plate, and the corners are cut off to form the connecting position.

7. A temporary support auxiliary device that can be used in steel structure engineering according to any one of claims 1 to 4, characterized in that: The base of the steel support column (1) is a supporting steel plate.