Steel-concrete composite beam flange plate supporting bracket

By designing a triangular support structure bracket for the construction of wing plates of steel-concrete composite beams and using screws to fix them on the side of the steel beam, the problems of complex support structure and occupying ground space in the prior art are solved, and the effect of convenient road access and construction under the bridge is achieved.

CN222809871UActive Publication Date: 2025-04-29中交(青岛)城市建设有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322943535.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-31
Publication Date
2025-04-29
Estimated Expiration
2033-10-31

AI Technical Summary

Technical Problem

In the prior art, the support structure of the steel-concrete combination beam flange plate during casting construction is complex and requires the use of ground space, which cannot ensure the normal passage of the road under the bridge.

Method used

A steel-concrete combined beam flange plate support bracket is designed, and horizontal connectors, vertical connectors and oblique connectors are fixedly connected in sequence to form a triangular support structure. The first screw and the second screw are used to fix the triangular support structure on the side of the steel beam in a cantilever manner to support the flange plate casting formwork.

Benefits of technology

It does not occupy the ground space under the bridge, ensures normal passage of roads under the bridge, and is more convenient to erect and disassemble, solving the problems of complex bracket structure and occupying ground space.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222809871U_ABST
    Figure CN222809871U_ABST
Patent Text Reader

Abstract

The utility model discloses a steel-concrete composite beam flange plate supporting bracket which comprises a horizontal connecting piece, a vertical connecting piece and an inclined connecting piece, and the horizontal connecting piece, the vertical connecting piece and the inclined connecting piece are fixedly connected in sequence to form a triangular supporting structure. A first screw rod is fixed to the upper end of the triangular supporting structure in the vertical direction, and the first screw rod is used for penetrating through a reserved hole in a steel beam top plate and being fixed; a casing pipe is fixed to the lower end of the triangular supporting structure in the horizontal direction, a second screw rod is arranged in the casing pipe in a penetrating mode, the end of the second screw rod is used for abutting against a steel box girder web, a first nut is fastened to the second screw rod, the first nut is located between the casing pipe and the steel box girder web, and the first nut abuts against the end of the casing pipe. The problems that in the prior art, during pouring construction of a steel-concrete composite beam flange plate, a support is complex in structure and needs to occupy the ground space, and normal passing of a road under a bridge cannot be guaranteed are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge construction, and in particular to a flange plate support bracket for a steel-concrete composite beam. Background Art

[0002] During the construction of municipal elevated bridges, the casting of flange plates must not only consider the construction itself, but also ensure smooth traffic under the bridge.

[0003] However, in the related art, a full-height support is erected from the ground as a bracket for the flange plate casting construction. This structure is complicated to erect and occupies ground space, and cannot ensure the passage of the road under the bridge. Therefore, a bracket that is easy to operate is needed to ensure the casting construction of the flange plate of the steel-concrete composite beam. Utility Model Content

[0004] The main purpose of the present application is to provide a steel-concrete composite beam flange plate support bracket to solve the problem in the related art that the support structure of the steel-concrete composite beam flange plate during casting construction is complex, and it requires ground space and cannot ensure normal traffic on the road under the bridge.

[0005] In order to achieve the above-mentioned object, the present application provides a steel-concrete composite beam flange plate support bracket, comprising: a horizontal connector, a vertical connector and an oblique connector, wherein the horizontal connector, the vertical connector and the oblique connector are fixedly connected in sequence to form a triangular support structure;

[0006] A first screw is vertically fixed to the upper end of the triangular support structure, and the first screw is used to pass through the reserved hole of the steel beam top plate and be fixed;

[0007] A sleeve is fixed to the lower end of the triangular support structure in the horizontal direction, a second screw is passed through the sleeve, an end of the second screw is used to abut against the web of the steel box girder, a first nut is fastened on the second screw, the first nut is located between the sleeve and the web of the steel box girder, and the first nut abuts against the end of the sleeve.

[0008] Furthermore, it also includes a first connecting member, a connecting sheet and an isolation column;

[0009] The first connecting member is arranged at the upper end of the vertical connecting member and is opposite to the horizontal connecting member. Two isolation columns are provided, one of which is located between the first connecting member and the vertical connecting member and is fixed by welding, and the other is located between the first connecting member and the horizontal connecting member and is fixed by welding, so that a screw installation gap is formed between the first connecting member and the horizontal connecting member;

[0010] The connecting pieces are provided in two and are respectively fixed at the upper and lower ends of the first connecting member;

[0011] The connecting plate is provided with a connecting hole, the connecting hole corresponds to the screw installation gap, and the lower end of the first screw is fixed after passing through the connecting hole and the screw installation gap.

[0012] Furthermore, a second connecting member is fixed on one end of the second screw rod facing the web of the steel box girder, and a connecting groove is formed on the second connecting member on one side facing the web of the steel box girder, and a square timber is installed in the connecting groove, and the end surface of the square timber is used to abut against the web of the steel box girder.

[0013] Furthermore, the lower end of the first screw rod passes through the connecting plate and is locked by a second nut, and the upper end of the first screw rod passes through the top plate of the steel beam and is locked by the second nut.

[0014] Furthermore, the vertical connectors, the horizontal connectors and the oblique connectors are all made of channel steel, and the vertical connectors, the horizontal connectors and the oblique connectors are fixed by welding.

[0015] Furthermore, the length of the horizontal connecting member is 1.9 m, the length of the vertical connecting member is 1.2 m, and the length of the oblique connecting member is 1.98 m.

[0016] In the embodiment of the present application, a horizontal connector, a vertical connector and an oblique connector are provided, and the horizontal connector, the vertical connector and the oblique connector are fixedly connected in sequence to form a triangular support structure; a first screw is fixed vertically on the upper end of the triangular support structure, and the first screw is used to pass through the reserved hole of the steel beam top plate and be fixed; a sleeve is fixed horizontally on the lower end of the triangular support structure, and a second screw is passed through the sleeve, and the end of the second screw is used to abut against the web of the steel box beam, and a first nut is fastened on the second screw, and the first nut is located between the sleeve and the web of the steel box beam, and the first nut abuts against the end of the sleeve, so as to achieve the purpose of fixing the triangular support structure on the side of the steel beam in a cantilevered manner and using the triangular support structure to support the flange plate casting template, thereby achieving the technical effect of not occupying the ground space under the bridge, ensuring the normal traffic of the road under the bridge, and convenient erection and disassembly, thereby solving the problem that the support structure of the flange plate of the steel-concrete composite beam in the related art is complex during the casting construction, and the ground space needs to be occupied, and the normal traffic of the road under the bridge cannot be guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:

[0018] Figure 1 is a schematic diagram of the structure according to an embodiment of the present application;

[0019] Figure 2 is a schematic diagram of a partial top view of the structure according to an embodiment of the present application;

[0020] Among them, 1 is a triangular support structure, 11 is a horizontal connector, 12 is an oblique connector, 13 is a vertical connector, 2 is a steel box beam web, 3 is a steel beam top plate, 4 is a second nut, 5 is a first screw, 6 is a connecting plate, 7 is a second screw, 8 is a sleeve, 9 is a first nut, 20 is a square wood, 21 is a second connector, 22 is a spacer column, 23 is a screw installation gap, 24 is a first connector, and 25 is a connecting hole. DETAILED DESCRIPTION

[0021] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0022] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the numbers used in this way can be interchanged where appropriate, so as to describe the embodiments of the present application described herein.

[0023] In this application, the terms "upper", "lower", "inner", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.

[0024] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.

[0025] In addition, the terms "disposed", "provided with", "connected", "fixed" and the like should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to the specific circumstances.

[0026] In addition, the term "plurality" shall mean two or more.

[0027] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0028] In the related art, a method of setting up a full-height support from the ground is adopted as a bracket for the flange plate casting construction. However, this structure is complicated to set up and occupies ground space, and cannot ensure the passage of the road under the bridge. Therefore, a bracket that is easy to operate is needed to ensure the casting construction of the flange plate of the steel-concrete composite beam.

[0029] To solve the above technical problems, Figure 1 to Figure 2 As shown, the embodiment of the present application provides a steel-concrete composite beam flange plate support bracket, comprising: a horizontal connector 11, a vertical connector 13 and an oblique connector 12, wherein the horizontal connector 11, the vertical connector 13 and the oblique connector 12 are fixedly connected in sequence to form a triangular support structure 1;

[0030] A first screw rod 5 is vertically fixed to the upper end of the triangular support structure 1, and the first screw rod 5 is used to pass through the reserved hole of the steel beam top plate 3 and be fixed;

[0031] A sleeve 8 is fixed to the lower end of the triangular support structure 1 in the horizontal direction, and a second screw rod 7 is passed through the sleeve 8. The end of the second screw rod 7 is used to abut against the steel box girder web 2. A first nut 9 is fastened on the second screw rod 7. The first nut 9 is located between the sleeve 8 and the steel box girder web 2, and the first nut 9 abuts against the end of the sleeve 8.

[0032] In this embodiment, the horizontal connector 11, the vertical connector 13 and the oblique connector 12 are connected end to end to form a triangular support structure 1, wherein the horizontal connector 11 serves as a support structure in direct contact with the flange plate casting template. In order to enable the entire triangular support structure 1 to be fixed on the steel beam in a cantilevered manner, in this embodiment, a first screw 5 is fixed on the upper end of the triangular support structure 1, and a corresponding reserved hole matching the first screw 5 is reserved on the top plate 3 of the steel beam. The first screw 5 can be fixed after passing through the reserved hole vertically, and can be fixed by screwing on a nut, so that the triangular support structure 1 can be fixed on the top plate 3 of the steel beam. In order to make the triangular support structure 1 more stable when subjected to stress, it is necessary to support it laterally. For this purpose, a sleeve 8 is fixed at the lower end of the triangular support structure 1 in this embodiment. A second screw 7 is inserted into the sleeve 8. The second screw 7 is arranged in the horizontal direction, and one end of the second screw 7 can be against the steel box beam web 2. Therefore, when the triangular support structure 1 is subjected to downward pressure, the second screw 7 can be used to transfer the pressure to the steel box beam web 2, and the steel box beam web 2 supports it, thereby improving stability. At the same time, under the tightening action of the first nut 9, the first screw 5 cannot move in the direction away from the steel box beam web 2, and the transverse slope of the horizontal connector 11 can be fine-tuned by turning the first nut 9.

[0033] This embodiment achieves the purpose of fixing the triangular support structure 1 on the side of the steel beam in a cantilevered manner and using the triangular support structure 1 to support the flange plate casting formwork, thereby achieving the technical effect of not occupying the ground space under the bridge, ensuring the normal traffic of the road under the bridge, and being relatively convenient for erection and disassembly, thereby solving the problem in the related technology that the support structure of the flange plate of the steel-concrete composite beam during casting construction is complex, requires occupying ground space, and cannot ensure the normal traffic of the road under the bridge.

[0034] To facilitate the installation of the first screw rod 5, the support bracket in this embodiment further includes a first connecting member 24, a connecting piece 6 and an isolation column 22;

[0035] The first connecting member 24 is disposed at the upper end of the vertical connecting member 13 and is opposite to the horizontal connecting member 11. Two isolation columns 22 are provided, one of which is located between the first connecting member 24 and the vertical connecting member 13 and is fixed by welding, and the other is located between the first connecting member 24 and the horizontal connecting member 11 and is fixed by welding, so that a screw installation gap 23 is formed between the first connecting member 24 and the horizontal connecting member 11;

[0036] There are two connecting pieces 6 and they are fixed to the upper and lower ends of the first connecting member 24 respectively;

[0037] The connecting plate 6 is provided with a connecting hole 25 , which corresponds to the screw installation gap 23 . The lower end of the first screw 5 passes through the connecting hole 25 and the screw installation gap 23 and is then fixed.

[0038] In this embodiment, the isolation column 22 can be made of truncated steel bars, which is convenient for on-site production. The diameter of the isolation column 22 is slightly larger than the diameter of the first screw 5, so that a screw installation gap 23 that allows the first screw 5 to pass through can be formed between the first connector 24 and the horizontal connector 11. To facilitate the positioning of the first screw 5, a connecting piece 6 is welded and fixed at the upper and lower ends of the horizontal connector 11, and the connecting piece 6 can be a steel sheet. The first screw 5 can pass through the connecting hole 25 on the connecting piece 6 and be locked by a nut.

[0039] In order to prevent the end of the second screw 7 from directly applying pressure to the steel box girder web 2, resulting in paint peeling on the surface of the steel box girder web 2 and excessive local pressure, in this embodiment, a second connecting member 21 is fixed to one end of the second screw 7 facing the steel box girder web 2, and a connecting groove is formed on the second connecting member 21 on one side facing the steel box girder web 2, and a square timber 20 is installed in the connecting groove, and the end face of the square timber 20 is used to abut against the steel box girder web 2.

[0040] In one embodiment, the lower end of the first screw rod 5 passes through the connecting piece 6 and is locked by the second nut 4, and the upper end of the first screw rod 5 passes through the steel beam top plate 3 and is locked by the second nut 4. Further, the vertical connector 13, the horizontal connector 11 and the diagonal connector 12 are all made of channel steel, and the vertical connector 13, the horizontal connector 11 and the diagonal connector 12 are welded and fixed. Further, the length of the horizontal connector 11 is 1.9m, the length of the vertical connector 13 is 1.2m, and the length of the diagonal connector 12 is 1.98m.

[0041] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Within the spirit and principle of the present application, any modification, equivalent replacement, improvement, etc. made shall be included in the protection scope of the present application.

Claims

1. A steel-concrete composite beam flange plate support bracket, characterized in that: include: A horizontal connector, a vertical connector and an oblique connector, wherein the horizontal connector, the vertical connector and the oblique connector are fixedly connected in sequence to form a triangular support structure; A first screw is vertically fixed to the upper end of the triangular support structure, and the first screw is used to pass through the reserved hole of the steel beam top plate and be fixed; A sleeve is fixed to the lower end of the triangular support structure in the horizontal direction, a second screw is inserted into the sleeve, an end of the second screw is used to abut against the web of the steel box beam, a first nut is fastened on the second screw, the first nut is located between the sleeve and the web of the steel box beam, and the first nut abuts against the end of the sleeve; The steel-concrete composite beam flange plate support bracket also includes a first connecting member, a connecting piece and an isolation column; The first connecting member is arranged at the upper end of the vertical connecting member and is opposite to the horizontal connecting member. Two isolation columns are provided, one of which is located between the first connecting member and the vertical connecting member and is fixed by welding, and the other is located between the first connecting member and the horizontal connecting member and is fixed by welding, so that a screw installation gap is formed between the first connecting member and the horizontal connecting member; The connecting pieces are provided in two and are respectively fixed at the upper and lower ends of the first connecting member; The connecting plate is provided with a connecting hole, the connecting hole corresponds to the screw installation gap, and the lower end of the first screw is fixed after passing through the connecting hole and the screw installation gap.

2. The steel-concrete composite beam flange plate support bracket according to claim 1, characterized in that: A second connecting piece is fixed to one end of the second screw rod facing the steel box girder web, and a connecting groove is formed on the second connecting piece on one side facing the steel box girder web. A square timber is installed in the connecting groove, and the end surface of the square timber is used to abut against the steel box girder web.

3. The steel-concrete composite beam flange plate support bracket according to claim 2, characterized in that: The lower end of the first screw rod passes through the connecting plate and is locked by a second nut, and the upper end of the first screw rod passes through the top plate of the steel beam and is locked by the second nut.

4. The steel-concrete composite beam flange plate support bracket according to claim 3, characterized in that: The vertical connectors, the horizontal connectors and the oblique connectors are all made of channel steel, and the vertical connectors, the horizontal connectors and the oblique connectors are fixed by welding.