Novel skid-mounted barrack

By using large-diameter oblique tie rods and pin shaft connection methods in the skid-mounted barracks, the problem of easy loosening of structural connectors is solved, which significantly improves stability and durability, simplifies the maintenance process, and protects the appearance of the barracks.

CN222822932UActive Publication Date: 2025-05-02CHINA NAT PETROLEUM CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421816914.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2025-05-02
Estimated Expiration
2034-07-30

AI Technical Summary

Technical Problem

The structural connections of existing skid-mounted barracks are prone to loosening, resulting in insufficient stability and damage to the surface paint film, requiring frequent maintenance work, which increases the maintenance burden and may affect the appearance and service life.

Method used

The large-diameter oblique tie rod is used to cooperate with the pin shaft connection method to replace the original small-diameter threaded connection, and through a detachable connection structure design, such as bolt fixation of the bottom beam and the main beam and the oblique tie rod are connected to the pin shaft of the upper and lower fixing seats, to achieve rapid maintenance and component replacement.

Benefits of technology

It significantly enhances the overall stability and structural durability of the barracks, simplifies the maintenance process, reduces maintenance costs and frequency, and protects the appearance of the barracks, improving the reliability and adaptability of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222822932U_ABST
    Figure CN222822932U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of combined barracks, particularly relates to a novel skid-mounted barrack, and aims to solve the problems of insufficient stability and surface paint film damage caused by the fact that structural connecting pieces are easy to loosen in the conventional skid-mounted barrack technology. The bottom of the barrack is fixed with a bottom beam, and the bottom beam is detachably fixed with a main beam; the main pry further comprises a lower fixing seat, the lower fixing seat is fixed with the main beam, the lower fixing seat is detachably and fixedly connected with one end of an inclined pull rod, the other end of the inclined pull rod is detachably and fixedly connected with the bottom beam, and the inclined pull rod is symmetrically arranged along the center of the lower fixing seat; the barrack further comprises a rotating ladder, a fixing hole is formed in the rotating ladder, one end of a hook rod can be hung in the fixing hole, and the other end of the hook rod is hung on a prying head at the end of the barrack. According to the utility model, frequent maintenance caused by looseness of connecting parts is reduced, the damage to a paint film on the surface of the barrack is effectively avoided, and the integrity and attractiveness of the appearance of the barrack are kept.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of combined barracks, and specifically relates to a novel skid-mounted barracks. Background Art

[0002] Skid-mounted barracks are a type of temporary or semi-permanent building unit that can be quickly deployed, and are mainly used in the military, field operations, emergency rescue and other fields. The design concept of this type of barracks is modularity and portability, and can be quickly assembled and disassembled for easy transportation and redeployment. The "skid-mounted" in its name means that these barracks can be moved as a whole like a toolbox, without the need for extensive on-site construction.

[0003] Skid-mounted barracks are usually composed of high-strength steel frame structures and various prefabricated components. They may be covered with thermal insulation materials on the outside and equipped with basic living facilities such as doors and windows, electrical systems, lighting, and air conditioning. They can be combined into different layouts and functional areas as needed, such as dormitories, command centers, restaurants, medical stations, etc. Due to their high flexibility, short construction period, and low impact on the environment, skid-mounted barracks are particularly practical in scenarios such as emergency rescue in response to natural disasters, military exercises, oil drilling camps, and projects in remote areas.

[0004] The skid-mounted barracks use a main skid to tow two or more barracks to reduce the number of transport units and speed up the relocation of barracks and other facilities. The ancillary facilities can be quickly installed, put into place and put into operation quickly, so as to achieve the purpose of reducing costs and increasing efficiency. At present, the structure of the skid-mounted barracks uses a small-diameter diagonal tie rod between the main skid and the base of the barracks. Due to the small diameter and the tightness of the thread adjustment, it has a small pulling force and is easy to loosen due to the vibration of hoisting or the bumps of the transport vehicle. In addition, the fixation between the reinforced column of the end skid seat and the corner column of the barracks is tightened by screws against the column round tube, which is also prone to loosening, especially the part where the ladder tie rod is released from the barracks wall and the welding part of the reinforced column ear plate, which affects the paint film on the surface of the barracks to varying degrees.

[0005] In view of the above problems, the general solution is to regularly tighten the diagonal pull rods, regularly adjust the locking screws, and regularly repaint the local walls, which has the disadvantages of heavy maintenance work and affects the appearance.

[0006] Based on this, the utility model proposes a novel skid-mounted barracks. Utility Model Content

[0007] In order to solve the above-mentioned problems in the prior art, namely, the existing skid-mounted barracks technology has the problem that the structural connecting parts are easy to loosen, resulting in insufficient stability and damaged surface paint film, which requires frequent maintenance work, which not only increases the maintenance burden, but also may affect its appearance and service life. The utility model provides a new type of skid-mounted barracks, including a barracks and a main skid, the main skid includes a main beam, the bottom of the barracks is fixed to the bottom beam, and the bottom beam is detachably fixed to the main beam;

[0008] The main skid further comprises a lower fixing seat, the lower fixing seat is fixed to the main beam, the lower fixing seat is detachably fixedly connected to one end of an oblique tie rod, the other end of the oblique tie rod is detachably fixedly connected to the bottom beam, and the oblique tie rod is symmetrically arranged along the center of the lower fixing seat;

[0009] The novel skid-mounted barracks also includes a revolving ladder, which is provided with a fixing hole, in which one end of a hook rod can be hung, and the other end of the hook rod is hung on the skid head at the end of the barracks.

[0010] In some preferred embodiments, the main skid further comprises an end plate and a side bracket;

[0011] The two end plates are respectively fixed on both sides of the main beam, and the public ancillary facilities of the barracks are arranged on the end plates;

[0012] The side brackets are evenly installed on the main beams, wherein the side brackets installed on one main beam are used for arranging water supply and drainage pipelines, and the side brackets installed on the other main beam are used for arranging cables and auxiliary lines.

[0013] In some preferred embodiments, the bottom beam and the main beam are detachably fixed, and the structure is as follows:

[0014] The bottom beam and the main beam are fixed by bolts.

[0015] In some preferred embodiments, the lower fixing seat is detachably fixedly connected to one end of the oblique pull rod, and its structure is as follows:

[0016] One end of the oblique pull rod is fixed to the upper fixing plate, the upper fixing plate is fixed to the upper fixing seat, a bottom beam is arranged in the upper fixing seat, a pin hole is jointly provided in the upper fixing seat and the bottom beam, a pin shaft is inserted in the pin hole, and the upper fixing seat and the bottom beam are detachably fixed by the pin shaft.

[0017] In some preferred embodiments, the other end of the oblique pull rod is detachably fixedly connected to the bottom beam, and the structure is as follows:

[0018] The other end of the oblique pull rod is detachably fixed to the lower fixing seat.

[0019] In some preferred embodiments, the novel skid-mounted barracks further comprises a leg, one end of the leg can be supported on the ground, the other end of the leg is fixed to the outer surface of the collar, the collar is sleeved on the leg fixing bar and moves and rotates along the leg fixing bar, the leg fixing bar is fixed between two bottom beams, the leg can be detachably fixed to the connecting plate, and the connecting plate is fixed to the barracks;

[0020] The supporting legs are symmetrically arranged in two groups along the midpoint of the main beam.

[0021] In some preferred embodiments, the support legs are lead screw telescopic structures.

[0022] In some preferred embodiments, a sleeve hole is installed on the rotating ladder, and a fixed handrail is inserted into the sleeve hole.

[0023] In some preferred embodiments, one end of a hook rod can be hung in the fixing hole, and its structure is as follows:

[0024] The end of the hook rod close to the fixing hole is fixed to the connecting plate, the connecting plate is connected to the floating plate through a fixing pin, and the floating plate is hung in the fixing hole.

[0025] In some preferred embodiments, one end of the fixed handrail is plugged into one end of the lower hook, the other end of the lower hook is fixed to the barracks, the other end of the fixed handrail is hooked on the upper fixed hook, the fixed hook is opened on the fixed hook, and the fixed hook is fixed to the barracks through a baffle.

[0026] Beneficial effects of the utility model:

[0027] Enhanced structural stability and durability: The use of large-diameter oblique tie rods with pin connections replaces the original small-diameter threaded connections, which greatly improves the load-bearing capacity and vibration resistance of the tie rods, effectively avoiding loosening problems caused by vibration during transportation and lifting, thereby significantly enhancing the overall stability and structural durability of the barracks.

[0028] Simplify maintenance and improve reliability: Through the detachable connection structure design (such as the bolt fixation between the bottom beam and the main beam, the pin connection between the diagonal tie rod and the upper and lower fixed seats), quick maintenance and component replacement are achieved, which reduces the difficulty and cost of maintenance, while improving the reliability of the system and reducing the frequent maintenance caused by loose connection components.

[0029] Protect the appearance of the barracks: The fixing methods of the entrance ladder and the reinforced columns have been improved, and a hook rod and floating plate design that does not directly contact the barracks wall has been adopted, which effectively avoids damage to the paint film on the surface of the barracks and maintains the integrity and beauty of the barracks appearance.

[0030] Improved flexibility and adaptability: The additional rotating ladder and retractable outrigger design not only improve the convenience and safety of the barracks, but also enhance the barracks' ability to be quickly deployed under different terrain conditions. The symmetrical distribution of the outriggers and the lead screw telescopic structure ensure that the barracks can obtain good support balance on any ground, improving site adaptability.

[0031] Optimize functional layout and management: The integrated design of the end plate and the side bracket not only provides a standardized layout space for the barracks’ public ancillary facilities (such as water supply and drainage, cable lines), but also facilitates the maintenance and management of these systems, and improves the utilization efficiency and living comfort of the barracks’ internal space.

[0032] Enhanced user convenience and safety: The fixed handrail design on the revolving ladder and the application of sleeve holes not only facilitate the passage of personnel up and down, but also ensure safety during use, and improve the overall humanized design level of the barracks. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

[0034] Figure 1 This is a front view of a new type of skid-mounted barracks of the utility model;

[0035] Figure 2 It is a top view of the main skid in a new type of skid-mounted barracks of the utility model;

[0036] Figure 3 It is a schematic diagram of the main beam of the main skid in a new type of skid-mounted barracks of the utility model;

[0037] Figure 4 This is a schematic diagram of the installation of the main skid and the bottom beam in a new type of skid-mounted barracks of the utility model; wherein a is an installation schematic diagram; b is a positioning schematic diagram;

[0038] Figure 5 It is a schematic diagram of an oblique pull rod in a novel skid-mounted barrack of the utility model;

[0039] Figure 6 It is a schematic diagram of the connection of the two ends of the oblique pull rod in a new type of skid-mounted barracks of the utility model;

[0040] Figure 7 yes Figure 6 A partial enlarged view of

[0041] Figure 8 It is a schematic diagram of the connection between the oblique pull rod and the bottom beam in a new type of skid-mounted barracks of the utility model;

[0042] Fig. 9 yes Figure 1 A partial enlarged view of

[0043] Fig.10 yes Fig. 9 A partial enlarged view of

[0044] Fig.11 It is a schematic diagram of the connection between the outrigger and the bottom beam in a new type of skid-mounted barracks of the utility model; wherein a is a schematic diagram of the installation of the collar; b is a cross-sectional diagram of the DD of a;

[0045] Fig.12 yes Fig. 9 Dynamic change diagram of

[0046] Fig.13 It is a structural schematic diagram of a hook rod in a novel skid-mounted barrack of the utility model;

[0047] Fig.14 yes Fig.12 A partial enlarged view of the swimming plate; wherein a is the front view of the swimming plate; b is the side view of the swimming plate;

[0048] Fig.15 It is a structural schematic diagram of a fixed handrail in a new type of skid-mounted barracks of the utility model;

[0049] Fig.16 The utility model is a structural schematic diagram of a fixed hook in a novel skid-mounted barracks. DETAILED DESCRIPTION

[0050] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant utility model, rather than to limit the utility model. It is also necessary to explain that, for ease of description, only the parts related to the relevant utility model are shown in the accompanying drawings.

[0051] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0052] like Figure 1-Figure 16 As shown, see Figure 1 , Figure 2 , Figure 3 and Figure 6 The utility model provides a novel skid-mounted barracks, comprising a barracks 1 and a main skid 2, wherein the main skid 2 comprises a main beam 38, the bottom of the barracks 1 is fixed to a bottom beam 14, and the bottom beam 14 and the main beam 38 are detachably fixed;

[0053] The main skid 2 further includes a lower fixing seat 30, the lower fixing seat 30 is fixed to the main beam 38, the lower fixing seat 30 is detachably fixedly connected to one end of the oblique tie rod 3, the other end of the oblique tie rod 3 is detachably fixedly connected to the bottom beam 14, and the oblique tie rod 3 is symmetrically arranged along the center of the lower fixing seat 30;

[0054] The novel skid-mounted barracks further comprises a revolving ladder 15 , on which a fixing hole 17 is provided, in which one end of a hook rod 29 can be hooked, and the other end of the hook rod 29 is hooked on a pry head at the end of the barracks 1 .

[0055] Wherein, the pry head is Fig.12 and Fig.13 The hanging loop 16.

[0056] In this utility model, see Figure 2 , the main skid 2 also includes an end plate 39 and a side bracket 28;

[0057] The two end plates 39 are respectively fixed on both sides of the main beam 38, and the public ancillary facilities of the barracks 1 are arranged on the end plates 39;

[0058] The side brackets 28 are evenly installed on the main beams 38 , wherein the side brackets 28 installed on one main beam 38 are used to arrange water supply and drainage pipelines, and the side brackets 28 installed on the other main beam 38 are used to arrange cables and auxiliary lines.

[0059] Among them, the auxiliary lines at least include water supply lines, drainage lines, cables, data lines, etc.

[0060] The main skid 2 meets the towing requirements of the self-carrying vehicles at both ends and the lifting requirements of the cranes at both ends.

[0061] Among them, the public ancillary facilities include centralized power boxes, water tanks, etc.

[0062] For further explanation of the present invention, see Figure 4 The bottom beam 14 and the main beam 38 are detachably fixed, and the structure is as follows:

[0063] The bottom beam 14 and the main beam 38 are fixed by bolts.

[0064] Specifically, when the barracks 1 and the main pry 2 are installed, the cone pin 26 is first used for positioning, and the number of positioning holes is not less than 3 / 4 of the number of installation bolt holes; then the cone pin 26 is removed, and the barracks bottom beam 14 and the main pry 38 are fixedly connected by a bolt group consisting of a spring washer 22, a wedge washer 23, a bolt 24, and a flat washer 25.

[0065] As a further explanation of the present invention, please refer to Figure 5-Figure 8 The lower fixing seat 30 is detachably fixedly connected to one end of the oblique pull rod 3, and its structure is as follows:

[0066] One end of the oblique pull rod 3 is fixed to the upper fixing plate 33, and the upper fixing plate 33 is fixed to the upper fixing seat 31. A bottom beam 14 is arranged in the upper fixing seat 31. The upper fixing seat 31 and the bottom beam 14 are jointly provided with a pin hole, and a pin shaft 32 is inserted in the pin hole. The upper fixing seat 31 and the bottom beam 14 are detachably fixed by the pin shaft 32.

[0067] Specifically, the oblique tie rod 3 between the barrack 1 and the lower fixing seat 30 of the main skid 2 is made of a large-diameter thick-walled steel pipe (pipe diameter ”, SCH80), the upper part of which is an upper fixing seat 31 welded from a steel plate with a thickness of 12 mm, the upper fixing seat 31 is welded to an upper fixing plate 33, the upper fixing plate 33 is welded to the upper end of the oblique pull rod 3, and the upper fixing seat is connected and fixed to the bottom beam 14 of the barracks through a pin shaft 32.

[0068] For further explanation of the present invention, see Figure 6 The other end of the oblique pull rod 3 is detachably fixedly connected to the bottom beam 14, and its structure is as follows:

[0069] The other end of the oblique pull rod 3 is detachably fixed to the lower fixing seat 30 .

[0070] The specific method of detachable fixing is as follows: the lower end of the oblique pull rod 3 is connected to the lower fixing seat 30 of the main pry by another pin shaft 32 , and the pin shaft 32 needs to be provided with a secondary protection pin.

[0071] For further explanation of the present invention, see Fig. 9 , Fig.10 and Fig.11 The novel skid-mounted barracks further comprises a leg 4, one end of which can be supported on the ground, and the other end of which is fixed to the outer surface of a collar 13, the collar 13 is sleeved on a leg fixing bar 7 and moves and rotates along the leg fixing bar 7, the leg fixing bar 7 is fixed between two bottom beams 14, the leg 4 can be detachably fixed to a connecting plate 11, and the connecting plate 11 is fixed to the barracks 1;

[0072] The legs 4 are symmetrically arranged in two groups along the midpoint of the main beam 38 .

[0073] Among them, the support leg 4 is a screw telescopic structure, specifically including an adjustable screw 9 and an adjusting disk 10. The adjustable screw 9 is threadedly connected to the support leg 4. The adjustable screw 9 is coaxially fixed with the adjusting disk 10. The lower end of the adjustable screw 9 is fixed to the support leg bottom plate 8.

[0074] Specifically, the leg 4 provided below the end of the barrack 1 is fixed to the leg fixing bar 7 through the collar 13, and can be rotated more than 90° to achieve temporary fixation (horizontal direction) and support fixation (vertical direction). When supporting and fixing, the leg bottom plate 8, the adjustable screw 9 and the adjustment plate 10 are adjusted to achieve the support of the end of the house body by the ground, thereby increasing the stability of the house body; when relocating, the leg 4 is rotated 90°, and the leg bottom plate 8 and the connecting plate 11 on the barrack 1 are locked through the pin 12 to achieve temporary fixation.

[0075] A through hole 34 is provided on the leg bottom plate 8 , and the pin 12 is inserted through the through hole 34 into the connecting plate 11 to achieve locking of the leg bottom plate 8 and the connecting plate 11 .

[0076] For further explanation of the present invention, see Fig.12 A sleeve hole 18 is installed on the rotating ladder 15, and a fixed handrail 5 is inserted into the sleeve hole 18.

[0077] The sleeve hole 18 provided on the rotating ladder 15 can be used to conveniently install and fix the handrail 5 .

[0078] Among them, a blocking plate is installed on the inner surface of the sleeve hole 18, and the vertical pipe at the lower end of the fixed handrail 5 can be directly inserted into the sleeve hole 18.

[0079] For further explanation of the present invention, see Figure 12-14 The fixing hole 17 can be hung with one end of a hook rod 29, and its structure is as follows:

[0080] The end of the hook rod 29 close to the fixing hole 17 is fixed to the connecting plate 11 . The connecting plate 11 is connected to the floating plate 20 via a fixing pin 21 . The floating plate 20 is hung in the fixing hole 17 .

[0081] Among them, the hook end of the hook rod 29 is at a 45° angle. Under the action of the fixed plate 19, the floating plate 20, and the fixed pin 21, the revolving ladder 15 is fixed to the end of the barracks 1 (the revolving ladder can also be smoothly detached) and is not associated with the wall.

[0082] For further explanation of the present invention, see Fig.12 , Fig.15 and Fig.16 The fixed handrail 5 is plugged into one end of the lower hook 6, and the other end of the lower hook 6 is fixed to the barracks 1. An upper fixed hook 35 is installed on the fixed handrail 5, and the upper fixed hook 35 is hooked with a fixed curved hook 37, and the fixed curved hook 37 is fixed to the barracks 1 through a baffle 36.

[0083] The baffle 36 is provided to prevent the fixed handrail 5 from directly contacting the wall surface of the barracks 1 .

[0084] Specifically, one end of the fixed handrail 5 is plugged into one end of the lower hook 6, the other end of the lower hook 6 is fixed to the barracks 1, and the other end of the fixed handrail 5 is hooked on the upper fixed hook 37, the fixed hook 37 is opened on the fixed hook 35, and the fixed hook 35 is fixed to the barracks 1 through a baffle 36.

[0085] The fixed hook 37 and the blocking piece 36 on the fixed hook 35 ensure that the handrail will not come into contact with the wall of the barracks.

[0086] The assembly sequence of a novel skid-mounted barracks of the utility model is as follows:

[0087] Before assembly, make sure that the foundation bearing strength is appropriate and the ground is flat; first place the main skid 2, then install the barracks 1 (from one end to the other). When placing the barracks 1, first use the taper pin 26 for positioning, and then use the bolt group to fix the bottom main beam 14 of the barracks 1 and the main beam 38 of the main skid 2; install the oblique tie rod 3, and fix it with the pin shaft 32 (reinforce the secondary pin protection); install the support leg 4, place the rotating ladder 15, and install the fixed handrail 5. Finally, install the remaining auxiliary facilities. When dismantling and relocation is required, the operation can be carried out in the reverse order of the above.

[0088] In the description of the present invention, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" and the like indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings, which are only for the convenience of description, and do not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0089] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0090] The term "comprise" or any other similar term is intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus / device that includes a list of elements includes not only those elements but also other elements not expressly listed, or also includes elements inherent to such process, method, article, or apparatus / device.

[0091] So far, the technical solution of the utility model has been described in conjunction with the preferred embodiments shown in the accompanying drawings, but it is easy for those skilled in the art to understand that the protection scope of the utility model is obviously not limited to these specific embodiments. Without departing from the principle of the utility model, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the utility model.

Claims

1. A novel skid-mounted barracks, comprising a barracks (1) and a main skid (2), wherein the main skid (2) comprises a main beam (38), characterized in that: The bottom of the barracks (1) is fixed to a bottom beam (14), and the bottom beam (14) is detachably fixed to a main beam (38); The main skid (2) further comprises a lower fixing seat (30), the lower fixing seat (30) and the main beam (38) are fixed, the lower fixing seat (30) is detachably fixedly connected to one end of the oblique tie rod (3), the other end of the oblique tie rod (3) is detachably fixedly connected to the bottom beam (14), and the oblique tie rod (3) is symmetrically arranged along the center of the lower fixing seat (30); The novel skid-mounted barracks also includes a revolving ladder (15), the revolving ladder (15) is provided with a fixing hole (17), one end of a hook rod (29) can be hooked in the fixing hole (17), and the other end of the hook rod (29) is hooked on the skid head at the end of the barracks (1).

2. A novel skid-mounted barracks according to claim 1, characterized in that: The main skid (2) further comprises an end plate (39) and a side bracket (28); The two end plates (39) are respectively fixed on both sides of the main beam (38), and the public auxiliary facilities of the barracks (1) are arranged on the end plates (39); The side brackets (28) are evenly installed on the main beams (38), wherein the side brackets (28) installed on one main beam (38) are used to arrange water supply and drainage pipelines, and the side brackets (28) installed on the other main beam (38) are used to arrange cables and auxiliary lines.

3. The novel skid-mounted barracks according to claim 1 is characterized in that: The bottom beam (14) and the main beam (38) are detachably fixed, and the structure is as follows: The bottom beam (14) and the main beam (38) are fixed by bolts.

4. The novel skid-mounted barracks according to claim 1 is characterized in that: The lower fixing seat (30) is detachably fixedly connected to one end of the oblique pull rod (3), and its structure is as follows: One end of the oblique pull rod (3) is fixed to an upper fixing plate (33), and the upper fixing plate (33) is fixed to an upper fixing seat (31). A bottom beam (14) is arranged inside the upper fixing seat (31), and a pin hole is provided in the upper fixing seat (31) and the bottom beam (14). A pin shaft (32) is inserted into the pin hole, and the upper fixing seat (31) and the bottom beam (14) are detachably fixed by means of the pin shaft (32).

5. The novel skid-mounted barracks according to claim 1 is characterized in that: The other end of the oblique pull rod (3) is detachably fixedly connected to the bottom beam (14), and its structure is as follows: The other end of the oblique pull rod (3) is detachably fixed to the lower fixing seat (30).

6. The novel skid-mounted barracks according to claim 1 is characterized in that: The novel skid-mounted barracks further comprises a leg (4), one end of the leg (4) being capable of supporting on the ground, the other end of the leg (4) being fixed to the outer surface of a collar (13), the collar (13) being sleeved on a leg fixing bar (7) and moving and rotating along the leg fixing bar (7), the leg fixing bar (7) being fixed between two bottom beams (14), the leg (4) being capable of being detachably fixed to a connecting plate (11), and the connecting plate (11) being fixed to the barracks (1); The supporting legs (4) are symmetrically arranged in two groups along the midpoint of the main beam (38).

7. The novel skid-mounted barracks according to claim 6 is characterized in that: The supporting leg (4) is a lead screw telescopic structure.

8. The novel skid-mounted barracks according to claim 1 is characterized in that: The rotating ladder (15) is provided with a sleeve hole (18), and a fixed handrail (5) is inserted into the sleeve hole (18).

9. The novel skid-mounted barracks according to claim 8 is characterized in that: One end of a hook rod (29) can be hung in the fixing hole (17), and the structure is as follows: The end of the hook rod (29) close to the fixing hole (17) is fixed to the connecting plate (11), the connecting plate (11) is connected to the floating plate (20) via a fixing pin (21), and the floating plate (20) is hung in the fixing hole (17).

10. The novel skid-mounted barracks according to claim 8 is characterized in that: During transportation, one end of the fixed handrail (5) is plugged into one end of the lower hook (6), the other end of the lower hook (6) is fixed to the barracks (1), the other end of the fixed handrail (5) is hooked on the upper fixed hook (37), the fixed hook (37) is provided on the fixed hook (35), and the fixed hook (35) is fixed to the barracks (1) via a baffle (36).