Rapid drilling machine for composite sleeper
By designing a synthetic sleeper rapid drilling machine, multiple hole positions are drilled simultaneously using multi-axis drilling components and moving mechanisms, the problems of large deviations in manual positioning, low efficiency and low accuracy in the prior art are solved, and the drilling efficiency and accuracy are improved, and driving safety is ensured.
Patent Information
- Application Number
- CN202420998409.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2025-05-09
- Estimated Expiration
- 2034-05-10
AI Technical Summary
When drilling through synthetic sleepers in the prior art, the artificial positioning deviation is large, the efficiency is low, and the accuracy is not high, which affects driving safety.
A synthetic sleeper rapid drilling machine is designed, using a two-hole multi-axis drilling assembly and a four-hole multi-axis drilling assembly. The drilling accuracy is improved by moving the mechanism.
It improves drilling efficiency, reduces operating time, enhances drilling accuracy, ensures the accuracy of rail installation position, and improves driving safety.
Smart Images

Figure CN222843179U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of synthetic sleeper drilling equipment, in particular to a synthetic sleeper rapid drilling machine. Background Art
[0002] Polyurethane synthetic sleepers are a new type of sleepers with the advantages of light weight, excellent physical and mechanical properties, good anti-pullout performance of track gauge spikes, and abundant synthetic material resources. They have great potential to replace traditional wooden sleepers and concrete sleepers.
[0003] During the manufacturing process of composite sleepers, it is necessary to punch rail fastener holes and guard rail fastener holes on the upper surface to facilitate fixing the composite sleepers and fasteners during installation. Currently, handheld drilling tools or radial drilling machines are generally used for drilling. These two operation methods require each hole to be positioned and then drilled separately. Manual positioning will have certain deviations and take a long time, which can easily lead to low drilling efficiency and affect the drilling position accuracy. Since the fastener holes determine the installation position of the rails, if the fastener holes have too large deviations, it will also affect the final driving safety. Utility Model Content
[0004] The technical problem to be solved by the utility model is to provide a rapid drilling machine for synthetic sleepers, which can quickly locate the drilling positions and realize simultaneous drilling of multiple holes, thereby improving the drilling efficiency and drilling accuracy.
[0005] In order to solve the above technical problems, the technical solutions adopted by the present utility model are as follows.
[0006] A rapid drilling machine for synthetic sleepers comprises a machine tool, on which are mounted a plurality of conveying rollers for conveying synthetic sleepers; clamping assemblies for clamping synthetic sleepers are symmetrically arranged on both sides of the machine tool; a mounting frame is arranged on one side of the machine tool, on which are mounted a four-hole multi-axis drilling assembly for drilling holes for main rail fasteners and a two-hole multi-axis drilling assembly for drilling holes for guard rail fasteners; the four-hole multi-axis drilling assembly comprises a four-hole drill and a first moving mechanism for driving the four-hole drill to move up and down for drilling holes, and the four-hole drill is movably connected to the first moving mechanism; the two-hole multi-axis drilling assembly comprises a two-hole drill, a second moving mechanism for driving the two-hole drill to move up and down, and a left-right moving mechanism for driving the two-hole drill to move left-right, the two-hole drill is mounted on the second moving mechanism, and the second moving mechanism is mounted on the left-right moving mechanism.
[0007] In the above-mentioned synthetic sleeper rapid drilling machine, the first moving mechanism includes a first bracket installed on a mounting frame, a first screw is installed on the first bracket, and a first motor is arranged at the top of the first bracket to drive the first screw to rotate; first slide rails are respectively arranged on both sides of the first bracket to ensure the stability of the four-hole drill when it moves up and down.
[0008] The above-mentioned synthetic sleeper rapid drilling machine, the four-hole drill includes a first machine head threadedly mounted on a first lead screw, and both sides of the first machine head are slidably mounted with a first slide rail; a four-hole multi-axis device is provided at the bottom of the first machine head, and four first drill bits are installed at the bottom of the four-hole multi-axis device.
[0009] The above-mentioned synthetic rail sleeper rapid drilling machine, the left and right moving mechanism includes a fixed plate installed on the mounting frame, a third screw threadedly connected to the second moving mechanism is arranged at the center of the fixed plate, and the third screw is arranged horizontally in the left and right directions; a third motor for driving the third screw to rotate is also installed on one side of the fixed plate; the upper and lower ends of the fixed plate are also provided with third slide rails slidably assembled with the second moving mechanism.
[0010] The above-mentioned synthetic rail sleeper rapid drilling machine, the second moving mechanism includes a second bracket threadedly equipped with a third lead screw, and both ends of the second bracket are slidably arranged on a third slide rail; a second lead screw is installed on the second bracket, and the second lead screw is threadedly connected to the two-hole drill; a second motor that drives the second lead screw to rotate is installed on the top of the second bracket; and second slide rails slidably equipped with the two-hole drill are respectively arranged on the left and right sides of the second bracket.
[0011] The above-mentioned synthetic sleeper rapid drilling machine, the two-hole drill includes a second head threadedly equipped with the second lead screw, and the second head is slidably equipped with the second slide rail; a two-hole multi-axis device is arranged at the bottom of the second head, and two second drill bits are installed at the bottom of the two-hole multi-axis device.
[0012] In the above-mentioned synthetic sleeper rapid drilling machine, the clamping assembly comprises a cylinder arranged on the machine tool, and the other end of the cylinder piston rod is connected to the clamping plate.
[0013] Due to the adoption of the above technical scheme, the technical progress achieved by the present invention is as follows.
[0014] The utility model provides a rapid drilling machine for synthetic sleepers. By arranging a two-hole multi-axis drilling assembly and a four-hole multi-axis drilling assembly, a plurality of main rail fastener holes and a plurality of guard rail fastener holes can be drilled simultaneously. The four-hole multi-axis drilling assembly and the two-hole multi-axis drilling assembly can be controlled to move up and down and drill holes by arranging a first moving mechanism and a second moving mechanism, thereby improving the drilling efficiency and reducing the operation time.
[0015] At the same time, the utility model adjusts the horizontal distance between the two-hole multi-axis drilling assembly and the four-hole multi-axis drilling assembly by setting a left and right moving mechanism, thereby realizing the precise adjustment of the drilling position of the guardrail fastener holes, and at the same time cooperates with the clamping assembly to clamp the synthetic sleeper, thereby effectively improving the drilling accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the specific structure of the utility model;
[0017] Figure 2 This is a schematic diagram of the specific structure of the installation of the four-hole multi-axis drilling assembly of the utility model;
[0018] Figure 3 This is a schematic diagram of the specific structure of the installation of the two-hole multi-axis drilling assembly described in the utility model.
[0019] Wherein: 1. machine tool, 2. conveying roller, 3. synthetic rail sleeper, 4. cylinder, 5. clamping plate, 6. mounting frame, 7. four-hole multi-axis drilling assembly, 71. first machine head, 72. four-hole multi-axis device, 73. first drill bit, 74. first bracket, 75. first slide rail, 76. first lead screw, 77. first motor, 8. two-hole multi-axis drilling assembly, 81. second machine head, 82. two-hole multi-axis device, 83. second drill bit, 84. second bracket, 85. second slide rail, 86. second lead screw, 87. second motor, 9. fixing plate, 10. third slide rail, 11. third lead screw, 12. third motor. DETAILED DESCRIPTION
[0020] The present invention will be further described in detail below with reference to the accompanying drawings and specific implementation methods.
[0021] A synthetic sleeper rapid drilling machine, such as Figures 1 to 3 As shown, it includes a machine tool 1, on which are installed a plurality of conveying rollers 2 for conveying synthetic sleepers 3, on both sides of the machine tool 1 are symmetrically provided a plurality of clamping assemblies for clamping the synthetic sleepers 3, and on one side of the machine tool 1 is symmetrically provided a mounting frame 6, on which are installed a four-hole multi-axis drilling assembly 7 for drilling holes for main rail fasteners and a two-hole multi-axis drilling assembly 8 for drilling holes for guard rail fasteners.
[0022] The clamping assembly includes a cylinder 4 arranged on the machine tool 1, the other end of the piston rod of the cylinder 4 is connected to a clamping plate 5, and the clamping plate 5 contacts the side of the synthetic sleeper to clamp the synthetic sleeper 3.
[0023] like Figure 2 As shown, the four-hole multi-axis drilling assembly 7 includes a four-hole drill and a first moving mechanism for driving the four-hole drill to move up and down to perform drilling, and the four-hole drill is movably connected to the first moving mechanism.
[0024] The four-hole drill comprises a first machine head 71 , a four-hole multi-axis device 72 is arranged at the bottom of the first machine head 71 , and four first drill bits 73 are installed at the bottom of the four-hole multi-axis device 72 .
[0025] The first moving mechanism includes a first bracket 74 mounted on the mounting frame 6, such as Figure 2 As shown, a first screw 76 is installed on the first bracket 74 , the first head 71 is threadedly mounted on the first screw 76 , and a first motor 77 is disposed at the top end of the first bracket 74 to drive the first screw 76 to rotate.
[0026] First slide rails 75 slidably mounted with the first head 71 are respectively provided on both sides of the first bracket 74 to ensure the stability of the four-hole drill when it moves up and down.
[0027] like Figure 3 As shown, the two-hole multi-axis drilling assembly 8 includes a two-hole drill, a second moving mechanism for driving the two-hole drill to move up and down, and a left-right moving mechanism for driving the two-hole drill to move left and right. The two-hole drill is installed on the second moving mechanism, and the second moving mechanism is installed on the left-right moving mechanism.
[0028] The two-hole drill comprises a second machine head 81 , a two-hole multi-axis device 82 is arranged at the bottom of the second machine head 81 , and two second drill bits 83 are installed at the bottom of the two-hole multi-axis device 82 .
[0029] The left and right moving mechanism includes a fixed plate 9 installed on the mounting frame 6, and a third screw 11 threadedly connected to the second moving mechanism is arranged at the center of the fixed plate 9. The third screw is arranged horizontally in the left and right directions. A third motor 12 for driving the third screw 11 to rotate is also installed on one side of the fixed plate 9.
[0030] The upper and lower ends of the fixed plate 9 are also provided with third slide rails 10 slidably assembled with the second moving mechanism.
[0031] The second moving mechanism includes a second bracket 84 threadedly mounted on the third lead screw 11, both ends of the second bracket 84 are slidably arranged on the third slide rail 10, a second lead screw 86 is installed on the second bracket 84, the second lead screw 86 is threadedly connected to the second machine head 81, and a second motor 87 that drives the second lead screw 86 to rotate is installed on the top of the second bracket 84.
[0032] Second slide rails 85 slidably fitted with the second head 81 are respectively provided on the left and right sides of the second bracket 84 .
[0033] When in use, the synthetic sleeper 3 is transported by the transport roller 2. When drilling is required, the cylinder 4 is started to clamp the two sides of the synthetic sleeper with the clamping plate 5, and then the first motor 77 is started to drive the first screw 76 to rotate, so that the four-hole drill moves downward along the length direction of the screw to drill the holes for the main rail fasteners. After the drilling is completed, the screw is driven to rotate in the opposite direction to drive the four-hole drill to move upward.
[0034] At the same time, the second motor 87 is started to drive the second screw 86 to rotate, driving the two-hole puncher to move downward, so that the drill bit contacts the surface of the synthetic sleeper and completes the drilling of the guardrail fastener holes. After the drilling is completed, the screw is driven to rotate in the opposite direction to drive the two-hole puncher to move upward.
[0035] When the drilling position of the guardrail fastener hole needs to be adjusted, the third motor 12 is started to drive the third screw 11 to rotate, and the two-hole drill is driven to move horizontally to the left and right, so that the two-hole drill reaches a suitable drilling position, and then the drilling can be performed according to the above process.
[0036] The utility model provides a rapid drilling machine for synthetic sleepers. By arranging a two-hole multi-axis drilling assembly and a four-hole multi-axis drilling assembly, a plurality of main rail fastener holes and a plurality of guard rail fastener holes can be drilled simultaneously. The four-hole multi-axis drilling assembly and the two-hole multi-axis drilling assembly can be controlled to move up and down and drill holes by arranging a first moving mechanism and a second moving mechanism, thereby improving the drilling efficiency and reducing the operation time.
[0037] At the same time, the utility model adjusts the horizontal distance between the two-hole multi-axis drilling assembly and the four-hole multi-axis drilling assembly by setting a left and right moving mechanism, thereby realizing the precise adjustment of the drilling position of the guardrail fastener holes, and at the same time cooperates with the clamping assembly to clamp the synthetic sleeper, thereby effectively improving the drilling accuracy.
Claims
1. A synthetic sleeper rapid drilling machine, characterized in that: The invention comprises a machine tool (1), on which a plurality of conveying rollers (2) for conveying synthetic sleepers (3) are installed; clamping assemblies for clamping the synthetic sleepers (3) are symmetrically arranged on both sides of the machine tool (1); a mounting frame (6) is symmetrically arranged on one side of the machine tool (1), on which a four-hole multi-axis drilling assembly (7) for drilling holes for regular rail fasteners and a two-hole multi-axis drilling assembly (8) for drilling holes for guard rail fasteners are respectively installed; the four-hole multi-axis drilling assembly (7) comprises a four-hole drill and a first moving mechanism for driving the four-hole drill to move up and down for drilling holes, and the four-hole drill is movably connected to the first moving mechanism; the two-hole multi-axis drilling assembly (8) comprises a two-hole drill, a second moving mechanism for driving the two-hole drill to move up and down, and a left-right moving mechanism for driving the two-hole drill to move left-right, the two-hole drill is installed on the second moving mechanism, and the second moving mechanism is installed on the left-right moving mechanism.
2. A synthetic sleeper rapid drilling machine according to claim 1, characterized in that: The first moving mechanism comprises a first bracket (74) mounted on a mounting frame (6), a first lead screw (76) being mounted on the first bracket (74), a first motor (77) for driving the first lead screw (76) to rotate being arranged at the top end of the first bracket (74); first slide rails (75) for ensuring the stability of the four-hole drill when it moves up and down are respectively arranged on both sides of the first bracket (74).
3. A synthetic sleeper rapid drilling machine according to claim 2, characterized in that: The four-hole drill comprises a first machine head (71) threadedly mounted on a first lead screw (76), and both sides of the first machine head (71) are slidably mounted on first slide rails (75); a four-hole multi-axis device (72) is arranged at the bottom of the first machine head (71), and four first drill bits (73) are installed at the bottom of the four-hole multi-axis device (72).
4. A synthetic sleeper rapid drilling machine according to claim 1, characterized in that: The left-right moving mechanism comprises a fixed plate (9) mounted on a mounting frame (6); a third lead screw (11) threadedly connected to the second moving mechanism is arranged at the center of the fixed plate (9); the third lead screw is arranged horizontally in the left-right direction; a third motor (12) for driving the third lead screw (11) to rotate is also installed on one side of the fixed plate (9); and third slide rails (10) slidably assembled with the second moving mechanism are also arranged at the upper and lower ends of the fixed plate (9).
5. A synthetic sleeper rapid drilling machine according to claim 4, characterized in that: The second moving mechanism comprises a second bracket (84) threadedly mounted on the third lead screw (11), and both ends of the second bracket (84) are slidably mounted on the third slide rail (10); a second lead screw (86) is mounted on the second bracket (84), and the second lead screw (86) is threadedly connected to the two-hole drill; a second motor (87) for driving the second lead screw (86) to rotate is mounted on the top of the second bracket (84); and second slide rails (85) slidably mounted on the two-hole drill are respectively arranged on the left and right sides of the second bracket (84).
6. A synthetic sleeper rapid drilling machine according to claim 5, characterized in that: The two-hole drill comprises a second machine head (81) threadedly mounted on a second lead screw (86), and the second machine head (81) is slidably mounted on a second slide rail (85); a two-hole multi-axis device (82) is arranged at the bottom of the second machine head (81), and two second drill bits (83) are installed at the bottom of the two-hole multi-axis device (82).
7. The synthetic sleeper rapid drilling machine according to claim 1, characterized in that: The clamping assembly comprises a cylinder (4) arranged on a machine tool (1), and the other end of a piston rod of the cylinder (4) is connected to a clamping plate (5).