Overwater vertical and horizontal transportation system applied to construction of upper structure of long-piled wharf
By designing a water vertical horizontal transportation system for the construction of the upper structure of the high pile dock, the problems of traditional floating gondolas in the construction of high pile docks and the difficulties in positioning and stability affected by natural conditions are solved, and efficient, safe and economical construction results are achieved.
Patent Information
- Application Number
- CN202421907066.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2025-05-13
- Estimated Expiration
- 2034-08-08
AI Technical Summary
In the construction of the superstructure of the high pile dock, there are problems such as cumbersome positioning, difficulty in positioning adjustment, large vertical and horizontal transportation blind spots, influence of natural conditions, low construction time utilization, uncontrollable construction period, high safety risks and high equipment costs.
A water vertical horizontal transportation system was designed, including two steel pipe pile foundations, bottom beams, foundation beams, footbridges, door machine tracks, water gantry cranes, electric hoist, wire ropes, flat boxes and anti-shaking components. The system achieves vertical and horizontal transportation through steel pipe pile foundations and water gantry cranes, and improves lifting stability and safety through electric hoists and trim boxes.
The system simplifies the assembly process, reduces costs, improves the reuse rate of equipment and materials, shortens the time for installing components, enhances safety, simplifies operations, overcomes the problems of floating gondolas being affected by water levels and waves, poor component installation accuracy and poor night construction safety, and improves the safety, efficiency and economicality of construction.
Smart Images

Figure CN222861006U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water transportation systems, in particular to a water vertical and horizontal transportation system used for the construction of a high-pile dock superstructure. Background Art
[0002] In recent years, with the continuous development of my country's economy, a large number of high-pile wharf projects have been built in domestic offshore and inland ports. In the construction of the superstructure of high-pile wharf projects, traditional technology usually uses floating cranes for water hoisting and auxiliary construction.
[0003] Traditional processes usually use floating cranes to assist in water lifting construction. The main disadvantages are: the positioning of the operating ship is cumbersome, there are many difficulties in the positioning and adjustment of the lifting components, there are blind spots in vertical and horizontal transportation, the stability of the ship is greatly affected by natural conditions such as tides and waves, hydrological and meteorological conditions, the construction time utilization rate is low, there are many uncontrollable factors in the construction period, there are great safety risks in water construction, and the cost of ship machinery and equipment is high. Utility Model Content
[0004] The utility model aims to solve the problems existing in the background technology and proposes an above-water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock.
[0005] The technical solution of the utility model is: a water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock, including two steel pipe pile foundations, and also including:
[0006] A bottom cross beam is arranged on the steel pipe pile foundation, a foundation beam and a footbridge are installed on the bottom cross beam, a gantry track is fixedly installed on the foundation beam, a water gantry crane is installed on the gantry track, a first driving device for driving the water gantry crane to move along the gantry track is arranged on the steel pipe pile foundation, and a cable laying platform is arranged on one of the steel pipe pile foundations.
[0007] Optionally, an electric winch is installed on the water gantry crane, and a second driving mechanism for driving the electric winch to move along the water gantry crane is installed on the electric winch. A steel wire rope is fixedly installed on the electric winch, and a balance box is fixedly installed on one end of the steel wire rope, and a hook is fixedly installed on the balance box.
[0008] Optionally, an anti-sway component is installed in the balancing box, and the anti-sway component applies resistance to the wire rope in the opposite direction to the shaking direction of the wire rope.
[0009] Optionally, the anti-sway component includes a traction rope fixedly installed in the balancing box, and a plurality of installation boxes are fixedly installed on the other end of the traction rope, and two adjacent installation boxes are fixedly connected by a connecting block.
[0010] Optionally, the anti-sway component also includes a counterweight assembly fixedly installed in the installation box, the counterweight assembly includes two support rods fixed in the installation box, a first connecting plate is rotatably installed on the support rods, and a counterweight block is fixedly installed on the first connecting plate.
[0011] Optionally, the anti-sway component further includes a stamping mechanism installed on the installation box, and the stamping mechanism drives the plurality of counterweights to perform periodic reciprocating swings.
[0012] Optionally, the stamping mechanism includes a motor fixedly mounted on an installation box located at the bottom, an eccentric wheel fixedly mounted on the output shaft of the motor, a connecting rod rotatably mounted on the eccentric wheel, a transmission rod slidably mounted in the plurality of installation boxes, the other end of the connecting rod is rotatably connected to the transmission rod, a plurality of second connecting plates are fixedly mounted on the transmission rod, the second connecting plates correspond one-to-one to the installation boxes, the second connecting plates are located inside the installation box, a driving rod rotatably mounted on the second connecting plate, the driving rod corresponds one-to-one to the first connecting plate and is rotatably connected.
[0013] In summary, the present application includes at least one of the following beneficial technical effects:
[0014] The advantages of simple assembly, low expense and low cost are that equipment and materials can be reused, components can be installed quickly, safety is high and operation is convenient. It can effectively overcome the problems of floating cranes being affected by water levels and waves, poor component installation accuracy and poor safety during nighttime construction, ensure the smooth implementation of the superstructure construction of high-pile docks, and improve the safety, efficiency and economy of construction.
[0015] By decomposing the gravity inside the trim box and the pulling force exerted on the trim box by the counterweight block into a pulling force in the opposite direction of the shaking of the trim box, the shaking degree of the trim box can be reduced. While making the gravity inside the trim box smaller, a greater pulling force can be exerted on the hoisted cargo, which can effectively reduce the output power of the electric winch and help reduce energy consumption. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A structural schematic diagram of an embodiment of the utility model is given;
[0017] Figure 2 A schematic diagram of the internal structure of the trim box of the utility model is given;
[0018] Figure 3 A structural schematic diagram of the punching mechanism of the utility model is given;
[0019] Figure 4 for Figure 2 A partial enlarged view of point A in the middle.
[0020] Figure numerals: 1. steel pipe pile foundation; 2. bottom cross beam; 3. foundation beam; 4. footbridge; 5. gantry crane track; 6. cable laying platform; 7. water gantry crane; 8. electric winch; 9. wire rope; 10. balance box; 11. hook; 12. traction rope; 13. installation box; 14. support rod; 15. first connecting plate; 16. counterweight; 17. motor; 18. eccentric wheel; 19. connecting rod; 20. transmission rod; 21. second connecting plate; 22. drive rod; 23. mud surface line; 24. water surface line. DETAILED DESCRIPTION
[0021] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0022] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. Several embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive.
[0023] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
[0024] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art in the technical field of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more of the related listed items.
[0025] Example:
[0026] like Figure 1As shown, the utility model proposes a water vertical and horizontal transportation system used for the construction of the upper structure of a high-pile dock, including two steel pipe pile foundations 1, the bottom of the steel pipe pile foundation 1 penetrates into the bottom of the mud surface line 23 and is higher than the water surface line 24, and the steel pipe pile foundation 1 bears the weight of the construction hoisting objects, the weight of the equipment, the operating strength, the influence of geology and working conditions, etc. It also includes a bottom cross beam 2 arranged on the steel pipe pile foundation 1, a foundation beam 3 and a pedestrian bridge 4 are installed on the bottom cross beam 2, a gantry track 5 is fixedly installed on the foundation beam 3, and a water gantry crane 7 is installed on the gantry track 5. The bottom cross beam 2 transmits the weight of the construction hoisting objects, the weight of the equipment, the operating strength, the influence of geology and working conditions, etc. The foundation beam 3 serves as the foundation of the water gantry crane 7, fixes the gantry track 5, and transmits the weight of the construction hoisting objects, the weight of the equipment, the operating strength, the influence of geology and working conditions, etc. The pedestrian bridge 4 is used for construction personnel and maintenance personnel to pass. A first driving device is provided on the steel pipe pile foundation 1 for driving the water gantry crane 7 to move along the gantry track 5. The water gantry crane 7 is a main equipment for hoisting components, materials, and tools, and the longitudinal displacement of the hoisted objects is achieved through the first driving device.
[0027] A cable laying platform 6 is arranged on one of the steel pipe pile foundations 1. The cable laying platform 6 is used to lay the cables of the water gantry crane 7. The water gantry crane 7 is equipped with an electric winch 8, and the electric winch 8 is equipped with a second driving mechanism for driving the electric winch 8 to move along the water gantry crane 7. The electric winch 8 is used to hoist the main equipment of components, materials, and tools, and the horizontal displacement of the hoisted weight is achieved through the second driving mechanism.
[0028] A steel wire rope 9 is fixedly installed on the electric hoist 8, and a trim box 10 is fixedly installed on one end of the steel wire rope 9, and a hook 11 is fixedly installed on the trim box 10. Components, materials, and tools are hoisted by the hook 11.
[0029] When lifting cargo, the following steps should be followed:
[0030] Step 1: Before operating the equipment system, technical explanations must be conducted to clarify the weight, specifications, dimensions and other information of the items to be transferred, and operators must receive pre-shift education on operating procedures, construction methods, safety precautions, etc.;
[0031] Step 2: The operator operates the water gantry crane 7 and the electric winch controller to move the water gantry crane 7 to the object to be transferred, and the electric winch 8 is synchronously put into place;
[0032] Step 3: Lower the wire rope 9 connected to the hook 11, lower the hook 11 above the hanging object, and the construction personnel fix the hanging object on the hook 11;
[0033] Step 4: Test lifting, that is, lifting the heavy object to no more than 0.5 meters, and then braking when it descends close to the ground. The lifting object should be ensured to be stable and the wire rope 9 should be checked for normal use before the next step can be carried out;
[0034] Step 5: The operator operates the controllers of the water gantry crane 7 and the electric winch 8 to transfer the hanging object to the target position;
[0035] Step 6: Install or place the hanging objects. The process should be carried out smoothly and orderly.
[0036] Step 7: The water gantry crane 7 is reset, moved to a safe parking area, the limiter is locked, and the safety cables are fixed.
[0037] like Figure 2-Figure 4 As shown, an anti-sway component is installed in the trim box 10, and the anti-sway component applies resistance to the wire rope 9 in the opposite direction of the swaying direction of the wire rope 9. Due to the particularity of the operating environment of the water gantry crane 7 on the dock compared to the gantry crane on the ground, special attention should be paid to the sea breeze problem. The water gantry crane 7 needs to consider the wind force level, which will affect the stability and safety of the hoisting. When the sea breeze is strong, the sea breeze will blow the hoisted cargo to move, and at this time it will drive the wire rope 9 to swing. The swing of the cargo may cause damage to the packaging, structural damage or functional failure, especially for precision instruments or fragile items. And the swinging of the cargo may hit nearby facilities, ships or personnel, causing personal injury or property loss.
[0038] The anti-sway component includes a traction rope 12 fixedly installed in the trim box 10, and a plurality of installation boxes 13 are fixedly installed at the other end of the traction rope 12, and two adjacent installation boxes 13 are fixedly connected by a connecting block. When the cargo swings under the influence of the sea breeze, the trim box 10 will be driven to swing synchronously. At this time, the installation box 13 inside the trim box 10 is connected to the trim box 10 by the traction rope 12. The connection method here is a flexible connection, so that under the gravity of the installation box 13, the installation box 13 can maintain a vertical state. At this time, the shaking trim box 10 will have a certain angle with the installation box 13. The gravity inside the trim box 10 can be decomposed into a pulling force in the opposite direction of the shaking of the trim box 10, thereby reducing the shaking degree of the trim box 10. However, in order to resist stronger sea breezes, it is necessary to continuously increase the gravity of the installation box 13, which leads to an increase in the energy consumption of the electric winch 8, which is not conducive to energy saving and emission reduction.
[0039] The anti-sway component also includes a counterweight assembly fixedly installed in the installation box 13, and the counterweight assembly includes two support rods 14 fixed in the installation box 13, and a first connecting plate 15 is rotatably installed on the support rods 14, and a counterweight block 16 is fixedly installed on the first connecting plate 15. When the first connecting plate 15 rotates, it will drive the counterweight block 16 to rotate, and the rotating counterweight block 16 will generate centrifugal force, which will act on the support rods 14 and then on the installation box 13, so that the pulling force applied by the installation box 13 to the balance box 10 can be increased in disguise through the rotating counterweight block 16, so as to resist stronger sea wind.
[0040] The anti-sway component also includes a stamping mechanism installed on the installation box 13, and the stamping mechanism drives multiple counterweights 16 to perform periodic reciprocating swings. The stamping mechanism includes a motor 17 fixedly installed on the installation box 13 located at the bottom, an eccentric wheel 18 is fixedly installed on the output shaft of the motor 17, and a connecting rod 19 is rotatably installed on the eccentric wheel 18. A transmission rod 20 is slidably installed in multiple installation boxes 13, and the other end of the connecting rod 19 is rotatably connected to the transmission rod 20. A plurality of second connecting plates 21 are fixedly installed on the transmission rod 20, and the second connecting plates 21 correspond to the installation boxes 13 one by one. The second connecting plates 21 are located inside the installation box 13, and a driving rod 22 is rotatably installed on the second connecting plate 21, and the driving rod 22 corresponds to the first connecting plate 15 one by one and is rotatably connected. The starting motor 17 drives the eccentric wheel 18 to rotate, and the rotating eccentric wheel 18 will drive the connecting rod 19 to rotate. The rotation of the connecting rod 19 can drive the transmission rod 20 to slide in the installation box 13, thereby driving the second connecting plate 21 to slide back and forth, and then pushing the driving rod 22 to rotate. The rotating driving rod 22 will push the two first connecting plates 15 located in the same installation box 13 to rotate periodically. The rotation process is a small amplitude approaching and moving away from each other, so that the counterweight block 16 can rotate and generate sufficient centrifugal force to act on the installation box 13, so that the installation box 13 can produce sufficient pulling force on the balancing box 10 to overcome the lateral force on the balancing box 10 that causes the balancing box 10 to rotate.
[0041] The working principle of this embodiment is as follows: the operator operates the water gantry crane 7 and the electric winch controller to move the water gantry crane 7 to the object to be transferred, the electric winch 8 is synchronously in place, the wire rope 9 connected to the hook 11 is lowered, the hook 11 is lowered above the hanging object, the construction personnel fix the hanging object on the hook 11, the operator operates the water gantry crane 7 and the electric winch 8 controller to transfer the hanging object to the target position, when the hanging cargo is shaken by the sea breeze, the starting motor 17 drives the eccentric wheel 18 to rotate, and the rotating eccentric wheel 18 drives the connecting rod 19 to rotate, through The rotation of the connecting rod 19 can drive the transmission rod 20 to slide in the installation box 13, thereby driving the second connecting plate 21 to slide back and forth, and then driving the driving rod 22 to rotate. The rotating driving rod 22 will drive the two first connecting plates 15 located in the same installation box 13 to rotate periodically. The rotation process is to approach and move away from each other in a small range, so that the counterweight block 16 can rotate and generate sufficient centrifugal force to act on the installation box 13, so that the installation box 13 can produce enough pulling force on the trim box 10 to overcome the lateral force on the trim box 10 that causes the trim box 10 to rotate. The gravity inside the trim box 10 and the pulling force on the trim box 10 caused by the counterweight block 16 can be decomposed into a pulling force in the opposite direction of the shaking of the trim box 10, thereby reducing the shaking degree of the trim box 10.
[0042] The above-mentioned specific embodiments are only several optional embodiments of the present invention. Based on the technical solution of the present invention and the relevant inspiration of the above-mentioned embodiments, those skilled in the art can make various alternative improvements and combinations to the above-mentioned specific embodiments.
Claims
1. A water vertical and horizontal transportation system used for the construction of a high-pile wharf superstructure, comprising two steel pipe pile foundations (1), characterized in that: Also includes: The steel pipe pile foundation (1) is provided with a bottom cross beam (2), a foundation beam (3) and a pedestrian bridge (4) are mounted on the bottom cross beam (2), a gantry track (5) is fixedly mounted on the foundation beam (3), a water gantry crane (7) is mounted on the gantry track (5), a first driving device for driving the water gantry crane (7) to move along the gantry track (5) is provided on the steel pipe pile foundation (1), and a cable laying platform (6) is provided on one of the steel pipe pile foundations (1).
2. The water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock according to claim 1 is characterized in that: The above-water gantry crane (7) is equipped with an electric winch (8), and the electric winch (8) is equipped with a second driving mechanism for driving the electric winch (8) to move along the above-water gantry crane (7). A steel wire rope (9) is fixedly mounted on the electric winch (8), and a trim box (10) is fixedly mounted on one end of the steel wire rope (9), and a hook (11) is fixedly mounted on the trim box (10).
3. The water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock according to claim 2 is characterized in that: An anti-sway component is installed in the trim box (10), and the anti-sway component applies a resistance to the steel wire rope (9) in a direction opposite to the swaying direction of the steel wire rope (9).
4. The water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock according to claim 3 is characterized in that: The anti-sway component comprises a traction rope (12) fixedly mounted in a balancing box (10), a plurality of installation boxes (13) being fixedly mounted on the other end of the traction rope (12), and two adjacent installation boxes (13) being fixedly connected via a connecting block.
5. The water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock according to claim 4 is characterized in that: The anti-sway component also includes a counterweight assembly fixedly mounted in the installation box (13), the counterweight assembly including two support rods (14) fixed in the installation box (13), a first connecting plate (15) rotatably mounted on the support rods (14), and a counterweight block (16) fixedly mounted on the first connecting plate (15).
6. The water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock according to claim 5, characterized in that: The anti-sway component also includes a stamping mechanism installed on the installation box (13), and the stamping mechanism drives the plurality of counterweight blocks (16) to perform periodic reciprocating swings.
7. The water vertical and horizontal transportation system used for the construction of the superstructure of a high-pile dock according to claim 6 is characterized in that: The punching mechanism comprises a motor (17) fixedly mounted on an installation box (13) located at the bottom, an eccentric wheel (18) fixedly mounted on the output shaft of the motor (17), a connecting rod (19) rotatably mounted on the eccentric wheel (18), a transmission rod (20) slidably mounted in the plurality of installation boxes (13), the other end of the connecting rod (19) being rotatably connected to the transmission rod (20), a plurality of second connecting plates (21) fixedly mounted on the transmission rod (20), the second connecting plates (21) corresponding one-to-one to the installation boxes (13), the second connecting plates (21) being located inside the installation box (13), a driving rod (22) rotatably mounted on the second connecting plates (21), the driving rod (22) corresponding one-to-one to the first connecting plates (15) and being rotatably connected.