Elevation survey lofting device before construction of leveling layer
By designing the elevation measurement and staking device before leveling layer construction, using the second vertical rod and the frame to clamp the curb, move the device and observe the scale line to obtain the height difference, efficient staking in leveling layer construction is achieved, and the problems of complex operation and inefficiency in the prior art are solved.
Patent Information
- Application Number
- CN202421924778.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2025-05-23
- Estimated Expiration
- 2034-08-09
AI Technical Summary
In the prior art, the leveling layer is complex and inefficient during construction, and more than 3 people are required to carry instruments and equipment for elevation measurement and stake.
A pre-level elevation measurement and staking device is designed. By placing the curb in the measurement area, clamping the curb with the second vertical rod and the frame, moving the device and observing the scale line to obtain the height difference, taking the average value as the staking elevation line, and drawing lines on the side wall of the curb with marking components to achieve staking.
The stake operation on the curb can be completed by one person, which is simple and efficient, and solves the problem of complex and inefficient operation in the prior art.
Smart Images

Figure CN222893470U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction, and particularly relates to a height measurement and setting-out device before the construction of a leveling layer. Background Art
[0002] At present, the overall pavement of the immersed tube tunnel is composed of a ballast layer, a leveling layer and a pavement layer. The construction of the leveling layer is mainly based on elevation control. As the base layer of the asphalt pavement, the leveling layer has very strict requirements on the flatness and elevation control of the top surface. When the leveling layer is constructed, the curb has been completed, and the design requirements for the elevation deviation of the leveling layer and the curb are the same, both of which are ±10mm.
[0003] However, in the prior art, it is necessary to measure the top surface of the leveling layer by instruments, and more than three people are required to carry instruments and equipment and cooperate with each other to perform the elevation setting out. Moreover, after the instrument setting out is completed, two people are required to draw the ink line, which is complicated and inefficient. Therefore, in order to meet the design requirements and improve the construction efficiency, it is necessary to design a device for measuring and setting out the elevation of the leveling layer before construction. Utility Model Content
[0004] In view of the shortcomings existing in the related art, the utility model provides a device for measuring and laying out the elevation before the construction of the leveling layer. The device is used to place the curb in the measurement area, clamp the curb by the second vertical rod and the frame, and move the device for measuring and laying out the elevation before the construction of the leveling layer. The difference between the actual elevation of the top of the curb and the designed elevation of the top surface of the leveling layer can be obtained by observing the scale line on the second vertical rod. The average value of the maximum and minimum values of the height difference is taken as the laying out elevation line of the top surface elevation of the leveling layer, the position of the marking component is adjusted to the position of the laying out elevation line of the top surface elevation of the leveling layer, and then the device for measuring and laying out the elevation before the construction of the leveling layer is moved again, and the marking component is used to draw a line on the side wall of the curb to achieve laying out. The laying out on the curb can be achieved by one person. The operation is simple and efficient. It solves the technical problems of complex operation and low efficiency existing in the prior art.
[0005] The utility model provides a device for measuring and setting out elevation before construction of a leveling layer, comprising:
[0006] A frame, the frame comprising a first vertical rod and a cross rod connected and arranged at right angles, one end of the first vertical rod being connected to one end of the cross rod;
[0007] a second vertical rod, wherein the second vertical rod is provided with scale lines along its length direction; the second vertical rod is slidably connected to the cross rod along the length direction of the cross rod; the second vertical rod is parallel to the first vertical rod; a measuring area is formed between the first vertical rod, the cross rod and the second vertical rod;
[0008] A locking member, the locking member is used to fix the relative position between the second vertical rod and the cross rod;
[0009] A marking assembly is slidably connected to the second vertical rod along the length direction of the second vertical rod, and the marking assembly is used for marking the curb.
[0010] In the technical solution, by placing the curb in the measurement area, clamping the curb by the second vertical rod and the frame, moving the elevation measurement and layout device before the construction of the leveling layer, the height difference between the measured elevation of the top of the curb and the designed elevation of the top surface of the leveling layer can be obtained by observing the scale line on the second vertical rod. The average value of the maximum and minimum values of the height difference is taken as the layout elevation line of the top surface elevation of the leveling layer, the position of the marking component is adjusted to the position of the layout elevation line of the top surface elevation of the leveling layer, and then the elevation measurement and layout device before the construction of the leveling layer is moved again, and the marking component is used to draw a line on the side wall of the curb to achieve layout. It can be realized by one person to layout on the curb. The operation is simple and efficient. It solves the technical problems of complex operation and low efficiency existing in the prior art.
[0011] In some embodiments, a first roller is disposed on the first vertical rod, and a peripheral wall of the first roller is used to roll on a side wall of the curb.
[0012] In the technical solution, the setting of the first roller makes the device move more smoothly and steadily along the side wall of the curb, reduces the friction and resistance between the device and the curb, improves work efficiency, protects the curb from scratches, and improves the accuracy and efficiency of measurement.
[0013] In some embodiments, a first sliding sleeve is sleeved on the first vertical rod, and the first sliding sleeve can slide along the length direction of the first vertical rod; and the first roller is disposed on the first sliding sleeve.
[0014] In the technical solution, the first sliding sleeve allows the user to adjust the position of the first roller according to actual needs to adapt to curbs of different heights or shapes, thereby enhancing the adaptability and flexibility of the device.
[0015] In some embodiments, a first threaded member is disposed on and threadedly connected to the first sliding sleeve. The first threaded member is disposed on the first sliding sleeve and is used to abut against the first vertical rod.
[0016] In the technical solution, the first threaded member fixes the position of the first sliding sleeve on the first vertical rod through a threaded connection, thereby ensuring the stability of the first roller after adjustment and preventing the first roller from accidentally sliding during use.
[0017] In some of the embodiments, a second roller is disposed on the cross bar, and a peripheral wall of the second roller is used to roll on the top wall of the curb.
[0018] In the technical solution, the setting of the second roller makes the device move more smoothly and steadily along the side wall of the curb, reduces the friction and resistance between the device and the curb, improves work efficiency, protects the curb from scratches, and improves the accuracy and efficiency of measurement.
[0019] In some embodiments, a second sliding sleeve is sleeved on the cross bar, and the second sliding sleeve can slide along the length direction of the cross bar; the second roller is arranged on the second sliding sleeve.
[0020] In the technical solution, the second sliding sleeve allows the position of the second roller to be flexibly adjusted to accommodate curbstones of different widths or measurement requirements, further enhancing the adaptability and flexibility of the device.
[0021] In some embodiments, a second threaded member is disposed on and threadedly connected to the second sliding sleeve, and the second threaded member is disposed on the second sliding sleeve and is used to abut against the cross bar.
[0022] In the technical solution, the second threaded member fixes the position of the second sleeve on the cross bar through a threaded connection, thereby ensuring the stability of the second roller after adjustment, preventing the second roller from shifting during use, and ensuring the accuracy of the measurement.
[0023] In some embodiments, the marking assembly includes a third sliding sleeve and a marking tool, the third sliding sleeve is sleeved and slid on the second vertical rod, the marking tool is detachably connected to the third sliding sleeve, and the marking tool is used to mark the side wall of the curb.
[0024] In the technical solution, the design of the marking assembly allows the user to adjust the position of the marking tool by sliding the third sliding sleeve, so that the curb can be accurately marked. The detachable connection of the marking tool facilitates the replacement of different types of marking tools to meet different marking requirements.
[0025] In some embodiments, a third roller is provided on a side of the third sliding sleeve facing the first vertical rod, a third threaded member is passed through and threadedly connected to the third sliding sleeve, and the third threaded member is used to abut against the second vertical rod.
[0026] In the technical solution, the third roller makes the marking assembly more stable when sliding along the second vertical rod, reduces the friction between the marking assembly and the curb, and improves the accuracy and efficiency of marking. The third threaded member is used to fix the position of the third sleeve on the second vertical rod to ensure the stability of the marking tool during use.
[0027] In some embodiments, a slide groove is passed through the second vertical rod, the cross rod is passed through and slidably connected to the slide groove, and the distance between each side wall of the slide groove and the corresponding side wall of the cross rod is 1 mm.
[0028] In the technical solution, the slot design on the second vertical rod enables the crossbar to slide accurately along its length, and the 1mm spacing between the side walls of the slot and the side walls of the crossbar provides the necessary clearance to ensure smooth sliding and prevent problems such as poor sliding or shaking caused by being too tight or too loose. This design helps to improve the accuracy and stability of the measurement.
[0029] Based on the above technical scheme, in the embodiment of the utility model, by placing the curb in the measurement area, clamping the curb by the second vertical rod and the frame, moving the elevation measurement and layout device before the construction of the leveling layer, the height difference between the measured elevation of the top of the curb and the designed elevation of the top surface of the leveling layer can be obtained by observing the scale line on the second vertical rod. Take the average of the maximum and minimum values of the height difference as the layout elevation line of the top surface elevation of the leveling layer, adjust the position of the marking component to the position of the layout elevation line of the top surface elevation of the leveling layer, and then move the elevation measurement and layout device before the construction of the leveling layer again, and use the marking component to draw a line on the side wall of the curb to achieve layout. It can be realized by one person to layout on the curb. It is simple and efficient to operate. It can solve the technical problems of complex operation and low efficiency existing in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:
[0031] Figure 1 This is a schematic diagram of the overall structure of an embodiment of the elevation measurement and setting out device before the leveling layer construction of the utility model;
[0032] Figure 2 This is a schematic diagram of the overall structure of an embodiment of the elevation measurement and setting out device before the leveling layer construction of the utility model;
[0033] Figure 3 This is a front view of an embodiment of the elevation measurement and setting out device before the leveling layer construction of the utility model;
[0034] Figure 4 It is a right view of an embodiment of the elevation measurement and setting out device before the leveling layer construction of the utility model;
[0035] Figure 5 The utility model is a top view of an embodiment of the elevation measurement and layout device before the leveling layer construction.
[0036] In the figure:
[0037] 100, frame; 101, first vertical rod; 102, horizontal rod; 200, second vertical rod; 201, slide groove; 300, first sleeve; 400, first roller; 500, first threaded member; 600, second sleeve; 700, second roller; 800, second threaded member; 900, marking assembly; 901, third sleeve; 902, marking tool; 903, third threaded member; 110, locking member; 120, third roller. DETAILED DESCRIPTION
[0038] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0039] In the description of the present invention, it should be understood that the terms "center", "lateral", "longitudinal", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0040] The terms "first", "second", and "third" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the technical features indicated. Thus, a feature defined as "first", "second", and "third" may explicitly or implicitly include one or more of the features.
[0041] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0042] Please refer to all the accompanying drawings. In an illustrative embodiment of the device for measuring and staking out the elevation before the construction of the leveling layer of the utility model, the device for measuring and staking out the elevation before the construction of the leveling layer includes: a frame 100, a second vertical rod 200, a locking member 110 and a marking assembly 900; wherein the frame 100 includes a first vertical rod 101 and a horizontal rod 102 connected and arranged at right angles, and one end of the first vertical rod 101 is connected to one end of the horizontal rod 102.
[0043] The second vertical rod 200 is provided with scale lines along its length direction; the second vertical rod 200 is slidably connected to the cross bar 102 along the length direction of the cross bar 102; the second vertical rod 200 is parallel to the first vertical rod 101; a measuring area is formed between the first vertical rod 101, the cross bar 102 and the second vertical rod 200.
[0044] The locking member 110 is used to fix the relative position between the second vertical rod 200 and the horizontal rod 102 .
[0045] The marking assembly 900 is slidably connected to the second vertical rod 200 along the length direction of the second vertical rod 200 , and the marking assembly 900 is used to mark the curb.
[0046] Through the above scheme, by placing the curb in the measurement area, clamping the curb by the second vertical rod 200 and the frame 100, moving the elevation measurement and layout device before the construction of the leveling layer, the height difference between the measured elevation of the top of the curb and the designed elevation of the top surface of the leveling layer can be obtained by observing the scale line on the second vertical rod 200. Take the average value of the maximum and minimum values of the height difference as the layout elevation line of the top surface elevation of the leveling layer, adjust the position of the marking component 900 to the position of the layout elevation line of the top surface elevation of the leveling layer, and then move the elevation measurement and layout device before the construction of the leveling layer again, and use the marking component 900 to draw a line on the side wall of the curb to achieve layout. It can be realized by one person to layout on the curb. The operation is simple and efficient. It solves the technical problems of complex operation and low efficiency in the prior art.
[0047] In some embodiments, a plurality of scale marks are evenly spaced along the length direction of the second vertical rod 200 .
[0048] In some embodiments, the second vertical rod 200 can directly use a steel ruler.
[0049] In some embodiments, during operation, the length direction of the first vertical rod 101 is vertically arranged, and the first vertical rod 101 is used to be located at one side in the width direction of the curb.
[0050] In some embodiments, during operation, the length direction of the cross bar 102 is horizontally arranged, and one end of the cross bar 102 is connected to the top end of the first vertical bar 101 .
[0051] In some embodiments, during operation, the length direction of the crossbar 102 is the same as the width direction of the curb.
[0052] In some embodiments, the length of the first vertical rod 101 is 3 cm to 5 cm greater than the height of the curb. This size is convenient for operation and sufficient to cope with errors. When the length of the first vertical rod 101 is approximately 3 cm greater than the height of the curb, it is convenient for operation. If the length of the first vertical rod 101 is greater than the height of the curb by more than 5 cm, the overall structure may be large and inconvenient to operate.
[0053] In some embodiments, the length of the crossbar 102 is 3 cm to 5 cm greater than the width of the curb. This size is convenient for operation and sufficient to cope with errors. When the length of the crossbar 102 is approximately 3 cm greater than the width of the curb, it is convenient for operation. If the length of the crossbar 102 is greater than the width of the curb by more than 5 cm, the overall structure may be large and inconvenient to operate.
[0054] In some embodiments, the length of the second vertical rod 200 is 3 cm to 5 cm greater than the height of the curb. This size is convenient for operation and sufficient to cope with errors. When the length of the second vertical rod 200 is approximately 3 cm greater than the height of the curb, it is convenient for operation. If the length of the second vertical rod 200 is greater than the height of the curb by more than 5 cm, the overall structure may be large and inconvenient to operate.
[0055] In some embodiments, the frame 100 may be provided with a handle for manual holding, so as to facilitate manual movement of the elevation measurement and layout device before the construction of the leveling layer in an upright walking posture.
[0056] In some embodiments, a first roller 400 is disposed on the first vertical rod 101, and the peripheral wall of the first roller 400 is used to roll on the side wall of the curb. The provision of the first roller 400 makes the device move more smoothly and steadily along the side wall of the curb, reduces the friction and resistance between the device and the curb, improves work efficiency, protects the curb from scratches, and improves the accuracy and efficiency of measurement.
[0057] In some embodiments, the axial direction of the first roller 400 is the same as the length direction of the first vertical rod 101 , so as to facilitate the rolling of the first roller 400 .
[0058] In some embodiments, the first vertical rod 101 is sleeved with a first sliding sleeve 300, and the first sliding sleeve 300 can slide along the length direction of the first vertical rod 101; the first roller 400 is disposed on the first sliding sleeve 300. The first sliding sleeve 300 allows the user to adjust the position of the first roller 400 according to actual needs to adapt to curbs of different heights or shapes, thereby enhancing the adaptability and flexibility of the device.
[0059] In some embodiments, the first roller 400 is disposed on a side of the first sliding groove 201 facing the second vertical rod 200 .
[0060] In some embodiments, the first roller 400 is rotatably connected to the first sleeve 300. Because the first vertical rod 101 may not always be vertically arranged when the layout device is moved, the first roller 400 can adapt itself according to the moving direction.
[0061] In some embodiments, a first threaded member 500 is provided on and threadedly connected to the first sleeve 300, and the first threaded member 500 is provided on the first sleeve 300 and is used to abut against the first vertical rod 101. The first threaded member 500 fixes the position of the first sleeve 300 on the first vertical rod 101 through threaded connection, ensures the stability of the first roller 400 after adjustment, and prevents the first roller 400 from accidentally sliding during use.
[0062] In some embodiments, the first threaded member 500 may be disposed on a side of the first sliding sleeve 300 away from the second vertical rod 200 , so as to facilitate manual adjustment.
[0063] In some embodiments, a second roller 700 is provided on the crossbar 102, and the peripheral wall of the second roller 700 is used to roll on the top wall of the curb. The provision of the second roller 700 makes the device move more smoothly and steadily along the side wall of the curb, reduces the friction and resistance between the device and the curb, improves work efficiency, protects the curb from scratches, and improves the accuracy and efficiency of measurement.
[0064] In some embodiments, the crossbar 102 is sleeved with a second sliding sleeve 600, which can slide along the length direction of the crossbar 102; the second roller 700 is disposed on the second sliding sleeve 600. The second sliding sleeve 600 allows the position of the second roller 700 to be flexibly adjusted to accommodate curbstones of different widths or measurement requirements, further enhancing the adaptability and flexibility of the device.
[0065] In some embodiments, the second roller 700 is rotatably connected to the first sleeve 300. Because the crossbar 102 may be offset when the layout device is moved, the second roller 700 can adapt itself according to the moving direction.
[0066] In some embodiments, a second threaded member 800 is provided on and threadedly connected to the second sleeve 600, and the second threaded member 800 is provided on the second sleeve 600 and is used to abut the cross bar 102. The second threaded member 800 fixes the position of the second sleeve 600 on the cross bar 102 through threaded connection, ensures the stability of the second roller 700 after adjustment, prevents the second roller 700 from deflecting during use, and ensures the accuracy of measurement.
[0067] In some embodiments, the second threaded member 800 may be disposed on a side of the second sleeve 600 away from the measuring area, that is, the second threaded member 800 may be disposed on a side of the second sleeve 600 away from the curbstone, so as to facilitate manual operation.
[0068] In some embodiments, the marking assembly 900 includes a third sliding sleeve 901 and a marking tool 902. The third sliding sleeve 901 is sleeved and slid on the second vertical rod 200. The marking tool 902 is detachably connected to the third sliding sleeve 901. The marking tool 902 is used to mark the side wall of the curb. The design of the marking assembly 900 allows the user to adjust the position of the marking tool 902 by sliding the third sliding sleeve 901, so that the curb can be accurately marked. The detachable connection of the marking tool 902 makes it easy to replace different types of marking tools 902 to meet different marking requirements.
[0069] In some embodiments, the marking tool 902 can be a pencil, a marker, etc.
[0070] In some embodiments, a buckle is provided on the third sliding sleeve 901 , and the buckle is used to snap into the marking tool 902 .
[0071] In some embodiments, a third roller 120 is provided on the side of the third sleeve 901 facing the first vertical rod 101, and a third threaded member 903 is provided and threadedly connected on the third sleeve 901, and the third threaded member 903 is used to abut the second vertical rod 200. The provision of the third roller 120 makes the marking assembly 900 more stable when sliding along the second vertical rod 200, reduces the friction between the marking assembly 900 and the curb, and improves the accuracy and efficiency of the marking. The third threaded member 903 is used to fix the position of the third sleeve 901 on the second vertical rod 200, ensuring the stability of the marking tool 902 during use.
[0072] In some embodiments, a slide groove 201 is passed through the second vertical rod 200, and the cross bar 102 is passed through and slidably connected to the slide groove 201. The distance between each side wall of the slide groove 201 and the corresponding side wall of the cross bar 102 is 1 mm. The design of the slide groove 201 on the second vertical rod 200 enables the cross bar 102 to slide accurately along its length direction, and the 1 mm distance between each side wall of the slide groove 201 and the side wall of the cross bar 102 provides the necessary clearance, ensures the smoothness of sliding, and prevents the problem of poor sliding or shaking caused by being too tight or too loose. This design helps to improve the accuracy and stability of measurement.
[0073] In some embodiments, the locking member 110 is a fourth threaded member, which passes through the second vertical rod 200, and the end of the fourth threaded member can be located in the slide groove 201. The end of the fourth threaded member abuts against the cross bar 102, so that the cross bar 102 and the second vertical rod 200 are fixed.
[0074] In some embodiments, the locking member 110 can also be a latch pin. A positioning hole connected to the slide groove 201 is penetrated on the second vertical rod 200, and a plurality of pin holes are provided on the cross bar 102 along its length direction. The latch pin passes through the positioning hole and is plugged into the corresponding pin hole to fix the cross bar 102 and the second vertical rod 200.
[0075] In some embodiments, an identification member is further included, and the identification member is used to identify and record the corresponding position of the upper surface of the curb and the scale line on the second vertical rod 200. It is not necessary to manually observe the relationship between the upper surface of the curb and the scale line all the time.
[0076] In some embodiments, specific forms of the first threaded member 500 , the second threaded member 800 , the third threaded member 903 , and the fourth threaded member include but are not limited to bolts, screws, threaded rods, and studs.
[0077] In some embodiments, the first threaded member 500 , the second threaded member 800 , the third threaded member 903 , and the fourth threaded member are specifically in the form of hand-tightened bolts, which are convenient for manual operation.
[0078] In some embodiments, the construction method is:
[0079] S100, preparation.
[0080] S101, determining the lengths of the cross bar 102, the first vertical bar 101, and the second cross bar 102 according to the height difference between the measured elevation of the top of the curb and the designed elevation of the top surface of the leveling layer.
[0081] S102, controlling the length of the horizontal bar 102 to be greater than the width of the upper surface of the curb by 3 cm-5 cm. Controlling the length of the first vertical bar 101 and the second vertical bar 200 to be greater than the height of the curb by 3 cm-5 cm.
[0082] S103 , marking a scale line on the second vertical rod 200 .
[0083] S104, a slide groove 201 is provided on the second vertical rod 200 according to the cross-sectional size of the cross rod 102, so that the distance between each side wall of the slide groove 201 and the corresponding side wall of the cross rod 102 is 1 mm.
[0084] S200, observation phase.
[0085] S201, placing the measuring area at the curbstone, making the first roller 400 contact the side wall of the curbstone in the width direction, and the second roller 700 contact the top wall of the curbstone.
[0086] S202 , according to the width of the curb, the second vertical rod 200 is slid on the cross bar 102 , and the third roller 120 is brought into contact with the side wall of the curb. The relative position of the second vertical rod 200 and the cross bar 102 is fixed by the locking member 110 .
[0087] S203, moving the second sliding sleeve 600 so that the second sliding sleeve 600 and the second roller 700 are located in the middle of the top of the curb;
[0088] S204, elevation measurement and setting out device before the overall mobile leveling layer construction. Observe the height difference between the measured elevation of the top of the curb and the designed elevation of the top of the leveling layer.
[0089] S205, taking the average of the maximum value and the minimum value of the height difference as the lofting elevation line of the top surface elevation of the leveling layer;
[0090] S300, lofting stage.
[0091] S301 , move the third sliding sleeve 901 so that the center of the mark of the marking tool 902 is located at the position of the lofting elevation line of the top surface elevation of the leveling layer. Tighten the third threaded member 903 so that the end of the third threaded member 903 abuts against the second vertical rod 200 .
[0092] S302, moving the elevation measurement and layout device before the mobile leveling layer construction, and drawing lines on the side wall of the curbstone by using the marking tool 902 to achieve layout.
[0093] Through the description of multiple embodiments of the device for measuring and setting out elevation before construction of the leveling layer of the utility model, it can be seen that the device for measuring and setting out elevation before construction of the leveling layer of the utility model has at least one or more of the following advantages:
[0094] 1. Place the curbstone in the measurement area, clamp the curbstone with the second vertical rod 200 and the frame 100, move the elevation measurement and layout device before the leveling layer construction, and observe the scale line on the second vertical rod 200 to obtain the elevation difference between the actual elevation of the top of the curbstone and the design elevation of the top surface of the leveling layer. Take the average of the maximum and minimum values of the elevation difference as the layout elevation line of the top surface elevation of the leveling layer, adjust the position of the marking component 900 to the position of the layout elevation line of the top surface elevation of the leveling layer, and then move the elevation measurement and layout device before the leveling layer construction again, and use the marking component 900 to draw lines on the side wall of the curbstone to achieve layout. One person can achieve layout on the curbstone. It is easy to operate and efficient. To solve the technical problems of complex operation and low efficiency in the prior art;
[0095] 2. The second vertical rod 200 is penetrated by a slide groove 201, and the cross bar 102 is inserted and slidably connected to the slide groove 201. The distance between each side wall of the slide groove 201 and the corresponding side wall of the cross bar 102 is 1 mm. The design of the slide groove 201 on the second vertical rod 200 enables the cross bar 102 to slide accurately along its length direction, and the 1 mm distance between each side wall of the slide groove 201 and the side wall of the cross bar 102 provides the necessary clearance, ensuring the smoothness of sliding and preventing the problem of poor sliding or shaking caused by being too tight or too loose. This design helps to improve the accuracy and stability of measurement.
[0096] Finally, it should be noted that: the various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0097] The above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model is described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the utility model can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the utility model, which should be included in the scope of the technical solution for which protection is requested in the utility model.
Claims
1. A device for measuring and laying out elevation before construction of a leveling layer, characterized in that: include: A frame, the frame comprising a first vertical rod and a cross rod connected and arranged at right angles, one end of the first vertical rod being connected to one end of the cross rod; A second vertical rod, wherein the second vertical rod is provided with scale lines along its length direction; the second vertical rod is slidably connected to the cross rod along the length direction of the cross rod; The second vertical rod is parallel to the first vertical rod; a measuring area is formed between the first vertical rod, the cross rod and the second vertical rod; A locking member, the locking member is used to fix the relative position between the second vertical rod and the cross rod; A marking assembly is slidably connected to the second vertical rod along the length direction of the second vertical rod, and the marking assembly is used for marking the curb.
2. The elevation measurement and setting-out device before leveling layer construction according to claim 1 is characterized in that: A first roller is arranged on the first vertical rod, and a peripheral wall of the first roller is used for rolling on the side wall of the curbstone.
3. The elevation measurement and setting-out device before leveling layer construction according to claim 2 is characterized in that: The first vertical rod is sleeved with a first sliding sleeve, and the first sliding sleeve can slide along the length direction of the first vertical rod; the first roller is arranged on the first sliding sleeve.
4. The elevation measurement and setting-out device before leveling layer construction according to claim 3 is characterized in that: A first threaded member is disposed on and threadedly connected to the first sliding sleeve. The first threaded member is disposed on the first sliding sleeve and is used to abut against the first vertical rod.
5. The elevation measurement and setting-out device before leveling layer construction according to claim 1 is characterized in that: A second roller is arranged on the cross bar, and a peripheral wall of the second roller is used for rolling on the top wall of the curbstone.
6. The elevation measurement and setting-out device before leveling layer construction according to claim 5 is characterized in that: The cross bar is sleeved with a second sliding sleeve, and the second sliding sleeve can slide along the length direction of the cross bar; the second roller is arranged on the second sliding sleeve.
7. The elevation measurement and setting-out device before leveling layer construction according to claim 6 is characterized in that: A second threaded member is disposed on and threadedly connected to the second sliding sleeve. The second threaded member is disposed on the second sliding sleeve and is used to abut against the cross bar.
8. The device for measuring and laying out elevation before construction of the leveling layer according to claim 1 is characterized in that: The marking assembly includes a third sliding sleeve and a marking tool. The third sliding sleeve is sleeved and slid on the second vertical rod. The marking tool is detachably connected to the third sliding sleeve and is used for marking on the side wall of the curb.
9. The elevation measurement and setting-out device before leveling layer construction according to claim 8 is characterized in that: A third roller is disposed on the side of the third sliding sleeve facing the first vertical rod. A third threaded member is passed through and threadedly connected to the third sliding sleeve. The third threaded member is used to abut against the second vertical rod.
10. The device for measuring and laying out elevation before construction of the leveling layer according to claim 1, characterized in that: The second vertical rod is penetrated by a slide groove, the cross bar is penetrated by and slidably connected to the slide groove, and the distance between each side wall of the slide groove and the corresponding side wall of the cross bar is 1 mm.