Space structure large-span rope net combined operation platform

By adopting an operating platform combining 10# wire rope, safety flat net and tensioning parts, the safety hazards of uneven loads in high-altitude and large span construction are solved, safe and reliable construction results are achieved and costs are reduced.

CN222909381UActive Publication Date: 2025-05-27ZHEJIANG XINHUA CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421838581.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2025-05-27
Estimated Expiration
2034-07-31

AI Technical Summary

Technical Problem

The existing operating platforms have uneven loads during high-altitude and large span construction, resulting in safety hazards and high cost of erection and demolition.

Method used

The space structure large-span rope mesh combination operation platform is used to combine 10# wire rope, safety flat net and tensioning parts. Through the connection of tension anchor components, steel pipes and wire ropes, an operating platform with single-point concentrated load is formed.

Benefits of technology

It realizes safety and reliability in high-altitude and large span construction, reduces the cost of erection and demolition, and is not affected by the space span.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222909381U_ABST
    Figure CN222909381U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building construction, in particular to a spatial structure large-span rope net combined operation platform which comprises a tensioning anchor assembly, a steel pipe, a steel wire rope, a safety flat net and a flat net pull rope. The tensioning anchor assemblies are fixed to the structural plate, and the adjacent tensioning anchor assemblies distributed transversely are connected through steel pipes. A steel wire rope is connected between the adjacent tensioning anchor assemblies which are longitudinally distributed; the safety flat net is arranged above the structural beams, and the periphery of the safety flat net is connected with the steel pipes through a plurality of flat net pull ropes. The construction platform is formed by combining the 10 # steel wire ropes, the safety flat net and the tensioning pieces, the construction safety requirement can be met through single-point concentrated loads, meanwhile, the cost can be effectively reduced, and construction of the whole platform is safe and reliable and is not affected by the space span.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a large-span rope net combined operating platform with a spatial structure. Background Art

[0002] At the building elevation of 66.9m, there is a steel structure + aluminum plate + glass skylight. The net height of the space structure is 45.4 meters, and the plane size of the space opening is a net length of 44 meters and a net width of 13.7 meters. The space opening starts from the sixth-floor structure to the roof structure. Due to the decorative construction requirements of the steel structure skylight, it is necessary to provide a work platform for the installers. The existing work platform uses steel pipe fastener type, steel beam type, and disc buckle type scaffolding, but due to the large height and area, the six-story structure beam plate is insufficient to bear the load and is unsafe; if the material rental fee is not considered, the cost of erection and dismantling alone is about 200,000, and the investment cost is relatively large. Utility Model Content

[0003] The purpose of the utility model is to address the defects and shortcomings of the prior art and provide a spatial structure large-span rope net combined operating platform, which is composed of 10# steel wire rope, safety flat net and tensioning parts. The single-point concentrated load can meet the construction safety requirements and can effectively reduce costs. The construction of the entire platform is safe and reliable and is not affected by the spatial span.

[0004] In order to achieve the above-mentioned purpose, the utility model adopts the following technical solutions: it includes a tension anchor assembly, a steel pipe, a steel wire rope, a safety flat net and a flat net pull rope; the tension anchor assembly is fixed on the structural plate, and the adjacent tension anchor assemblies distributed laterally are connected by steel pipes; the adjacent tension anchor assemblies distributed longitudinally are connected by steel wire ropes; the safety flat net is placed above the structural beam, and the periphery is connected to the steel pipe by a plurality of flat net pull ropes.

[0005] Preferably, a hard moving platform is provided on the safety net.

[0006] Preferably, the end of the steel pipe is inserted into the ear plate in the tension anchor assembly and fixed by a bolt assembly.

[0007] Preferably, the steel wire rope is a 10# steel wire rope.

[0008] Preferably, the steel pipe is a 50×5 steel pipe.

[0009] Preferably, the steel wire rope is inserted into two steel wire rope insertion plates in the tension anchor assembly and is fixed by a double semicircular anchor clamp.

[0010] Compared with the prior art, the beneficial effects of the utility model are: providing a spatial structure large-span rope net combined operating platform, using 10# steel wire rope + safety flat net + tensioning parts to form an operating platform, 10 mm diameter steel wire rope, taking 6×7 structure, hemp core 1570MPa strength level as an example, its minimum breaking tensile force is 52.1 kilonewtons, about 5.3 tons, all materials and labor costs total about 30,000, the safety flat net is set on two floors, and the decoration construction personnel are required to work at the same time. No more than 3 people (calculated at 75KG per person), no more than 50KG of materials are placed on the platform wooden board, and the total single-point concentrated load is about 275KG, and safety belts must be worn, and the safety belts are hung on the top steel structure, so the entire platform construction is safe and reliable and is not affected by the spatial span. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the installation structure of the utility model.

[0012] Figure 2 It is a connection schematic diagram of the tension anchor assembly, steel pipe and steel wire rope in the utility model.

[0013] Figure 3 It is a side view of the connection between the tension anchor assembly and the steel wire rope in the utility model.

[0014] Description of reference numerals:

[0015] Structural plate 1, tension anchor assembly 2, ear plate 2-1, wire rope insertion plate 2-2, double semicircular anchor clamp 2-3, steel pipe 3, wire rope 4, safety flat net 5, flat net pull rope 6, hard mobile platform 7, structural beam 8. DETAILED DESCRIPTION

[0016] The technical solution of the utility model will be clearly and completely described below in conjunction with the accompanying drawings. The preferred embodiments in the description are only used as examples, and all other embodiments obtained by those skilled in the art without making any creative work are within the scope of protection of the utility model.

[0017] like Figure 1-Figure 3As shown, this specific embodiment adopts the following technical scheme: it includes a tension anchor assembly 2, a steel pipe 3, a steel wire rope 4, a safety flat net 5 and a flat net pull rope 6; the tension anchor assembly 2 is fixed on the structural plate 1, and the adjacent tension anchor assemblies 2 distributed laterally are connected by the steel pipe 3, and the end of the steel pipe 3 is inserted in the ear plate 2-1 in the tension anchor assembly 2 and fixed by a bolt assembly; the adjacent tension anchor assemblies 2 distributed longitudinally are connected by a steel wire rope 4, the steel wire rope 4 is a 10# steel wire rope, the steel wire rope 4 is inserted in the two steel wire rope insertion plates 2-2 in the tension anchor assembly 2, and is fixed by a double semicircular anchor clamp 2-3; the safety flat net 5 is placed above the structural beam 8, and the periphery is connected to the steel pipe 3 by a plurality of flat net pull ropes 6, and a hard mobile platform 7 is arranged on the safety flat net 5.

[0018] The manufacturing and installation method of the utility model is as follows:

[0019] 1. The laser cutting method is used for plate cutting to ensure the consistency of size. Each finished plate after cutting must be clearly marked;

[0020] 2. The pipes are cut with a toothless saw according to the actual size measured on site. The safety net 5 and 10# steel wire rope 4 are purchased from the market, and the tension anchor assembly 2 is rented;

[0021] 3. The tension anchor assembly 2 is transported to the site and transported vertically to the installation site by a tower crane or a passenger and cargo elevator. First, the dimension flush with the column edge is measured from the side beam of the space opening structure beam 8 to the outside, and the line is drawn. Generally, it is controlled to be 100mm outside the column edge. Then, the grid is divided at a spacing of 1.5-2m. When encountering a column, it needs to be avoided. After all the divisions are completed, the tension anchor assembly 2 is installed. The tension anchor assembly 2 is placed on the control line, and a mark is marked with a pen to drill holes. After all 6 holes are drilled, the tension anchor assembly 2 can be placed, and then the screw cap is tightened. This is repeated until all tension parts are installed.

[0022] 4. Then thread the 10# steel wire rope 4. After one end passes through the tension anchor assembly 2, tie the nylon rope prepared in advance and let the personnel at the other end pull it manually until it reaches the tension anchor assembly 2 at the other end and passes through the steel wire rope insertion plate 2-2, ensuring that each end has an exposed head of no less than 100mm. Then clamp one end with the double semicircular anchor clamp 2-3, and use a tensioning machine to tension the steel wire rope 4 at the other end until it is straightened and tight. Generally, the tensioning force can be controlled at 3KN, which can be adjusted according to the actual use on site;

[0023] 5. Cut the 50×5 steel pipe 3 according to the size measured on site and install it between the two tension anchor assemblies 2, and use M10 long bolts to cap it to prevent it from slipping;

[0024] 6. Lay the safety flat net 5: The holes of the flat net are made of a special net of 70-100mm. Nylon ropes (flat net pull ropes 6) are used to tie the net around. The other end of the nylon rope is firmly tied to the 50×5 steel pipe 3 at the tension anchor assembly 2. Canvas ropes are used to tie the net every 500mm, and special clamps can also be used for fastening;

[0025] 7. Carry out physical test. Use a 100KG sandbag to throw down from the roof to see if the wire rope is broken or deflected more than 200mm, and if there is any crack in the flat net. If necessary, correct the tension and replace the specifications of the safety flat net 5. If all the test requirements are met, it can be put into use. There should be no less than 3 test points.

[0026] Compared with the prior art, the beneficial effects of the utility model are: providing a spatial structure large-span rope net combined operating platform, using 10# steel wire rope + safety flat net + tensioning parts to form an operating platform, 10 mm diameter steel wire rope, taking 6×7 structure, hemp core 1570MPa strength level as an example, its minimum breaking tensile force is 52.1 kilonewtons, about 5.3 tons, all materials and labor costs total about 30,000, the safety flat net is set on two floors, and the decoration construction personnel are required to work at the same time. No more than 3 people (calculated at 75KG per person), no more than 50KG of materials are placed on the platform wooden board, and the total single-point concentrated load is about 275KG, and safety belts must be worn, and the safety belts are hung on the top steel structure, so the entire platform construction is safe and reliable and is not affected by the spatial span.

[0027] For those skilled in the art, they can modify the technical solutions recorded in the aforementioned embodiments and make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present utility model should be included in the protection scope of the present utility model.

Claims

1. A spatial structure large-span rope net combined operation platform, characterized by: It comprises a tension anchor assembly (2), a steel pipe (3), a steel wire rope (4), a safety net (5) and a net pull rope (6); the tension anchor assembly (2) is fixed on the structural plate (1), and adjacent tension anchor assemblies (2) distributed transversely are connected by means of the steel pipe (3); adjacent tension anchor assemblies (2) distributed longitudinally are connected by means of the steel wire rope (4); the safety net (5) is placed above the structural beam (8), and the periphery is connected to the steel pipe (3) by means of a plurality of net pull ropes (6).

2. The spatial structure large-span rope net combined operation platform according to claim 1, characterized in that: A hard moving platform (7) is arranged on the safety flat net (5).

3. The spatial structure large-span rope net combined operation platform according to claim 1, characterized in that: The end of the steel pipe (3) is inserted into the ear plate (2-1) in the tension anchor assembly (2) and fixed by means of a bolt assembly.

4. The spatial structure large-span rope net combined operation platform according to claim 1, characterized in that: The steel wire rope (4) is inserted into two steel wire rope insertion plates (2-2) in the tension anchor assembly (2), and is clamped and fixed by means of a double semicircular anchor clamp (2-3).

5. The spatial structure large-span rope net combined operation platform according to claim 1, characterized in that: The steel wire rope (4) is a 10# steel wire rope.

6. The spatial structure large-span rope net combined operation platform according to claim 1, characterized in that: The steel pipe (3) is a 50×5 steel pipe.