Boiler header long pipe joint pipe bundle positioning device
By assembling components such as porous positioning plates and U-shaped bolts on the long pipe joint of the boiler container into an integrated part, the problem of deformation and falling off during lifting and transportation of traditional fixing methods is solved, and a more efficient installation process and better quality assurance is achieved.
Patent Information
- Application Number
- CN202422249843.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-13
- Publication Date
- 2025-06-20
- Estimated Expiration
- 2034-09-13
AI Technical Summary
The traditional method of fixing the pipe bundle of the long pipe joint of the boiler container can easily cause the fixing plate to deform or fall off during lifting and transportation, resulting in the inability to guarantee the dimensional accuracy and overall shape of the pipe bundle of the joint, which affects the installation operation.
The porous positioning plate, U-shaped bolts, vertical plates, flat pads and nuts are used to assemble into an integrated piece and fixed on the long pipe joint tube bundle to prevent the porous positioning plate from deforming and falling off.
It effectively prevents the fixing plate from deforming and falling off during lifting and transportation, ensures the dimensional accuracy and overall shape of the joint tube bundle, and improves installation efficiency and quality.
Smart Images

Figure CN223004956U_ABST
Abstract
Description
Technical Field
[0001] This application belongs to the technical field of boiler headers, and particularly relates to a positioning device for the long pipe joint tube bundle of a boiler header. Background Art
[0002] In the current field of large-capacity boiler manufacturing, as a key component, a large number of long pipe joint tube bundles are widely integrated on the header. After these components are manufactured, they need to be hoisted and transported, and finally delivered to the construction site for precise tube-to-tube docking operations with the membrane wall tube row. Traditionally, a simple fixing method is generally adopted, that is, a flat steel with a thickness of 5 to 6 mm is drilled and simply sleeved on the joint tube bundle for positioning and fixing.
[0003] However, this traditional fixing method has shown significant limitations in practice. For example, during hoisting and transportation, the fixing plate deforms or even falls off, thus unable to ensure the dimensional accuracy and overall shape of the joint tube bundle. When these components are transported to the construction site, the deviation between the actual size and the preset standard has become a problem that cannot be ignored, directly affecting the subsequent installation operations. Specifically, on-site installers have to spend a large amount of extra time and effort on calibration and assembly to make up for the dimensional deviation caused by the fixing failure during transportation. This process not only increases the labor intensity of construction workers but also significantly prolongs the overall installation cycle, which has an adverse impact on the progress control of the project.
[0004] In view of the above background, there is an urgent need for a more efficient and reliable method for fixing the long pipe joint tube bundle of the header to ensure its stability and accuracy during hoisting, transportation, and installation, thereby effectively improving the overall efficiency and quality of boiler manufacturing and installation. Summary of the Utility Model
[0005] The purpose of the present utility model is to provide a positioning device for the long pipe joint tube bundle of a boiler header to solve the problems of deformation and falling off of the fixing plate that may occur during hoisting and transportation, and to improve the overall installation efficiency and quality.
[0006] To achieve the above application purpose, the technical solution adopted in this application is as follows:
[0007] The embodiment of this application provides a positioning device for the long pipe joint tube bundle of a boiler header, including:
[0008] A porous positioning plate, which is used to be sleeved on the pipe ends of the long pipe joint tube bundle of the boiler header and ensure the spacing position between the long pipe joint tube bundles;
[0009] A U-shaped bolt, which is used to be inserted into a vertical plate and a flat washer, and sleeved with a nut for connection to assemble into a single piece, and the single piece is used to be sleeved and fixed on the pipe ends on both sides of the porous positioning plate;
[0010] Among them, the vertical plate is fixedly connected to the porous positioning plate.
[0011] In some embodiments, the vertical plate is welded to the porous positioning plate.
[0012] In some embodiments, the sleeving positions of the integral parts on both sides of the porous positioning plate have the same depth.
[0013] In some embodiments, the porous positioning plate is provided with a plurality of positioning holes at preset intervals, and the positioning holes are sleeved on the pipe ends.
[0014] Compared with the prior art, the beneficial effects of the embodiments of the present application are as follows:
[0015] A boiler header long pipe joint tube bundle positioning device provided by an embodiment of the present application forms an integral part through a U-shaped bolt, a vertical plate, a flat washer and a nut, and then the integral part is fixed on the long pipe joint tube bundle, which can prevent the porous positioning plate from deforming and falling off, solves the problem of deformation and falling off during the hoisting and transportation of the header, and improves the assembly and installation efficiency and saves the installation time. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the following will briefly introduce the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings in the following description are only some embodiments of the present application. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative efforts.
[0017] Figure 1 Shows the front view of a boiler header long pipe joint tube bundle positioning device provided by an embodiment of the present application;
[0018] Figure 2 Shows the left view of a boiler header long pipe joint tube bundle positioning device provided by an embodiment of the present application;
[0019] Figure 3 Shows the structural schematic diagram of the U-shaped bolt provided by an embodiment of the present application.
[0020] Illustration:
[0021] 1. Porous positioning plate; 2. Vertical plate; 3. U-shaped bolt; 4. Nut; 5. Flat washer; 6. Pipe end. DETAILED DESCRIPTION OF THE EMBODIMENTS
[0022] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present application more clearly understood, the following further details the present application in conjunction with the drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0023] It should be noted that when an element is referred to as "fixed to" or "disposed on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element.
[0024] In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be construed as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, the features defined with "first" and "second" may explicitly or implicitly include one or more of such features. In the description of the present application, "a plurality of" means two or more, unless otherwise specifically defined.
[0025] In order to illustrate the technical solutions described in the present application, the following will be described through specific embodiments.
[0026] Please refer to Figures 1 to 3 As shown, the embodiment of the present application provides a positioning device for a long pipe joint tube bundle of a boiler header, including: a U-shaped bolt 3 for fixing, a porous positioning plate 1 for positioning, a vertical plate 2 for supporting, and a nut 4 for pressing.
[0027] Specifically, at the pipe end 6 of the long pipe joint tube bundle of the boiler header, the porous positioning plate 1 is inserted, and the porous positioning plate 1 can ensure the distance position between the long pipe joint tube bundles. For example, a plurality of positioning holes with preset intervals are provided on the porous positioning plate 1, and the positioning holes are sleeved on the pipe end 6.
[0028] The vertical plate 2 and a flat washer 5 are successively inserted on the U-shaped bolt 3, and the nut 4 is sleeved, so as to be assembled into an integral part. Then the integral part is respectively sleeved on the pipe ends 6 of the long pipe joint tube bundles on both sides of the porous positioning plate 1, and the position depths are the same. Then, the nut 4 on the U-shaped bolt 3 is tightened by a wrench for the U-shaped bolt 3 and the vertical plate 2, so as to be fixed on the long pipe joint tube bundle. Finally, the porous positioning plate 1 located on the long pipe joint tube bundle of the boiler header is moved so that the porous positioning plate 1 contacts the vertical plate 2, so that the vertical plate 2 and the porous positioning plate 1 are welded and connected. For example, in the integral part, a fastening hole for clamping and fixing the pipe end 6 is formed between the U-shaped opening of the U-shaped bolt 3 and the vertical plate 2.
[0029] The above-mentioned vertical plate 2 is used to transmit the pressure borne, the nut 4 is used to connect and press the vertical plate 2, and the U-shaped bolt 3 is fixed on the long pipe joint tube bundle, which can prevent the porous positioning plate 1 from deforming and falling off.
[0030] The above-mentioned positioning device for the long pipe joint bundle of the boiler header can solve the problems of deformation and shedding during hoisting and transportation in the manufacturing process, and the inability to guarantee the position dimensions of the long pipe joint bundle of the boiler header, and better realize the welding of the long pipe joint of the boiler header and the membrane wall at the construction site, improving the installation efficiency and quality.
[0031] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them; although the present application has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that they can still modify the technical solutions recorded in the foregoing embodiments, or perform equivalent replacements on some of the technical features; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the various embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A boiler header long pipe joint tube bundle positioning device, characterized in that: include: A multi-hole positioning plate, which is used to be sleeved on the pipe ends of the long pipe joint bundles of the boiler header and ensure the spacing position between the long pipe joint bundles; U-shaped bolts, the U-shaped bolts are used to be inserted into the vertical plates and the flat washers, and are connected by sleeve nuts to be assembled into an integrated piece, and the integrated piece is used to sleeve and fix the pipe ends on both sides of the porous positioning plate; Wherein, the vertical plate is fixedly connected to the porous positioning plate.
2. The boiler header long pipe joint tube bundle positioning device according to claim 1 is characterized in that: The vertical plate is connected to the porous positioning plate by welding.
3. The boiler header long pipe joint tube bundle positioning device according to claim 1, characterized in that: The sleeve positions of the one-piece parts on both sides of the porous positioning plate have the same depth.
4. The boiler header long pipe joint tube bundle positioning device according to claim 1, characterized in that: The multi-hole positioning plate is provided with a plurality of positioning holes with preset intervals, and the positioning holes are sleeved on the pipe ends.