Quick splicing type vertical greening wall

By designing the upper and lower two-stage green wall bracket and ball screw transmission system, the problem of inconvenience in installation of the existing vertical green wall is solved, and rapid splicing and maintenance without ladders or lifting equipment is achieved.

CN223110598UActive Publication Date: 2025-07-18YANCHENG LIANGCHENG GARDEN CONSTR ENG CO LTD

Patent Information

Application Number
CN202421626172.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-10
Publication Date
2025-07-18
Estimated Expiration
2034-07-10

AI Technical Summary

Technical Problem

The existing vertical green walls require the use of ladders or lifts during the installation process, which leads to inconvenient installation, especially in areas that are inconvenient to reach, and it is difficult to quickly splice.

Method used

The green wall bracket is designed in two-stage upper and lower stages, combining ball screws, synchronous belts and brake stepper motors. The motor drives the screw nuts to lift and lower the green walls to achieve stable lifting and rapid splicing, avoiding dependence on ladders or lifting equipment.

Benefits of technology

The rapid installation and maintenance of green walls is achieved without the need for ladders or lifting equipment, which improves the convenience and efficiency of the installation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223110598U_ABST
    Figure CN223110598U_ABST
Patent Text Reader

Abstract

The utility model relates to a quick splicing type vertical greening wall, which belongs to the technical field of vertical greening walls, and comprises a mounting bracket, an upper greening wall frame, a lower greening wall frame and green plant flowerpots, the mounting bracket is provided with two equipment grooves, the equipment grooves are rotatably connected with ball screws, the outer walls of the ball screws are in threaded connection with screw nuts, and the screw nuts are in threaded connection with the upper greening wall frame and the lower greening wall frame. The ball screws are fixedly connected with synchronous wheels, the outer walls of the synchronous wheels on the two sides are sleeved with synchronous belts, the synchronous wheels are in transmission connection through the synchronous belts, and a band-type brake stepping motor is fixedly installed on the inner wall of the equipment groove. The greening wall support is integrally arranged into the upper section and the lower section, the greening wall support of the upper section can be adjusted downwards so that workers can quickly splice and install the greening wall at the bottom, the greening wall support of the upper section can be adjusted upwards after installation and splicing are completed, then the greening wall of the lower section is spliced and installed, a ladder or lifting equipment is not needed in the installation process, and the installation is convenient. And the installation and maintenance work can be more convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of vertical greening walls, in particular to a quickly spliced vertical greening wall. Background Technique

[0002] Vertical greening, also known as three-dimensional greening, is to make full use of space by planting climbing plants on walls, balconies, window sills, roofs, pergolas, etc., so as to increase the greening coverage rate and improve the living environment. A vertical greening wall is a wall used to achieve vertical greening.

[0003] After retrieval, a Chinese patent with the application number CN202321118734.0 discloses a vertically greening wall that is convenient to install. The receiving box can receive the soil and water flowing out of the planting frame, which can effectively prevent the soil and water from flowing out from soiling the ground below the greening wall. By setting a connecting bottom plate slidably inserted on the fixed sliding seat, the installation of the planting mechanism is convenient. By moving the connecting bottom plate on the right to the left and making the connecting protrusion at its end extend into the back side of the connecting pressing edge at the right end of the left connecting bottom plate, and then inserting a limiting pin shaft into the corresponding limiting jack, the connection strength between the planting mechanisms can be enhanced.

[0004] The above technical solution has the following defects. Although such a vertically greening wall structure can install the planting frame on the wall skeleton through the pin shaft structure, thus facilitating disassembly and assembly, in the actual use process, the wall height is too high, and a ladder or a lifting machine needs to be used for assistance during installation and splicing. However, the lifting machine has a large volume, and it is difficult to carry out installation and splicing work in inaccessible areas. In order to facilitate the staff to quickly splice the vertical greening wall and without the need to use a ladder or a lifting device, a quickly spliced vertical greening wall is now proposed. The overall greening wall bracket is set in an upper and lower two-section form. The upper section of the greening wall bracket is adjustable downward to facilitate the staff to quickly splice and install the greening wall at the bottom. After the installation and splicing are completed, it can be adjusted upward, and then the lower section of the greening wall is spliced and installed. The installation process does not require the use of a ladder or a lifting device, making the installation and maintenance work more convenient.

[0005] In view of this, this creation improves and solves the above problems, conducts painstaking research and combines theoretical application, and finally proposes a technical solution with reasonable design and effective improvement of the above defects.

[0006] The information disclosed in this background art section is only intended to deepen the understanding of the overall background art of the utility model, and should not be regarded as an admission or any form of suggestion that this information constitutes the prior art known to those skilled in the art. Summary of the Utility Model

[0007] The utility model provides a quick - splicing vertical greening wall, which solves the problems raised in the above - mentioned background. The greening wall support is integrally set in an upper - lower two - section type. The upper - section greening wall support is adjustable downwards, which is convenient for workers to quickly splice and install the greening wall at the bottom. After the installation and splicing are completed, it can be adjusted upwards, and then the lower - section greening wall is spliced and installed. The installation process does not require the use of ladders or lifting equipment, making the installation and maintenance work more convenient.

[0008] The solution of the utility model to the above - mentioned technical problems is as follows: A quick - splicing vertical greening wall, including an installation support, an upper - placed greening wall frame, a lower - placed greening wall frame, and green plant flower pots. The installation support is provided with equipment slots, and there are two equipment slots. The equipment slots are rotatably connected with ball screws. The outer wall of the ball screw is thread - connected with a screw nut. The ball screw is fixedly connected with a synchronous pulley. The outer walls of the two synchronous pulleys are sleeved with a synchronous belt, and the synchronous pulleys are drivingly connected through the synchronous belt. The inner wall of the equipment slot is fixedly installed with a brake stepping motor, and the driving end of the brake stepping motor is fixedly connected with one side of the ball screw. The inner wall of the installation support is fixedly installed with a limiting rod, and the outer wall of the limiting rod is slidably connected with a limiting slider. Both the limiting slider and the screw nut are fixedly connected with a first connecting frame. The installation support is fixedly installed with a second connecting frame. The upper - placed greening wall frame can be connected to the first connecting frame by screws, and the lower - placed greening wall frame can be connected to the second connecting frame by screws. Both the upper - placed greening wall frame and the lower - placed greening wall frame are installed with placing cylinders, and the green plant flower pots are placed in the placing cylinders.

[0009] On the basis of the above - mentioned technical solution, the utility model can be further improved as follows.

[0010] Further, the installation support is integrally set in a structure of a "day" - shaped frame.

[0011] Further, the limiting slider is provided with a sliding hole corresponding to the limiting rod, and the inner wall of the sliding hole is slidably connected with the limiting rod, and the limiting rod can limit the limiting slider.

[0012] Further, the installation support is provided with a strip - shaped hole corresponding to the first connecting frame, and the first connecting frame passes through the strip - shaped hole and is fixedly connected with the screw nut.

[0013] Further, the first connecting frame is provided with a positioning block, the upper - placed greening wall frame is provided with a positioning groove corresponding to the positioning block, the positioning block is provided with a screw groove, and the positioning groove is provided with a through - hole corresponding to the screw groove.

[0014] Further, the second connecting frame is provided with a connecting block, the lower - placed greening wall frame is provided with a connecting groove corresponding to the connecting block, the connecting block is provided with a screw groove, and the connecting groove is provided with a through - hole corresponding to the screw groove.

[0015] Further, water passing holes are evenly formed in the outer wall of the placing cylinder, so that irrigation water can be transmitted out.

[0016] Further, connecting brackets are fixedly installed on the installation brackets, bolt holes are formed in the connecting brackets, and the installation brackets can be installed on the wall surface by passing expansion screws through the connecting brackets.

[0017] The utility model provides a quick-splicing vertical greening wall, which has the following advantages:

[0018] 1. The connecting bracket of the installation bracket can be installed on the wall surface through expansion bolts. Starting the brake stepping motor can drive the lead screw nut to lift. After the lead screw nut descends, the positioning groove of the upper greening wall frame corresponds to the first connecting frame connected to the lead screw nut and the limit slider, and then they are connected by screws, so that the first connecting frame can be connected to the upper greening wall frame. Such a lifting structure can lower the greening wall at a high place, so that the installation and maintenance work of the greening wall does not require climbing to a high place.

[0019] 2. After placing the green plant flowerpot in the placing cylinder of the upper greening wall frame, start the brake stepping motor to drive the upper greening wall frame to rise. During the rising process of the upper greening wall frame, the limit slider can slide on the outer wall of the limit rod, so that the upper greening wall frame can be stably lifted at the installation bracket.

[0020] 3. After the upper greening wall frame rises to a high place, align the connecting groove of the lower greening wall frame with the second connecting frame and then connect them by screws, so that the lower greening wall frame can be quickly spliced with the second connecting frame. The lower greening wall frame is closely attached to the upper greening wall frame, and the staff can place the green plant flowerpot in the placing cylinder of the lower greening wall frame.

[0021] 4. The greening wall bracket of such a quick-splicing vertical greening wall is integrally arranged in an upper and lower two-section type. The upper section of the greening wall bracket is adjustable downwards, which is convenient for the staff to quickly splice and install the greening wall at the bottom. After the installation and splicing are completed, it can be adjusted upwards, and then the lower section of the greening wall is spliced and installed. The installation process does not require the use of ladders or lifting equipment, making the installation and maintenance work more convenient.

[0022] The above description is only an overview of the technical solution of the utility model. In order to be able to understand the technical means of the utility model more clearly and implement it according to the content of the description, the following takes the preferred embodiments of the utility model and combines with the attached drawings to describe in detail as follows. The specific implementation manners of the utility model are given in detail by the following embodiments and their attached drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The attached drawings described herein are used to provide a further understanding of the utility model, and constitute a part of this application. The schematic embodiments of the utility model and their descriptions are used to explain the utility model and do not constitute an improper limitation to the utility model. In the attached drawings:

[0024] Figure 1 Schematic structural diagram of a quickly spliced vertical greening wall from a side view angle provided by an embodiment of the present utility model;

[0025] Figure 2 Side view of a quickly spliced vertical greening wall provided by an embodiment of the present utility model;

[0026] Figure 3 Schematic structural diagram of an upper greening wall frame in a lowered state of a quickly spliced vertical greening wall provided by an embodiment of the present utility model;

[0027] Figure 4 Schematic structural diagram of an installation bracket in a quickly spliced vertical greening wall provided by an embodiment of the present utility model;

[0028] Figure 5 Front view of an installation bracket in a quickly spliced vertical greening wall provided by an embodiment of the present utility model.

[0029] In the attached drawings, the list of components represented by each reference numeral is as follows:

[0030] 1. Installation bracket; 2. Equipment slot; 3. Ball screw; 4. Lead screw nut; 5. Synchronous pulley; 6. Synchronous belt; 7. Brake stepper motor; 8. Limit rod; 9. Limit slider; 10. First connecting frame; 11. Second connecting frame; 12. Upper greening wall frame; 13. Lower greening wall frame; 14. Placing cylinder; 15. Green plant flowerpot; 16. Connecting bracket. Detailed implementation manners

[0031] The following describes the principles and features of the present utility model with reference to the attached Figures 1-5 drawings. The examples given are only used to explain the present utility model and are not intended to limit the scope of the present utility model. In the following paragraphs, the present utility model will be described more specifically by way of example with reference to the attached drawings. According to the following description and the claims, the advantages and features of the present utility model will be more clearly understood. It should be noted that the attached drawings are all in a very simplified form and use non-precise scales, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present utility model.

[0032] It should be noted that when a component is referred to as being "fixed to" another component, it can be directly on the other component or there can also be an intermediate component. When a component is considered to be "connected" to another component, it can be directly connected to the other component or there may be an intermediate component at the same time. When a component is considered to be "disposed on" another component, it can be directly disposed on the other component or there may be an intermediate component at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are only for the purpose of illustration.

[0033] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the technical field to which this utility model belongs. The terms used in the specification of this utility model herein are for the purpose of describing specific embodiments only and are not intended to limit this utility model. The term "and / or" used herein includes any and all combinations of one or more of the related listed items.

[0034] As Figures 1-5 shown, a quick-splicing vertical greening wall includes an installation bracket 1, an upper greening wall frame 12, a lower greening wall frame 13, and green plant flowerpots 15. The installation bracket 1 is provided with equipment grooves 2. There are two equipment grooves 2. A ball screw 3 is rotatably connected to the equipment groove 2. A screw nut 4 is threadedly connected to the outer wall of the ball screw 3. A synchronous pulley 5 is fixedly connected to the ball screw 3. A synchronous belt 6 is sleeved on the outer walls of the two synchronous pulleys 5. The synchronous pulleys 5 are drivingly connected through the synchronous belt 6. A brake stepping motor 7 is fixedly installed on the inner wall of the equipment groove 2. The driving end of the brake stepping motor 7 is fixedly connected to one side of the ball screw 3. A limiting rod 8 is fixedly installed on the inner wall of the installation bracket 1. A limiting slider 9 is slidably connected to the outer wall of the limiting rod 8. Both the limiting slider 9 and the screw nut 4 are fixedly connected to a first connecting frame 10. A second connecting frame 11 is fixedly installed on the installation bracket 1. The upper greening wall frame 12 and the first connecting frame 10 can be connected by screws. The lower greening wall frame 13 and the second connecting frame 11 can be connected by screws. The upper greening wall frame 12 and the lower greening wall frame 13 are both provided with placing cylinders 14. The green plant flowerpots 15 are placed in the placing cylinders 14.

[0035] Preferably, the installation bracket 1 is integrally arranged in a shape of a Chinese character 'Ri' frame structure.

[0036] Preferably, the limiting slider 9 is provided with a sliding hole corresponding to the limiting rod 8. The inner wall of the sliding hole is slidably connected to the limiting rod 8, and the limiting rod 8 can limit the limiting slider 9.

[0037] Preferably, the installation bracket 1 is provided with a strip-shaped hole corresponding to the first connecting frame 10. The first connecting frame 10 passes through the strip-shaped hole and is fixedly connected to the screw nut 4.

[0038] Preferably, the first connecting frame 10 is provided with a positioning block. The upper greening wall frame 12 is provided with a positioning groove corresponding to the positioning block. The positioning block is provided with a screw groove, and the positioning groove is provided with a through hole corresponding to the screw groove.

[0039] Preferably, the second connecting frame 11 is provided with a connecting block. The lower greening wall frame 13 is provided with a connecting groove corresponding to the connecting block. The connecting block is provided with a screw groove, and the connecting groove is provided with a through hole corresponding to the screw groove.

[0040] Preferably, water passing holes are evenly formed in the outer wall of the placing cylinder 14 so that irrigation water can be transmitted out.

[0041] Preferably, connecting brackets 16 are fixedly installed on the mounting brackets 1. Bolt holes are formed in the connecting brackets 16. The mounting brackets 1 can be mounted on the wall surface by passing expansion screws through the connecting brackets 16.

[0042] The specific working principle and usage method of the present utility model are as follows: The connecting brackets 16 of the mounting brackets 1 can be mounted on the surface of the wall body by expansion bolts. Start the brake stepping motor 7 to rotate one side of the ball screw 3. The synchronous wheels 5 of the two sides of the ball screws 3 are connected by a synchronous belt 6. The two sides of the ball screws 3 can rotate synchronously in the equipment groove 2. The two sides of the ball screws 3 can drive the lead screw nuts 4 to move up and down. After the lead screw nuts 4 are lowered, the positioning grooves of the upper greening wall frame 12 correspond to the first connecting frames 10 connected to the lead screw nuts 4 and the limit sliders 9, and then are connected by screws, so that the first connecting frames 10 can be connected to the upper greening wall frame 12. After placing the green plant flowerpots 15 in the placing cylinders 14 of the upper greening wall frame 12, start the brake stepping motor 7 to drive the upper greening wall frame 12 to rise. During the rising process of the upper greening wall frame 12, the limit sliders 9 can slide on the outer wall of the limit rods 8, so that the upper greening wall frame 12 can be stably lifted and lowered at the mounting brackets 1. After the upper greening wall frame 12 rises to a high position, the connecting grooves of the lower greening wall frame 13 correspond to the second connecting frames 11 and are then connected by screws, so that the lower greening wall frame 13 can be stably connected to the second connecting frames 11. The lower greening wall frame 13 is closely attached to the upper greening wall frame 12. The staff can place the green plant flowerpots 15 in the placing cylinders 14 of the lower greening wall frame 13.

[0043] The above are only the preferred embodiments of the present utility model, and do not impose any form of limitation on the present utility model. Any person skilled in the art of this industry can smoothly implement the present utility model according to the illustrations in the specification and the above description. However, any equivalent changes made by those skilled in the art in the scope of the technical solution of the present utility model by using the technical content disclosed above for minor modifications, decorations and evolutions are all equivalent embodiments of the present utility model. At the same time, any equivalent changes, modifications and evolutions made to the above embodiments based on the essential technology of the present utility model still fall within the protection scope of the technical solution of the present utility model.

Claims

1. A quick - splicing vertical greening wall, comprising an installation bracket (1), an upper greening wall frame (12), a lower greening wall frame (13), and green plant flowerpots (15), characterized in that: The installation bracket (1) is provided with equipment slots (2), and there are two equipment slots (2). A ball screw (3) is rotatably connected to the equipment slot (2). A lead screw nut (4) is threadedly connected to the outer wall of the ball screw (3). A synchronous pulley (5) is fixedly connected to the ball screw (3). A synchronous belt (6) is sleeved on the outer walls of the two synchronous pulleys (5). The synchronous pulleys (5) are drivingly connected through the synchronous belt (6). A brake stepper motor (7) is fixedly installed on the inner wall of the equipment slot (2). The driving end of the brake stepper motor (7) is fixedly connected to one side of the ball screw (3). A limiting rod (8) is fixedly installed on the inner wall of the installation bracket (1). A limiting slider (9) is slidably connected to the outer wall of the limiting rod (8). A first connecting frame (10) is fixedly connected to both the limiting slider (9) and the lead screw nut (4). A second connecting frame (11) is fixedly installed on the installation bracket (1). The upper greening wall frame (12) and the first connecting frame (10) can be connected by screws. The lower greening wall frame (13) and the second connecting frame (11) can be connected by screws. The upper greening wall frame (12) and the lower greening wall frame (13) are both provided with placing cylinders (14). The green plant flowerpots (15) are placed in the placing cylinders (14).

2. The quick-splicing vertical greening wall according to claim 1, wherein The installation bracket (1) is integrally arranged in a shape of a Chinese character 'Ri' frame structure.

3. The quick-assembling vertical greening wall according to claim 1, wherein The limiting slider (9) is provided with a sliding hole corresponding to the limiting rod (8), and the inner wall of the sliding hole is slidably connected to the limiting rod (8).

4. The quick-splicing vertical greening wall according to claim 1, wherein, The installation bracket (1) is provided with a strip-shaped hole corresponding to the first connecting frame (10), and the first connecting frame (10) passes through the strip-shaped hole and is fixedly connected to the lead screw nut (4).

5. The quick-assembling vertical greening wall according to claim 1, wherein The first connecting frame (10) is provided with a positioning block. The upper greening wall frame (12) is provided with a positioning groove corresponding to the positioning block. The positioning block is provided with a screw groove, and the positioning groove is provided with a through hole corresponding to the screw groove.

6. The quick-splicing vertical greening wall according to claim 1, characterized in that The second connecting frame (11) is provided with a connecting block. The lower greening wall frame (13) is provided with a connecting groove corresponding to the connecting block. The connecting block is provided with a screw groove, and the connecting groove is provided with a through hole corresponding to the screw groove.

7. The quick-assembling vertical greening wall according to claim 1, characterized in that, The outer wall of the placing cylinder (14) is evenly provided with water passing holes.

8. The quick-assembling vertical greening wall according to claim 1, wherein Connecting brackets (16) are fixedly installed on the installation bracket (1), and the connecting brackets (16) are provided with bolt holes.

Citation Information

Patent Citations

  • Vertical greening wall convenient to install

    CN220476384U

Cited By

  • Vertical greening wall capable of being quickly built

    CN224504140U