Temporary water supply and drainage device for construction engineering construction
By setting up intercepting components and filter covers in the pumping pipes, and using spiral blades to intercept silt and sand, the problem of silt and sand blockage is solved and the service life of the pumping pump is extended.
Patent Information
- Application Number
- CN202422461991.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-11
- Publication Date
- 2025-08-01
- Estimated Expiration
- 2034-10-11
AI Technical Summary
Existing temporary water supply and drainage devices are prone to clogging when dealing with sewage containing a large amount of silt, affecting the pumping efficiency and possibly damaging the pump.
The interception assembly in the pumping pipe is adopted, including a rotating shaft and spiral blade, which is used to intercept and transport silt and sand in reverse. Combined with a filter cover and a support cover, the soil and sand are initially intercepted. The spiral blade is equipped with water filter holes to allow water to flow through.
Effectively reduce silt and sand entering the pipeline, prevent blockage, and extend the service life of the pump.
Smart Images

Figure CN223176776U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of construction engineering, and in particular to a temporary water supply and drainage device for construction projects. Background Art
[0002] During the construction process of construction projects, temporary water supply and drainage devices are indispensable and important equipment, mainly used for pumping the accumulated water in the foundation pit to ensure the smooth progress of construction. At present, there are various temporary water supply and drainage devices on the market, but most of the devices are prone to clogging problems when dealing with sewage containing a large amount of sediment, which affects the pumping efficiency, and even causes damage to the water pump and shortens its service life.
[0003] In the existing technical solutions, generally, a filter screen is added at the pumping end to reduce the sediment entering the pump body. For example, a foundation pit drainage anti-clogging system with the authorization announcement number CN211285662U reduces the sediment passing through by setting a connection pipe to be quickly disassembled from the box body and the pipe joint, and at the same time setting multiple independently used connection pipes, so that the filter screen connected to the connection pipe can be replaced while the water pump is running, reducing the sediment passing through and facilitating the quick replacement of the filter screen. However, in the actual use process, although a filtering device is used to reduce the sediment entering the pipeline, there will still be a small part of the sediment entering the pipeline and then causing clogging, which affects the operation of the pump body. Summary of the Utility Model
[0004] In order to solve the problem that sediment still passes through the filter screen and enters the pump body, and there is still sediment entering the pipeline causing clogging or damage to the pump body, this application provides a temporary water supply and drainage device for construction projects.
[0005] A temporary water supply and drainage device for construction projects provided by this application adopts the following technical solutions:
[0006] A temporary water supply and drainage device for construction projects includes a pumping pipeline connected to the water inlet end of the temporary drainage device. The end of the pumping pipeline is connected with a filter cover, and an interception component is arranged inside the pumping pipeline;
[0007] The interception component includes a rotating shaft rotatably arranged inside the pumping pipeline, and spiral blades are arranged on the rotating shaft for intercepting and reversely conveying the sediment in the water.
[0008] Preferably, a number of water filtering holes are arranged on the spiral blades, and a driving component is also arranged on the rotating shaft for driving the rotating shaft and the spiral blades to rotate.
[0009] Preferably, the pumping pipeline includes a vertical pipe and a straight pipe. The straight pipe is arranged on the side of the vertical pipe and above the spiral blades.
[0010] Preferably, the filter cover includes a connecting pipe provided at the lower end of the vertical pipe. A support cover is provided at the lower end of the connecting pipe, and a partition is provided inside the support cover.
[0011] Preferably, the support cover includes a filter net provided on the connecting pipe, and a strengthening structure is provided on the side of the filter net to improve the overall support strength.
[0012] In summary, the present application includes the following beneficial technical effects:
[0013] Through the combined use of the pumping pipeline, the filter cover, and the interception component, the pumping pipeline is connected to the water pump to pump the water in the foundation pit. The support cover is used to initially intercept the soil and sand, reducing the sediment entering the pumping pipeline. After the water enters the vertical pipe, the spiral blades and the water filtering holes facilitate the flow of water while effectively intercepting and discharging the sediment in the water, preventing pipeline blockage and reducing pump body damage; compared with the prior art, it has the effects of preventing blockage and extending the service life of the pump body. Description of the Drawings
[0014] Figure 1 is the first perspective three-dimensional structural schematic diagram of the application embodiment;
[0015] Figure 2 is the second perspective three-dimensional structural schematic diagram of the application embodiment;
[0016] Figure 3 is the third perspective three-dimensional structural schematic diagram of the application embodiment.
[0017] Description of the reference numerals: 1, pumping pipeline; 101, vertical pipe; 102, end cover; 103, straight pipe; 2, filter cover; 201, connecting pipe; 202, support cover; 2021, filter net; 2022, support skeleton; 203, partition; 3, interception component; 301, rotating shaft; 302, spiral blade; 303, turbine. Detailed Description of the Embodiment
[0018] The following will further describe the present application in detail Figures 1 - 3 with reference to the accompanying drawings.
[0019] The embodiment of the present application discloses a temporary water supply and drainage device for construction engineering construction. Refer to Figures 1 - 3, A temporary water supply and drainage device for construction engineering construction, including a pumping pipeline 1 connected to the water inlet end of the temporary drainage device. A filter cover 2 is connected to the lower end of the pumping pipeline 1. An interception component 3 is installed inside the pumping pipeline 1. The interception component 3 includes a rotating shaft 301 rotatably installed inside the pumping pipeline 1. A spiral blade 302 with water filtering holes is installed on the rotating shaft 301. A driving component is also installed on the rotating shaft 301. The driving component can be selected in the way of electric or fluid drive, such as a turbine 303 installed on the rotating shaft 301. The turbine 303 is located above the spiral blade 302. The water flow passing through the pumping pipeline 1 can be used to drive the turbine 303 to rotate, and then drive the turbine 303 to rotate. Then, the turbine 303 drives the spiral blade 302 to discharge the intercepted sediment downward.
[0020] Refer to Figure 3 , The pumping pipeline 1 includes a straight pipe 103 connected to the water inlet end of the temporary water supply and drainage device through a flange. The end of the straight pipe 103 is connected to a vertical pipe 101. The rotating shaft 301 is rotatably installed on an end cover 102. The straight pipe 103 is located above the turbine 303 to ensure that the water flow can always pass through the turbine 303 and drive the turbine 303 to operate. The top of the vertical pipe 101 is detachably installed with an end cover 102, such as by bolts, and a sealing ring is used for sealing at the connection between the vertical pipe 101 and the end cover 102. The temporary water supply and drainage device can select a suitable water pump according to needs.
[0021] Refer to Figure 2 , The filter cover 2 includes a connecting pipe 201 detachably installed at the lower end of the vertical pipe 101. A support cover 202 is installed at the lower end of the connecting pipe 201. The support cover 202 includes a filter net 2021 installed on the connecting pipe 201. The end of the spiral blade 302 is located inside the filter net 2021. A reinforcing structure is installed on the side of the filter net 2021. The reinforcing structure adopts a support skeleton 2022 composed of several reinforcing ribs to improve the support and anti-deformation ability of the support cover 202. The support cover 202 is designed in a horn shape. By installing a partition 203 inside the support cover 202, the support area is expanded, the support cover 202 is prevented from sinking into the sediment, and at the same time, the sediment can be separated from the internal space of the support cover 202 to prevent the sediment from surging up.
[0022] The implementation principle of a temporary water supply and drainage device for construction engineering construction in an embodiment of this application is as follows:
[0023] First, connect the straight pipe part 103 of the pumping pipeline 1 to the water inlet end of the water pump at the construction site of the construction project through a flange to ensure a tight and leak-free connection. Then, install the connecting pipe 201 of the filter cover 2 at the lower end of the vertical pipe 101 to ensure a tight connection between the two.
[0024] Start the water pump. When the water flow at the construction site passes through the filter screen 2021 to filter out the sand, small stones and mud in the water and enters the pumping pipeline 1 through the temporary drainage device, the water flow first passes through the spiral blade 302. The spiral blade 302 is provided with water filtering holes, allowing water to pass through but intercepting impurities such as sediment. At the same time, the water flow drives the turbine 303 installed above the rotating shaft 301 to rotate, and the turbine 303 drives the rotating shaft 301 and the spiral blade 302 to rotate. The rotation of the spiral blade 302 pushes the intercepted sediment and other impurities downward into 2021.
[0025] Finally, the following points should be noted: First, in the description of the present application, it should be noted that unless otherwise specified and limited, the terms "installation", "connection", and "connection" should be understood in a broad sense, which can be mechanical connection or electrical connection, or the internal connection of two components, and can be directly connected. "Up", "down", "left", "right", etc. are only used to represent the relative position relationship. When the absolute position of the object being described changes, the relative position relationship may change;
[0026] Second: In the attached drawings of the disclosed embodiments of the present utility model, only the structures related to the disclosed embodiments are involved. For other structures, reference can be made to the general design. Without conflict, the same embodiment and different embodiments of the present utility model can be combined with each other;
[0027] Finally: The above are only the preferred embodiments of the present utility model and are not used to limit the present utility model. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present utility model shall be included within the protection scope of the present utility model.
[0028] The above are all the preferred embodiments of the present application, and do not limit the protection scope of the present application accordingly. Therefore, all equivalent changes made according to the structure, shape, and principle of the present application shall be covered within the protection scope of the present application.
Claims
1. A temporary water supply and drainage device for construction engineering construction, including a pumping pipeline (1) connected to the water inlet end of the temporary drainage device, characterized in that: A filter cover (2) is connected to the end of the pumping pipeline (1), and an interception component (3) is arranged inside the pumping pipeline (1); The interception component (3) includes a rotating shaft (301) rotatably arranged inside the pumping pipeline (1), and a spiral blade (302) is arranged on the rotating shaft (301) for intercepting and reversely conveying sediment in water.
2. The temporary water supply and drainage device for construction engineering construction according to claim 1, wherein: A number of water filtering holes are arranged on the spiral blade (302), and a driving component is also arranged on the rotating shaft (301) for driving the rotating shaft (301) and the spiral blade (302) to rotate.
3. The temporary water supply and drainage device for construction works according to claim 1, characterized in that: The pumping pipeline (1) includes a vertical pipe (101) and a straight pipe (103). The straight pipe (103) is arranged on the side of the vertical pipe (101) and above the spiral blade (302).
4. A temporary water supply and drainage device for construction engineering construction according to claim 3, characterized in that: The filter cover (2) includes a connecting pipe (201) arranged at the lower end of the vertical pipe (101). A support cover (202) is arranged at the lower end of the connecting pipe (201), and a partition plate (203) is arranged inside the support cover (202).
5. The temporary water supply and drainage device for construction engineering construction according to claim 4, characterized in that: The support cover (202) includes a filter net (2021) arranged on the connecting pipe (201), and a strengthening structure is arranged on the side of the filter net (2021) for improving the overall support strength.
Citation Information
Patent Citations
Foundation pit drainage anti-blocking system
CN211285662U