Glass curtain wall steel structure assembly

Through the design of embedded parts, connecting seats and adjustment structures, combined with a bubble level, precise adjustment of the glass curtain wall steel structure components is achieved, solving the problem of low installation accuracy under welding connection methods and improving installation efficiency and safety.

CN223398261UActive Publication Date: 2025-09-30CHINA RAILWAY 12TH BUREAU GRP SOUTH CHINA ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422516478.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-17
Publication Date
2025-09-30
Estimated Expiration
2034-10-17

AI Technical Summary

Technical Problem

The existing welding connection method of glass curtain wall steel structure components leads to high installation precision requirements and cannot be adjusted, which increases installation cost and time.

Method used

Embedded parts, connecting seats, U-shaped clamps and adjustment structures are used, combined with a circular bubble level to achieve horizontal and angular adjustment of steel structure components. Precise installation is achieved by adjusting the coordination of bolts and threaded rods.

Benefits of technology

It improves installation accuracy, reduces installation difficulty and cost, enhances installation flexibility and efficiency, and avoids safety hazards caused by errors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223398261U_ABST
    Figure CN223398261U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of glass curtain wall installation, in particular to a glass curtain wall steel structure assembly. The glass curtain wall steel structure assembly comprises an embedded part, a connecting base and an adjusting structure, the embedded part is installed in the wall face, the front face of the embedded part is flush with the outer surface of the wall face, the connecting base is welded to the front face of the embedded part, a circular sliding groove is formed in the middle of the connecting base, a U-shaped clamping plate is installed on one side of the circular sliding groove, and the adjusting structure is arranged outside the U-shaped clamping plate. The adjusting structure and the embedded part are installed in a matched mode. By means of the unique adjusting structure, horizontal and angle adjustment of the steel structure assembly in the installation process is achieved; by means of the adjusting mechanism, installation personnel can conduct fine adjustment on site according to actual conditions, so that the installation precision is greatly improved, levelness correction is conducted through the round bubble level gauge, the levelness of the steel structure assembly is further ensured, and potential safety hazards caused by installation errors are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of glass curtain wall installation, in particular to a glass curtain wall steel structure component. Background Art

[0002] In existing glass curtain wall installation processes, the steel structure components of the glass curtain wall are usually fixed to the embedded parts by welding. Specifically, the channel steel structure is directly welded to the surface of the embedded parts, and then connected to the glass curtain wall. However, this traditional installation method has significant drawbacks.

[0003] First, since the connection between the steel structure and the embedded parts during the welding process is rigid, once the welding is completed, the position and angle of the steel structure can no longer be adjusted; this places extremely high demands on the welding accuracy; in actual operation, even a slight tilt in the welding position may lead to unsatisfactory installation effects of the entire glass curtain wall; at this time, in order to correct this tilt, it is often necessary to dismantle the welded steel structure and reposition and re-weld it, which undoubtedly greatly increases the cost and time of installation.

[0004] Therefore, it is necessary to provide a new glass curtain wall steel structure component to solve the above technical problems. Utility Model Content

[0005] In order to solve the above technical problems, the utility model provides a glass curtain wall steel structure assembly.

[0006] The glass curtain wall steel structure assembly provided by the utility model includes: embedded parts, connecting seats and adjustment structures. The embedded parts are installed inside the wall surface, and the front surface of the embedded parts is flush with the outer surface of the wall surface. The connecting seats are welded to the front surface of the embedded parts. A circular sliding groove is opened in the middle of the connecting seat. A U-shaped card is installed on one side of the circular sliding groove. The outside of the U-shaped card is provided with an adjustment structure. The adjustment structure and the embedded parts are installed in coordination.

[0007] Preferably, a placement groove is provided on the top of the U-shaped card plate, a magnet is fixedly connected to the inner wall of the placement groove, a circular bubble level is placed on the inner wall of the placement groove, and the bottom of the circular bubble level is made of iron.

[0008] Preferably, the adjustment structure includes: an ear plate, an internal thread, an adjusting bolt, a connecting ball, a threaded rod, a through hole and a nut. The outer wall of the U-shaped card plate is fixedly connected to the ear plate, an internal thread is opened in the middle of the ear plate, and the inner wall of the internal thread of the ear plate is threadedly connected to the adjusting bolt. The end of the adjusting bolt is spherical in design, and the inner wall of the circular slide is slidingly connected to the connecting ball. The outer wall of the connecting ball is fixedly connected to the threaded rod. A through hole is opened in the middle of the U-shaped card plate, the threaded rod extends into the inner wall of the through hole, and the outer wall of the threaded rod is symmetrically threaded with a nut at the through hole.

[0009] Preferably, the height of the adjusting bolt is smaller than the height of the U-shaped clamping plate.

[0010] Preferably, the end of the threaded rod that extends beyond the U-shaped clamping plate needs to be cut off, and an avoidance groove is provided at the through hole of the U-shaped clamping plate.

[0011] Preferably, after the adjustment structure is adjusted, the spherical ends of several adjustment bolts need to be welded to the embedded parts.

[0012] Preferably, a fixing bolt is provided in the middle of the U-shaped card plate, and the fixing bolt is fixed to the glass curtain wall.

[0013] Preferably, the back side of the embedded part is symmetrically fixedly connected with a J-shaped claw.

[0014] Compared with related technologies, the glass curtain wall steel structure assembly provided by the present invention has the following beneficial effects:

[0015] Improve installation accuracy:

[0016] The present invention uses a unique adjustment structure to achieve horizontal and angular adjustment of steel structure components during installation. This adjustment mechanism enables installers to make fine adjustments on site based on actual conditions, thereby greatly improving installation accuracy.

[0017] The use of a circular bubble level for level correction further ensures the horizontality of the steel structure components and avoids safety hazards caused by installation errors;

[0018] Enhanced installation flexibility:

[0019] Traditional installation methods often require precise measurement and positioning before welding. Once welding is completed, adjustments cannot be made. However, the adjustment structure of the present invention allows multiple adjustments during the installation process until the optimal installation effect is achieved.

[0020] This flexibility not only reduces the difficulty and cost of installation, but also improves installation efficiency, making the entire installation process smoother and more efficient. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 A schematic diagram of the structure of the glass curtain wall steel structure assembly provided by the utility model;

[0022] Figure 2 for Figure 1 The structural diagram of the connecting seat and the connecting ball shown;

[0023] Figure 3 for Figure 1 The structural diagram of the U-shaped pallet shown.

[0024] Numbers in the figure: 1. Embedded part; 2. Connecting seat; 3. Circular slide; 4. U-shaped clamp; 5. Adjustment structure; 6. Placement groove; 7. Circular bubble level; 8. Fixing bolt; 9. J-shaped claw; 10. Avoidance groove; 51. Ear plate; 52. Internal thread; 53. Adjusting bolt; 54. Connecting ball; 55. Threaded rod; 56. Through hole; 57. Nut. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0026] The specific implementation of the present invention is described in detail below with reference to specific embodiments.

[0027] See also Figure 1-3 , a glass curtain wall steel structure component, the glass curtain wall steel structure component includes: an embedded part 1, a connecting seat 2 and an adjustment structure 5. The embedded part 1 is installed inside the wall, and the front of the embedded part 1 is flush with the outer surface of the wall. The connecting seat 2 is welded to the front of the embedded part 1, and a circular slide 3 is opened in the middle of the connecting seat 2. A U-shaped card plate 4 is installed on one side of the circular slide 3. An adjustment structure 5 is provided on the outside of the U-shaped card plate 4. The adjustment structure 5 and the embedded part 1 are installed in coordination. A placement groove 6 is opened on the top of the U-shaped card plate 4, and a magnet is fixedly connected to the inner wall of the placement groove 6. A circular bubble level 7 is placed on the inner wall of the placement groove 6, and the bottom of the circular bubble level 7 is made of iron. A fixing bolt 8 is provided in the middle of the U-shaped card plate 4, and the fixing bolt 8 is fixed to the glass curtain wall. The back of the embedded part 1 is symmetrically fixed with a J-shaped claw 9.

[0028] See also Figure 2-3 The adjustment structure 5 includes: an ear plate 51, an internal thread 52, an adjusting bolt 53, a connecting ball 54, a threaded rod 55, a through hole 56 and a nut 57. The outer wall of the U-shaped card plate 4 is fixedly connected with the ear plate 51. The middle part of the ear plate 51 is provided with an internal thread 52. The inner wall of the internal thread 52 of the ear plate 51 is threadedly connected with the adjusting bolt 53. The end of the adjusting bolt 53 is spherical in design. The inner wall of the circular slide 3 is slidably connected with the connecting ball 54. The outer wall of the connecting ball 54 is fixedly connected with the threaded rod 5 5. A through hole 56 is provided in the middle of the U-shaped card plate 4, and the threaded rod 55 extends into the inner wall of the through hole 56, and the outer wall of the threaded rod 55 is symmetrically threaded with a nut 57 at the through hole 56. The height of the adjusting bolt 53 is less than the height of the U-shaped card plate 4. The end of the threaded rod 55 that exceeds the U-shaped card plate 4 needs to be cut off, and an avoidance groove 10 is provided at the through hole 56 of the U-shaped card plate 4. After the adjustment structure 5 is adjusted, the spherical ends of several adjusting bolts 53 need to be welded to the embedded part 1.

[0029] The working principle of the glass curtain wall steel structure assembly provided by the utility model is as follows:

[0030] Initial Installation:

[0031] First, the embedded part 1 is firmly installed inside the wall, ensuring that the front surface of the embedded part 1 is flush with the outer surface of the wall; this step is key to ensuring the accuracy of subsequent installation;

[0032] Next, the connecting seat 2 is fixed to the front face of the embedded part 1 by welding; the design of the connecting seat 2 allows it to bear and support subsequent steel structure components;

[0033] Measurement and preparation:

[0034] Measuring the actual distance between the U-shaped clamp 4 and the embedded part 1 is crucial because it will directly affect the adjustment range of the subsequent adjustment bolts 53 and the final installation position of the steel structure component;

[0035] According to the measurement results, prepare the corresponding number and specifications of the adjustment structure 5, including the ear plate 51, the internal thread 52, the adjustment bolt 53, the connecting ball 54, the threaded rod 55, the through hole 56 and the nut 57;

[0036] Initial installation and nut fixing:

[0037] Install the U-shaped card plate 4 on one side of the circular slide groove 3 of the connecting seat 2 and ensure its position is accurate;

[0038] Connect the ear plate 51 of the adjustment structure 5 to the outer wall of the U-shaped clamping plate 4 through the internal thread 52, and preliminarily tighten the adjustment bolt 53;

[0039] Two nuts 57 are pre-placed and fixed at the through hole 56 of the U-shaped clamping plate 4; these two nuts will be used to lock the position of the threaded rod 55 later, thereby fixing the adjustment structure 5;

[0040] Adjusting bolt rotation and adjustment:

[0041] According to actual needs, several adjusting bolts 53 are rotated, and the spherical ends of the adjusting bolts 53 come into contact with the connecting balls 54, pushing or pulling the connecting balls 54 to slide in the circular chute 3;

[0042] The connecting ball 54 is connected to the through hole 56 of the U-shaped clamping plate 4 through the threaded rod 55. Therefore, the rotation of the adjusting bolt 53 will directly cause the threaded rod 55 to expand and contract, thereby adjusting the level and angle of the steel structure component;

[0043] During the adjustment process, a circular bubble level 7 can be used to observe whether the steel structure component has reached the required horizontal state;

[0044] Final welding and fixing:

[0045] Weld the spherical ends of several adjusting bolts 53 to the embedded parts 1; this step is key to ensuring that the steel structure components will not be displaced due to external forces during long-term use;

[0046] Finally, the glass curtain wall is firmly connected to the steel structure assembly using the fixing bolts 8 in the middle of the U-shaped clamping plate 4.

[0047] The above description is merely an embodiment of the present invention and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the description and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A glass curtain wall steel structure assembly, characterized in that: include: An embedded part (1), the embedded part (1) is installed inside the wall surface, and the front surface of the embedded part (1) is flush with the outer surface of the wall surface; A connecting seat (2), the connecting seat (2) is welded to the front of the embedded part (1), a circular slide groove (3) is opened in the middle of the connecting seat (2), and a U-shaped card plate (4) is installed on one side of the circular slide groove (3); An adjusting structure (5) is provided on the outside of the U-shaped card plate (4), and the adjusting structure (5) is installed in coordination with the embedded part (1).

2. The glass curtain wall steel structure assembly according to claim 1, characterized in that: A placement groove (6) is provided at the top of the U-shaped card plate (4), a magnet is fixedly connected to the inner wall of the placement groove (6), a circular bubble level (7) is placed on the inner wall of the placement groove (6), and the bottom of the circular bubble level (7) is made of iron.

3. The glass curtain wall steel structure assembly according to claim 1, characterized in that: The adjustment structure (5) includes: an ear plate (51), an internal thread (52), an adjustment bolt (53), a connecting ball (54), a threaded rod (55), a through hole (56) and a nut (57). The outer wall of the U-shaped card plate (4) is fixedly connected with the ear plate (51). The middle part of the ear plate (51) is provided with an internal thread (52). The inner wall of the internal thread (52) of the ear plate (51) is threadedly connected with the adjustment bolt (53). The end of the adjustment bolt (53) is spherical in design. The inner wall of the circular slide (3) is slidably connected with the connecting ball (54). The outer wall of the connecting ball (54) is fixedly connected with the threaded rod (55). The middle part of the U-shaped card plate (4) is provided with a through hole (56). The threaded rod (55) extends into the inner wall of the through hole (56), and the outer wall of the threaded rod (55) is symmetrically threadedly connected with the nut (57) at the through hole (56).

4. The glass curtain wall steel structure assembly according to claim 3, characterized in that: The height of the adjusting bolt (53) is smaller than the height of the U-shaped clamping plate (4).

5. The glass curtain wall steel structure assembly according to claim 3, characterized in that: One end of the threaded rod (55) that extends beyond the U-shaped card plate (4) needs to be cut off, and an avoidance groove (10) is provided at the through hole (56) of the U-shaped card plate (4).

6. The glass curtain wall steel structure assembly according to claim 3, characterized in that: After the adjustment structure (5) is adjusted, the spherical ends of the plurality of adjustment bolts (53) need to be welded to the embedded parts (1).

7. The glass curtain wall steel structure assembly according to claim 1, characterized in that: A fixing bolt (8) is provided in the middle of the U-shaped card plate (4), and the fixing bolt (8) is fixed to the glass curtain wall.

8. The glass curtain wall steel structure assembly according to claim 1, characterized in that: The back side of the embedded part (1) is symmetrically fixedly connected with a J-shaped claw (9).