Scaffold for civil engineering construction

The design of the connection box and the rotary locking mechanism solves the problem of complex assembly of existing scaffolding used in civil engineering construction, and achieves convenient and efficient installation and stable connection.

CN223423586UActive Publication Date: 2025-10-10HEFEI CEMENT RESEARCH AND DESIGN INSTITUTE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422679321.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-04
Publication Date
2025-10-10
Estimated Expiration
2034-11-04

AI Technical Summary

Technical Problem

The existing scaffolding used in civil engineering construction is cumbersome to assemble, and the installation process is complicated and time-consuming.

Method used

It adopts a connection box design, is assembled by plug-in, and is fixed with a rotary locking mechanism. It is combined with reinforcement rods and support plates to enhance stability.

Benefits of technology

The difficulty of loading and unloading is reduced, and the convenience of assembly and overall stability are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223423586U_ABST
    Figure CN223423586U_ABST
Patent Text Reader

Abstract

The utility model discloses a scaffold for civil engineering construction, relates to the technical field of scaffolds, and aims at solving the technical problems that an existing scaffold is complex to assemble and poor in convenience, the scaffold comprises end frames, reinforcing rods, panels, four connecting boxes and filling blocks, the two connecting boxes on the same side are connected through a cross rod, and the reinforcing rods are arranged on the end frames. The end frames are installed on the lower sides of the two connecting boxes at the same end, a ladder stand is arranged on the inner side of each end frame, positioning rods are fixed to the middles of the two sides of each end frame, inserting openings are formed in the upper sides of the inner ends of the connecting boxes, bottom cavities are formed in the bottom ends of the interiors of the connecting boxes, and the bottom cavities communicate with the inserting openings. A lifting piece is fixed to the top end of the interior of the bottom cavity, a middle piece is arranged at the bottom end of the interior of the inserting opening, the panel is installed between the two transverse rods, and the transverse rods are sleeved with sleeves at the upper ends of the reinforcing rods. The utility model has the advantages of convenient assembly, no need of bolt combination, and reduced loading and unloading difficulty.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to the technical field of scaffold, more particularly to a scaffold for civil engineering construction. BACKGROUND

[0002] Scaffold is a kind of equipment commonly used on construction site, mainly used for outer wall, interior decoration or higher place where direct construction is impossible, to provide operation platform for construction personnel and solve vertical and horizontal transportation problems.

[0003] In the process of civil engineering construction, artificial work at high place is often completed by means of scaffold. However, the existing scaffold structure assembly is not convenient enough when used in interior decoration. At present, the scaffold used in interior is mostly designed in assembled type, which is connected through fastener, and the fastener needs to be used in cooperation with bolt, resulting in complicated and time-consuming installation process. In view of this, the utility model provides a scaffold for civil engineering construction. SUMMARY

[0004] The utility model aims at overcoming the deficiency of prior art, adapting to practical needs, and providing a scaffold for civil engineering construction to solve the technical problem of current scaffold assembly being more complicated and poor in convenience.

[0005] To solve the above technical problems, the utility model provides the following technical scheme: a scaffold for civil engineering construction, comprising end frame, reinforcing rod, panel, connecting box and filling block, the connecting box is provided with four, and the two connecting boxes on the same side are connected through cross bar, the end frame is installed on the lower side of two connecting boxes on the same end, the inner side of end frame is provided with ladder, the middle of both sides of end frame is fixed with positioning rod, the inner end upper side of connecting box is provided with socket, the inner bottom end of connecting box is provided with bottom cavity, and the bottom cavity is communicated with socket, the inner top end of bottom cavity is fixed with lifting piece, the inner bottom end of socket is provided with middle piece, and the lower end of middle piece is connected with lifting piece, the panel is installed between two cross bars, the sleeve of reinforcing rod upper end is sleeved on cross bar, and the lower end hole of reinforcing rod is connected with positioning rod.

[0006] When assembling the present invention, the sleeve is sleeved on the cross bar, and then the cross end of the cross bar is inserted into the socket of the connection box. During the insertion process, the plane of the cross end is made to correspond to the position of the middle piece. After the connection is completed, the plug-in block of the end frame is inserted into the inner opening of the connection box so that it enters the bottom cavity. After the preliminary assembly is completed, the cross bar is rotated 180 degrees, and the arcuate surface of the cross bar squeezes the middle piece to make it fall, and the middle piece drives the lifting piece to fall. The sleeve groove of the lifting piece is sleeved on the sleeve part of the plug-in block to achieve fixation. At this time, the plug-in block is locked inside the connection box, and then the filling block is inserted into the filling port from the filling port. The connection box and the cross bar are locked and connected by the filling block to achieve fixation of the assembly position. It is installed by plugging in, and then the internal locking is completed by a rotary locking mechanism to achieve overall connection and fixation, reducing the difficulty of loading and unloading. The sliding sleeve makes the lower end of the reinforcement rod correspond to the positioning rod, and then the sleeve is deflected to dock the hole at the lower end of the reinforcement rod with the positioning rod to achieve connection and positioning, forming a triangular area to ensure the overall stability of the device. Then the panel is placed between the two cross bars so that the arc-shaped openings at both ends of the support plate are clamped on the cross bar to achieve installation and positioning of the panel. At the same time, the pressure piece fits the upper side of the cross bar to increase the support surface and ensure load-bearing stability. At the same time, the sleeve is limited between the two connected pressure pieces to achieve positioning, and the overall stability of the device is enhanced by the reinforcement rod and the support plate.

[0007] Preferably, plug-in blocks are fixed to the upper ends of both sides of the end frame, and the plug-in blocks are inserted into the bottom cavity from the inner opening of the connection box.

[0008] Preferably, springs are provided at both ends of the lower end surface of the middle piece, and the lower ends of the springs are connected to the bottom of the socket.

[0009] Preferably, a sleeve groove is formed at the outer end of the lifting piece, and the sleeve groove is sleeved on the sleeve port into which the plug-in block is inserted.

[0010] Preferably, a filling port is provided at the upper end of the connection box, and the filling port is connected to the socket.

[0011] Preferably, both ends of the cross bar are provided with a transverse end, and the transverse end is adapted to the upper arc surface of the middle piece, and a filling port is opened on the transverse end.

[0012] Preferably, the filling block passes through the filling opening and is inserted into the interior of the filling opening.

[0013] Preferably, support plates are fixed to both ends of the panel, and arc openings at both ends of the support plates are respectively clamped on corresponding cross bars.

[0014] Preferably, pressing sheets are fixed at equal distances on both sides of the panel, and the pressing sheets are in contact with the upper side of the crossbar.

[0015] Compared with the prior art, the beneficial effects of the present invention are:

[0016] 1. The utility model designs a connection box. During assembly, the sleeve is sleeved on the cross bar, and then the cross end of the cross bar is inserted into the socket of the connection box. During the insertion process, the plane of the cross end corresponds to the position of the middle piece. After the connection is completed, the plug-in block of the end frame is inserted into the inner opening of the connection box so that it enters the bottom cavity. After the initial assembly is completed, the cross bar is rotated 180 degrees, and the curved surface of the cross bar squeezes the middle piece to make it descend, and the middle piece drives the lifting piece to descend. The sleeve groove of the lifting piece is sleeved on the sleeve part of the plug-in block to achieve fixation. At this time, the plug-in block is locked inside the connection box, and then the filling block is inserted into the filling port from the filling port. The connection box and the cross bar are locked and connected by the filling block to achieve the fixation of the assembly position. The device is installed by plugging, and then the internal locking is completed by the rotary locking mechanism to achieve the overall connection fixation, reducing the difficulty of loading and unloading.

[0017] 2. The utility model also designs a reinforcement rod and a support plate, and slides the sleeve so that the lower end of the reinforcement rod corresponds to the positioning rod. Then, after deflecting the sleeve, the hole at the lower end of the reinforcement rod is docked with the positioning rod to achieve connection and positioning, forming a triangular area to ensure the overall stability of the device. Then, the panel is placed between the two cross bars, so that the arc-shaped openings at both ends of the support plate are clamped on the cross bar to achieve the installation and positioning of the panel. At the same time, the pressure plate fits the upper side of the cross bar to increase the support surface and ensure load-bearing stability. At the same time, the sleeve is limited between the two connected pressure plates to achieve positioning, and the overall stability of the device is enhanced by the reinforcement rod and the support plate. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 This is a schematic diagram of the main structure of the utility model;

[0019] Figure 2 This is a schematic diagram of the end frame structure of the utility model;

[0020] Figure 3 This is a schematic diagram of the crossbar structure of the utility model;

[0021] Figure 4 This is a schematic diagram of the connection box structure of the utility model;

[0022] Figure 5 This is a schematic diagram of the filling port structure of the present utility model.

[0023] Explanation of the numbers in the figure: 1. End frame; 101. Ladder; 102. Positioning rod; 103. Plug-in block; 2. Reinforcement rod; 201. Sleeve; 3. Panel; 301. Pressing piece; 4. Support plate; 5. Connection box; 501. Bottom cavity; 502. Spring; 503. Slot; 504. Lifting piece; 505. Middle piece; 506. Socket; 507. Filling socket; 6. Cross bar; 601. Horizontal end; 602. Filling port; 603. Filling block. DETAILED DESCRIPTION

[0024] likeFigures 1 to 4 As shown, the utility model relates to a scaffold for civil engineering construction, comprising an end frame 1, a reinforcement rod 2, a panel 3, a connection box 5 and a filling block 603. There are four connection boxes 5 in total, and the two connection boxes 5 on the same side are connected by a cross bar 6. The end frame 1 is installed on the lower side of the two connection boxes 5 at the same end. A ladder 101 is provided on the inner side of the end frame 1, and a positioning rod 102 is fixed at the middle of both sides of the end frame 1. Plug-in blocks 103 are fixed at the upper ends of both sides of the end frame 1, and the plug-in blocks 103 are inserted into the bottom cavity 501 from the inner opening of the connection box 5. A socket 506 is provided on the upper side of the inner end of the connection box 5, and a bottom cavity 501 is provided at the inner bottom end of the connection box 5, and the bottom cavity 501 and the plug-in block 103 are connected. The sockets 506 are connected, and a lifting piece 504 is fixed to the top of the bottom cavity 501. A middle piece 505 is provided at the bottom end of the inner part of the socket 506, and the lower end of the middle piece 505 is connected to the lifting piece 504. Springs 502 are provided at both ends of the lower end surface of the middle piece 505, and the lower end of the spring 502 is connected to the bottom of the socket 506. When disassembled, the middle piece 505 is reset by the rebound of the spring 502. A sleeve groove 503 is provided at the outer end of the lifting piece 504, and the sleeve groove 503 is sleeved on the sleeve port where the plug-in block 103 is inserted. The sleeve groove 503 is sleeved on the plug-in block 103 to achieve locking. A filling port 507 is provided at the upper end of the connection box 5, and the filling port 507 is connected to the socket 506.

[0025] like Figures 2 to 5 As shown, the utility model relates to a scaffold for civil engineering construction, comprising an end frame 1, a reinforcement rod 2, a panel 3, a connection box 5 and a filling block 603. The panel 3 is installed between two cross bars 6. Both ends of the panel 3 are fixed with a support plate 4, and the arc openings at both ends of the support plate 4 are respectively clamped on the corresponding cross bars 6. The sleeve 201 at the upper end of the reinforcement rod 2 is sleeved on the cross bar 6. Both ends of the cross bar 6 are provided with a transverse end 601, and the transverse end 601 is adapted to the middle piece. The upper end of the curved surface 505 is provided with a filling port 602 on the horizontal end 601, the lower end of the reinforcement rod 2 is opened to connect with the positioning rod 102, and the filling block 603 passes through the filling port 507 and is inserted into the inside of the filling port 602. The filling block 603 is used to lock the connection box 5 and the cross bar 6. The two sides of the panel 3 are equidistantly fixed with pressing plates 301, and the pressing plates 301 are attached to the upper side of the cross bar 6. When the upper end of the panel 3 is subjected to force, the pressure is dispersed to the cross bar 6 through the pressing plate 301.

[0026] Working principle: This embodiment provides a scaffold for civil engineering construction. During assembly, the sleeve 201 is sleeved on the crossbar 6, and then the transverse end 601 of the crossbar 6 is inserted into the socket 506 of the connection box 5. During the insertion process, the plane of the crossbar end 601 corresponds to the position of the middle piece 505. After the connection is completed, the plug-in block 103 of the end frame 1 is inserted into the inner opening of the connection box 5 so that it enters the bottom cavity 501. After the preliminary assembly is completed, the crossbar 6 is rotated 180 degrees, and the curved surface of the crossbar 6 squeezes the middle piece 505 to make it descend. The middle piece 505 drives the lifting piece 504 to descend, and the sleeve groove 503 of the lifting piece 504 is sleeved on the sleeve part of the plug-in block 103 to achieve fixation. At this time, the plug-in block 103 is locked inside the connection box 5, and then the filling block 603 is removed from the filling plug-in block. The opening 507 is inserted into the filling opening 602, and the connecting box 5 is locked and connected to the cross bar 6 through the filling block 603 to fix the assembly position. The sliding sleeve 201 makes the lower end of the reinforcement rod 2 correspond to the positioning rod 102, and then the sleeve 201 is deflected to dock the hole at the lower end of the reinforcement rod 2 with the positioning rod 102 to achieve connection and positioning, forming a triangular area to ensure the overall stability of the device, and then the panel 3 is placed between the two cross bars 6, so that the arc-shaped openings at both ends of the support plate 4 are clamped on the cross bar 6 to achieve installation and positioning of the panel 3. At the same time, the pressing piece 301 is attached to the upper side of the cross bar 6 to increase the support surface and ensure load-bearing stability. At the same time, the sleeve 201 is limited between the two connected pressing pieces 301 to achieve positioning, and the overall stability of the device is enhanced by the reinforcement rod 2 and the support plate 4.

[0027] The embodiments disclosed in the present invention are preferred embodiments, but are not limited to them. Ordinary technicians in this field can easily understand the spirit of the present invention based on the above embodiments and make different extensions and changes. As long as they do not deviate from the spirit of the present invention, they are all within the scope of protection of the present invention.

Claims

1. A scaffold for civil engineering construction, comprising an end frame (1), a reinforcement rod (2), a panel (3), a connection box (5) and a filling block (603), characterized in that: There are four connection boxes (5) in total, and two connection boxes (5) on the same side are connected by a cross bar (6). The end frame (1) is installed on the lower side of the two connection boxes (5) on the same end. A ladder (101) is provided on the inner side of the end frame (1). Positioning rods (102) are fixed at the middle of both sides of the end frame (1). A socket (506) is provided on the upper side of the inner end of the connection box (5). A bottom cavity (501) is provided at the inner bottom end of the connection box (5), and the bottom cavity (501) is connected to the socket (506), a lifting plate (504) is fixed to the top end of the inner side of the bottom cavity (501), a middle plate (505) is provided at the bottom end of the inner side of the socket (506), and the lower end of the middle plate (505) is connected to the lifting plate (504), the panel (3) is installed between the two cross bars (6), the sleeve (201) at the upper end of the reinforcing rod (2) is sleeved on the cross bar (6), and the lower end of the reinforcing rod (2) has a hole for docking with the positioning rod (102).

2. A scaffold for civil engineering construction according to claim 1, characterized in that: Plug-in blocks (103) are fixed to the upper ends of both sides of the end frame (1), and the plug-in blocks (103) are inserted into the bottom cavity (501) from the inner opening of the connection box (5).

3. A scaffold for civil engineering construction according to claim 1, characterized in that: Springs (502) are provided at both ends of the lower end surface of the middle piece (505), and the lower ends of the springs (502) are connected to the bottom of the socket (506).

4. A scaffold for civil engineering construction according to claim 3, characterized in that: The outer end of the lifting piece (504) is provided with a sleeve groove (503), and the sleeve groove (503) is sleeved on the sleeve port into which the plug-in block (103) is inserted.

5. A scaffold for civil engineering construction according to claim 4, characterized in that: The upper end of the connection box (5) is provided with a plug-in port (507), and the plug-in port (507) is connected to the socket (506).

6. A scaffold for civil engineering construction according to claim 5, characterized in that: Both ends of the crossbar (6) are provided with transverse ends (601), and the transverse ends (601) are adapted to the upper arc surface of the middle piece (505), and a filling port (602) is opened on the transverse ends (601).

7. A scaffold for civil engineering construction according to claim 6, characterized in that: The filling block (603) passes through the filling port (507) and is inserted into the interior of the filling port (602).

8. A scaffold for civil engineering construction according to claim 1, characterized in that: Support plates (4) are fixed to both ends of the panel (3), and arc openings at both ends of the support plates (4) are respectively clamped on corresponding cross bars (6).

9. A scaffold for civil engineering construction according to claim 1, characterized in that: Pressing sheets (301) are fixed at equal distances on both sides of the panel (3), and the pressing sheets (301) are in contact with the upper side of the crossbar (6).