Creeping formwork platform capable of being used for high pier concrete curing

The formwork angle is adjusted by a screw rod system driven by a hydraulic rod and a motor, and the position of the deformed plate is adjusted by a gear rack system. This solves the problems of formwork angle adjustment and adaptability to working conditions during high pier concrete curing, achieves uniform curing and efficient water resource utilization, and improves the curing effect and versatility of the formwork.

CN223458685UActive Publication Date: 2025-10-21KUNMING YINQIAO STEEL FORM CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202422012674.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2025-10-21
Estimated Expiration
2034-08-20

AI Technical Summary

Technical Problem

Traditional high pier concrete curing equipment makes it difficult to adjust the formwork angle, resulting in uneven curing, low water resource utilization efficiency, and insufficient curing of special parts, which reduces the curing effect and the versatility of the formwork.

Method used

The angle of the formwork is adjusted by a screw system driven by hydraulic rods and motors, and the position of the deformable plate is adjusted by a rack and pinion system, so that the formwork can fit closely to the concrete surface and adapt to different working conditions.

Benefits of technology

Ensure uniform distribution of maintenance water, improve water resource utilization efficiency, enhance maintenance of special parts, improve comprehensiveness of maintenance and versatility of templates, and ensure that maintenance results are not affected.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223458685U_ABST
    Figure CN223458685U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of concrete construction, in particular to a creeping formwork platform capable of being used for high pier concrete curing, which comprises a creeping formwork frame, one side of the top of the creeping formwork frame is fixedly connected with a cross beam, one side of the cross beam is fixedly connected with a plurality of hydraulic rods, and output shafts of the hydraulic rods are fixedly connected with supports. When the device is used and the sizes and the shapes of high piers are different, a worker firstly outputs power to the support through the hydraulic rod, the formwork is moved through transmission of the support and other parts, then the worker outputs power to the lead screw through the motor, the formwork is rotated through transmission of the lead screw and other parts, and the high piers are driven to move. The purpose of adjusting the angle of the formwork is achieved, the formwork can be tightly attached to the surface of concrete by adjusting the angle of the formwork, it is guaranteed that curing water is evenly distributed, the utilization efficiency of water resources is improved, curing of special parts is enhanced, curing comprehensiveness is improved, and it is guaranteed that the curing effect is not affected.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model belongs to concrete construction technical field, concretely relates to a climbing form platform for high pier concrete maintenance. BACKGROUND

[0002] In the traditional construction method, the maintenance of high pier concrete faces many challenges, because the height of high pier is higher, the conventional maintenance method is often difficult to effectively cover the entire concrete surface, which is easy to lead to uneven and insufficient maintenance, thereby affecting the strength development and crack resistance of concrete.

[0003] Chinese patent: CN217556696U, proposes a climbing form platform for high pier concrete maintenance, including climbing form body and guide rail, the climbing form body is formed by three layers of climbing form units connected in turn, the first layer of climbing form unit is provided with a formwork matched with the size of high pier, the second layer of climbing form unit is provided with a roller matched with the size of high pier, the roller is provided with a protective film, the third telescopic rod is connected with a cutting blade matched with the size of high pier and used for cutting the protective film at one end close to the high pier, the top end of the third layer of climbing form unit is provided with a plurality of maintenance spray heads, the guide rail is installed on the side wall of high pier, the second layer of climbing form unit and the third layer of climbing form unit are installed on the guide rail, the maintenance spray head is connected with a water pipe, the other end of the water pipe is connected with a water pump, the water pump is communicated with the water storage tank. The utility model has the beneficial effects that after the high pier concrete is poured, the concrete can be safely and conveniently maintained with high quality along with the climbing form rising.

[0004] The above-mentioned patent cannot adjust the angle of the formwork well during use, which may cause the formwork to be difficult to closely adhere to the surface of the concrete, resulting in uneven distribution of maintenance water, low water resource utilization efficiency, insufficient maintenance of special parts, reduced comprehensiveness of maintenance, and affected maintenance effect, and cannot well realize the adjustment of the position of the deformation plate to adapt to different working conditions or achieve specific functions, reducing the universality of the formwork. UTILITY MODEL CONTENTS

[0005] To solve the above-mentioned problems in the prior art, the utility model provides a climbing form platform for high pier concrete maintenance, which can adjust the angle of the formwork, make the formwork closely adhere to the surface of the concrete, ensure the uniform distribution of maintenance water, improve the water resource utilization efficiency, enhance the maintenance of special parts, improve the comprehensiveness of maintenance, ensure the maintenance effect is not affected, and can realize the adjustment of the position of the deformation plate, make the deformation plate become arc-shaped to adapt to different working conditions or achieve specific functions, and improve the universality of the formwork.

[0006] In order to achieve the above object, the utility model provides the following technical scheme: a kind of climbing formwork platform for high pier concrete maintenance, including climbing formwork, the top side of the climbing formwork is fixedly connected with crossbeam, the side of the crossbeam is fixedly connected with several hydraulic rods, the output shaft of several hydraulic rods is fixedly connected with support, the support one end is movably connected with second U-shaped frame, the side of the second U-shaped frame is fixedly connected with formwork, the top side of the climbing formwork is fixedly installed with motor, the output shaft of the motor is penetrated in support block and fixedly sleeved with lead screw, the outer surface of the lead screw is threadedly connected with sliding block, the top of the sliding block is fixedly connected with first U-shaped frame, the angle adjusting rod is movably connected in the inner wall of the first U-shaped frame, the angle adjusting rod one end is fixedly connected to formwork bottom.

[0007] As a preferred technical scheme of the utility model, the formwork includes a deformation assembly, a plurality of fixed boxes are fixedly connected to one side of the formwork, and a transmission groove is formed in one end of each fixed box.

[0008] As a preferred technical scheme of the utility model, a gear is arranged on the inner wall of the transmission groove, a bearing is fixedly sleeved in the gear, the bearing penetrates the fixed box at one end and is movably connected with a hand wheel, a rack is engagedly installed at the bottom end of the gear, the rack is movably connected to the inner wall of the third U-shaped frame, and a deformation plate is fixedly connected to one side of the third U-shaped frame.

[0009] As a preferred technical scheme of the utility model, screw rods are fixedly connected to both ends of the deformation plate, connecting rods are movably connected to the outer surfaces of the screw rods, and the connecting rods are movably connected to both ends of the formwork.

[0010] As a preferred technical scheme of the utility model, a plurality of limiting plates are fixedly installed on the top of the climbing formwork, a plurality of rollers are fixedly installed at the bottom end of the support, and the rollers are slidably connected to the top notches of the limiting plates.

[0011] As a preferred technical scheme of the utility model, a protective plate is fixedly installed on one side of the climbing formwork, and a plurality of holes are formed in the protective plate.

[0012] As a preferred technical scheme of the utility model, one side of the climbing formwork is provided with a wall body, a plurality of fixing members are fixedly connected to one side of the wall body, and guide rails are fixedly connected to one side of the fixing members.

[0013] Compared with the prior art, the utility model has the following beneficial effects:

[0014] 1. The utility model discloses a when using, when high pier size and shape are different, staff first carries out power output to support through hydraulic rod, moves the formwork under the transmission of support and other components, and staff then carries out power output to screw rod through motor, rotates the formwork under the transmission of screw rod and other components, to reach the purpose of adjusting the angle of formwork, and the angle of formboard can be adjusted to make formboard closely adhere to concrete surface, ensure the uniform distribution of maintenance water, improve water resource utilization efficiency, strengthen the maintenance of special parts, improve the comprehensiveness of maintenance, guarantee the maintenance effect is not influenced.

[0015] 2. The utility model discloses a when using, when staff rotates hand wheel, hand wheel drives bearing to rotate, and bearing drives gear to rotate, and gear rotates simultaneously, drives rack to carry out straight line motion, and rack moves deformed plate through third U -shaped frame to push, to realize the adjustment of deformed plate position, and make deformed plate become arc to adapt to different working conditions or reach specific function, improve the versatility of formwork. ACCURACY

[0016] The accompanying drawings are included to provide a further understanding of the utility model, and constitute a part of the specification, and are used to explain the utility model together with embodiments of the utility model, and do not constitute the limitation to the utility model. In the drawings:

[0017] Figure 1 It is side surface structure schematic view of the utility model;

[0018] Figure 2 It is overhead structure schematic view of the utility model;

[0019] Figure 3 It is Figure 2 The enlarged structure schematic view of A in the middle;

[0020] Figure 4 It is top end partial structure schematic view of the utility model;

[0021] Figure 5 It is Figure 4 The partial section structure schematic view of;

[0022] Figure 6 It is Figure 5 The enlarged structure schematic view of deformed subassembly in the middle.

[0023] In the figure: 1, climbing formwork; 2, wall; 3, fixing piece; 4, guide rail; 5, formwork; 6, protection plate; 7, deformation plate; 8, crossbeam; 9, limiting plate; 10, hydraulic rod; 11, support; 12, roller; 13, screw rod; 14, connecting rod; 15, angle adjusting rod; 16, first U-shaped frame; 17, screw rod; 18, supporting block; 19, motor; 20, sliding block; 21, second U-shaped frame; 22, deformation assembly; 2201, hand wheel; 2202, fixed box; 2203, bearing; 2204, gear; 2205, transmission groove; 2206, rack; 2207, third U-shaped frame. DETAILED DESCRIPTION

[0024] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the protection scope of the utility model. EMBODIMENT

[0025] Please refer to Figures 1-4 The utility model provides the following technical scheme: a climbing formwork platform for high pier concrete maintenance, which comprises a climbing formwork 1, the top of the climbing formwork 1 is fixedly connected with a crossbeam 8 on one side, the crossbeam 8 is fixedly connected with a plurality of hydraulic rods 10 on one side, the output shafts of the plurality of hydraulic rods 10 are all fixedly connected with supports 11, one end of the support 11 is movably connected with a second U-shaped frame 21, the second U-shaped frame 21 is fixedly connected with a formwork 5 on one side, a motor 19 is fixedly installed on one side of the top of the climbing formwork 1, the output shaft of the motor 19 penetrates through a supporting block 18 and is fixedly sleeved with a screw rod 17, the outer surface of the screw rod 17 is threadedly connected with a sliding block 20, the top end of the sliding block 20 is fixedly connected with a first U-shaped frame 16, the inner wall of the first U-shaped frame 16 is movably connected with an angle adjusting rod 15, one end of the angle adjusting rod 15 is fixedly connected to the bottom of the formwork 5.

[0026] Specifically, when the high pier size and shape are different, the staff first powers the support 11 through the hydraulic rod 10 to make the support 11 move, the support 11 drives the second U-shaped frame 21 to move, the second U-shaped frame 21 drives the formwork 5 to move, and then the staff powers the screw rod 17 through the motor 19, the screw rod 17 is driven by the motor 19 to rotate under the position fixing of the two end support blocks 18, the screw rod 17 drives the sliding block 20 to move, the sliding block 20 drives the first U-shaped frame 16 to move, and the first U-shaped frame 16 moves while pushing the formwork 5 to move through the angle adjusting rod 15, the moving formwork 5 is fixed in the position of the second U-shaped frame 21, so that the formwork 5 only rotates by a small angle, so as to achieve the purpose of adjusting the angle of the formwork 5, and the angle of the formwork 5 is adjusted to make the formwork 5 closely fit the concrete surface, ensure uniform distribution of maintenance water, improve water resource utilization efficiency, enhance maintenance of special parts, improve comprehensive maintenance, and ensure that the maintenance effect is not affected.

[0027] Please refer to Figures 5-6 The formwork 5 comprises a deformation assembly 22, and a plurality of fixed boxes 2202 are fixedly connected to one side of the formwork 5, and a transmission groove 2205 is formed at one end of the fixed boxes 2202.

[0028] Specifically, the transmission groove 2205 at one end of the fixed box 2202 is used to cooperate with other components to realize deformation control of the formwork 5, so as to ensure that the formwork 5 is better fitted with the surface of the pier body, thereby improving the coverage area and effect of maintenance.

[0029] Please refer to Figures 5-6 A gear 2204 is arranged on the inner wall of the transmission groove 2205, a bearing 2203 is fixedly sleeved in the gear 2204, the bearing 2203 penetrates through the fixed box 2202 at one end and is movably connected with a hand wheel 2201, a rack 2206 is meshingly installed at the bottom end of the gear 2204, the rack 2206 is movably connected to the inner wall of a third U-shaped frame 2207, and the third U-shaped frame 2207 is fixedly connected with the deformation plate 7 on one side.

[0030] Specifically, when the staff rotates the hand wheel 2201, the hand wheel 2201 drives the bearing 2203 to rotate, the bearing 2203 drives the gear 2204 to rotate, the gear 2204 drives the rack 2206 to move linearly at the same time, the rack 2206 drives the deformation plate 7 to move through the third U-shaped frame 2207, so as to realize adjustment of the position of the deformation plate 7, make the deformation plate 7 become arc-shaped to adapt to different working conditions or achieve a specific function, and improve the universality of the formwork.

[0031] Please refer to Figures 5-6 The deformation plate 7 is fixedly connected with a screw rod 13 at both ends, the screw rod 13 is movably connected with a connecting rod 14 on the outer surface, and the connecting rod 14 is movably connected to both ends of the formwork 5.

[0032] Specifically, the deformation plate 7 can be linked with the mold plate 5 through the screw rods 13 and the connecting rods 14 at both ends, which helps the whole mold plate system to better adapt to complex shapes and size changes, improves the versatility of the mold plate, and facilitates individual maintenance or replacement of the deformation plate 7 or related connecting parts without the need to replace the whole mold plate structure.

[0033] Please refer to Figure 2 and Figure 4 The climbing formwork 1 is fixedly installed with a plurality of limiting plates 9 at the top, and the support 11 is fixedly installed with a plurality of rollers 12 at the bottom, and the plurality of rollers 12 are slidingly connected to the top slots of the limiting plates 9.

[0034] Specifically, the rollers 12 slide in the slots at the top of the limiting plates 9, which provides clear guidance for the movement of the support 11, making the movement of the support 11 more smooth and labor-saving, ensuring that it moves along the predetermined path, avoiding deviation or misalignment, thereby improving the precision and quality of construction.

[0035] Please refer to Figure 1 The climbing formwork 1 is fixedly installed with a protective plate 6 on one side, and a plurality of holes are formed in the protective plate 6.

[0036] Specifically, this design provides a physical barrier for personnel working on the climbing formwork 1, reducing the risk of accidental falling, and the holes help air circulation, improving the ventilation conditions of the working area, reducing the feeling of stuffiness, and improving the comfort of the working environment.

[0037] Please refer to Figure 1 The climbing formwork 1 is provided with a wall 2 on one side, the wall 2 is fixedly connected with a plurality of fixing members 3 on one side, and the fixing members 3 are fixedly connected with guide rails 4 on one side.

[0038] Specifically, the guide rails 4 are connected with the wall 2 through the fixing members 3, which provides a clear guide path for the climbing of the climbing formwork 1, ensuring that the climbing formwork 1 can move smoothly along the predetermined vertical direction, and at the same time, the guide rails 4 also provide a certain lateral support for the climbing formwork 1, increasing the stability of the climbing formwork 1 during work.

[0039] The utility model discloses a working principle and use flow: the utility model discloses in the process of using, when high pier size and shape are different, staff first carries out power output to support 11 to the hydraulic rod 10, makes support 11 move, and support 11 drives second U -shaped frame 21 to move, and second U -shaped frame 21 drives formwork 5 to move, and staff then carries out power output to screw rod 17 to motor 19, and screw rod 17 is rotated to be driven by motor 19 under the position fixation of both end support block 18, and screw rod 17 drives sliding block 20 to move, and sliding block 20 drives first U -shaped frame 16 to move, and first U -shaped frame 16 moves simultaneously, and through angle adjusting rod 15 pushes formwork 5 to move, and the formwork 5 of moving is fixed under the position of second U -shaped frame 21, makes only small angle rotation of itself, to reach the purpose of adjusting the angle of formwork 5, and the angle of formwork 5 can be adjusted to make formwork 5 closely adhere to concrete surface, ensure the uniform distribution of maintenance water, improve water resource utilization efficiency, strengthen the maintenance to special part, improve the comprehensiveness of maintenance, guarantee the maintenance effect not to be influenced, when staff rotates hand wheel 2201, hand wheel 2201 drives bearing 2203 to rotate, and bearing 2203 drives gear 2204 to rotate, and gear 2204 rotates simultaneously, drives rack 2206 to move linearly, and rack 2206 pushes deformation plate 7 to move through third U -shaped frame 2207, to realize the adjustment of deformation plate 7 position, make deformation plate 7 become arc to adapt to different working conditions or reach specific function, improve the versatility of formwork.

[0040] Finally, it should be noted that: the above only for the preferred embodiment of the utility model has been described, and is not used to limit the utility model, although the utility model has been described in detail with reference to the foregoing embodiment, for the person skilled in the art, it still can modify the technical scheme recorded in the foregoing each embodiment, or equivalent replacement to part technical feature. Any modification, equivalent replacement, improvement etc. that is made within the spirit and principle of the utility model, should be contained in the protection scope of the utility model.

Claims

1. A climbing form platform that can be used for high pier concrete curing, comprising a climbing form frame (1), characterized in that: The climbing formwork frame (1) top side is fixedly connected with a cross beam (8), one side of the cross beam (8) is fixedly connected with a plurality of hydraulic rods (10), the output shafts of the plurality of hydraulic rods (10) are all fixedly connected with supports (11), one end of the support (11) is movably connected with a second U-shaped frame (21), one side of the second U-shaped frame (21) is fixedly connected with a formwork (5), the top side of the climbing formwork frame (1) is fixedly installed with a motor (19), the output shaft of the motor (19) penetrates through a supporting block (18) and is fixedly sleeved with a lead screw (17), the outer surface of the lead screw (17) is threadedly connected with a sliding block (20), the top end of the sliding block (20) is fixedly connected with a first U-shaped frame (16), the inner wall of the first U-shaped frame (16) is movably connected with an angle adjusting rod (15), one end of the angle adjusting rod (15) is fixedly connected to the bottom of the formwork (5).

2. The climbing form platform for curing high pier concrete according to claim 1, characterized in that: The formwork (5) comprises a deformation assembly (22), a plurality of fixed boxes (2202) are fixedly connected to one side of the formwork (5), and a transmission groove (2205) is formed in one end of each fixed box (2202).

3. The climbing form platform for curing high pier concrete of claim 2, wherein: A gear (2204) is arranged on the inner wall of the transmission groove (2205), a bearing (2203) is fixedly sleeved in the gear (2204), one end of the bearing (2203) penetrates through the fixed box (2202) and is movably connected with a hand wheel (2201), a rack (2206) is engagedly installed at the bottom of the gear (2204), one end of the rack (2206) is movably connected to the inner wall of a third U-shaped frame (2207), and the third U-shaped frame (2207) is fixedly connected with a deformation plate (7) on one side.

4. The climbing form platform for curing high pier concrete of claim 3, wherein: The deformation plate (7) is fixedly connected with a screw rod (13) at both ends, the outer surface of the screw rod (13) is movably connected with a connecting rod (14), and the connecting rod (14) is movably connected to both ends of the formwork (5).

5. The climbing form platform for curing high pier concrete of claim 1, wherein: A plurality of limiting plates (9) are fixedly installed on the top of the climbing formwork frame (1), a plurality of rollers (12) are fixedly installed at the bottom of the support (11), and the plurality of rollers (12) are slidingly connected to the top notch of the limiting plate (9).

6. The climbing form platform for curing high pier concrete of claim 1, wherein: The climbing formwork frame (1) is fixedly installed with a protective plate (6) on one side, and a plurality of holes are formed in the protective plate (6).

7. The climbing form platform for curing high pier concrete of claim 1, wherein: One side of the climbing formwork frame (1) is provided with a wall body (2), a plurality of fixing members (3) are fixedly connected to one side of the wall body (2), and a guide rail (4) is fixedly connected to one side of the fixing member (3).