Scaffold for building construction

By designing a scaffolding with a support frame and a height adjustment mechanism, the problem of difficult height adjustment of traditional scaffolding is solved, and the rapid and stable adjustment of the pedal height is achieved, thereby improving construction efficiency and safety.

CN223459098UActive Publication Date: 2025-10-21SHANDONG GUOJIA ENG INSPECTION & APPRAISAL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422900004.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-27
Publication Date
2025-10-21
Estimated Expiration
2034-11-27

AI Technical Summary

Technical Problem

Traditional scaffolding cannot quickly adjust its height, resulting in low construction efficiency, time-consuming and labor-intensive.

Method used

A scaffold including a support frame, a lifting rod and a height adjustment mechanism is designed. The height of the pedal is adjusted quickly and stably through the height adjustment mechanism, and the position of the lifting rod is fixed and adjusted by the cooperation of the pin and the bracket.

Benefits of technology

The flexible adjustment of the pedal height is realized, the construction efficiency is improved, the operation is simple and easy, time and labor are saved, and the flexibility and safety of construction are enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223459098U_ABST
    Figure CN223459098U_ABST
Patent Text Reader

Abstract

The utility model relates to a scaffold for building construction, which comprises two groups of support frames arranged front and back, each group of support frames comprises two vertically arranged hollow support rods, a plurality of horizontal foot bars are fixed between the two support rods, a lifting rod is inserted in each support rod, a plurality of transverse fixing pin holes are arranged on each lifting rod, and the horizontal foot bars are fixed on the horizontal foot bars through the transverse fixing pin holes. The pin is selectively inserted into the transverse fixing pin hole to fix the position of the lifting rod; the top end of each lifting rod is vertically fixed with the pedal; a height adjusting mechanism used for adjusting the height of the lifting rod is arranged on one side of each supporting frame. The pedal can be moved to a proper height according to different construction requirements so as to adapt to construction at different heights, and the flexibility is high.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to the technical field of building construction, especially building construction with scaffold. BACKGROUND

[0002] The scaffold is a kind of support that is erected at construction site for worker operation and solves vertical and horizontal transportation, and it is mainly used for the outer wall of construction site, interior decoration or the place where direct construction is impossible due to higher height.The traditional scaffold is generally fixed structure, and the height of pedal cannot be adjusted, so that only upper layer scaffold can be built to adapt to higher position construction, and the built scaffold needs to consume a lot of working time, which is time-consuming and laborious, and reduces work efficiency.

[0003] Therefore, a building construction scaffold with convenient height adjustment is needed, which can quickly complete the height adjustment of pedal to adapt to the construction needs of different heights. CONTENT OF UTILITY MODEL

[0004] The utility model provides building construction scaffold for the shortage of prior art.

[0005] The utility model is through following technical scheme realizes, provide building construction scaffold, including two groups of support frame that set up before and after, every group of support frame all includes two vertical settings and inside hollow support pole, between two support poles fixed multiple horizontal pedal rod, in every support pole all insert has lifting rod, on every lifting rod all set up several horizontal fixed pin holes, pin chooses insert horizontal fixed pin hole in make lifting rod position fixed;Every lifting rod top end all with pedal vertical fixed;Every group of support frame one side all set up one for adjusting lifting rod height's height adjusting mechanism.

[0006] Preferably, the height adjusting mechanism includes a clamping seat for holding the upward movement of the pin, an operating rod fixed with the clamping seat for changing the position of the clamping seat, and a support plate fixed with the upper end of one support rod, the support plate is connected with the clamping seat through a connecting rod, one end of the connecting rod is hinged with the clamping seat, and the other end is hinged with the support plate, a clamping groove for the pin is arranged on the clamping seat. The operating rod of the height adjusting mechanism is held by the worker to change the position of the clamping seat so that the pin enters the clamping groove, and then the operating rod is pressed down to make the clamping seat pick up the pin, so that the lifting rod moves upward, the worker inserts the spare pin into the appropriate horizontal fixed pin hole below, completes the height adjustment of the lifting rod, and then takes out the pin above for standby. During specific operation, two workers can operate two height adjusting mechanisms at the same time to make four lifting rods rise at the same time, the height adjusting mechanism makes the pedal move upward stably, and the operation is simple and easy to operate, time-saving and labor-saving.

[0007] Preferably, the plurality of pedal rods are evenly distributed up and down. The pedal rod facilitates the upward climbing of the worker.

[0008] Preferably, in order to improve the support stability of the support frame, a reinforcing rod is fixedly connected between two support rods on the same side of different groups of support frames.

[0009] Preferably, a plurality of transverse fixing pin holes are uniformly arranged along the longitudinal direction of the lifting rod. According to the construction needs, the pin is inserted into the appropriate transverse fixing pin hole, and the lifting rod is limited by the two ends of the pin blocking the top end of the support rod.

[0010] Preferably, in order to further improve the safety of construction operation, a protective fence is arranged on the step.

[0011] Preferably, in order to facilitate the staff to climb onto the step after the position of the step is raised, a climbing frame is fixed on the front side of the step, and the top end of the climbing frame is fixed with the step through a connecting plate. When the step moves up and down, the climbing frame moves up and down, and the climbing frame is located on the front side of the support frame and does not interfere with the step between the two support rods.

[0012] Preferably, a pass-through opening is arranged on the protective fence above the climbing frame. The pass-through opening facilitates the staff to enter the protective fence. When the position of the step is moved to a certain height, the staff can conveniently climb onto the step through the climbing frame.

[0013] The beneficial effects of the utility model are as follows:

[0014] 1. The utility model can move the step to a suitable height according to different construction needs, so as to adapt to construction of different heights and be high in flexibility.

[0015] 2. The height of the step can be quickly and stably adjusted through the height adjusting mechanism, time and labor are saved, work efficiency is greatly improved, the adjustment mode is stable and reliable, simple and easy to operate, high in convenience, and easy to popularize and apply. DRAWINGS

[0016] Figure 1 It is a front view structural schematic diagram of one state of the utility model;

[0017] Figure 2 It is a side view structural schematic diagram of one state of the utility model;

[0018] Figure 3 It is a front view structural schematic diagram of another state of the utility model;

[0019] Figure 4 It is a front view structural schematic diagram of the height adjusting mechanism of the utility model when adjusting the height of the lifting rod;

[0020] Figure 5 It is a plan view structural schematic diagram of the step and the fence of the utility model;

[0021] In the drawings:

[0022] 1, support pole, 2, step pole, 3, reinforcing pole, 4, lifting pole, 5, transverse fixing pin hole, 6, pin, 7, step, 8, clamping seat, 9, operating rod, 10, support plate, 11, connecting rod, 12, clamping groove, 13, guardrail, 14, climbing frame, 15, connecting plate, 16, through hole. DETAILED DESCRIPTION

[0023] To clearly illustrate the technical features of the present application, the present application will be described below through specific embodiments.

[0024] As shown in Figures 1-5 the utility model discloses two groups of support frames set up front and back, and each group of support frames includes two vertically arranged and internally hollow support poles 1, a plurality of horizontal step poles 2 are fixed between the two support poles 1, the plurality of step poles 2 are evenly distributed upwards and downwards, and the staff can conveniently climb upwards through the step poles 2. In order to improve the support stability of the support frame, the two support poles 1 on the same side of different groups of support frames are connected with the cross-fixed reinforcing poles 3, so that the support stability is enhanced.

[0025] A lifting pole 4 is inserted into each support pole 1, a plurality of transverse fixing pin holes 5 are arranged on each lifting pole 4, the plurality of transverse fixing pin holes 5 are evenly arranged along the long axis direction of the lifting pole 4, the pin 6 is selected to be inserted into the transverse fixing pin hole 5 to fix the position of the lifting pole 4, the pin 6 is selected to be inserted into the appropriate transverse fixing pin hole 5 according to the construction requirement, and the lifting pole 4 is limited by the two ends of the pin 6 stopping at the top end of the support pole 1. The top end of each lifting pole 4 is vertically fixed with the step 7, the lifting pole 4 is raised to move the step 7 upwards, and the lifting pole 4 is lowered to move the step 7 downwards.

[0026] In order to conveniently adjust the height of the lifting pole 4, one height-adjusting mechanism for adjusting the height of the lifting pole 4 is arranged on one side of each group of support frames, the height-adjusting mechanism includes the clamping seat 8 for supporting the upward movement of the pin 6, the operating rod 9 fixed with the clamping seat 8 for changing the position of the clamping seat 8, and the support plate 10 fixed with the upper end of one support pole 1, the support plate 10 is connected with the clamping seat 8 through the connecting rod 11, one end of the connecting rod 11 is hinged with the clamping seat 8, the other end is hinged with the support plate 10, and the clamping groove 12 for embedding the pin 6 is arranged on the clamping seat 8. The staff changes the position of the clamping seat 8 by holding the operating rod 9 of the height-adjusting mechanism to make the pin 6 enter the clamping groove 12, then presses down the operating rod 9 to make the clamping seat 8 lift the pin 6, so that the lifting pole 4 moves upwards, the staff inserts the standby pin 6 into the appropriate transverse fixing pin hole 5 below, completes the height adjustment of the lifting pole 4, and then takes out the pin 6 above for standby. In the specific operation, two staffs can simultaneously operate two height-adjusting mechanisms to simultaneously raise four lifting poles 4, the height-adjusting mechanism can stably move the step 7 upwards, the operation is simple and easy to implement, and time and labor are saved.

[0027] In order to further improve the safety of construction operation, the guardrail 13 is arranged on the step 7. After the step 7 is lifted, the climbing frame 14 is arranged on the front side of the step 7 for the convenience of the workers to climb to the step 7. The top of the climbing frame 14 is fixed with the step 7 through the connecting plate 15, and the climbing frame 14 moves up and down with the step 7. The climbing frame 14 is arranged on the front side of the support frame and does not interfere with the step rod 2 between the two support rods 1. The through hole 16 is arranged on the guardrail 13 above the climbing frame 14, so that the workers can enter the guardrail 13. When the step 7 is lifted to a certain height, the workers can climb to the step 7 through the cooperation of the step rod 2 and the climbing frame 14.

[0028] In the specific work, the step 7 is first placed at the lowest position, and the workers climb to the step 7 through the step rod 2 to perform the construction. As the construction height is gradually increased, the workers adjust the lifting rods 4 through the height adjusting mechanism to lift the step 7, and the workers climb to the step 7 through the cooperation of the step rod 2 and the climbing frame 14 to perform the construction. After the construction at the high position is completed, the pins 6 on the four lifting rods 4 are removed from the corresponding horizontal fixing pin holes 5, and the lifting rods 4 and the step 7 fall under the dead weight. The lifting rods 4 are all arranged in the support rods 1, and the step 7 is lowered to the lowest position.

[0029] The utility model discloses can according to different construction needs with step 7 moves to the appropriate height, in order to adapt to the construction of different height, and the flexibility is strong, through the height adjusting mechanism can quickly and stably realize the quick adjustment of the height of step 7, save time and effort, greatly improve the work efficiency, and the adjustment mode is stable and reliable, and the operation is simple and easy to operate, and the convenience is strong, and it is easy to popularize and apply.

[0030] Of course, the above description is not limited to the above examples, and the technical features not described in the utility model can be realized by or using the prior art, which will not be repeated here. The above embodiments and drawings are only used to illustrate the technical scheme of the utility model and are not limited to the utility model. The preferred embodiments of the utility model are described in detail, and those skilled in the art should understand that the changes, modifications, additions or replacements made by those skilled in the art within the essential scope of the utility model do not deviate from the purpose of the utility model, and should also belong to the protection scope of the claims of the utility model.

Claims

1. A scaffold for construction work, characterised in that: The support frame comprises two groups of support frames arranged in front and back, each group of support frames comprises two vertically arranged and internally hollow support rods, a plurality of horizontal stepping rods are fixed between the two support rods, a lifting rod is inserted in each support rod, a plurality of transverse fixing pin holes are arranged on each lifting rod, and a pin is selectively inserted into the transverse fixing pin hole to fix the position of the lifting rod; the top end of each lifting rod is vertically fixed with a stepping plate; one height adjusting mechanism for adjusting the height of the lifting rod is arranged on one side of each group of support frames; the height adjusting mechanism comprises a clamping seat for supporting the upward movement of the pin, an operating rod fixed with the clamping seat for changing the position of the clamping seat, and a support plate fixed with the upper end of one support rod, the support plate and the clamping seat are connected through a connecting rod, one end of the connecting rod is hinged with the clamping seat, and the other end is hinged with the support plate, and a clamping groove for embedding the pin is arranged on the clamping seat.

2. The construction scaffold of claim 1, wherein: The plurality of stepping rods are uniformly distributed up and down.

3. The construction scaffold of claim 1, wherein: The two support rods on the same side of the different groups of support frames are connected with cross-fixed reinforcing rods.

4. The construction scaffold of claim 1, wherein: The plurality of transverse fixing pin holes are uniformly arranged along the long axis direction of the lifting rod.

5. The construction scaffold of claim 1, wherein: A guardrail is arranged on the stepping plate.

6. The construction scaffold of claim 5, wherein: A climbing frame is fixed on the front side of the stepping plate, and the top end of the climbing frame is fixed with the stepping plate through a connecting plate.

7. The construction scaffold of claim 6, wherein: A through hole is arranged at the guardrail above the climbing frame.