Building engineering pipeline embedded part

By designing embedded pipe components for building engineering and utilizing components such as base plates, support frames, fixing frames, and flanges, the problems of complex and inefficient pipe installation in existing technologies have been solved, achieving efficient and stable pipe installation and convenient maintenance.

CN223460024UActive Publication Date: 2025-10-21SHANDONG QINGTAI ENG MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423263776.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-30
Publication Date
2025-10-21
Estimated Expiration
2034-12-30

AI Technical Summary

Technical Problem

Existing technologies involve complex pipeline installation processes and low construction efficiency, leading to increased construction difficulty and costs, especially in large-scale construction projects where the construction period is significantly extended.

Method used

An embedded component for building engineering pipes was designed, including components such as a base plate, support frame, fixing frame and flange. Through multi-level and multi-dimensional fixing and support, the installation process is simplified and the stability is improved. The use of flange bolts facilitates disassembly and maintenance.

Benefits of technology

It simplifies the pipeline installation process, improves construction efficiency, enhances the stability of connections, and reduces maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223460024U_ABST
    Figure CN223460024U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pipeline embedding, and discloses a building engineering pipeline embedded part which comprises a bottom plate, a supporting frame is fixedly installed on the top of the bottom plate, a fixing frame is connected to the middle of the supporting frame in a clamped mode, a pipeline chassis is fixedly installed in the middle of the bottom plate, and a connecting pipe is connected to the top of the pipeline chassis in a clamped mode. A flange is fixedly mounted at the top of the connecting pipe. According to the building engineering pipeline embedded part, the bottom plate, the supporting frame, the fixing frame and the flange plate are arranged in a matched mode, when the building engineering pipeline embedded part is used, a pipeline can be more conveniently fixed through the device, multi-layer and multi-dimensional fixing and supporting are achieved through the arrangement of the bottom plate, the supporting frame and the fixing frame, and through the arrangement between the supporting frame and the bottom plate, the pipeline can be more conveniently fixed. And through the design of clamping the through holes of the fixing frame and the supporting frame, the overall stability is greatly enhanced, meanwhile, the installation process is simplified, the construction efficiency is improved, and due to the design of the flange plates and the flange bolts on the flange plates, the pipeline connecting positions are easy and rapid to disassemble and assemble.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to pipeline pre -buried technical field, concretely is a kind of constructional engineering pipeline pre -buried part. BACKGROUND

[0002] In constructional engineering, the installation of pipeline system is a crucial link, which is directly related to the functionality and safety of the building. The traditional pipeline installation method often needs to be laid and fixed after the completion of the main structure of the building, which not only increases the construction difficulty and cost, but also may lead to unstable connection between the pipeline and the building structure, resulting in safety hazards.

[0003] The prior art has the following problems in actual use:

[0004] The prior art has the following problems in actual use: The prior art has the following problems in actual use:

[0005] (I) Technical problem solved

[0006] In order to overcome the above-mentioned defects of the prior art, the utility model provides a constructional engineering pipeline pre -buried part, which solves the problems of the prior art:

[0007] The prior art has the following problems in actual use:

[0008] (II) Technical scheme

[0009] To achieve the above purpose, the utility model is realized by the following technical scheme: a constructional engineering pipeline pre -buried part, comprising a bottom plate, the top of the bottom plate is fixedly installed with a support frame, the middle part of the support frame is connected with a fixed frame, the middle part of the bottom plate is fixedly installed with a pipeline bottom disc, the top of the pipeline bottom disc is connected with a connecting pipe, and the top of the connecting pipe is fixedly installed with a flange plate.

[0010] Further, the two sides of the bottom plate are fixedly connected with limiting blocks, the top of the limiting block is fixedly installed with a hexagonal bolt, the middle part of the bottom plate is provided with a threaded hole, and the bottom of the bottom plate is fixedly installed with a pre -buried fixed rod.

[0011] Furthermore, the bottom of the embedded fixing rod is fixedly connected to the embedded steel bar, and the top of the embedded fixing rod is threadedly connected to the bottom of the base plate.

[0012] Furthermore, a through hole is opened in the middle of the support frame, and a limiting nail is fixedly installed on the bottom of the support frame. The bottom of the support frame is threadedly connected to the threaded hole in the middle of the base plate through the limiting nail.

[0013] Furthermore, a stud is fixedly connected to one side of the fixing frame, a handle is fixedly installed on one side of the fixing frame, and the fixing frame is snap-connected with the through hole of the support frame through the stud.

[0014] Furthermore, the four corners of the pipeline chassis are fixedly connected with cross fixing rods, and the tops of the cross fixing rods are fixedly installed with triangular steel plates.

[0015] Furthermore, a stabilizing plate is clamped in the middle of the connecting pipe, and the bottom of the connecting pipe is clamped to the triangular steel plate of the pipeline chassis.

[0016] Furthermore, a flange bolt is fixedly installed on the top of the flange, and the middle part of the flange is welded to the top of the connecting pipe.

[0017] (3) Beneficial effects

[0018] The utility model provides a pre-embedded part for construction engineering pipelines, which has the following beneficial effects:

[0019] The embedded pipe parts of the construction project can make the device more convenient to fix the pipes when in use through the coordinated arrangement of the base plate, support frame, fixing frame and flange plate. The arrangement of the base plate, support frame and fixing frame realizes multi-level and multi-dimensional fixation and support. The arrangement between the support frame and the base plate, as well as the through-hole card connection design between the fixing frame and the support frame, greatly enhance the overall stability, simplify the installation process and improve construction efficiency. The design of the flange plate and the flange bolts thereon makes the disassembly and assembly of the pipe connection simple and quick, and is convenient for subsequent maintenance and inspection work. This design not only improves work efficiency, but also reduces the cost caused by repair and replacement. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Fig. 1 This is a schematic diagram of the structure of the utility model;

[0021] Fig. 2 This is a schematic diagram of the connecting pipe structure of the utility model;

[0022] Fig. 3 This is a schematic diagram of the bottom plate structure of the utility model;

[0023] Fig. 4 This is a structural diagram of the fixing frame of the utility model.

[0024] In the figure: 1, bottom plate; 2, support frame; 3, fixed frame; 4, pipeline bottom disc; 5, connecting pipe; 6, flange plate; 7, limiting block; 8, hexagonal bolt; 9, threaded hole; 10, pre-buried fixed rod; 11, pre-buried steel bar; 12, penetrating hole; 13, limiting nail; 14, stud; 15, handle; 16, cross fixed rod; 17, triangular steel plate; 18, stabilizing disc; 19, flange bolt. DETAILED DESCRIPTION

[0025] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the utility model.

[0026] Please refer to Figs. 1 to 4 The utility model provides a kind of technical scheme: a kind of building engineering pipeline preformed part, which is mainly applied to the scene of building pipeline preformed.

[0027] Embodiment one:

[0028] In order to make the device more convenient to fix when in use, the device bottom plate 1 and the support frame 2 are provided;

[0029] The support frame 2 is fixedly installed on the top of the bottom plate 1, the limiting blocks 7 are fixedly connected to the two sides of the bottom plate 1, the hexagonal bolts 8 are fixedly installed on the top of the limiting blocks 7, the threaded holes 9 are formed in the middle of the bottom plate 1, the pre-buried fixed rods 10 are fixedly installed on the bottom of the bottom plate 1, the pre-buried steel bars 11 are fixedly connected to the bottom of the pre-buried fixed rods 10, the top of the pre-buried fixed rods 10 is threadedly connected to the bottom of the bottom plate 1, the penetrating holes 12 are formed in the middle of the support frame 2, the limiting nails 13 are fixedly installed on the bottom of the support frame 2, and the bottom of the support frame 2 is threadedly connected to the threaded holes 9 in the middle of the bottom plate 1 through the limiting nails 13, so that the bottom plate 1 is usually made of high-strength steel material, has sufficient load-carrying capacity and stability, the top of the bottom plate 1 is designed with a fixing structure for installing the support frame 2, the middle of the bottom plate 1 is provided with the threaded holes 9 for cooperating with the installation of the limiting nails 13 and the pre-buried fixed rods 10, the support frame 2 is connected to the top of the bottom plate 1 to provide additional support and stability, the penetrating holes 12 are formed in the middle of the support frame 2 for clamping with the studs 14 of the fixed frame 3, and the bottom of the support frame 2 is threadedly connected to the threaded holes 9 of the bottom plate 1 through the limiting nails 13 to ensure the stability of the structure, the pre-buried steel bars 11 are fixedly connected to the bottom of the pre-buried fixed rods 10, and the top of the pre-buried fixed rods 10 is threadedly connected to the bottom of the bottom plate 1 to firmly fix the preformed part in the concrete structure;

[0030] Embodiment two:

[0031] In order to make the device more convenient to reinforce the pipeline in use, the device fixing frame 3 and the pipeline bottom plate 4 are arranged;

[0032] The middle part of the support frame 2 is clamped with the fixing frame 3, the middle part of the bottom plate 1 is fixedly installed with the pipeline bottom plate 4, one side of the fixing frame 3 is fixedly connected with the stud 14, one side of the fixing frame 3 is fixedly installed with the handle 15, the fixing frame 3 is clamped with the penetrating hole 12 of the support frame 2 through the stud 14, the four corners of the pipeline bottom plate 4 are fixedly connected with the cross fixing rod 16, and the top of the cross fixing rod 16 is fixedly installed with the triangular steel plate 17, so that the fixing frame 3 is clamped in the middle part of the support frame 2, and the further fixing of the connecting pipe 5 is realized through the cooperation of the stud 14 and the penetrating hole 12, and the handle 15 is further fixedly installed on one side, so that the operation in the installation and dismounting process is facilitated, the pipeline bottom plate 4 is fixedly installed in the middle part of the bottom plate 1 and is used for bearing and fixing the connecting pipe 5, and the top is designed with a clamping structure and cooperates with the bottom of the connecting pipe 5, so that the stable installation of the connecting pipe 5 is ensured;

[0033] Example three:

[0034] In order to make the device more convenient to connect in use, the device connecting pipe 5 and the flange plate 6 are arranged.

[0035] The top of the connecting pipe 5 is fixedly installed with the flange plate 6, the middle part of the connecting pipe 5 is clamped with the stabilizing disc 18, the bottom of the connecting pipe 5 is clamped with the triangular steel plate 17 of the pipeline bottom plate 4, the top of the flange plate 6 is fixedly installed with the flange bolt 19, and the middle part of the flange plate 6 is welded with the top of the connecting pipe 5, so that the connecting pipe 5 is part of the pipeline system, the top of the connecting pipe 5 is fixedly installed with the flange plate 6, the bottom is clamped with the pipeline bottom plate 4, the middle part of the connecting pipe 5 is further clamped with the stabilizing disc 18, so as to enhance the stability, the flange plate 6 is welded on the top of the connecting pipe 5 and is used for being connected with the flanges of other pipelines or equipment, and the flange bolt 19 is fixedly installed on the flange plate 6, so as to facilitate dismounting and maintenance.

[0036] The electrical elements appearing in the text are all connected with the main controller and 220V mains electricity, and the main controller can be a conventional known device such as a computer.

[0037] In the utility model, the working steps of the device are as follows:

[0038] First, the embedded fixed rod 10 and embedded steel bar 11 are fixed in the concrete structure according to the design requirements, then the bottom plate 1 is placed on the embedded fixed rod 10 and fixed through threaded connection, then the limiting block 7 is fixed on both sides of the bottom plate 1 by using hexagonal bolts 8 to ensure the position stability of the embedded part in the concrete structure, then the support frame 2 is placed on the top of the bottom plate 1 and is screwed with the threaded hole 9 of the bottom plate 1 through the limiting nails 13, then the fixed frame 3 is clamped with the penetrating hole 12 of the support frame 2 through the stud 14 and is fastened by using appropriate tools, the bottom of the connecting pipe 5 is matched with the clamping structure of the pipe base 4 to ensure its stable installation, then the middle part of the connecting pipe 5 is clamped with the stabilizing disc 18 to enhance its stability, finally, the flange plate 6 is welded on the top of the connecting pipe 5 and the flange bolt 19 is installed to connect with other pipes or equipment, finally, after the installation is completed, the embedded part is comprehensively checked to ensure that each part is firmly and stably connected, then necessary debugging work is carried out to ensure that the embedded part can meet the design requirements and use requirements.

[0039] Although the embodiments of the utility model have been shown and described, it can be understood by those skilled in the art that various changes, modifications, replacements and variations can be made to these embodiments without departing from the principles and spirits of the utility model, the scope of the utility model is defined by the appended claims and their equivalents.

Claims

1. A construction engineering pipe pre-embedded part, comprising a base plate (1), characterized in that: The top of the bottom plate (1) is fixedly installed with a support frame (2), the middle part of the support frame (2) is clamped with a fixing frame (3), the middle part of the bottom plate (1) is fixedly installed with a pipeline bottom disc (4), the top of the pipeline bottom disc (4) is clamped with a connecting pipe (5), and the top of the connecting pipe (5) is fixedly installed with a flange plate (6).

2. A construction engineering pipe pre-embedded component according to claim 1, characterized in that: Both sides of the bottom plate (1) are fixedly connected with limiting blocks (7), the top of the limiting block (7) is fixedly installed with a hexagonal bolt (8), the middle part of the bottom plate (1) is provided with a threaded hole (9), and the bottom of the bottom plate (1) is fixedly installed with a pre-buried fixing rod (10).

3. A construction engineering pipe pre-embedded component according to claim 2, characterized in that: The bottom of the pre-buried fixing rod (10) is fixedly connected with a pre-buried steel bar (11), and the top of the pre-buried fixing rod (10) is threadedly connected with the bottom of the bottom plate (1).

4. A construction engineering pipe pre-embedded component according to claim 2, characterized in that: The middle part of the support frame (2) is provided with a penetrating hole (12), the bottom of the support frame (2) is fixedly installed with a limiting nail (13), and the bottom of the support frame (2) is threadedly connected with the threaded hole (9) in the middle part of the bottom plate (1) through the limiting nail (13).

5. A construction engineering pipe pre-embedded component according to claim 4, characterized in that: One side of the fixing frame (3) is fixedly connected with a stud (14), one side of the fixing frame (3) is fixedly installed with a handle (15), and the fixing frame (3) is clamped with the penetrating hole (12) of the support frame (2) through the stud (14).

6. A construction engineering pipe pre-embedded component according to claim 1, characterized in that: The four corners of the pipeline bottom disc (4) are fixedly connected with cross fixed rods (16), and the top of the cross fixed rod (16) is fixedly installed with a triangular steel plate (17).

7. A construction engineering pipe pre-embedded component according to claim 6, characterized in that: The middle part of the connecting pipe (5) is clamped with a stabilizing disc (18), and the bottom of the connecting pipe (5) is clamped with the triangular steel plate (17) of the pipeline bottom disc (4).

8. A construction engineering pipe pre-embedded component according to claim 1, characterized in that: The top of the flange plate (6) is fixedly installed with a flange bolt (19), and the middle part of the flange plate (6) is welded with the top of the connecting pipe (5).