Bridge construction hanging basket convenient to disassemble and assemble
By fixing the columns and guard plates on the bottom plate of the bridge construction hanging basket and setting up a second-layer auxiliary frame, the problems of high construction risks and difficulty in approaching high-altitude construction were solved, and safety and construction scope were improved.
Patent Information
- Application Number
- CN202422950466.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-02
- Publication Date
- 2025-10-28
- Estimated Expiration
- 2034-12-02
AI Technical Summary
Existing bridge construction hanging baskets lack protective structures, resulting in high construction risks and difficulty in carrying out construction near the heights of the bridge.
Four columns are fixed on the bottom plate of the hanging basket, and the guard plate is connected by screws, and a protective net is added. Two-layer auxiliary frames and ladders are set on both sides of the bottom plate to facilitate workers to work at height.
It improves construction safety, reduces construction risks, expands the construction scope, and reduces construction difficulty.
Smart Images

Figure CN223481671U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of bridge construction suspended platform technology, and in particular to a bridge construction suspended platform that is easy to assemble and disassemble. Background Technology
[0002] A search revealed a patent (application number: 201920666061.X) disclosing "a bridge bracket maintenance basket that is easy to disassemble and assemble." The device, with its combination of pipe grooves, threaded blocks, connecting grooves, limiting grooves, and bolts, facilitates the disassembly and transportation of the T-shaped support column, concave limiting frame, support pipe, side plate, protective plate, limiting frame, and framed wire mesh. It can be quickly assembled when needed, making it highly practical. However, the following problems exist during the use of this device:
[0003] First, the bridge construction scaffold mainly relies on a limiting frame for support. Workers operate by standing on the limiting frame. However, bridge construction is a dangerous operation, and the limiting frame has no protective structure at the top, posing a significant risk during construction. In addition, the bottom of the bridge has a certain curvature, especially towards the middle where it is lower and towards the sides where it is higher. The bridge construction scaffold in the aforementioned document uses a flat structure, making it difficult for workers to approach the higher positions for construction, thus increasing the difficulty of the construction. Utility Model Content
[0004] In view of the shortcomings of the existing technology, this utility model provides a bridge construction scaffold that is easy to assemble and disassemble, which overcomes the shortcomings of the existing technology and effectively solves the problems of construction risks and high construction difficulty.
[0005] To achieve the above objectives, the present invention adopts the following technical solution:
[0006] A bridge construction scaffold that is easy to assemble and disassemble includes a base plate. Symmetrically distributed columns are fixedly connected to the top outer wall of the base plate. A front guard plate is fixedly connected between two front columns by screws. A rear guard plate is fixedly connected between two rear columns by screws. A left guard plate is fixedly connected between two left columns by screws. A right guard plate is fixedly connected between two right columns by screws. Protective netting is fixedly installed on the inner walls of the front, rear, left, and right guard plates.
[0007] Two auxiliary frames are fixedly connected to both ends of the top outer wall of the base plate, and a ladder plate is welded to the bottom of one side of the outer wall of the two auxiliary frames. The inclined surface of the ladder plate is welded with equally spaced ladder platforms.
[0008] Preferably, the inner walls of the second-layer auxiliary frame are welded with vertical bars that are evenly distributed.
[0009] Preferably, reinforcing rods are welded at equal intervals between the upper and lower inner walls of the front and rear guard plates.
[0010] Preferably, the second-layer auxiliary frame is provided with a second-layer construction chamber.
[0011] Preferably, the second-layer auxiliary frame is provided with construction openings on three external sides of the second-layer construction chamber.
[0012] Preferably, support seats are welded at the corners of the outer perimeter of the bottom wall of the base plate.
[0013] Preferably, a lifting ring is welded to the top outer wall of the base plate, and the inner wall of the lifting ring has a steel wire rope with a hook.
[0014] The beneficial effects of this utility model are as follows:
[0015] 1. The bridge construction scaffold designed in this way is easy to assemble and disassemble. Four columns are fixed on the base plate, and four protective plates are added on the base of the columns. The protective plates are fixed to the columns with screws, which makes disassembly and assembly convenient. In addition, each protective plate is equipped with a protective net, which can increase the safety of the construction scaffold on all four sides and reduce the risk factor of construction.
[0016] 2. The bridge construction scaffold designed in this way is easy to assemble and disassemble. The bottom plate serves as a first-level construction platform. On this basis, two second-level construction platforms are added on both sides of the bottom plate. Workers can move to the second-level auxiliary frame through ladders and platforms, and use the second-level construction chamber and construction opening to carry out high-altitude operations, which expands the construction scope and reduces the difficulty of bridge construction. Attached Figure Description
[0017] Figure 1 This is a schematic diagram of the overall structure of a bridge construction scaffold that is easy to assemble and disassemble, as proposed in this utility model.
[0018] Figure 2 This utility model presents a schematic diagram showing the disassembled structure of the front guard plate, rear guard plate, left guard plate, and right guard plate of a bridge construction scaffold that is easy to assemble and disassemble.
[0019] Figure 3 This is a schematic diagram of a two-layer auxiliary frame structure for a bridge construction scaffold that is easy to assemble and disassemble, as proposed in this utility model.
[0020] In the diagram: 1. Base plate; 2. Column; 3. Front guard plate; 4. Rear guard plate; 5. Left guard plate; 6. Right guard plate; 7. Protective net; 8. Second-floor auxiliary frame; 9. Ladder; 10. Ladder platform; 11. Vertical bar; 12. Reinforcing bar; 13. Second-floor construction compartment; 14. Construction opening; 15. Support base; 16. Lifting ring; 17. Steel wire rope. Detailed Implementation
[0021] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments.
[0022] Example 1, refer to Figure 1-2 A bridge construction scaffold that is easy to assemble and disassemble includes a base plate 1. Symmetrically distributed columns 2 are fixedly connected to the top outer wall of the base plate 1. A front guard plate 3 is fixedly connected between the two front columns 2 by screws. A rear guard plate 4 is fixedly connected between the two rear columns 2 by screws. A left guard plate 5 is fixedly connected between the two left columns 2 by screws. A right guard plate 6 is fixedly connected between the two right columns 2 by screws. Protective nets 7 are fixedly installed on the inner walls of the front guard plate 3, rear guard plate 4, left guard plate 5 and right guard plate 6.
[0023] In this embodiment, four columns 2 are fixed on the base plate 1, and four protective plates are added based on the columns 2. The protective plates are fixed to the columns 2 with screws, which makes disassembly and assembly convenient. In addition, each protective plate is equipped with a protective net 7 inside, which can increase the safety of the construction scaffold on all four sides and reduce the risk factor of construction.
[0024] Example 2, refer to Figure 3 A bridge construction scaffold that is easy to assemble and disassemble has two layers of auxiliary frames 8 fixedly connected to both ends of the top outer wall of the base plate 1, and a ladder plate 9 is welded to the bottom of one side of the outer wall of the two layers of auxiliary frames 8. The inclined surface of the ladder plate 9 is welded with ladder platforms 10 distributed at equal intervals.
[0025] In this embodiment, the base plate 1 serves as a first-level construction platform. On this basis, two second-level construction platforms are added on both sides of the base plate 1. Workers can move to the second-level auxiliary frame 8 through the ladder 9 and ladder platform 10, and use the second-level construction chamber 13 and construction opening 14 to carry out high-altitude operations, thereby expanding the scope of construction and reducing the difficulty of bridge construction.
[0026] Reference Figure 3 The inner walls of the second-layer auxiliary frame 8 are all welded with vertical rods 11 that are evenly distributed.
[0027] Reference Figure 1-2 Reinforcing rods 12, which are evenly distributed, are welded between the upper and lower inner walls of the front guard plate 3 and the rear guard plate 4.
[0028] Reference Figure 3 The second-layer auxiliary frame 8 has a second-layer construction chamber 13 inside.
[0029] Reference Figure 3 The second-layer auxiliary frame 8 is located on the three external sides of the second-layer construction chamber 13, and construction openings 14 are provided.
[0030] Reference Figure 1Support seats 15 are welded to the corners of the outer wall at the bottom of the base plate 1.
[0031] Reference Figure 1 The top outer wall of the base plate 1 is welded with a lifting ring 16, and the inner wall of the lifting ring 16 is equipped with a steel wire rope 17 with a hook.
[0032] Working principle: Four columns 2 are fixed on the base plate 1. Based on the columns 2, four protective plates are added. The front protective plate 3, rear protective plate 4, left protective plate 5 and right protective plate 6 are all fixed to the columns 2 with screws, which is convenient for disassembly and assembly. In addition, each protective plate is equipped with a protective net 7 to improve the safety of construction. On this basis, workers can move to the second-level auxiliary frame 8 through the ladder 9 and ladder platform 10, and use the second-level construction chamber 13 and construction opening 14 to carry out high-altitude operations.
[0033] The above description is only a preferred embodiment of the present utility model, but the protection scope of the present utility model is not limited thereto. Any equivalent substitutions or changes made by those skilled in the art within the technical scope disclosed in the present utility model, based on the technical solution and the inventive concept of the present utility model, should be included within the protection scope of the present utility model.
Claims
1. A bridge construction scaffold that is easy to assemble and disassemble, comprising a base plate (1), characterized in that, The top outer wall of the base plate (1) is fixedly connected with symmetrically distributed columns (2), and the two front columns (2) are fixedly connected with a front guard plate (3) by screws, the two rear columns (2) are fixedly connected with a rear guard plate (4) by screws, the two left columns (2) are fixedly connected with a left guard plate (5) by screws, and the two right columns (2) are fixedly connected with a right guard plate (6) by screws. The inner walls of the front guard plate (3), rear guard plate (4), left guard plate (5) and right guard plate (6) are all fixedly installed with protective nets (7). The bottom plate (1) has two auxiliary frames (8) fixedly connected to both ends of the top outer wall, and a ladder plate (9) is welded to the bottom of one side of the auxiliary frame (8). The inclined surface of the ladder plate (9) is welded with ladder platforms (10) distributed at equal intervals.
2. The bridge construction scaffolding that is easy to assemble and disassemble according to claim 1, characterized in that, The inner walls of the second-layer auxiliary frame (8) are all welded with vertical rods (11) that are evenly distributed.
3. The bridge construction scaffolding that is easy to assemble and disassemble according to claim 1, characterized in that, The upper and lower inner walls of the front guard plate (3) and the rear guard plate (4) are welded with reinforcing rods (12) that are evenly distributed.
4. The bridge construction scaffolding that is easy to assemble and disassemble according to claim 1, characterized in that, The second-layer auxiliary frame (8) has a second-layer construction chamber (13) inside.
5. A bridge construction scaffold that is easy to assemble and disassemble according to claim 1, characterized in that, The second-layer auxiliary frame (8) is located on the three external sides of the second-layer construction chamber (13) and has construction openings (14).
6. A bridge construction scaffold that is easy to assemble and disassemble according to claim 1, characterized in that, Support seats (15) are welded to the corners of the outer wall of the bottom of the base plate (1).
7. A bridge construction scaffold that is easy to assemble and disassemble according to claim 1, characterized in that, The bottom plate (1) has a lifting ring (16) welded to the top outer wall, and the inner wall of the lifting ring (16) has a steel wire rope (17) with a hook.
Citation Information
Patent Citations
Bridge bracket overhauling hanging basket convenient to disassemble and assemble
CN209891095U