Strip-shaped centering positioner for PHC (prestressed high-strength concrete) pipe pile

The combined structure of bosses, positioning steel pipes and binding belts solves the problem of PHC piles being difficult to maintain verticality in the drilled hole, ensures pile quality, improves construction efficiency and simplifies the installation process.

CN223482608UActive Publication Date: 2025-10-28CONSTR DEV OF CHINA CONSTR SIXTH ENG DIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422791271.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-15
Publication Date
2025-10-28
Estimated Expiration
2034-11-15

AI Technical Summary

Technical Problem

In traditional PHC pipe pile construction, it is difficult to maintain verticality in the drilled hole, resulting in uneven stress on the pile body and affecting the quality of the load-bearing structure. In addition, the existing positioner structure is complex, affecting construction efficiency.

Method used

The combined structure of bosses, positioning steel pipes and binding belts is adopted. The positioning steel pipes are fixed between the bosses by binding belts to ensure that the pile remains centered and vertical in the drilled hole. The fixing method including nylon rope or nylon belt simplifies the installation process.

Benefits of technology

The verticality requirement of the PHC pipe pile in the drilled hole is achieved, ensuring the quality of the pile body. At the same time, it has a simple structure, is easy to install, saves labor costs, and improves lifting efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223482608U_ABST
    Figure CN223482608U_ABST
Patent Text Reader

Abstract

The utility model relates to a belt-shaped centering positioner for a PHC (prestressed high-strength concrete) pipe pile, which comprises a plurality of pairs of circular bosses, a plurality of positioning blocks, a plurality of positioning blocks and a plurality of positioning blocks, and is characterized in that the bosses are preset on the outer wall of the pipe pile from top to bottom; the plurality of positioning steel pipes are circumferentially and uniformly inserted between the opposite surfaces of each pair of bosses; the plurality of positioning steel pipes are connected in series and fixed through the binding belt, and the two ends of the binding belt are bound and fixed. The positioning device can effectively solve the problem that the PHC pipe pile is easy to incline in a drill hole or the perpendicularity of the PHC pipe pile cannot meet the requirement during post-insertion type construction of the PHC pipe pile, is simple in structure, can be operated by only one person in the installation process, saves labor cost, is simple to operate, is convenient to construct, saves time and labor, and improves the hoisting efficiency of the PHC pipe pile.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of pipe pile construction technology, and in particular to a PHC pipe pile strip centering positioner. Background Technology

[0002] Traditional PHC pipe pile installation methods involve using steel wire ropes or slings to hoist the PHC pipe piles into the borehole. When the PHC pipe pile is inserted, the verticality is adjusted and controlled by a pile driver or a theodolite to ensure it meets the required verticality. However, once the PHC pipe pile is fully inserted, its verticality cannot be adjusted, easily leading to tilting or toppling within the borehole. This results in uneven distribution of the protective layer thickness, severely affecting the pile's load-bearing capacity. Especially when the PHC pipe pile is used as a vertically load-bearing component, insufficient verticality can easily compromise the quality of the load-bearing structure.

[0003] Currently, centering positioners are generally used to keep the pipe piles centered and vertical during drilling. However, most positioners have a complex structure and are difficult to install, which affects construction efficiency. Summary of the Invention

[0004] This utility model aims to address the shortcomings of existing technologies by providing a PHC pipe pile strip centering positioner.

[0005] To achieve the above objectives, this utility model adopts the following technical solution:

[0006] A PHC pipe pile strip centering positioner includes:

[0007] A series of protrusions are pre-installed on the outer wall of the pipe pile from top to bottom, and the protrusions are in the shape of a ring.

[0008] Positioning steel pipes are evenly distributed around the circumference of each pair of bosses and inserted between their opposite faces.

[0009] The binding straps are used to fix several positioning steel pipes in series, and the two ends of the binding straps are tied together.

[0010] Specifically, the boss is a concrete boss.

[0011] Specifically, the protrusion is a circular steel plate pre-embedded on the outer wall of the pipe pile.

[0012] Specifically, the binding strap is made of nylon rope, and there are through holes in the middle of both sides of the positioning steel pipe. The nylon rope passes through the through holes and is fixed to the positioning steel pipe by knotting. The two ends of the nylon rope are also knotted for fixation.

[0013] Specifically, the binding strap is made of nylon. The outer wall of the positioning steel pipe has a groove in the middle. The nylon strap is bonded and fixed to the groove. One end of the nylon strap has a buckle, and both ends of the nylon strap are fixed by the buckle.

[0014] Specifically, the bottom of the positioning steel pipe is tilted away from the side of the pipe pile.

[0015] The beneficial effects of this utility model are as follows: By setting up a boss, positioning steel pipe, and binding strap, this utility model can effectively keep the PHC pipe pile in a centered and vertical state in the borehole, ensuring that the verticality of the PHC pipe pile in the borehole meets the requirements, ensuring that the PHC pipe pile is subjected to vertical force, and guaranteeing the quality of the pile body; at the same time, the locator has a simple structure, and the installation process only requires one person to operate, saving labor costs. It is easy to operate, convenient to construct, saves time and effort, and improves the hoisting efficiency of PHC pipe piles. Attached Figure Description

[0016] Figure 1 It is a structural diagram of the utility model;

[0017] Figure 2 for Figure 1 Sectional view of AA;

[0018] Figure 3 for Figure 1 Top view of the structure shown;

[0019] Figure 4 This is a schematic diagram showing the connection between the nylon rope and the positioning steel pipe of this utility model;

[0020] Figure 5 This is a schematic diagram showing the connection between the nylon strap and the positioning steel pipe of this utility model;

[0021] Figure 6 This is a schematic diagram of the positioning steel pipe structure of this utility model;

[0022] In the diagram: 1-Pipe pile; 2-Lead; 3-Positioning steel pipe; 4-Nylon rope; 5-Perforation; 6-Nylon strap; 7-Groove; 8-Belt buckle;

[0023] The following will describe in detail the embodiments of this utility model with reference to the accompanying drawings. Detailed Implementation

[0024] The present invention will be further described below with reference to the accompanying drawings and embodiments:

[0025] Example 1

[0026] like Figures 1-4 , Figure 6 As shown, a PHC pipe pile strip centering positioner includes:

[0027] A number of protrusions 2 are pre-installed on the outer wall of the pipe pile 1 from top to bottom. The protrusions 2 are circular and are made of concrete. The protrusions 2 provide installation space for the locator and can limit the positioning steel pipe 3. The positioning steel pipe 3 is easy to install.

[0028] Positioning steel pipes 3 are evenly distributed around the circumference of each pair of bosses 2 and inserted between their opposite faces. The bottom of the positioning steel pipes 3 is inclined on the side away from the pipe pile 1, and the corners at the intersection of the inclined surfaces are rounded to facilitate lowering into the borehole.

[0029] The binding straps are used to fix several positioning steel pipes 3 in series, and the two ends of the binding straps are tied and fixed. The binding straps are nylon ropes 4. There are through holes 5 in the middle of both sides of the positioning steel pipes 3. The nylon ropes 4 pass through the through holes 5 and are fixed by knotting. The two ends of the nylon ropes 4 are tied and fixed.

[0030] When this utility model is in operation, a suitable positioning steel pipe 3 is selected according to the borehole diameter. A through hole 5 is processed in the positioning steel pipe 3. Then, a nylon rope 4 is passed through the positioning steel pipe 3, and knots are tied on both sides of the positioning steel pipe 3 to fix the positioning steel pipe 3. Then, the series-connected positioning steel pipes 3 are inserted between a pair of bosses 2. After wrapping around once, the two ends of the nylon rope 4 are tightly tied and fixed. At this time, the centering positioner is installed. When the pipe pile 1 is lowered into the borehole, the positioning steel pipe 3 is in close contact with the inner wall of the borehole to ensure that the pipe pile 1 is centered and lowered vertically.

[0031] Example 2

[0032] like Figure 1 , Figure 5 , Figure 6 As shown, a PHC pipe pile strip centering positioner includes:

[0033] Boss 2, several pairs of bosses 2 are pre-installed on the outer wall of the pipe pile 1 from top to bottom. The bosses 2 are circular and are circular steel plates pre-embedded on the outer wall of the pipe pile 1. The setting of bosses 2 provides installation space for the positioner, which can limit the positioning steel pipe 3. The positioning steel pipe 3 is easy to install.

[0034] Positioning steel pipes 3 are evenly distributed around the circumference of each pair of bosses 2 and inserted between their opposite faces. The bottom of the positioning steel pipes 3 is inclined on the side away from the pipe pile 1, and the corners at the intersection of the inclined surfaces are rounded to facilitate lowering into the borehole.

[0035] A binding strap is used to fix several positioning steel pipes 3 in series, and the two ends of the binding strap are also fixed. The binding strap is a nylon strap 6. The outer wall of the positioning steel pipe 3 has a groove 7 in the middle. The nylon strap 6 is bonded and fixed to the groove 7. One end of the nylon strap 6 has a belt buckle 8. The two ends of the nylon strap 6 are fixed by the belt buckle 8.

[0036] When this utility model is in operation, a suitable positioning steel pipe 3 is selected according to the borehole diameter, and a groove 7 is processed on the positioning steel pipe 3. Then, a nylon strap 6 is bonded to the groove 7 of several positioning steel pipes 3. Then, the series-connected positioning steel pipes 3 are inserted between a pair of bosses 2. After wrapping around once, one end of the nylon strap 6 is passed through the belt buckle 8 and tightly fastened and fixed. At this time, the centering positioner is installed. When the pipe pile 1 is lowered into the borehole, the positioning steel pipe 3 is in close contact with the inner wall of the borehole to ensure that the pipe pile 1 is centered and lowered vertically.

[0037] This invention effectively keeps PHC pipe piles centered and vertical in the borehole, ensuring that the verticality of the PHC pipe piles meets the requirements, guaranteeing the vertical force on the PHC pipe piles, and ensuring the quality of the pile body. At the same time, the locator has a simple structure, and the installation process only requires one person to operate, saving labor costs. It is easy to operate, convenient to construct, saves time and effort, and improves the hoisting efficiency of PHC pipe piles.

[0038] In the description of this utility model, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this utility model and simplifying the description, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model.

[0039] In this utility model, unless otherwise specified or limited, the terms "installed," "connected," "connect," "fixed," etc. should be understood in a broad sense. For example, they can refer to fixed connection, detachable connection, or integration; mechanical connection, electrical connection, or communication; direct connection or indirect connection through an intermediate medium; internal communication between two elements or interaction between two elements, unless otherwise specified. For those skilled in the art, the specific meanings of the above terms in this utility model can be understood according to specific circumstances.

[0040] The present invention has been described above with reference to the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-described manner. Any improvements made using the inventive concept and technical solution of the present invention, or direct application to other situations without modification, are all within the protection scope of the present invention.

Claims

1. A PHC pipe pile strip centering positioner, characterized in that it includes: A protrusion (2), several pairs of protrusions (2) are pre-installed on the outer wall of the pipe pile (1) from top to bottom, and the protrusions (2) are in the shape of a ring; Positioning steel pipes (3) are evenly distributed around the circumference of each pair of bosses (2) between their opposite faces; The binding straps and several positioning steel pipes (3) are connected in series and fixed by binding straps, and the two ends of the binding straps are tied and fixed.

2. The PHC pipe pile strip centering positioner according to claim 1, characterized in that, The boss (2) is a concrete boss.

3. The PHC pipe pile strip centering positioner according to claim 1, characterized in that, The boss (2) is a circular steel plate pre-embedded on the outer wall of the pipe pile (1).

4. A PHC pipe pile strip centering locator according to claim 1, characterized in that, The binding strap is a nylon rope (4). The positioning steel pipe (3) has through holes (5) in the middle of both sides. The nylon rope (4) passes through the through holes (5) and is fixed to the positioning steel pipe (3) by knotting. The two ends of the nylon rope (4) are knotted and fixed.

5. A PHC pipe pile strip centering locator according to claim 1, characterized in that, The binding strap is a nylon strap (6). The outer wall of the positioning steel pipe (3) has a groove (7) in the middle. The nylon strap (6) is bonded and fixed on the groove (7). One end of the nylon strap (6) is provided with a belt buckle (8). Both ends of the nylon strap (6) are fixed by the belt buckle (8).

6. A PHC pipe pile strip centering locator according to claim 1, characterized in that, The bottom of the positioning steel pipe (3) is inclined away from the side of the pipe pile (1).