Climbing frame wall-attached supporting column for protruding part of outer wall of building

By installing anchor columns and support frames through pre-drilled holes in the exterior wall, the difficulty of installing climbing scaffolds on protruding parts of the exterior wall of high-rise buildings was solved, achieving faster construction progress, improved quality, and enhanced safety.

CN223510594UActive Publication Date: 2025-11-04SHANXI WUJIAN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423063041.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-12
Publication Date
2025-11-04
Estimated Expiration
2034-12-12

AI Technical Summary

Technical Problem

The installation of climbing scaffolds on protruding parts of the exterior walls of high-rise buildings is difficult, resulting in slow construction progress, high costs, and poor safety.

Method used

Anchor supports are installed by pre-drilling holes in the exterior wall. The support frame is fixed by connecting bolts and channel steel anchor plates. The anchor supports pass through the pre-drilled slots and connect to the climbing frame guide rail. The support frame is connected to the exterior wall to achieve stable wall attachment.

Benefits of technology

Accelerate construction progress, reduce secondary construction, improve construction quality and safety, reduce costs, and ensure the integrity of the design and main structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223510594U_ABST
    Figure CN223510594U_ABST
Patent Text Reader

Abstract

The utility model discloses a climbing frame wall-attached supporting column for a protruding part of a building outer wall, which belongs to the technical field of climbing frame wall-attached supporting columns and comprises a top plate, a preformed hole, a connecting bolt, an anchoring supporting column, a connecting nut, a channel steel anchor plate, an anchoring bolt, an anchoring nut, the outer wall, a preformed groove, a fixing machine base, a climbing frame guide rail and a supporting frame. According to the utility model, a method of fixing the support frame installed outside the wall through the preformed hole in the wall is adopted, so that the construction progress is accelerated, the secondary construction is reduced, the construction quality of the modeling concrete is improved, the molding effect is ensured, and the modeling and the main body structure form a whole. And meanwhile, the climbing frame installation of the outer wall with a bay window and a bulge is solved, the secondary construction of the outer wall modeling is reduced, the construction progress is accelerated, the construction safety is ensured, and the purposes of high construction efficiency and cost saving are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of climbing scaffold wall-mounted support technology, specifically a climbing scaffold wall-mounted support for a protruding part of a building's exterior wall. Background Technology

[0002] In recent years, there has been a significant increase in high-rise buildings, and the exterior wall designs of these buildings have also become more diverse in order to enhance their aesthetics. However, using climbing scaffolding for safety protection presents numerous challenges. The protruding exterior wall designs necessitate either moving the entire climbing scaffolding outwards during installation, resulting in a greater distance from the wall, or dismantling the design and requiring secondary construction. Summary of the Invention

[0003] The purpose of this utility model is to solve the problems mentioned in the background art by providing a climbing frame wall-mounted support for the protruding part of the building exterior wall.

[0004] This utility model is achieved through the following technical solution:

[0005] A climbing scaffold wall-mounted support for a protruding part of a building's exterior wall includes a top plate, pre-drilled holes, connecting bolts, anchoring supports, connecting nuts, channel steel anchor plates, anchoring bolts, anchoring nuts, an exterior wall, a pre-drilled groove, a fixed base, a climbing scaffold guide rail, and a support frame. The top plate has pre-drilled holes. The connecting bolts pass through two anchoring supports and engage with the connecting nuts. The anchoring supports are attached to the top plate. The channel steel anchor plates are located above the two anchoring supports. The anchoring bolts pass through the channel steel anchor plates and the pre-drilled holes and engage with the anchoring nuts. The exterior wall has pre-drilled grooves. The ends of the anchoring supports pass through the pre-drilled grooves and are fixedly connected to the fixed base. The climbing scaffold guide rail is installed on the fixed base. The support frame is located between the anchoring supports and the exterior wall, with one end bolted to the anchoring supports and the other end bolted to the exterior wall.

[0006] Furthermore, the anchoring support and channel steel anchor plate are made of No. 8 channel steel, and the length of the part of the anchoring support that is in contact with the top plate is not less than 1.5 meters.

[0007] Furthermore, the support surface dimension of the support frame is not less than the cross-sectional dimension between the two anchored supports.

[0008] Furthermore, the support frame is in the shape of a right triangle, and there are no fewer than two bolts connecting the right-angled sides of the support frame to the anchor column and the outer wall, respectively.

[0009] Furthermore, the distance between the climbing frame guide rail and the protruding shape on the outer wall is 300mm.

[0010] The climbing scaffold wall-mounted support column for protruding parts of building exterior walls provided by this utility model has the following beneficial effects:

[0011] This device, through its structural design, addresses situations where fixed wall supports cannot be secured to exterior walls with decorative features, such as bay windows or openings in the exterior wall. Instead, it utilizes pre-drilled holes in the top plate at these locations to install anchor supports. The anchor supports extend through pre-drilled grooves in the exterior wall and connect to the climbing scaffold guide rail. The extension length of the anchor supports directly affects the distance between the climbing scaffold guide rail and the exterior wall. The anchor supports extending beyond the exterior wall must be connected to the support frame. The height of the pre-drilled groove in the exterior wall is the height of the anchor supports.

[0012] Compared with existing technologies, this utility model adopts a method of fixing the external support frame to the wall through pre-drilled holes inside the wall, which speeds up the construction progress, reduces secondary construction, improves the construction quality of the shaped concrete, ensures the forming effect, and makes the shape and the main structure form an integral whole. It solves the problem of climbing frame installation on exterior walls with bay windows and protrusions, reduces secondary construction of exterior wall shapes, speeds up the construction progress, ensures construction safety, and achieves the goals of high construction efficiency and cost savings. Attached Figure Description

[0013] Figure 1 This is a schematic diagram of the structure of this utility model.

[0014] Figure 2 This is a schematic diagram of the planar structure of the anchor support column in this utility model.

[0015] In the diagram: 1. Top plate; 2. Reserved hole; 3. Connecting bolt; 4. Anchor support; 5. Connecting nut; 6. Channel steel anchor plate; 7. Anchor bolt; 8. Anchor nut; 9. Exterior wall; 10. Reserved groove; 11. Fixed base; 12. Climbing frame guide rail; 13. Support frame. Detailed Implementation

[0016] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0017] Please see Figure 1-2 This embodiment provides a climbing scaffold wall-mounted support column for a protruding part of a building's exterior wall, including a top plate 1, a reserved hole 2, a connecting bolt 3, an anchor column 4, a connecting nut 5, a channel steel anchor plate 6, an anchor bolt 7, an anchor nut 8, an exterior wall 9, a reserved groove 10, a fixed base 11, a climbing scaffold guide rail 12, and a support frame 13.

[0018] A pre-drilled hole 2 is provided on the top plate 1. A connecting bolt 3 passes through two anchor pillars 4 and engages with a connecting nut 5. The two anchor pillars 4 are attached to the top plate 1. A channel steel anchor plate 6 is located above the two anchor pillars 4. Anchor bolts 7 pass through the channel steel anchor plate 6 and the pre-drilled hole 2 and engage with an anchor nut 8. A pre-drilled groove 10 is provided on the outer wall 9. The end of the anchor pillar 4 passes through the pre-drilled groove 10 and is fixedly connected to the fixed base 11. The climbing frame guide rail 12 is installed on the fixed base 11. The support frame 13 is located between the anchor pillar 4 and the outer wall 9, with one end connected to the anchor pillar 4 by bolts and the other end connected to the outer wall 9 by bolts.

[0019] In this embodiment, the anchor post 4 and the channel steel anchor plate 6 are made of No. 8 channel steel, and the length of the part of the anchor post 4 that is in contact with the top plate 1 is not less than 1.5 meters; increasing the contact area with the top plate 1 can make the anchor post 4 more stably connected to the top plate 1.

[0020] In this embodiment, the support surface size of the support frame 13 is not less than the cross-sectional size between the two anchor pillars 4, which enables the support frame 13 to support the anchor pillars 4 more stably.

[0021] In this embodiment, the support frame 13 is a right-angled triangle, and there are no fewer than two bolts connecting the two right-angled sides of the support frame 13 to the anchor column 4 and the outer wall 9 respectively; having no fewer than two fixing points makes the connection between the support frame 13 and the anchor column 4 and the outer wall 9 more secure.

[0022] In this embodiment, the distance between the climbing frame guide rail 12 and the protruding shape on the outer wall 9 is 300mm. The distance of 300mm can ensure safety while also facilitating the work of construction personnel.

[0023] In the implementation scheme of this embodiment: First, the wall-mounted supports for fixing the climbing scaffold on the exterior wall 9 are arranged using a computer. The longitudinal load on each fixing point is evenly distributed to minimize the load on the supports with fixing points inside the wall. When it is not possible to fix the wall-mounted supports in areas such as shaped exterior walls 9, window openings with bay windows, or openings in the exterior wall 9, pre-drilled holes 2 are made in the top plate 1 at that location to install anchor supports 4. During installation, two anchor supports 4 are symmetrically placed and connected with bolts 3. The ends of the bolts 3 engage with the connecting nuts 5 to connect the two anchor supports 4 into one unit. Then, the anchor supports 4 are placed on the top plate 1. The part of the anchor supports 4 that is in contact with the top plate 1 is covered by a channel steel anchor plate 6, and anchor bolts 7 are inserted through the channel steel anchor plate 6 and the pre-drilled holes 2. The ends of the anchor bolts 7 engage with the anchor nuts 8 to fix the channel steel anchor plate 6. The two anchor pillars 4 are completely fixed in position, and the number of channel steel anchor plates 6 is not less than two, with a spacing of 400mm between them. The outer ends of the two anchor pillars 4 extend out of the outer wall 9 through the reserved grooves 10 on the outer wall 9 to connect with the climbing scaffold guide rail 12. The extension length of the anchor pillar 4 directly affects the distance between the climbing scaffold guide rail 12 and the outer wall 9, and is generally set at 300mm between the climbing scaffold guide rail 12 and the protruding shape on the outer wall. The anchor pillars 4 extending out of the outer wall 9 must be connected to the support frame 13, which is generally 300*300mm in size. The reserved width of the reserved grooves 10 on the outer wall 9 is consistent with the spacing between the two anchor pillars 4, and the reserved height is the height of the anchor pillars 4. This method is convenient to construct, safe to operate, efficient in construction, has little impact on subsequent wall decoration, and saves costs.

[0024] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A climbing scaffold wall-mounted support for a protruding part of a building's exterior wall, characterized in that, The structure includes a top plate (1), reserved holes (2), connecting bolts (3), anchoring supports (4), connecting nuts (5), channel steel anchor plates (6), anchoring bolts (7), anchoring nuts (8), an outer wall (9), reserved slots (10), a fixed base (11), climbing frame guide rails (12), and a support frame (13). The top plate (1) has reserved holes (2). The connecting bolts (3) pass through two anchoring supports (4) and engage with the connecting nuts (5). The anchoring supports (4) are attached to the top plate (1). The channel steel anchor plates (6) are located between the two anchoring supports. (4) Above, the anchor bolt (7) passes through the channel steel anchor plate (6) and the reserved hole (2) and is engaged with the anchor nut (8). The outer wall (9) has a reserved groove (10). The end of the anchor support (4) passes through the reserved groove (10) and is fixedly connected to the fixed base (11). The climbing frame guide rail (12) is installed on the fixed base (11). The support frame (13) is located between the anchor support (4) and the outer wall (9) and one end is bolted to the anchor support (4). The other end of the support frame (13) is bolted to the outer wall (9).

2. The climbing scaffold wall support for the protruding part of the building exterior wall according to claim 1, characterized in that, The anchoring support (4) and the channel steel anchor plate (6) are made of No. 8 channel steel, and the length of the part of the anchoring support (4) that is in contact with the top plate (1) is not less than 1.5 meters.

3. The climbing scaffold wall support for the protruding part of the building exterior wall according to claim 1, characterized in that, The support surface dimension of the support frame (13) is not less than the cross-sectional dimension between the two anchor pillars (4).

4. The climbing scaffold wall support for the protruding part of the building exterior wall as described in claim 1, characterized in that, The support frame (13) is a right triangle in shape, and there are no fewer than two bolts on both sides of the support frame (13) that are connected to the anchor column (4) and the outer wall (9).

5. The climbing scaffold wall support for the protruding part of the building exterior wall according to claim 1, characterized in that, The distance between the climbing frame guide rail (12) and the protruding shape on the outer wall (9) is 300mm.