Safety supporting bracket for high-speed rail bridge construction
By using a lifting system driven by metal ropes and motors, combined with guide chutes and roller shock absorption structures, the safety and height adjustment issues of existing bridge construction support brackets have been solved, and the stability and safety of single-person operation have been improved.
Patent Information
- Application Number
- CN202422925432.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-29
- Publication Date
- 2025-11-07
- Estimated Expiration
- 2034-11-29
AI Technical Summary
Existing bridge construction support brackets have low safety, cannot automatically adjust height, and are difficult for a single person to operate, resulting in inconvenience and instability.
The lifting system, which uses metal ropes and a motor, combined with guide chutes and roller shock absorption structures, enables automatic height adjustment and reduces swaying. It is equipped with a control console and a fence to ensure safety.
This technology improves the safety and stability of single-person operation, saves manpower, reduces swaying amplitude, and enhances construction efficiency and safety.
Smart Images

Figure CN223522990U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model belongs to bridge construction technical field, specifically, relate to a high -speed rail bridge construction is with safe support bracket. BACKGROUND
[0002] Bridge, generally refers to the erection on river lake sea, make the vehicle pedestrian etc. can smoothly pass through the construction, for adapting modern high -speed development traffic industry, bridge also extends to cross the mountain, bad geology or meets other traffic needs and erects the building that makes the traffic more convenient, bridge generally is composed of upper structure, lower structure, support and accessory structure, need to support bracket for installation in the bridge construction process, the simple structure of prior art support bracket is low in safety, reduce the practicability of the equipment, in addition, the existing support bracket cannot automatically adjust the height, inconvenient for user's use.
[0003] The Chinese patent with publication number CN213448121U discloses a bridge construction safety support bracket, which comprises a base, support columns, a lifting platform, a sliding groove, a pulley, a winding frame, a control box and universal wheels, the top end faces of the base are fixedly connected with support columns on both sides, pulleys are installed at the top ends of the two support columns, a lifting platform is arranged between the two support columns, a guardrail is fixedly connected to the top end of the lifting platform, a winding frame is fixedly connected to the top end of the base on one side of the support column, the bottom end face of the control box is fixedly connected with the top end of the base, and universal wheels are installed on the bottom end face of the base. The control console of the prior art is on the outer side of the lifting platform, so the personnel working on the lifting platform cannot operate the lifting platform, and therefore more than one worker is required to use the device, which cannot be used by a single person, and the lifting platform is easy to shake and unstable when lifting, affecting personnel work
[0004] Therefore, the utility model is provided. UTILITY MODEL CONTENT
[0005] The utility model solves the problems in the background art.
[0006] To solve the above technical problems, the basic idea of the technical scheme of the utility model is:
[0007] The utility model provides a safe support bracket for high -speed railway bridge construction, including bottom plate, both sides top of bottom plate is fixedly connected with side frame, bottom between one side side frame is provided with fixed link, top between one side side frame is provided with rotating link, the top of bottom plate is provided with lifting plate, both sides of lifting plate are fixedly connected with the supporting plate of plate, the supporting plate of plate top is provided with winding support, the winding support between both sides is provided with winding link, one side of winding link is provided with motor, the surface of winding link is wound with metal pull rope, metal pull rope passes through rotating link top other end and is fixed on fixed link.
[0008] Optionally, a control console is installed on the top of the lifting plate near the front face, and the control console is connected to the two motors through internal wires.
[0009] Optionally, a guide column is arranged outside the side frame, a sliding groove is formed in the center of the guide column, an adjusting cavity is formed in the front and back of both sides of the lifting plate, a spring column is arranged longitudinally in the adjusting cavity, a roller frame is arranged in the center of the spring column, a roller is arranged in the roller frame, and springs are sleeved on both ends of the spring column.
[0010] Optionally, a vertical rod is arranged on the top of the lifting plate near the outer ring, a fence is arranged on the top of the vertical rod, and a turnover door is arranged on the back of the lifting plate.
[0011] Optionally, the outer ring of the rotating link at the top of the side frame is semicircular, and a support frame is arranged at the edge of the side frame below the rotating link.
[0012] Optionally, the metal pull rope is provided with a plurality of metal pull ropes on one side.
[0013] After the above technical scheme is adopted, the utility model has the following advantages compared with the prior art, of course, any product implementing the utility model does not necessarily need to achieve all the advantages described below:
[0014] 1. The safe support bracket for high-speed railway bridge construction connects two motors through a control console on a lifting plate, the motors drive a winding link to rotate and wind a metal pull rope, shorten the distance between the rotating link and the winding link to lift the lifting plate, the control console moves with the lifting plate to enable the staff on the lifting plate to control the lifting plate, without the need to arrange personnel to control, saving human resources.
[0015] 2. The safe support bracket for high-speed railway bridge construction is installed in a sliding groove through a roller, when the lifting plate shakes, the roller hits the sliding groove wall, the spring is compressed and rebounded to extrude the roller frame at the spring column position to restore it, at the same time, the adjusting cavity is pushed in the opposite direction to reset the lifting plate, reducing the shaking of the lifting plate during lifting, protecting the safety of the operator.
[0016] The specific embodiments of the present application will be further described in detail below with reference to the accompanying drawings. BRIEF DESCRIPTION OF DRAWINGS
[0017] The drawings in the following description are only some embodiments, and other drawings can be obtained by those skilled in the art without creative labor on the basis of these drawings. In the drawings:
[0018] Figure 1 is a structural schematic diagram of the present application;
[0019] Figure 2 is a lifting structure schematic diagram of the present application;
[0020] Figure 3 is a roller damping structure schematic diagram of the present application.
[0021] In the drawings, the component list represented by each number is as follows:
[0022] 1, bottom plate; 101, side frame; 102, fixed rod; 103, rotating rod; 104, support frame; 105, guide column; 106, sliding groove;
[0023] 2, lifting plate; 201, winding support; 202, winding rod; 203, motor; 204, adjusting inner cavity; 205, spring column; 206, spring; 207, roller frame; 208, roller; 209, supporting plate;
[0024] 3, metal pull rope;
[0025] 4, control console; 401, fence; 402, vertical rod; 403, turnover door.
[0026] It should be noted that these drawings and textual descriptions are not intended to limit the scope of the concept of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments. DETAILED DESCRIPTION
[0027] The present application will now be further described in detail with reference to the accompanying drawings.
[0028] Please refer to Figures 1-3 shown, a safety support bracket for high-speed rail bridge construction is provided in the embodiment, which comprises.
[0029] The application of an aspect of the present embodiment is: a safety support bracket for high-speed rail bridge construction. It should be noted that all electrical equipment involved in the present application can be powered by a battery or an external power source.
[0030] As Figure 1 , 2As shown, the metal pull rope 3 of the embodiment is fixed at one end of the fixed rod 102 and wound, the upper end is wound from the top of the rotating rod 103, and the bottom is finally wound and installed on the winding rod 202. The motor 203 is started to drive the winding rod 202 to rotate, the metal pull rope 3 is wound to shorten the length of the external metal pull rope 3, and the distance between the rotating rod 103 and the winding rod 202 is shortened by winding, and the winding rods 202 on both sides rotate synchronously to make the lifting plate 2 horizontally lifted, thereby facilitating the operator to perform construction work on the high bridge position. The surface of the rotating rod 103 is attached to the metal pull rope 3 to follow the rotation to reduce friction, and the console 4 is installed on the lifting plate 2 to start and stop the motor 203 by setting the internal wire in the lifting plate 2 to follow the lifting, so that the construction worker can adjust the height of the lifting plate 2.
[0031] As shown in Figure 2 , 3 As shown, the guide column 105 of the embodiment is in a concave shape, the inside is opened to the sliding groove 106, and the opening direction is towards the position of the lifting plate 2. The roller frame 207 installed in the adjusting inner cavity 204 of the lifting plate 2 corresponds to the sliding groove 106, the center of the roller frame 207 passes through the roller shaft and is installed with the roller 208, the diameter of the roller 208 is smaller than the groove width of the sliding groove 106, so that the roller 208 does not contact the groove wall of the sliding groove 106 on both sides at the same time. A part of the roller frame 207 extending out of the adjusting inner cavity 204 is installed with the roller 208 in the center, the center passing through the spring column 205 and being supported by the spring 206 on both sides, when the lifting plate 2 shakes forward and backward during the lifting process, the roller 208 contacts the wall of the sliding groove 106, so that the position of the roller frame 207 on the spring column 205 is offset, thereby pressing the spring 206 on one side, and the two springs 206 release the elastic force to quickly make the roller frame 207 return to the center position, thereby reducing the shaking time and amplitude of the lifting plate 2, and ensuring the balance.
[0032] As shown in Figure 1 As shown, the entire lifting plate 2 of the embodiment is surrounded by the fence 401 on the top, which protects the operator from falling during high-altitude construction, and the fence 401 is supported by multiple vertical rods 402 and has an entrance opposite the console 4. The rail of the entrance is set as a flip door 403 by a rotating shaft, which is convenient to open and close.
[0033] As shown in Figure 2 , 3As shown, the side frame 101 of the embodiment is attached to the lifting plate 2, the winding support 201 is arranged on the extension plate 209 extended from both sides of the lifting plate 2, so that the winding support 201 and the winding rod 202 extend into the space between the side frames 101, and the rotating rod 103 at the top extends to the direction of the winding rod 202, so that the rotating rod 103 and the winding rod 202 are close to each other in the vertical direction, and the distance between them is the width of the metal pull rope 3, so that the metal pull rope 3 is perpendicular to the downward direction when it is connected to the rotating rod 103 and the winding rod 202, and the force is perpendicular to the upward direction when it is wound, so that the force is not dispersed in other directions, and the whole lifting is more labor-saving, the extension part of the side frame 101 at the top is used for mounting the rotating rod 103, and the extension part cannot be too much, otherwise the motor 203 will hit the side frame 101 when the lifting plate 2 rises, and the part of the side frame 101 suspended below the rotating rod 103 is reinforced by the support frame 104 to prevent deformation of this area.
[0034] As shown, Figure 2 The multiple metal pull ropes 3 of the embodiment are wound synchronously, the stress of each metal pull rope 3 is reduced, and the service life of the metal pull rope 3 is longer.
[0035] Embodiment 1:
[0036] In the embodiment, the operator logs in the area of the lifting plate 2, starts the motors 203 on both sides through the control console 4 to rotate, drives the winding rod 202 to rotate with the cloth to wind the metal pull rope 3, shortens the distance between the rotating rod 103 and the winding rod 202, thereby lifting the lifting plate 2, so that the operator can contact the higher bridge position to reduce the labor operation, and the control console 4 rises and falls with the lifting platform 2, so that the operator can adjust the height of the lifting plate 2 at any time during work.
[0037] Embodiment 2:
[0038] In the embodiment, when the lifting plate 2 shakes forward and backward during the rising process, the roller 208 contacts the wall of the sliding groove 106, so that the position of the roller frame 207 on the spring column 205 is offset, thereby allowing the roller frame 207 to press one side of the spring 206, the two springs 206 release the elastic force to quickly make the roller frame 207 return to the center position, and reversely push the inner wall of the adjusting cavity 204 to reset the lifting plate 2, thereby reducing the shaking time and amplitude of the lifting plate 2 and ensuring the balance of the lifting plate 2 during the lifting process.
[0039] The utility model is not limited to the above-mentioned embodiments, anyone should know that the structural changes made under the inspiration of the utility model, any technical scheme with the same or similar technical scheme of the utility model falls within the protection scope of the utility model. The utility model does not describe the technology, shape and structure part in detail, which is the known technology.
Claims
1. A safety support bracket for high iron bridge construction, characterized in that, Include: The bottom plate (1), the top of both sides is fixedly connected with side frame (101), the bottom of one side side frame (101) is provided with fixed rod (102), the top of one side side frame (101) is provided with rotating rod (103), the top of bottom plate (1) is provided with lifting plate (2), the both sides of lifting plate (2) are fixedly connected with supporting plate (209), the top of supporting plate (209) is provided with winding support (201), the both sides of two winding supports (201) are provided with winding rod (202), one side of winding rod (202) is provided with motor (203), the surface of winding rod (202) is wound with metal pull rope (3), the other end of metal pull rope (3) is fixed on fixed rod (102) through rotating rod (103) above.
2. The safety support bracket for high-speed railway bridge construction of claim 1, wherein The top of lifting plate (2) is installed with control console (4) near the front, and the bottom of control console (4) is connected with both sides of motor (203) through inner wire.
3. The safety support bracket for high-speed railway bridge construction of claim 1, wherein The outer side of side frame (101) is provided with guide column (105), the sliding groove (106) is opened towards the center position of guide column (105), the both sides of lifting plate (2) are opened with adjusting inner cavity (204) near the front and back, the spring column (205) is longitudinally arranged in adjusting inner cavity (204), the roller frame (207) is arranged in the center position of spring column (205), the roller (208) is installed in roller frame (207), and the spring (206) is sleeved on both ends of spring column (205).
4. The safety support bracket for high-speed railway bridge construction of claim 1, wherein The top of lifting plate (2) is provided with vertical rod (402) near the outer ring, the top of vertical rod (402) is provided with fence (401), and the fence (401) is provided with turnover door (403) at the back of lifting plate (2).
5. The safety support bracket for high-speed railway bridge construction of claim 1, wherein The top of side frame (101) is semicircular at the outer ring of rotating rod (103), and the support frame (104) is arranged at the edge of side frame (101) below rotating rod (103).
6. The safety support bracket for high-speed railway bridge construction of claim 1, wherein The metal pull rope (3) is provided with a plurality of metal pull ropes (3) on one side.
Citation Information
Patent Citations
Safety supporting bracket for bridge construction
CN213448121U