Pre-embedded perpendicularity control device for high-concentration ground foundation bolt

By combining support and positioning mechanisms, the precise positioning and vertical installation of pre-embedded bolts for high-concentration grinding equipment were achieved, solving the problem of quality control in the installation of pre-embedded bolts and improving construction efficiency and equipment installation accuracy.

CN223524840UActive Publication Date: 2025-11-07YUNNAN SECOND INSTALLATION ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423281612.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-30
Publication Date
2025-11-07
Estimated Expiration
2034-12-30

AI Technical Summary

Technical Problem

Existing technology cannot meet the precision requirements of pre-embedded bolts in large equipment such as high-concentration mills, making it difficult to control the installation quality.

Method used

A high-density ground anchor bolt pre-embedded verticality control device, consisting of a support mechanism and a positioning mechanism, is used. The support mechanism is fixedly connected to the ground to ensure the stability of the positioning mechanism, thereby achieving precise positioning and vertical installation of the bolts.

Benefits of technology

It improved construction efficiency, solved the problem of quality control in the installation of pre-embedded bolts, and ensured the accuracy and stability of equipment installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223524840U_ABST
    Figure CN223524840U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of chemical equipment, in particular to a high-concentration ground foundation bolt pre-embedding perpendicularity control device which comprises a device body, the device body is composed of a supporting mechanism and a positioning mechanism, and the supporting mechanism comprises a plurality of stand columns, a plurality of supporting rods and a plurality of positioning rods. The supporting mechanism is fixedly connected with the positioning mechanism, the two bearing main beams are symmetrically arranged, and the two ends of each bearing main beam are fixedly connected with the upper ends of the adjacent stand columns respectively. The supporting mechanism, the positioning mechanism and the like are arranged, and after the positioning mechanism determines the position, the positioning mechanism is fixedly connected with the supporting mechanism; and then the supporting mechanism is fixedly connected with the ground, the embedded bolt device is vertically positioned, long-rod bolts are accurately positioned and vertically installed, the problem that the installation quality of the embedded bolts of heavy equipment such as a high-concentration mill is difficult to control is solved, the construction efficiency is improved, and high practicability is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to chemical equipment technical field, concretely is a high concentration mill anchor bolt embedded perpendicularity control device. BACKGROUND

[0002] The heavy mill equipment is the important engineering of chemical papermaking industry, and the high concentration mill is the core equipment of the wood fiber hot mill washing and selecting workshop in the paper mill, is the intermediate equipment connecting from wood chip to paper pulp, in the whole paper mill pulp line device, the high concentration mill is the key equipment installation control point, in addition to the high concentration mill, the medium concentration mill, the low concentration mill, the pulp washing machine etc. CONTENT OF THE UTILITY MODEL

[0003] The utility model discloses a high concentration mill anchor bolt embedded perpendicularity control device to solve the problem in the background art.

[0004] To achieve the above object, the utility model provides the following technical scheme:

[0005] A high concentration mill anchor bolt embedded perpendicularity control device, including device body, the device body is by support mechanism and positioning mechanism composition, still including:

[0006] The support mechanism includes:

[0007] The column is provided with a plurality of;

[0008] The bearing main girder is provided with two and is symmetrically arranged, and the both ends of the bearing main girder are fixedly connected with the upper end of adjacent column respectively;

[0009] The positioning mechanism includes:

[0010] The hanging frame is provided with two and is symmetrically arranged, and both ends between the hanging frame are fixedly connected with one connecting mechanism respectively;

[0011] Through the support mechanism and positioning mechanism etc.

[0012] As the preferred scheme of the utility model,

[0013] The cross beams are arranged above the load-bearing main beams and are fixedly connected with the upper surfaces of the load-bearing main beams at the lower ends;

[0014] The hangers are arranged above the cross beams and are fixedly connected with the upper ends of the cross beams;

[0015] The stand column, the load-bearing main beam and the cross beam form a frame structure;

[0016] The base plates are arranged below the stand columns and are fixedly connected with the lower ends of the stand columns;

[0017] The expansion bolts are arranged above the base plates and are fixedly connected with the upper surfaces of the base plates;

[0018] After the position of the positioning mechanism is determined, the lower ends of the hangers are directly fixed, and then the stand columns are directly fixed on the designated ground through the expansion bolts and the base plates, so that the stand columns, the load-bearing main beam and the cross beam are in a stable and fixed state; the positioning mechanism can be fixed and positioned in the air through the supporting mechanism, so that the problem that the positioning bolt is difficult to accurately fix is solved.

[0019] As the preferred scheme of the utility model,

[0020] The bolt positioning sleeves are arranged above the hangers and are fixedly connected with the hangers;

[0021] The bolts are arranged above the bolt positioning sleeves and are threadedly connected with the bolt positioning sleeves;

[0022] The left positioning frame is fixedly connected with the inner sides of the hangers at the two ends;

[0023] The right positioning frame is arranged on one side of the left positioning frame and is fixedly connected with the inner sides of the hangers at the two ends;

[0024] The fixed cross beam is arranged between the left positioning frame and the right positioning frame and is fixedly connected with the left positioning frame and the right positioning frame at the two ends;

[0025] The bolt is arranged in the bolt positioning sleeve, the bolt is aligned and positioned through the movement of the supporting mechanism, then the hangers are fixed with the lower ends of the adjacent hangers, and the vertical positioning of the bolt is completed.

[0026] Compared with the prior art, the utility model has the advantages of:

[0027] 1. In this utility model, by setting up a support mechanism and a positioning mechanism, after the positioning mechanism determines the position, the positioning mechanism is fixedly connected to the support mechanism, and then the support mechanism is fixedly connected to the ground. The vertical positioning pre-embedded bolt device accurately positions and vertically installs the long bolts, which solves the problem of difficult quality control of pre-embedded bolt installation in heavy equipment such as high-concentration mills, improves construction efficiency, and has strong practicality.

[0028] 2. In this utility model, after the position of the positioning mechanism is determined, it is directly fixed to the lower end of the rod. Then, the column is directly fixed to the designated ground using expansion bolts and pads. At this time, the column, the main load-bearing beam and the crossbeam are all in a stable and fixed state. Through the set support mechanism, the entire positioning mechanism can be suspended and fixed in place, thereby solving the problem of the positioning bolts being difficult to fix accurately. Attached Figure Description

[0029] Fig. 1 This is a schematic diagram of the overall three-dimensional structure of this utility model;

[0030] Fig. 2 This is a schematic diagram of the support mechanism structure of this utility model;

[0031] Fig. 3 This is a schematic diagram of the positioning mechanism of this utility model.

[0032] In the diagram: 1. Device body; 2. Support mechanism; 3. Positioning mechanism; 4. Column; 5. Load-bearing main beam; 6. Crossbeam; 7. Hanging rod; 8. Pad plate; 9. Expansion bolt; 10. Hanging frame; 11. Left positioning frame; 12. Right positioning frame; 13. Fixed crossbeam; 14. Bolt positioning sleeve; 15. Bolt. Detailed Implementation

[0033] To make the technical means and objectives and effects of this utility model easier to understand, the embodiments of this utility model will be described in detail below with reference to specific figures.

[0034] It should be noted that all directional and positional terms used in this utility model, such as "up," "down," "left," "right," "front," "back," "vertical," "horizontal," "inner," "outer," "top," "lower," "lateral," "longitudinal," and "center," are only used to explain the relative positional relationships and connections between components in a specific state (as shown in the accompanying drawings). They are merely for the convenience of describing this utility model and do not require that this utility model be constructed and operated in a specific orientation; therefore, they should not be construed as limitations on this utility model. Furthermore, descriptions involving "first," "second," etc., in this utility model are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated.

[0035] In the description of the utility model, unless another explicit provision and limitation, the term "mounting", "connection", "connection" should be broad sense, for example, can be fixed connection, can be detachable connection, or integrally connected, can be mechanical connection, can be directly connected, can be indirectly connected through the intermediate medium, can be two elements inside the communication. For ordinary skilled in the art, the specific meaning of the above terms in the utility model can be understood according to the specific circumstances.

[0036] In the description of the specification, the description of the terms "one embodiment", "some embodiments", "exemplary embodiment", "example", "specific example" or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In the specification, the exemplary description of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0037] Please refer to Figs. 1-3 The utility model provides a technical scheme:

[0038] A high concentration mill foot bolt embedded verticality control device, including device body 1, device body 1 is composed of support mechanism 2 and positioning mechanism 3, still including:

[0039] Support mechanism 2 includes:

[0040] Stand 4, stand 4 is provided with several;

[0041] Load main beam 5, load main beam 5 is provided with two and symmetrically arranged, and load main beam 5 both ends are fixedly connected with the upper end of adjacent stand 4 respectively;

[0042] Positioning mechanism 3 includes:

[0043] Hanging rack 10, hanging rack 10 is provided with two and symmetrically arranged, and one connecting mechanism is fixedly connected between the both ends of hanging rack 10;

[0044] Through the support mechanism 2 and positioning mechanism 3 etc. are arranged, after positioning mechanism 3 determines the position, positioning mechanism 3 is fixedly connected with support mechanism 2, then again support mechanism 2 is fixedly connected with the ground, and the vertical positioning embedded bolt device is installed, the long rod bolt is accurately positioned and vertically installed, the problem that the installation quality control of heavy equipment such as high concentration mill embedded bolt is solved, the construction efficiency is improved, and it has strong practicality.

[0045] As an example of the utility model,

[0046] The cross beam 6 is arranged above the load-bearing main beam 5, and the lower end of the cross beam 6 is fixedly connected to the upper surface of the load-bearing main beam 5.

[0047] The suspender 7 is arranged above the cross beam 6, and the upper end of the suspender 7 is fixedly connected to the cross beam 6.

[0048] The column 4, the load-bearing main beam 5 and the cross beam 6 form a frame structure.

[0049] The base plate 8 is arranged below the column 4, and the lower end of the base plate 8 is fixedly connected to the column 4.

[0050] The expansion bolt 9 is arranged above the base plate 8, and the expansion bolt 9 is fixedly connected to the base plate 8.

[0051] After the position of the positioning mechanism 3 is determined, the lower end of the suspender 7 is directly fixed, and then the column 4 is directly fixed on the designated ground through the expansion bolt 9 and the base plate 8, so that the column 4, the load-bearing main beam 5 and the cross beam 6 are in a stable and fixed state.

[0052] As an example of the utility model,

[0053] The bolt positioning sleeve 14 is arranged above the suspender 10, and the bolt positioning sleeve 14 is fixedly connected to the suspender 10.

[0054] The bolt 15 is arranged above the bolt positioning sleeve 14, and the bolt 15 is threadedly connected to the bolt positioning sleeve 14.

[0055] The left positioning frame 11 is arranged above the suspender 10, and the left positioning frame 11 is fixedly connected to the inside of the suspender 10.

[0056] The right positioning frame 12 is arranged above the left positioning frame 11, and the right positioning frame 12 is fixedly connected to the inside of the suspender 10.

[0057] The fixed cross beam 13 is arranged between the left positioning frame 11 and the right positioning frame 12, and the fixed cross beam 13 is fixedly connected to the left positioning frame 11 and the right positioning frame 12.

[0058] The bolt 15 is arranged in the bolt positioning sleeve 14, the bolt 15 is aligned through the movement of the supporting mechanism 2, then the suspender 10 is fixedly connected to the lower end of the suspender 7, and the vertical positioning of the bolt is completed.

[0059] Working principle: first bolt 15 is arranged in bolt positioning sleeve 14, through moving support mechanism 2, bolt 15 is aligned and positioned, then hanging frame 10 is fixed with the lower end of adjacent suspender 7, the vertical positioning operation of bolt is completed, after the position of positioning mechanism 3 is determined, it is directly fixed with the lower end of suspender 7, then the expansion bolt 9 and the pad 8 are used to fix the column 4 directly on the specified ground, at this time, the column 4, the load-bearing main beam 5 and the crossbeam 6 are in the stable fixed state.

[0060] Although the embodiments of the utility model have been shown and described, it can be understood by those of ordinary skill in the art that various changes, modifications, replacements and variations can be made to these embodiments without departing from the principles and spirits of the utility model, and the scope of the utility model is defined by the appended claims and their equivalents.

Claims

1. A high concentration grinding anchor bolt embedded verticality control device, comprising a device body (1), the device body (1) is composed of a supporting mechanism (2) and a positioning mechanism (3), characterized in that, Also include: The support mechanism (2) comprises: The column (4) is provided with several; The load-bearing main beam (5) is provided with two and symmetrically arranged, and the two ends of the load-bearing main beam (5) are respectively fixedly connected with the upper ends of the adjacent columns (4); The positioning mechanism (3) comprises: The hanging bracket (10) is provided with two and symmetrically arranged, and the two ends of the hanging bracket (10) are respectively fixedly connected with one connecting mechanism.

2. The high concentration mill anchor bolt pre-embedded perpendicularity control device according to claim 1, characterized in that, Also include: The crossbeam (6) is provided with several and arrayed above the load-bearing main beam (5), and the lower end of the crossbeam (6) is respectively fixedly connected with the upper surface of the adjacent load-bearing main beam (5); The suspender (7) is provided with several and the upper end of the suspender (7) is fixedly connected with the adjacent crossbeam (6).

3. The high concentration mill anchor bolt pre-embedded perpendicularity control device according to claim 1, characterized in that: Also include: The column (4), the load-bearing main beam (5) and the crossbeam (6) form a frame structure.

4. The high concentration mill anchor bolt pre-embedded perpendicularity control device according to claim 1, characterized in that, Also include: The base plate (8) is provided with several and is respectively fixedly connected with the lower end of the adjacent column (4); The expansion bolt (9) is provided with several and is respectively fixedly connected through the upper surface of each base plate (8).

5. The high concentration mill anchor bolt pre-embedded perpendicularity control device according to claim 1, characterized in that, Also include: The bolt positioning sleeve (14) is provided with several and is arrayed and fixedly connected with the two hanging brackets (10); The bolt (15) is provided with several and is threadedly connected with each bolt positioning sleeve (14).

6. The high concentration mill anchor bolt pre-burying verticality control device according to claim 1, wherein: The connecting mechanism comprises: The left positioning frame (11) is fixedly connected with the inner sides of the two hanging brackets (10) at both ends; The right positioning frame (12) is arranged on one side of the left positioning frame (11) and is fixedly connected with the inner sides of the two hanging brackets (10) at both ends.

7. The high concentration mill anchor bolt pre-embedded perpendicularity control device according to claim 6, characterized in that, Also include: The fixed crossbeam (13) is arranged between the left positioning frame (11) and the right positioning frame (12) and is fixedly connected with the left positioning frame (11) and the right positioning frame (12) at both ends.